0% found this document useful (0 votes)
135 views1 page

Cost Drivers for Software Projects

The constraints a and b are historical cost parameters from past projects in three categories: organic, semidetached, and embedded. Table 1 shows the values of a and b for each project category. The document also provides cost ratings for various product, hardware, personnel, and project attributes that may influence project costs.

Uploaded by

Baswamy Cse
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
135 views1 page

Cost Drivers for Software Projects

The constraints a and b are historical cost parameters from past projects in three categories: organic, semidetached, and embedded. Table 1 shows the values of a and b for each project category. The document also provides cost ratings for various product, hardware, personnel, and project attributes that may influence project costs.

Uploaded by

Baswamy Cse
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

The constraints a and b are delivered from the historical data of the past projects in the

organization tabulated in Table 1.

Project Category a b c d
Organic 3.2 1.05 2.5 0.38
Semidetached 3.0 1.12 2.5 0.35
Embedded 2.8 1.20 2.5 0.32
Table – 1

Ratings

Cost drivers Very Extra


Low Nominal High Very high
low high

Product attributes
Software reliability (RELY) 0.75 0.88 1.00 1.15 1.40 -
Size of database (DATA) - 0.94 1.00 1.08 1.16 -
Product complexity (CPLX) 0.70 0.85 1.00 1.15 1.30 1.65
Hardware attributes
Run-time performance constraints - - 1.00 1.11 1.30 1.66
(TIME)
Memory storage constraints - - 1.00 1.06 1.21 1.56
(STORE)
Virtual machine volatility (VIRT) - 0.87 1.00 1.15 1.30 -
Required turnabout time (TURN) - 0.87 1.00 1.07 1.15 -
Personnel attributes
Analyst capability (ACAP) 1.46 1.19 1.00 0.86 0.71 -
Applications experience (AEXP) 1.29 1.13 1.00 0.91 0.82 -
Programmer capability (PCAP) 1.42 1.17 1.00 0.86 0.70 -
Virtual machine experience (VEXP) 1.21 1.10 1.00 0.90 - -
Programming language experience 1.14 1.07 1.00 0.95 - -
(LEXP)
Project attributes
Modern programming practices 1.24 1.10 1.00 0.91 0.82 -
(MODP)
Use of software tools (TOOL) 1.24 1.10 1.00 0.91 0.83 -
Development schedule (SCHED) 1.23 1.08 1.00 1.04 1.10 -