Weekly Progress Report

During the first week of his internship, John inspected cracks at the South Parking of Mall of Asia and estimated costs for SM Taytay's proposed cyberzone. He toured ongoing constructions at The Galleon Museum, Conrad Mall and Hotel, and Mall of Asia phase 2 expansion. He monitored architectural works at The Galleon Museum. In the second week, he learned about billing processes and electrical plans. He re-inspected cracks at Mall of Asia and observed construction activities like installing LC perlins, dry walls, and demolishing skylights. He discussed post-construction procedures.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
613 views4 pages

Weekly Progress Report

During the first week of his internship, John inspected cracks at the South Parking of Mall of Asia and estimated costs for SM Taytay's proposed cyberzone. He toured ongoing constructions at The Galleon Museum, Conrad Mall and Hotel, and Mall of Asia phase 2 expansion. He monitored architectural works at The Galleon Museum. In the second week, he learned about billing processes and electrical plans. He re-inspected cracks at Mall of Asia and observed construction activities like installing LC perlins, dry walls, and demolishing skylights. He discussed post-construction procedures.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd

National University

Manila
College of Engineering

ISO 9001:2008
QUALITY MANAGEMENT SYSTEM
CERTIFIED

INDUSTRY INTERNSHIP TRAINING PROGRAM


WEEKLY PROGRESS REPORT
Name of Student: John Gerald S. Mallari

Age: 20

Sex: Male

Course: BS Civil Engineering


Name of the Company: SM Engineering Design and Development Corporation
Company Address: 9th Floor Mall of Asia Arena Annex, Mall of Asia Complex, Pasay City
Division/Plant/Site Assigned: Special Project/Mall of Asia Complex
Field of Training Assigned: Construction
Week No: 1

Inclusive Dates of Training: From April 12, 2016 To April 15, 2016

Write summary of all activities accomplished during the week


During the first week of the internship program, I was designated to the Mall
of Asia complex knowing that different constructions were on going. First task is to
check or inspect the cracks along the South Parking of Mall Of Asia includes
beams, columns and slabs. The next days we were assigned to estimate the SM
Taytay Proposed Cyberzoned and presented our computed values to project
engineers also Engr. Liongson explained briefly and discuss on MEFPS
(Mechanical, Electrical, Fire Protection & Sanitary Works) of a certain plan,
keywords were also elaborated. A tour on ongoing constructions at The Galleon
Museum, architectural fit outs at Conrad Mall and Hotel and briefly elaborated the
color coordinations of pipes and wirings at the Mall of Asia phase 2 expansion.
Lastly, Architectural works were monitored at the The Galleon Musuem.

Verified by:
______________________________
Signature over Printed Name of
Technical Training Supervisor

_________________
Date

DOCUMENTATION

The floor plan of SM Taytay Proposed


Cyberzone
Estimation of SM TayTay Proposed Cyberzone

On going fit outs at Directors Club, Conrad


Mall

Construction of Cinema, The Galleon Mall

Electrical and Ductings for Airconditioned were


place.

Estimation of Stairs for SM


Muntinlupa

Tenants Partition

Inspection of Architectural Works at


the The Galleon Mall.

National University
Manila
College of Engineering

ISO 9001:2008
QUALITY MANAGEMENT SYSTEM
CERTIFIED

INDUSTRY INTERNSHIP TRAINING PROGRAM


WEEKLY PROGRESS REPORT
Name of Student: John Gerald S. Mallari

Age: 20

Sex: Male

Course: BS Civil Engineering


Name of the Company: SM Engineering Design and Development Corporation
Company Address: 9th Floor Mall of Asia Arena Annex, Mall of Asia Complex, Pasay City
Division/Plant/Site Assigned: Special Project/Mall of Asia Complex
Field of Training Assigned: Construction
Week No: 2

Inclusive Dates of Training: From April 18, 2016 To April 22, 2016

Write summary of all activities accomplished during the week


. On the second week of the internship program Billing process were
explained by Engr. Acosta including all the documents needed and the step by step
procedures that need to conduct. Electrical plan was elaborated by Engr. Cloyd and
done a quick tour to MAAXs AHU and electrical rooms, wirings and other fixtures
were also familiarized. Moreover, Cracks along beams, columns and slabs on the
South Parking of Mall of Asia were inspected for the second time to ensure that all
the cracks were reported. LC Perlins were placed on the phase 2 expansion of Mall
of Asia and also dry walls, drop walls were placed. Demolition of the existing
skylights is on going and board ups around the demolition area were painted.
Lastly, Post construction procedures were explained and discuss which includes the
mobilization, Closed out and Project Turnover.