JOB SAFETY ANALYSIS WORK SHEET
ELECTRICIAN
ACTIVITY
HAZARDS
RISK CONTROL
MEASURES
RESPONSIBLE
Wiring repairs
Electrocution
Ensure complete lock out
tag out isolation before
commencing job. Provide
sign at isolation point to
advise of lock out.
Contractor
Trenching
Back injuries
Warm up prior to starting.
Do not lift objects over 16kg
per person. Use trolley to
move heavy objects. Wear
appropriate Personal
Protective Equipment.
Contractor
Trenching
Cave in
Ensure trench is constructed
in accordance with
Regulations and that
appropriate shoring is in
place where required. Have
at least one person on
standby when working in
trench.
Contractor
General/Clean up
Cuts / scratches
Wear appropriate personal
protective clothing
Contractor
General Labour
Working at height.
Electrical hazards
Do not use ladder over 2m
high. Use cherry picker or
scaffold. Establish perimeter
around area that is no-go
area. Ensure all tools are
appropriately guarded and
electrical appliances are
protected by means of a
residual current device.
Ensure all extension leads
are in a safe condition with
plugs and connections.
Ensure there are no
electrical cables in the
vicinity of area.
Contractor
Clean up
Insect bites / Broken
glass / syringes / spiders
Wear appropriate foot and
hand protection. Dispose of
material in an appropriate
manner.
Contractor
Using power tools
Noise /Vibration /Dust /
Electrical hazards.
Wear appropriate personal
protective equipment.
Ensure all tools are
appropriately guarded and
electrical appliances are
protected by means of a
residual current device.
Ensure all extension leads
are in a safe condition with
plugs and connections.
Contractor
ACTIVITY
HAZARDS
RISK CONTROL
MEASURES
RESPONSIBLE
Working outside
Sunburn
Sunhat / glasses /
sunscreen / protective
clothing.
Contractor
Using hand tools
Cuts / tears sprains etc.
Use tools in a manner that
will not cause jamming or
seizing. Wear appropriate
PPE.
Contractor
NOTE: It is recommended that every Contractor complete and sign the Solutions in
Engineering Contractors Safe Working Agreement
I have read the JSA Work Sheet and agree to comply with the guidelines as set out in the above
mentioned documentation.
Contractor:..
Signature:.. Date:...