Status Report
Project Name: ABC
Create and populate a Business Objects
Project Description universe to enable reporting from the ABC
transaction database. Use BO to create 11 ABC
reports.
Project Team Section
Project Lead: Bill Knecht, Anna Karneh
Customer: Linda Kingsley
Schedule Section
Phase 1
Lifecycle Description Plan Start Actual Plan End Actual Plan Effort Actual
Date Start Date Date End Date Hours Effort Hours
Planning/Analysis 10/29 11/14 11/16 11/25 64 135
Design Phase 11/19 11/26 11/30 1/11 114 197
Code & Unit Test 11/26 12/17 3/19 2/28 430 570
System Test 12/5 12/26 3/15 3/22
Acceptance Test 12/17 1/2 3/22 3/26 121 43.5
Implementation 12/24 3/29 45 0
Project 10/29 11/14 6/30 3/28 213.5
Management
Quality Assurance 69.25
Technical Platform 11/19 1/25 122 0
ABC Status Report Page 1 As of: 03/31/02
Budget Section
Labor Category Total Labor Rate Total Total Spent Remaining
Hours Estimated Balance
Cost
Consultant I (Off-Site) $69.90
Consultant I (On-Site) $66.28
Consultant II (Off-site) 872 $85.10 $74,207.20 $42,506.75 $31,699.23
Consultant II (On-site) $81.44
Sr. Consultant I (Off-site) 635 $100.31 $63,696.85 $39,322.19 $24,375.74
Sr. Consultant I (On-site) $96.71
Sr. Consultant II (Off-Site) $106.83
Sr. Consultant II (On-Site) $103.24
Principal Consultant I (Off-site) 272 $126.37 $34,372.64 $15,575.19 $18,797.64
Principal Consultant I (On-site) $122.72
Principal Consultant II (Off-site) 298 $150.28 $44,783.44 $32,084.14 $12,698.41
Principal Consultant II (On-site) $146.62
Labor Totals 2,077 ----- $217,060.13 $129,488.85 $87,571.28
ABC Status Report Page 2 As of: 03/31/02
Project Section
Accomplishments through 3-31-02
Accomplishment 1: Fixed problems with some of the Business Objects reports.
Made other changes requested by clients.
Planned Accomplishments for next week(s)
Planned Accomplishment 1 None. Project has been ended.
Issues/Risks & Schedule Exceptions
Issue/Risk 1: The ABC team has decided to replace Business Objects
with Cognos as the reporting tool.
Impact: JMCS was instructed to stop work on the project. None of the
Business Objects reports will be placed into production.
Resolution: None. Project is over.
Expected
Resolution
Date:
Resolution
Date:
ABC Status Report Page 3 As of: 03/31/02