INSTALLATION OF UNDERGROUND BURRIED DUCTS
Project: Owner: Project Manager: Consultant: Main Contractor : IR No.: Building No.: Level: Date:
CHECKED BY NO. 1 2 3 4 DESCRIPTION
Approved Material used (MIR)
REMARKS
Checking existing ground levels. Check Ducts, fittings & accessories used have an approved material submittal. Check that shop drawings are approved for construction. Check that trench has been cleared for duct laying. Check that the ducts have been installed as per approved shop drawing. Check the installation prior to back filling.
6 7
Remarks/Comments (if any):
COMPANY Name Signature Date