2019 Construction Project Schedule

The document outlines a project schedule showing the planned dates for rebar installation, formwork construction, and concrete pouring for the slabs, beams, columns, and shear walls on the 4th, 5th, and 6th floors of a building. Work will proceed floor by floor starting with the 4th floor between July 22 and August 2, then the 5th floor from August 3 to August 17, and finally the 6th floor from August 17 to August 31.

Uploaded by

scriba diver
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
47 views1 page

2019 Construction Project Schedule

The document outlines a project schedule showing the planned dates for rebar installation, formwork construction, and concrete pouring for the slabs, beams, columns, and shear walls on the 4th, 5th, and 6th floors of a building. Work will proceed floor by floor starting with the 4th floor between July 22 and August 2, then the 5th floor from August 3 to August 17, and finally the 6th floor from August 17 to August 31.

Uploaded by

scriba diver
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

PROJECT SCHEDULE

6th Floor SW and Column


Concreting August 27, 2019 August 31, 2019
Formwork August 26, 2019 August 30, 2019
Rebar August 23, 2019 August 27, 2019
6th Floor Slab and Beam
Concreting August 22, 2019 August 26, 2019
Rebar August 21, 2019 August 24, 2019
Formwork August 17, 2019 August 21, 2019
5th Floor SW and Column
Concreting August 13, 2019 August 17, 2019
Formwork August 12, 2019 August 16, 2019
Rebar August 9, 2019 August 13, 2019
5th Floor Slab and Beam
Concreting August 8, 2019 August 12, 2019
Rebar August 7, 2019 August 10, 2019
Formwork August 3, 2019 August 7, 2019
4th Floor SW and Column
Concreting July 30, 2019 August 2, 2019
Formwork July 29, 2019 August 1, 2019
Rebar July 27, 2019 July 30, 2019
4th Floor Slab and Beam
Concreting July 26, 2019 July 29, 2019
Rebar July 25, 2019 July 27, 2019
Formwork July 22, 2019 July 24, 2019
Zone 1 Zone 2