Safe erection of
structural steel
for buildings
Edition No. 1
May 2009
Acknowledgements
This industry standard was prepared on behalf of Foundations for Safety Victoria by a working group
comprising industry practitioners, employers, industry employer groups, unions, and WorkSafe Victoria.
The working group was chaired by WorkSafe Victoria, and included representatives from:
AMWU
Associated Rigging Australia
Aus Truestyle
Australand Industrial Construction
CFMEU
Contexx
Housing Industry Association
Master Builders Association of Victoria
National Association of Steel Housing
Salta Constructions P/L
Structural Steel Fabricators Association (Vic)
United Engineering Australia P/L
Victorian Construction Safety Alliance
WorkSafe Victoria.
2009 WorkSafe Victoria
WorkSafe Victoria is a trading name of the Victorian WorkCover Authority.
This publication is protected by copyright. WorkSafe encourages the free transfer, copying and
printing of this publication is such activities support the purpose and intent for which this
publication was developed.
Developing industry standards in partnership
Foundations for Safety Victoria is Victorias primary forum for dealing with occupational health and
safety issues in the construction industry.
Foundations for Safety brings together regulatory agencies, construction unions and employer
associations representing principle contractors and specialist trade sub-contractors.
Chaired by WorkSafe Victoria, it meets every three months to progress OHS issues relating to the
construction industry. One of its initiatives is establishing working parties to develop industry standards
which provide practical guidance to the industry on particular issues.
The organisations represented on Foundations for Safety Victoria are:
Air Conditioning and Mechanical Contractors Association
Association of Wall and Ceiling Industries
Australian Industry Group
Australian Manufacturing Workers Union
Australian Workers Union
Building Commission Victoria
CEPU Electrical Trades Union
CEPU Plumbing Division
CFMEU Construction and General Division
Civil Contractors Federation
Energy Safe Victoria
Finishing Trades Association of Australia
Housing Industry Association
Master Builders Association of Victoria
Master Plumbers and Mechanical Services Association of Australia
National Electrical and Communications Association
National Federation of Bricklayers and Masonry Employers
Plumbing Industry Commission
Royal Australian Institute of Architects
Victorian Construction Safety Alliance
Victorian Crane Association
Victorian Employers Chamber of Commerce and Industry
Victorian Volume Home Builders Safety Alliance
Victorian Trades Hall Council
WorkSafe Victoria
Help improve health and safety in the construction industry by providing feedback on this
Industry Standard or on other health and safety issues to any member organisation of
Foundations for Safety Victoria.
Contents
1. Introduction
05 5. Transportation stage
Purpose
Scope
What is the status of this industry standard?
How to read this industry standard
2. Overview
3. Design stage
General
Roles during the design stage
Managing risk at the design stage
4. Fabrication stage
Roles during the transportation stage
Managing risk at the transportation stage
6. Erection stage
Roles during the fabrication stage
Managing risk at the fabrication stage
18
General
Roles during the erection stage
Erection engineer
Erector
12
14
General
General
07
Management and control
Health and safety representatives
Key planning tools
Licences for high risk work
Competency and training
16
Erection crew
Documentation in the erection stage
Marking plan
Safe work method statement
Managing risk at the erection stage
Other hazards
Appendix 1
25
Appendix 2
28
Appendix 3
29
Definition of terms
30
References
33
Industry standard / Safe erection of structural steel for buildings
WorkSafe Victoria
1.
1.1
Introduction
Purpose
1.2
Under the Occupational Health and Safety
Act 2004 employers have a general duty to
ensure the health and safety of employees at
work. Employers involved in construction work
also have specific duties under the construction
part of the OHS regulations to control any
risk associated with construction work as far
as reasonablypracticable.
Scope
This industry standard applies to the
constructionof:
portal framed buildings
residential and other buildings where steel
frames provide structural strength and stability
to the whole building.
Generally, the structural steel members
This industry standard provides practical guidance coveredinclude:
for the design, fabrication, transportation and
portal and other frames
erection of steel members for buildings, to
columns, beams, rafters, purlins, girts
eliminate or reduce the risk to the health and
andbracings.
safety of:
The industry standard does not apply to the
employees and contractors involved in
construction of:
structural steel erection
buildings that have steel members such as
the public in the vicinity.
lintels, posts or frames that are not part of the
The main hazards risking the health and safety of
complete steel structure providing stability
workers in structural steel erection are:
light-gauge, cold-formed metal stud wall, floor
falls from heights
and roof systems for structures such as villa
housing and those homes, garages and sheds
falling objects
which come in a kit style.
collapse of the structure
Parties, who are excluded in the list above, are
plant used in the work.
encouraged to use this industry standard,
regardless, as a guide for the safe erection of
their steel framed structures.
WorkSafe Victoria
Industry standard / Safe erection of structural steel for buildings
1.
Introduction
1.3 What is the status of this
industry standard?
1.4 How to read this
industrystandard
The guidance in this industry standard should be
followed. An alternative method may be followed
if it will achieve an equivalent or better level of
health and safety.
This standard deals separately with each stage
of structural steelwork in sequence. Section 2
provides an overview of the key roles in the
whole process for safe erection of structural
steel, their responsibilities and methods of work
to ensure an efficient, co-operative and safe
working environment.
Where this industry standard reflects the OHS
Act and OHS Regulations (including the
construction regulations), this is indicated by the
use of the word must. In such cases, this
guidance must be followed.
Steel structures should be designed in
accordance with the key Australian standards
dealing with the design, fabrication and erection
of steel structures:
AS 3828:1998, Guidelines for the erection of
building steelwork
AS 4100:1998, Steel structures.
These documents, and other relevant Australian
standards, provide detailed technical guidance.
The sections that deal with the stages in the
process are:
Section 3:
Section 4:
Section 5:
Section 6:
Design
Fabrication
Transportation
Erection.
Each of these sections describes the key
responsibilities of that stage in the process, and
provides a table of common hazards and risk
control measures.
Where any technical conflict arises between a
provision of this industry standard and a technical
provision of the Australian standard, the
Australian standard provision should be followed.
However, where the guidance in this industry
standard reflects a legal requirement in Victoria,
this industry standard should be followed.
See Appendix 1 for a list of relevant Australian
standards and other guidance information.
Industry standard / Safe erection of structural steel for buildings
WorkSafe Victoria
2.
2.1
Overview
Management and control
Erecting structural steelwork for building construction takes place in a dynamic, changing environment
where there are many hazards andrisks.
Proper and timely planning and coordination are the most effective ways to manage those hazards
and risks.
Projects involving structural steel construction have four main stages (dealt with in sections 3to6)
where risks to health and safety need tobeconsidered:
design
fabrication
transport
erection.
The parties with roles and responsibilities at the various stages of projects are:
Structural
design engineer
Fabricator
The engineer, with experience in structural steel, who is responsible for the
engineering design of the overall building.
The party responsible for project managing the construction of the building
and who has control of the building site.
The engineer who is responsible for the engineering design and stability
aspects of the erection of the steel structure. This role requires the person to
have a sound knowledge of the structure and its capacity in a temporary state.
The party responsible for making the steelwork.
Shop detailer
Engaged (usually by the fabricator) to produce the shop drawings.
Transporter
The person who delivers the steel to the building site.
Erector
The employer responsible for engaging the erection crew and erecting
thestructure.
Builder
Erection
engineer
Note: On some projects, one person may perform more than one role, or parts of different roles.
Thisindustry standard assumes that each role is carried out by a different person.
WorkSafe Victoria
Industry standard / Safe erection of structural steel for buildings
2.
Overview
Diagram 1: Functional representation of the key roles (outlined in 2.1)
Architect
Client
Structural design engineer
produces the structural design of the building
reviews the shop drawings (produced by the shop detailer and fabricator)
Builder
project manages the construction of the building
controls the site
ensures contractors develop and implement relevant safe work practices
monitors and liaises with key parties at each stage
Erection engineer
approves the sequential erection procedure and prepares associated
erection designs
approves the stability of the structure during construction as and when required
Fabricator
manufactures the steel members
engages the shop detailer
Shop detailer
develops shop drawings for
fabricator, that are signed off by
the erection engineer
Erector
develops the sequential erection procedure
engages and briefs the erection crew
ensures stability of all stages in consultation
with erection engineer
produces the SWMS and discusses with the
erection crew and relevant parties
Transporter
transports the steel members from the
fabricator to the site
obtains authorised planned routes and all
necessary permits
Note: There may be variations to this flow chart.
Industry standard / Safe erection of structural steel for buildings
WorkSafe Victoria
2.
Overview
The functional relationship between each party is
outlined in Diagram 1, on the previous page.
Each party is responsible for the matters that are
under its management and control. Managing
risks arising from these matters is more effective
when parties regularly consult one another and
review how the next part of the process
willproceed.
For example, close co-operation between all
parties is essential to ensure that the procedure
for the erection of steel work is safe. They should:
ensure the procedure is acceptable to all
parties and signed off by the erection engineer
review the procedure before activities begin.
2.2 Health and safety
representatives
Planning and coordination must involve
consultation with those engaged in the work and
the health and safety representatives (if any).
A health and safety representative (HSR) is
elected by the workers to represent their health
and safety issues at work. HSRs must be
consulted alongside employees and contractors
on issues relating to health and safety, including
when processes are reviewed.
For further information, see publication, Employee
Representation.
2.3
Key planning tools
There are six key documents which help ensure
safe work in structural steel erection. These are:
construction drawings architectural
andstructural
shop drawings drawn up by the shop
detailer, who is engaged by the fabricator, in
consultation with the erection engineer, and
detail what steel members are to be
manufactured. Shop drawings are reviewed by
WorkSafe Victoria
the structural design engineer before
fabrication (see Section4 Fabrication)
marking plans developed by the fabricator
and detail where steel members will be
positioned in the erection process (see
Section6 Erection)
sequential erection procedure usually
developed by the erector and approved by the
erection engineer. The sequential erection
procedure sets out the steps for the work in
the correct order of erection (see Section6
Erection)
safe work method statement (SWMS)
developed by the erector in consultation with
the crew and the builder, and identifies the
hazards and risk controls for each step of the
erection sequence (see Section 6.3.3, as well
as Appendix 1 for an example)
erection design developed by the erection
engineer based on the sequential erection
procedures prepared by the erector.
The responsibility for completing and endorsing
these documents in each stage is discussed in
the relevant stage sections.
2.4
Licences for high risk work
The erection of structural steel is high risk work,
involving the operation of a variety of plant and
the use of certain skills. Those workers operating
cranes and other particular plant must have the
appropriate licence before anyone can perform
high risk work (see Table 1).
Anyone who is being trained, in order to obtain a
licence, must be directly supervised if operating
the relevant equipment or carrying out specific
works without a licence, to ensure that the work
is carried out safely.
The arrangements for issuing licences to
operators of industrial equipment are set out in
the OHS Regulations2007.
Industry standard / Safe erection of structural steel for buildings
2.
Overview
Table 1: Licences required for high risk work used in steel erection
Licence code
High risk work
LF
Forklift truck operation
DG
Dogging
A licence is required if:
there is a need to apply slinging techniques that require judgement to be exercised
there is a need to direct a crane or hoist operator in the movement of a load when the
load is out of the operators view.
RB
Basic rigging
Work involving:
movement of plant and equipment
steel erection
particular hoists
placement of pre-cast concrete
safety nets and static lines
mast climbers
perimeter safety screens and shutters
cantilevered crane loading platforms.
RI
Intermediate rigging
In addition to the work associated with basic rigging, this work involves the rigging of:
cranes, conveyors, dredges and excavators
all hoists
tilt slabs
demolition
dual lifts.
RA
Advanced rigging
In addition to the work associated with intermediate rigging, this work involves:
the rigging of gin poles and sheerlegs
flying foxes and cableways
guyed derricks and structures
suspended scaffolds and fabricated hung scaffolds.
10
Industry standard / Safe erection of structural steel for buildings
WorkSafe Victoria
2.
Overview
CT
Tower crane operation
CN
Non-slewing mobile crane operation (greater than 3tonnes)
CV
Vehicle loading, crane operation (greater than 10metre tons; the operation of crane
trucks will usually be limited to the delivery of steel members to site)
C2
Slewing mobile crane operation (up to 20tonnes)
C6
Slewing mobile crane operation (up to 60tonnes)
C1
Slewing mobile crane operation (up to 100tonnes)
C0
Slewing mobile crane operation (over 100tonnes)
WP
Boom-type elevating work platform operation (boom length greater than 11metres)
2.5
Competency and training
In addition to the licences listed above, employers must also ensure that their employees
havecompleted:
construction induction training (such as a construction induction card or equivalent)
training in the use of plant that does not require a licence for high risk work to operate for
example, a boom-type elevating work platform (boom length 11metres or less), telehandler or
non-slewing mobile crane less than 3tonnes
a site-specific induction
training on how to work in accordance with the SWMS developed for the task
training on how to eliminate or control specific hazards and risks involved in the work which are not
covered by an SWMS, for example, manual handling and UV-protection.
Where relevant, training for harnessed-based work positioning and fall protection systems may also
berequired.
WorkSafe Victoria
Industry standard / Safe erection of structural steel for buildings
11
3.
3.1
Design stage
General
3.2
There are two separate phases of design in
structural steel erection:
i) Structural design
The first phase involves the structural design of
the building, for in-service condition, which is
carried out by the structural design engineer.
The structural steel design should be produced
according to AS 4100, Steel structures and AS
3828, Guidelines for the erection of building
steelwork, which detail how risks can be
eliminated or reduced in the design stage. Any
associated concrete design, such as building
foundations, should comply with AS 3600
Concrete Structures.
ii) Erection
The second phase, the design for erection, is for
the handling, transportation and erection of the
individual members and structure. It may be
produced independently of the structural design
of the building.
Ideally, planning for the safe erection of structural
steel work should be considered at the design
stage. Structural design engineers should
consider the safe working conditions for those
involved in the erection stage, and eliminate as
many of the hazards as possible at this stage.
Roles during the design stage
The structural design engineer is responsible for
the structural design of the building.
3.3 Managing risk at the
designstage
Failure to plan and design for safety, from the
outset, can result in unsafe practices onsite and
in structural instability during erection. Accidents
in the erection of structural steelwork are not
restricted to falls. They can also occur because of
structural instability during erection, and while
handling, lifting and transporting material.
The stability of the building should be checked by
the erection engineer at agreed times with the
builder during erection.
Special care should be taken in design and during
construction to guard against progressive
collapse. Progressive collapse means a
continuous sequence of failures initiated by the
local failure of one part of the structure.
Progressive collapse may be prevented by providing:
adequate structural strength and continuity of
the structure and its parts, or
temporary bracing, shoring or ties, or
alternative load paths that cause applied forces
to be safely transmitted through the structure
The failure of a single member should not lead to
the complete collapse of the structure. This is
12
Industry standard / Safe erection of structural steel for buildings
WorkSafe Victoria
3.
Design stage
particularly important where structural stability is provided by steel roof and wall bracing systems. In
addition, consideration should be given to the effects of abnormal loads on the building, such as gas
explosions or vehicle impacts.
As part of the structural design process the structural design engineer must provide sufficient
details to allow the shop detailer to prepare shop drawings and the erection engineer to prepare the
erection design
The shop drawings and erection design should be submitted to the structural design engineer for
review to ensure that they comply with the requirements of the structural design
Before the shop drawings are produced, the parties involved in the design, fabrication, transport
and erection process should liaise to plan the complete construction and erectionsequence.
The following table lists what hazards may arise if the design does not adequately provide for safety in
the erection of the structure. Methods for managing and controlling the risk of hazards are also provided.
Common
hazards
Risk
controls
The buildability of the design
Collapse of structure due to member failure from temporary loading
during erection
Members not designed for transportation
The structural design engineer is required to provide design drawings
which include:
date and issue number of the drawing
plans and elevations clearly indicating the structural framing and layout
structurally critical dimensions (unless supplied on the architectural drawings)
make provision for positive connections between members of the structure that
have been specified to resist imposed lateral and vertical force
the grade of steel members
reinforcement required for in-service loads and temporary conditions
levelling pad details
structural design criteria affecting construction
purlin and frame details
framing connection locations and required type approval
Consideration should be given to details such as:
site limitations
local street access
delivery sequence
transport requirements
overhead obstructions.
These aspects can have a significant effect on the size of steel members and on
the erection process.
WorkSafe Victoria
Industry standard / Safe erection of structural steel for buildings
13
4.
4.1
Fabrication
stage
General
In consultation with the erection engineer, the
shop detailer produces the shop drawings, and
the fabricator works from these drawings to
produce the steel members.
The structural design engineer should ensure that
the shop drawings comply with the structural
design. The drawings are reviewed by the
structural design engineer before fabrication of
the steel members.
14
4.2 Roles during the
fabrication stage
The fabricator is responsible for the accurate
detailing and fabrication of the steelwork to
ensure members fit together correctly. Detailing
should include the ease of making connections
on site.
Industry standard / Safe erection of structural steel for buildings
WorkSafe Victoria
4.
Fabrication stage
4.3 Managing risk at the fabrication stage
Common
hazards
Risk
controls
WorkSafe Victoria
Incomplete or inaccurate shop drawings
Collapse of structure due to element failure
Members not clearly marked or identifiable
Weld failure due to poor quality or lack of testing
Incomplete fabrication (missing components)
Fabrication errors (angles, etc).
The fabricator must:
ensure strength of members by using grades of steel which are in accordance
with the relevant Australian standards
ensure shop drawings comply with structural design drawings and include the
following information:
the date and issue number
the project location
the structural design criteria affecting construction
plans and elevations indicating the structural framing, layout and orientation
clear identification and numbering of members
structurally critical dimensions
where appropriate, the tolerance limits on the element
the specifications and location of bracing or temporary supports
the requirements and locations for framing connections
the requirement for concrete foundations and base connections
the requirements for lifting and location of any lifting points
rigging details (for components that cannot be conventionally slung)
ensure components are manufactured in accordance with design specifications
ensure weld tests as per requirements
design approval by the structural design engineer.
Industry standard / Safe erection of structural steel for buildings
15
5.
5.1
Transportation
stage
General
Workers can be exposed to the risk of injury
when loading, transporting and unloading steel
from transport vehicles. Delivery of steel onto the
site requires co-operation between the fabricator,
builder, transporter and erector so that the steel is
delivered in a timely and efficient manner, and
that it does not overload the delivery area or the
construction zone.
5.2 Roles during the
transportation stage
The transporter should have planned the routes
and obtained all necessary permits and
authorisation for oversize or wide loads,
restricted routes, etc.
5.3
The builder should also provide a safe and
adequate unloading and lay-down area on the site
and ensure that the transporter has detailed
instructions on how to enter the site.
For information on the restraint of steel loads for
safety during transportation, see the VicRoads
publication A Guide to Restraining Steel.
For information on traffic management see the
VicRoads Code of Practice for Worksite Safety
Traffic Management and AS 1742.3, Manual of
uniform traffic control devices, Part 3: Traffic
control devices for works on roads.
Managing risk at the transportation stage
Common
hazards
16
The transporter should be familiar with the
builders traffic management plan that includes,
where necessary, traffic controllers, barricades
and road closure permits to allow unimpeded
access to the site.
Steel falling from slung loads while unloading
Steel falling because the vehicle load is unstable or becomes
unstable during unloading
Vehicle becoming unstable
Vehicle collapsing into a hole (if the site isnt adequately compacted)
Lack of set-up space
Lack of traffic management plan
Access/egress: steep grade and short pitch
Vehicle collision
Worker falling from vehicle during loading and unloading.
Industry standard / Safe erection of structural steel for buildings
WorkSafe Victoria
5.
Risk
controls
Transportation stage
Before loading vehicle
The Fabricator should check that:
the sequence of loading is agreed between the fabricator and the builder
each member is clearly marked (together with its mass where it is over
1.5tonnes) before loading.
The Transporter should check that:
trucks have restraining spikes in place
steel is supported and secured, so that there is no uncontrolled movement
ofthesteel until it is ready to lift
sufficient hardwood bearers, or equivalent, have been provided for loading.
The Builder should check that:
the sequence of loading is agreed between the builder and the erector
a crane of the required type and capacity is at the site
the area for unloading is firm and level and checked for load capacity and
whereapplicable or necessary, ground computations
there is an adequate set-up area
there is a traffic management plan
the grade and pitch of access/egress is suitable and safe for the vehicles
andtheir loads.
When loading the vehicle
The Transporter should check that:
the vehicle and load is stable and load will remain stable during unloading.
On vehicles arrival at site
The Transporter should check that:
securing chains or straps are not removed until restraining spikes in place
the steel has not shifted into a dangerous position
the vehicle is positioned as directed by the erector and stabilised before the
steelrestraints are released
if the unloading sequence can lead to the instability of loads, the steel is
individually restrained and the loading configuration checked so that
unloadingdoes not result in the load or the vehicle becoming unstable
the vehicle is not moved without the steel being properly secured.
The Erector should check that:
loads are lifted in a level manner
loads are not lifted vertically or at a slope
loads are sufficiently secured to prevent inside lengths from falling out if the
bundle is at an angle
there is fall protection for workers and doggers on the truck.
WorkSafe Victoria
Industry standard / Safe erection of structural steel for buildings
17
6.
6.1
Erection stage
General
Safe erection of structural steel work depends on
proper and timely planning. All personnel should
be aware that erection of any structural steel is
potentially hazardous and that planning must
control any risk from these hazards.
6.2
Roles in the erection stage
6.2.1
Builder
The builder has overall management and control
of the building site and should ensure that:
the building construction is in accordance with
the project schedule
a traffic management plan is developed and
implemented (which includes safe access /
egress points and delivery areas)
a marking plan has been submitted
a delivery schedule submitted by the fabricator
is agreed upon
the activities of all contractors are being
coordinated and supervised
the ground surface or supporting structure is
suitable for plant (such as EWP, mobile
scaffolds and cranes) to operate safely
holding-down bolts, cast in concrete footing,
pedestals or slabs, are within tolerance
shop drawings (prepared by the shop detailer)
18
have a signed statement from the structural
design engineer that the shop drawings comply
with the structural design
the erection engineer provides clear advice on
how to achieve stability for each stage of the
structures erection
weather conditions are continually monitored,
particularly potentially hazardous situations like
high or strong winds and electrical storms, and
that a contingency plan has been developed for
severe weather
at least one of the erection crew or another
person who remains on site throughout
erection should hold a current qualification as a
Level 2 first aider
a safe work method statement has been
developed and work is undertaken in
accordance with the SWMS.
These tasks are also contained in a checklist.
SeeAppendix 2 Builders checklist.
The builder must also provide to contractors a
detailed site plan, which includes information on:
site location
access points
structure location
suitable ground bearing locations
for crane operations
uploading areas
storage areas.
Industry standard / Safe erection of structural steel for buildings
WorkSafe Victoria
6.
Erection stage
The builder should ensure that the accuracy of
each contractors work is within the tolerance of
the level or position nominated by the erection
engineer or relevant standard. Any modifications
to the building layout also need to be checked by
the builder for approval by the erection engineer.
As principal contractor, the builder prepares the
Health and Safety Coordination Plan according to
section 5.1.16 of the Occupational Health and
Safety Regulations 2007 see handbook Working
safely in the general construction industry.
6.2.2
verifying the adequacy of the base
connections (steel to foundations)
checking stability under construction
load conditions
capacity to withstand accidental vehicle impact.
The fabricator can also provide guidance in
thisarea.
6.2.3
Erector
The erector ensures that:
Erection engineer
the structure is erected in accordance with the
sequential erection procedure
The erection engineer approves the sequential
an SWMS is developed in consultation with the
erection procedure which includes how the
erection crew (see the sample SWMS in
structure is stabilised at each stage and signs any
Appendix1)
modifications, and is required to provide guidance
work proceeds in accordance with the SWMS
to the builder and erection crew on
confirms with the builders representative that
mattersincluding:
the ground or supporting surface is suitable for
joints and additional erection cleats
mobile plant to safely operate
structural design criteria affecting construction pre-assembly of members and the movement
temporary bracing
and location of heavy members are considered
prior to installation
lifting points
weather conditions are continually monitored,
loads and conditions likely to be experienced
and in particular, potentially hazardous
during the lifting and erection
situations like high or strong winds and
any wind load limitations on the integrity of the
electrical storms for which a contingency plan
structure as it is being erected according to the
should be developed and implemented
signed-off sequential erection procedure
asrequired.
wind load on the braced members.
These tasks are also contained in a checklist.
joint positions (as they affect erection sequences) SeeAppendix3 Erectors checklist.
accessibility of connections
6.2.4 Erection crew
fixings for working platforms, hand rails etc
preferred method of connecting steel members
An erection crew consists of:
preferred type and number of cranes to erect
an experienced structural steel supervisor
members of particular size and shape, and for
vertical and horizontal bracing requirements
riggers
instructions on how to stabilise the structure at doggers
each stage of erection which involves:
crane operator.
WorkSafe Victoria
Industry standard / Safe erection of structural steel for buildings
19
6.
Erection stage
The erection supervisor is responsible for
directing and coordinating the agreed sequential
erection procedure (see 6.3.1). They should hold a
high risk work licence for rigging in either the
Intermediate Rigging or Advanced Rigging
classes (class codes RI or RA) as appropriate
(see Table 1).
the erection sequence
the stability requirements of the structure at all
stages during erection
requirements for working at height
overhead obstructions, including overhead
power lines
weather restrictions
The crane operator must hold a licence to perform
high risk work appropriate for the type of crane and, specialty bolting or site welding requirements,
included on the marking plan.
in the case of a slewing mobile crane, the cranes
capacity (WLL) (or be under the direct supervision
6.3.2 Marking plan
of the holder of the appropriate licence).
The size and make-up of the remainder of the
erection crew will vary depending upon the nature
of the site and the particular circumstances. All
members of the crew must hold the basic rigging
licence (class code RB) as a minimum. Anyone
who is being trained, in order to obtain a licence,
must be directly supervised to ensure that the
work is carried out safely.
6.3 Documentation in the
erection stage
6.3.1
Sequential erection procedure
The erector, in consultation with the builder,
erection engineer and other parties involved in
the work, needs to plan the process for lifting and
erecting individual members.
The process is set out in the sequential erection
procedure which is used by the erection crew.
Theerector is responsible for ensuring that a
sequential erection procedure is in place and that
it has been approved by the erection engineer.
The sequential erection procedure includes:
20
site limitations
member sizes
access for positioning and lifting of members
crane size, mobility and access, and use of
other large plant
The marking plan shows the erector where each
member will be placed on the site. It is prepared
by the shop detailer for the fabricator, and
approved by the structural design engineer.
The marking plan includes:
location of each element
configuration of braces and any temporary
bracing/supports
clear markings to identify each member.
6.3.3
Safe work method statement
Any erection of structural steel will require a site
specific SWMS (see Appendix 1). The SWMS must
list the high risk construction work, as a minimum,
and describe how the risks are to be controlled.
The SWMS is prepared by the erector in
consultation with the erection crew and reviewed
by the builder.
High risk construction work in steel erection
mayinclude:
a risk of falling more than two metres
structural alterations that may require
temporary support to prevent collapse
working near live power lines
tilt-up or precast concrete (which may be part
of the project).
Industry standard / Safe erection of structural steel for buildings
WorkSafe Victoria
6.
Erection stage
working on or adjacent to roadways or railways used by road or rail traffic
any movement of powered mobile plant, for example, the use of EWPs.
This particular information must be identified and provided by the builder to the person preparing the
SWMS. The SWMS should also identify any other hazards associated with the work and state the
measures necessary to control them. For more information, see handbook Working safely in the
general construction industry A handbook for the construction regulations.
6.4 Managing risk at the erection stage
The key risks involved in steel erection, and the controls for each of these are outlined below.
Common
hazards
1 Falling from a height while rigging
2 Falling objects
3 Collapse of the structure during construction
4 Being struck by plant
5 Plant contacting underground or overhead utility services
6 Being struck by objects such as steel members
1 The erector should reduce the need for work at height by:
Risk
controls
constructing as much of the steelwork as possible (such as modules or frames)
at ground level, or from erected floor slabs or decks in the structure, and
where reasonably practicable, releasing the lifting sling or device from ground
level by the use of long slings, remote release shackles or other suitable devices.
The erector should prevent the risk of a fall of a person working at a height by
using in order of effectiveness:
passive fall prevention devices, for example, work platforms and EWPs
work-positioning systems such as travel-restraint systems and industrial
rope-access systems, and/or
fall arrest systems such as catch platforms and safety-harness systems.
For further information, see the Compliance Code for the Prevention of Falls in
General Construction.
2 The erector should reduce the risk from falling objects by:
restricting access when there is overhead work by establishing, where
practicable, exclusion zones
preventing, where practicable, loads being lifted or transported over people
oramenities
ensuring only rigger/dogman slings loads and, where appropriate, fix tag lines
using lifting beams to position members where necessary to ensure the stability
of the member
WorkSafe Victoria
Industry standard / Safe erection of structural steel for buildings
21
6.
Risk
controls
Erection stage
considering perimeter screens, guardrails with integral toe-boards and wire
mesh, debris nets, cantilever work platforms, scaffolding sheathed with protective
material and/or lanyards to secure tools and equipment
using materials boxes which are fully sheeted to enclose the load
ensuring safety helmets are worn at all times.
3 a) Before erection, to avoid collapse, the erector should:
ensure a sequential erection procedure is prepared, which has been approved by
the erection engineer and is consistent with the marking plans
ensure that an experienced steel erection supervisor is present at all times to
oversee the implementation of the sequential erection procedure
ensure an adequate exclusion zone to prevent risk to other people not involved in
the erection
only start the erection of a member or sub-assembly when equipment to ensure
the structures stability is available and being used
ensure temporary guys or bracing are securely anchored
place adequate visual barriers between guys and plant/vehicle movement areas.
b) During erection, to avoid collapse, the erection supervisor must:
verify the stability of the structure in accordance with the erection engineers
specifications:
at the end of each work day
when fastenings may be incomplete
during strong winds or when strong winds are forecast
seek approval from the builder (or erection engineer where appropriate) to cease
work at unscheduled points where the structure has not been completed to the
specifications of the erection engineers design
Obtain, from the builder, the erection engineers written approval before loads are
placed onto the structure
where possible, start erection in a nominated braced bay (if this is not possible,
make sure that the erection engineer is involved in developing an alternative
site-specific sequential erection procedure)
check the fittings for the support of columns during erection, to ensure adequate
structural capacity for the erection conditions
make sure that all beams are secured before releasing the slings
make sure that all bolted connections are effective to ensure the stability of the
steel structure.
4 T
o avoid being struck by plant and before the use of a crane or any other
powered mobile equipment, the erector should consider:
crane selection, access and siting in accordance with AS 2550 Parts 1, 4 and 5
(cranes, hoists and winches)
protection of the public
22
Industry standard / Safe erection of structural steel for buildings
WorkSafe Victoria
6.
Risk
controls
Erection stage
the location of any excavations or underground services that may affect
a crane load
the proximity of overhead power lines
the capacity of the ground or supporting surface to bear the load
check the type and amount of packing required under the cranes outriggers to
support the proposed loads
written procedures for setting up and dismantling of the crane and the
liftingmethod
the composition of the rigging crew suits the job
procedures for visual and audible signals between the crane operator and the
erection crew
ground support conditions
selection of lifting gear
emergency procedures
prevailing or forecast weather conditions
the need to avoid lifting loads over people.
The use, of two or more cranes to move and position loads, is hazardous and
should be avoided if a single crane is capable of doing the job. Where it is
necessary to use two cranes to dual lift members, the following controls are to be
implemented:
the weight of the load and its centre of gravity as well as the weight of the lifting
gear must be carefully calculated.
cranes of similar characteristics should be selected.
the position of each crane should minimise movement and slewing.
the lifting capacity of each crane must be 20% greater than the share of
theload.
For further advice on multiple crane lifting, see A Guide toRigging, chapter18.
5 a) Where plant is working near overhead lines, the erector should:
identify all powerlines services before permitting any crane or other mobile
plant on site
check that material and plant is moved or operated outside the No Go Zone of
3000mm from an overhead electrical cable on a pole or 8000mm if the
electricity cable is on a tower line (If erecting scaffolding, the No Go Zone
during this process is 4.6m distant and 5m below from the nearest power line)
if work or plant is able to encroach on this clearance, the erector must obtain
permission from the electricity company or develop a SWMS and work in
accordance with it.
Note: Tiger battens do not protect from risk of electrocution or electric shock.
Theyprovide a visual warning only.
WorkSafe Victoria
Industry standard / Safe erection of structural steel for buildings
23
6.
Erection stage
Risk
controls
6.5
b) When plant is working near underground services, the erector should:
ensure that, unless permission has been obtained from the utility company, work
is not carried out closer to the services than:
3metres in the case of an underground asset registered under the Pipelines
Act or an electricity cable with an in-service voltage greater than 66kV, or
in the case of other services, 500mm for plant and equipment and 300mm
for individuals.
Other hazards
Consideration should be given to other hazards associated with steel work. Any risks posed by these
hazards must be controlled. They mayinclude:
24
noise
manual handling
hot work
exposure to hazardous substances
dangerous goods
electrical work
sun (UV) exposure.
Industry standard / Safe erection of structural steel for buildings
WorkSafe Victoria
Appendix 1
Note: This is a sample only. The purpose of a legislatively required SWMS is to include what has been
described in the document proper regarding hazards and risk controls.
Safe Work Method Statement Structural steel erection (sample)
This SWMS is a site-specific statement that must be prepared before any structural steel erection has begun.
Work must be performed only in accordance with this SWMS.
Erection supervisor:
(RI licence) responsible
for ensuring compliance
with thisSWMS
Date:
High-risk job:
Location:
Company:
Think about the worksite and each stage of the project, including preparation and clean-up.
What are the
tasks involved?
What are the hazards
and risks?
How will hazards and risks be controlled? (describe the
control measures and how they will be used)
1. Site planning
Workers unfamiliar
with the site and
notinducted
UV
Each worker must have a:
site induction
CI card and correct licence for high risk work
long sleeved shirt, safety boots, hard hat, riggers gloves,
safety glasses and ear plugs.
Crew unfamiliar
withsequential
erectionprocedure
Each worker must be briefed on the procedure and
theirduties.
Slips, trips, falls
Other workers in
thevicinity
Collapse of work
area/hard standing
Electric shock from
power lines
Inspect site and clear area of any obstructing material
ordebris
2. P
repare
workarea
WorkSafe Victoria
Isolate work zone; erect barricading and signage
Stabilise/compact ground where required
Identify all electrical lines in work area. Confirm electrical
current is disconnected to those lines.
Industry standard / Safe erection of structural steel for buildings
25
Appendix 1
Safe Work Method Statement Structural steel erection (sample)
What are the
tasks involved?
What are the hazards
and risks?
How will hazards and risks be controlled? (describe the
control measures and how they will be used)
3. Erecting stage
Weather makes
erection hazardous
Supervisor to check weather forecast and monitor on a
continual basis and have a contingency plan in place in
the event of extreme weather.
Mobile crane/EWP
injury through
unsafe use
overloading /
uncontrolled loads
Operator must:
have a current licence (or be a supervised trainee)
perform a daily check of crane and complete a log
check ground for stability
check overhead for electrical lines
wear and attach a safety harness if operating a boom lift
use crane only within known wind tolerances
not operate the crane outside its load charts
know the weight of each lift
use tag lines where appropriate
(minimum 16mm diameter).
Incorrect or poorly
maintained slings
Riggers / doggers must:
be licenced
only sling load with Grade80 lifting chain
check that lifting chains are inspected and tagged
not stand under the load.
Not following the
sequential erection
procedure
The sequential erection procedures must be followed
unless authorisation has been approved by both the
builder and the erection engineer
Steel frame to be inspected daily for stability and
resultsdocumented
Electrical hazards
Do not use electrical equipment that does not have a
current tag
Keep leads elevated or adequately protected and away
from sharp edges and water hazards
Check that power supply is RCD protected and undamaged.
Injury from releasing
load too soon
The riggers and doggers are the only people permitted to
release the load
Load is only to be released when adequately fixed
andsupported.
Loading incomplete
bays with panels
androofing
Check that the erection engineer has approved
placementload
Check that the placement load is within constraints
Check that columns have been grouted prior to loading.
26
Industry standard / Safe erection of structural steel for buildings
WorkSafe Victoria
Appendix 1
Safe Work Method Statement Structural steel erection (sample)
What are the
tasks involved?
What are the hazards
and risks?
How will hazards and risks be controlled? (describe the
control measures and how they will be used)
3. Erecting stage
(continued)
Unstable structure
Builder or builders representative and erection supervisor
to inspect the frame to ensure it meets the erection
engineers specifications
Check that bolts have been tensioned to specified torques.
4. End of shift
Unsecured site
Secure all plant and equipment
Inspect site and clean up area.
Please ensure you have completed this SWMS correctly by checking the following.
I have completed the form with the following information:
I have discussed with relevant employees, contractors and HSRs what work will be high risk, the tasks
involved, and associated hazards, risks and controls.
I have listed, in the first column What are the tasks involved? the main stages for the tasks involved.
I have listed, in the second column What are the hazards and risks? the hazards and risks for each work
task under the relevant stage of construction.
I have listed, in the third column How will the hazards and risks be controlled? control measures for the
hazards and risks, based on the hierarchy of control levels1 to 4 (listed below). I have chosen a control
measure (and how it is to be used) that is as close to level1 as is reasonably practicable.
Control levels 1 to 4:
1. Eliminate risk to health or safety associated with construction work.
2. Reduce risk to health or safety by any one or any combination of the following:
substituting a new activity, procedure, plant, process or substance
isolating people from the hazard, such as barricading, fencing or guardrailing, or
using engineering controls, such as mechanical or electrical devices.
3. Use administrative controls, such as changing the way the work is done.
4. Provide appropriate personal protective equipment (PPE).
The crew has been inducted to this SWMS, and briefed to stop work immediately if the SWMS
is not being followed.
I will monitor the work and, if controls are not adequate, I will stop the work, review the SWMS,
adjust it as required and re-brief the team.
I will retain this SWMS, and its amended form if applicable, for the duration of the project.
WorkSafe Victoria
Industry standard / Safe erection of structural steel for buildings
27
Appendix 2
Builders checklist
Builders checklist Structural steel erection
Project:
Date:
What are the tasks involved?
n/a Comment
1. Marking plans: Shop detailer has provided a marking plan.
2. Delivery schedule: fabricator has provided, and has
beenagreed.
3. Ground or supporting surface: suitable for plant
(cranes, EWPs) to operate safely.
4. Shop drawings: Fabricator has provided. Structural
design engineer has reviewed and approved. Erection
engineer has certified.
5. Sequential erection procedure: Erection engineer has
provided a certified sequential erection procedure which is
understood and agreed.
6. Supports tolerance: Holding-down bolts, cast-in concrete
footing and pedestals or slabs are within tolerance.
7. Traffic management plan: implemented (which includes
safe access, egress and delivery areas).
8. Health and safety coordination plan: is current and
available for inspection by all workers.
9. Weather conditions: are monitored for potentially
hazardous conditions such as strong winds and/or electrical
storms, and that a contingency plan can be activated
asrequired.
Erectors representative:
Signature:
28
Industry standard / Safe erection of structural steel for buildings
WorkSafe Victoria
Appendix 3
Erectors checklist
Erectors checklist Structural steel erection
Project:
Date:
What are the tasks involved?
n/a Comment
1. Sequential erection procedure: Erection engineer has
provided a sequential erection procedure which is
understood and agreed.
2. Sequential erection procedure: Erection crew has been
inducted into sequential erection procedure.
3. SWMS: Erection crew has been inducted into the safe
work method statement.
4. Pre-planning: Confirms with the builders representative
that the ground or supporting surface is suitable for mobile
plant to safely operate.
5. Pre-planning: Pre-assembly of members, and the
movement and location of heavy members have been
considered before installation.
6. Sequential erection: Structure has been erected in
accordance with the sequential erection procedure.
7. SWMS: Work has progressed in accordance with the safe
work method statement.
8. Weather conditions: Are monitored for potentially
hazardous conditions such as strong winds and / or electrical
storms and that a contingency plan can be activated
asrequired.
Erectors representative:
Signature:
WorkSafe Victoria
Industry standard / Safe erection of structural steel for buildings
29
Definition
of terms
General definitions
AS
Australian standard (produced by Standards Australia)
AS/NZS
Australian Standard/New Zealand Standard (a joint standard)
BOM
Bureau of Meteorology
Builder The company or person responsible for the construction of the building
and who has control of the building site. The builder may also be the client
or a company or person responsible to the client. (The builder may also be
the principal contractor.)
CI card Construction Induction card. A person carrying out construction work in
Victoria must have a Construction Induction Card, or recognised
equivalent, which provides evidence that they have received construction
induction training.
Client The owner of the building or the company or person responsible for
developing the building.
Structural design engineer An experienced structural steel engineer who is responsible for the
engineering design of the building. Should be a person eligible for
membership of the Institution of Engineers Australia, be a registered
building practitioner and be competent to practise in the structural
engineering field. Where necessary the structural design engineer will
need to consult with other persons who have specific expertise and
experience. The structural design engineer will usually be responsible to
the client.
Erection supervisor An experienced person with an Intermediate or Advanced Rigging licence
who is appointed by the erector to supervise the erection of the
structuralsteel.
Erector The company or person responsible for erecting the steel work. The
erector may be responsible either to the builder, fabricator or client.
Fabricator
30
The company or person responsible for manufacturing the steel work.
Industry standard / Safe erection of structural steel for buildings
WorkSafe Victoria
Definition of terms
High risk work Any work set out in schedule 3 of the OHS regulations which requires a
WorkSafe licence to perform this work.
High risk
High risk construction work is types of construction work listed in the
construction work construction part of the OHS regulations (part 5.1.3). Before any of this
work commences, a SWMS must be prepared if anyones health or safety
is at risk because of this work.
HSR
Health and safety representative
OHS
Occupational health and safety
OHS Act
Occupational Health and Safety Act 2004
OHS regulations
Occupational Health and Safety Regulations 2007
Erection engineer An experienced structural steel engineer who is responsible for the
engineering design for the erection of the building. The erection engineer
should be a person eligible for membership of the Institution of Engineers
Australia, be a registered building practitioner and be competent to
practise in the structural engineering field. Where necessary the erection
engineer will need to consult with other persons who have specific
expertise and experience. The erection engineer will usually be
responsible to the builder, the fabricator or the erector, or may also be the
structural design engineer.
SWMS
Safe work method statement, which:
lists the type of high risk construction work being done
states the health and safety hazards and risks arising from that work
describes how the risks will be controlled
describes how the risk control measures will be put in place.
Technical definitions
Dogging The application of slinging techniques, including the selection or
inspection of lifting gear, or the directing of a crane or hoist operator in
the movement of a load when the load is out of the operators view.
EWP Elevating work platform. A telescoping device, scissor device or
articulating device used to support a working platform.
Flying fox An arrangement where a rope is suspended between two tower
structures and which supports a carriage (or fox) from which a load may
be raised, traversed or lowered.
Gin pole A guyed derrick without a pivoted strut-boom. It can raise and lower a load
and a limited amount of slewing can be achieved by adjusting the guys.
Girt
WorkSafe Victoria
horizontal structural member in a wall of a steel structure which
A
supports the wall cladding sheets.
Industry standard / Safe erection of structural steel for buildings
31
Definition of terms
Guy A tensioned rope fixed at one end to a mast, tower or structure and
anchored some distance from the base to stabilise the structure.
PPE
Personal protective equipment
Purlin A longitudinal member spanning between roof trusses or beams and to
which roofing sheets are fixed.
RCD
Residual current device
Rigging The use of mechanical load shifting equipment and associated gear to
move, place or secure a load including plant, equipment or members of a
building or structure and to ensure the stability of those members, and for
the setting up and dismantling of cranes and hoists, other than the setting
up of a crane or hoist which only requires the positioning of integral
outriggers or stabilisers.
Shop detailer
Engaged by the fabricator to develop the shop drawings.
Shop drawing
A detailed drawing of an element used in the construction process.
Slinging techniques
( In relation to dogging) refer to techniques that require judgement to be
exercised in relation to the suitability and condition of lifting gear, and the
method of slinging, by consideration of the nature of the load, its mass
and centre of gravity.
Tagline A fibre rope attached to a suspended load to control the load
duringlifting.
Tower crane
32
A boom or jib crane mounted on a tower structure.
Industry standard / Safe erection of structural steel for buildings
WorkSafe Victoria
References
Australian standards
AS/NZS 1576.1:1996, Scaffolding General requirements
AS/NZS 1891.1:2007, Industrial fall-arrest systems and services Harness and ancillary equipment
AS/NZS 1892.1:1996, Portable ladders Metal
AS 2550.1, Cranes, hoists and winches Safe use General requirements
AS 2550.4, Cranes, hoists and winches Safe use Tower cranes
AS 2550.5:2002, Cranes, hoists and winches Safe use Mobile cranes
AS 2550.10, Cranes, hoists and winches Safe use Mobile elevating work platforms
AS 3600:2001, Concrete structures
AS 3828:1998, Guidelines for the erection of building steelwork
AS 4100:1998, Steel structures
AS/NZS 4576:1995, Guidelines for scaffolding
AS/NZS 4994, Roof edge protection equipment
AS/NZS 4389:1996, Safety mesh
AS/NZS 4360:2004, Risk management
AS/NZS 1554.1:2004/Amdt 1:2005 , Structural steel welding
Copies of standards can be obtained from Standards Australia at: 1300 654 646
or: standards.com.au
Legislation
Occupational Health and Safety Act 2004
Occupational Health and Safety Regulations 2007
View the legislation at: legislation.vic.gov.au
Acts and regulations are available from Information Victoria at: 1300 366 356
or: bookshop.vic.gov.au.
WorkSafe Victoria
Industry standard / Safe erection of structural steel for buildings
33
References
WorkSafe publications
Compliance Code for the Prevention of Falls in General Construction
Working safely in the general construction Industry: A handbook for the construction regulations
A guide to safety in the metal fabrication industry
Prevention of falls in the transport of steel
Employee Representation
Framework for Undertaking Work near Overhead and Underground Assets:
A guide to the No Go Zones
A Guide to Rigging, available from WorkCover NSW: workcover.nsw.gov.au
Energy Safe Victoria
Phone: (03) 9203 9700, esv.vic.gov.au
Other publications
A Guide to Restraining Steel (VicRoads, December 1998)
Code of Practice for Worksite Safety Traffic Management (VicRoads, December 2004)
Other information
Dial Before you Dig
Phone: 1100, dialbeforeyoudig.com.au
34
Industry standard / Safe erection of structural steel for buildings
WorkSafe Victoria
Further information
Worksafe Advisory Service
Phone
Freecall
Email
03 9641 1444
1800 136 089
[email protected]
Publications
Phone
Freecall
Email
Website
03 9641 1444
1800 136 089
[email protected]
worksafe.vic.gov.au
Worksafe Victoria
Head Office
222 Exhibition Street
Melbourne 3000
03 9641 1555
Local Offices
Ballarat
Bendigo
Dandenong
Geelong
Bourke Street
Mildura
Mulgrave
Preston
Shepparton
Traralgon
Wangaratta
Warrnambool
VWA1226/01/05.09
03 5338 4444
03 5443 8866
03 8792 9000
03 5226 1200
03 9941 0558
03 5021 4001
03 9565 9444
03 9485 4555
03 5831 8260
03 5174 8900
03 5721 8588
03 5564 3200