MSS Ref. No.
: OZ31317-ZL6001-SPE-MST-0048
PROJECT : ONE ZA’ABEEL
METHOD STATEMENT FOR INSTALLATION
Rev : 00
OF DX SPLIT SYSTEM, AC UNIT &
REFRIGERANT PIPE
Date : 04-11-2018
METHOD STATEMENT
METHOD STATEMENT
TITLE
FOR INSTALLATION OF DX SPLIT SYSTEM,
AC UNIT & REFRIGERANT PIPE
Rev Date Document Status Prepared By Reviewed by Approved by
00 04-11-2018 Submitted for Approval
[QA/QC Engineer] [QA/QC Manager] [Project Director]
CONTRACTOR: ALEC Engineering and Contracting LLC.
SUB - CONTRACTOR: SPECON LLC
Page 1 of 12
MSS Ref. No.: OZ31317-ZL6001-SPE-MST-0048
PROJECT : ONE ZA’ABEEL
METHOD STATEMENT FOR INSTALLATION Rev : 00
OF DX SPLIT SYSTEM, AC UNIT &
Date : 04-11-2018
REFRIGERANT PIPE
Page 2 of 12
CONTENT
1. INTRODUCTION ....................................................................................................................................... 4
2. SCOPE: ........................................................................................................................................................ 4
3. DEFINITIONS & ABBREVATIONS:........................................................................................................ 4
4. WORKING ACCESS: ................................................................................................................................. 5
5. LIGHTING: ................................................................................................................................................. 5
i. Safety Lighting: ........................................................................................................................................... 5
ii. Task Lighting: .............................................................................................................................................. 5
6. PLANT & EQUIPMENT: ........................................................................................................................... 5
i. General: ........................................................................................................................................................ 5
ii. Plant & Equipment Schedule: ...................................................................................................................... 5
iii. Personal Protective Equipment: ............................................................................................................... 6
iv. Power:....................................................................................................................................................... 6
v. Working Platforms: ...................................................................................................................................... 6
7. MATERIALS:.............................................................................................................................................. 7
8. SEQUENCE / METHOD OF WORK: ........................................................................................................ 7
9. PROGRAMME .......................................................................................................................................... 10
10. RISKS & CONTROLS: ............................................................................................................................. 10
i. Hazards / Risks .......................................................................................................................................... 10
ii. Control Measures / Permits........................................................................................................................ 10
iii. 3rd party Protection ................................................................................................................................ 11
11. TECHNICAL INFORMATION ................................................................................................................ 11
12. EMERGENCY ARRANGEMENTS ......................................................................................................... 11
i. General ....................................................................................................................................................... 11
ii. Fire Precautions ......................................................................................................................................... 11
iii. Communication .......................................................................................................................................... 12
13. TRAINING ................................................................................................................................................ 12
CONTRACTOR: ALEC Engineering and Contracting LLC
SUB - CONTRACTOR: SPECON LLC
Page 2 of 12
MSS Ref. No.: OZ31317-ZL6001-SPE-MST-0048
PROJECT : ONE ZA’ABEEL
METHOD STATEMENT FOR INSTALLATION Rev : 00
OF DX SPLIT SYSTEM, AC UNIT &
Date : 04-11-2018
REFRIGERANT PIPE
Page 3 of 12
14. SUPERVISION.......................................................................................................................................... 12
15. WORKING HOURS .................................................................................................................................. 12
16. HOUSEKEEPING ..................................................................................................................................... 12
17. OTHER INFORMATION ......................................................................................................................... 12
18. ATTACHMENTS ...................................................................................................................................... 12
CONTRACTOR AUTHORIZED SIGNATORY
Shanker. P.G Nicolaas Johannes Nel Niranjan Kumar
QA/QC MANAGER HSE MANAGER MEP MANAGER
CONTRACTOR: ALEC Engineering and Contracting LLC
SUB - CONTRACTOR: SPECON LLC
Page 3 of 12
MSS Ref. No.: OZ31317-ZL6001-SPE-MST-0048
PROJECT : ONE ZA’ABEEL
METHOD STATEMENT FOR INSTALLATION
Rev : 00
OF DX SPLIT SYSTEM, AC UNIT &
REFRIGERANT PIPE
Date : 04-11-2018
1. INTRODUCTION
The Purpose of this Method statement is to define the typical sequence of works for the installation of DX type
Ducted Split Units. This Method Statement provides the control sequence and methodology that will be used for
installation of DX type Ductable Split Units.
2. SCOPE:
Scope of this method statement includes sequence of works for supply, installation of DX type Ducted Split Units as
well as Room/wall mounted split units to provide the required cooling in the critical areas in the event of power
failure or loss of district cooling, through BMS system auto change over method, in Tower B on prepared bases in
approved manner, as specified in the related specification SECTION 238126 – Split Systems Air Conditioner, SECTION
230020 – HVAC Particular Specification, drawings, schedules etc. in One Za’abeel Project.
3. DEFINITIONS & ABBREVATIONS:
Client : ONE ZAABEEL LLC
Engineer : WSP/NIKKEN SEIKKI
Main-contractor : ALEC Engineering and Contracting LLC.
Contractor : Specon L.L.C
PD : Specon Project Director
DPD : Specon Deputy Project Director
PM : Specon Project Manager
QCM : Specon QA/QC Manager
DM : Specon Design Manager
SM : ALEC Section Manager
QCE : Specon Quality Control Engineer
HSEM : Specon Health, Safety & Environment Manager
LS : ALEC Surveyor
MEP : ALEC MEP Coordinator
LM : Specon Logistic Manager
ITP : Specon Inspection and Test Plan
MSS : Specon Method Statement Submittal
QCP : Specon Quality Control Plan
TS : Technical submittal Request
NCR : Non- Conformance Report
ITL : Independent Testing Laboratory
SD : Specon Shop Drawing
CD : Contract Drawing Issued for Construction
CONTRACTOR: ALEC Engineering and Contracting LLC.
SUB - CONTRACTOR: SPECON LLC
Page 4 of 12
MSS Ref. No.: OZ31317-ZL6001-SPE-MST-0048
PROJECT : ONE ZA’ABEEL
METHOD STATEMENT FOR Rev : 00
INSTALLATION OF DX SPLIT SYSTEM, AC UNIT Date : 04-11-2018
& REFRIGERANT PIPE
Page 5 of 12
CL : Check List
RA : Risk Assessment
MS : Material Submittal
MRS : Material Reference Schedule
IR : Inspection Request
PSSP : Project safety security plan
TC : Tower crane
MC : Mobile crane
MIM : Manufacturer instruction manual
4. WORKING ACCESS:
The access / egress for the construction vehicles for the installation of activities to be as per the logistic Plan.
Ensure Proper coordination with all interfacing contractors for Logistics, access prior to commencement of all
activities.
5. LIGHTING:
i. Safety Lighting:
The minimum safety lighting as per general requirements (Minimum 50 lux) will be provided.
ii. Task Lighting:
Task lighting to be provided in addition to the safety lighting to undertake the task with the proper level of
lighting to meet acceptable safety and quality of workmanship standards.
6. PLANT & EQUIPMENT:
i. General:
Appropriate plants and equipment to be used for the execution of the activity. The plant, tools and
equipment to be checked visually prior to use.
Only authorized applicator approved and trained by the manufacturer to install manufacturer's products
All Operators to be trained and certified by the 3rd party where required
No defective plant and equipment to be allowed to use on site
ii. Plant & Equipment Schedule:
SL No Description of Plant, Equipment & Tools
1 Crane, Chain block, fork lift, boom loader, Jack pallet trolley
2 Drill Machine, Angle cutter
3 Tape measure, plumb bob, chalk line, nylon string line
4 Spirit level, Torque wrench
CONTRACTOR: ALEC Engineering and Contracting LLC
SUB - CONTRACTOR: SPECON LLC
Page 5 of 12
MSS Ref. No.: OZ31317-ZL6001-SPE-MST-0048
PROJECT : ONE ZA’ABEEL
METHOD STATEMENT FOR Rev : 00
INSTALLATION OF DX SPLIT SYSTEM, AC UNIT Date : 04-11-2018
& REFRIGERANT PIPE
Page 6 of 12
5 Water level tube
6 Hand Tools
7 Hammer
8 Hacksaw Blade
9 Set of Spanner
10 Screw driver
11 Measuring tape
12 Tool Kit
13 Gloves, Eye Protection
iii. Personal Protective Equipment:
(Refer Attachment-1 for Risk Assessment)
All operatives involved in the activity to be provided with Job Specific Personal Protective equipment which
are and but not limited as mentioned below
Polycarbonate Safety Helmet
Safety boots with steel toe
Coverall with high visibility strips
Hand Gloves
Ear Plugs
Eye protection / Goggles
iv. Power:
The Power supply used on site for power tools to be 110V only. 230v or higher voltage power supply to
be provide to site welfare areas and other site establishment.
v. Working Platforms:
All working platforms shall be designed and comply with Dubai code of construction practice. All
work at height to follow the project fall prevention plan and Dubai code of construction practice.
All scaffoldings shall be recorded in the temporary works register / scaffolding log and coordinated
with the TC coordinator. The contractor shall refrain from using step ladders as working platforms
for installation works and shall use scaffoldings or podium steps.
The working platforms for the task to be firm and stable.
The elevated working platforms for the activity (if used) to be provided by means of cup lock
scaffold system
The scaffolds for the activity to be built by competent scaffolders trained by third party.
The built scaffolds to be inspected and signed off by a third party trained inspectors / supervisors
Where necessary access to be provide by means of scaffold
The working platforms to be used as only platforms for working and shall not be used for loading
heavy material or equipment on to it.
CONTRACTOR: ALEC Engineering and Contracting LLC
SUB - CONTRACTOR: SPECON LLC
Page 6 of 12
MSS Ref. No.: OZ31317-ZL6001-SPE-MST-0048
PROJECT : ONE ZA’ABEEL
METHOD STATEMENT FOR Rev : 00
INSTALLATION OF DX SPLIT SYSTEM, AC UNIT Date : 04-11-2018
& REFRIGERANT PIPE
Page 7 of 12
7. MATERIALS:
SL No. Material Description
1 Ducted Split Units and Wall mounted Split Units (as
per approved material submittal)
2 Copper pipes, Insulation and supports
The above listed materials/items to be in line with the approved material submittal and shop drawings in
compliance with Project Specification # 238126, requirements industry standards, code, regulation of the local
authority & regulations bodies.
8. SEQUENCE / METHOD OF WORK:
Reference
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK /Verifying
person
Document
PRE-CONSTRUCTION:
Preliminary Activities:
Submit material submission for all materials related to the task for Engineer PD/DPD/PE/ PROJECT
approval and obtain approval. QCM/HSEM SPEC
As per approved material submittal and IFC drawings/specification prepare and
submits shop drawing and obtain approval from the relevant project authorities
and local regulatory body.
Method statement, inspection & test plan and Risk Assessment to be submitted
for Engineer approval and obtain approval. Authorities (as applicable)
Implement the risk mitigation actions as per the approved risk assessment and
ensure that the risk is as low as reasonably practicable
Pre-Construction Activities:
Delivery notes to be obtained for materials delivered to site and stored in the
Stores In- Project
designated areas as per manufacturer recommendations.
charge/QCM/ SPEC/
Submit MIR for delivered materials on site
HSEM DO/MIR/
Ensure that all materials are approved prior to using the material on site.
RA
Ensure that method statement, ITP and shop drawing approved prior to starting
any activity on site.
Adequate lighting to be provided in the work areas to execute the task.
All risk hazards on operations have been identified and precautions are taken.
Ensure that all necessary personnel, plant, equipment and services are required
CONTRACTOR: ALEC Engineering and Contracting LLC
SUB - CONTRACTOR: SPECON LLC
Page 7 of 12
MSS Ref. No.: OZ31317-ZL6001-SPE-MST-0048
PROJECT : ONE ZA’ABEEL
METHOD STATEMENT FOR Rev : 00
INSTALLATION OF DX SPLIT SYSTEM, AC UNIT Date : 04-11-2018
& REFRIGERANT PIPE
Page 8 of 12
Reference
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK /Verifying
person
Document
for the works is in place.
Implement employee induction procedure and tool box talks for ongoing risk
assessment and identification of hazards.
Ensure RFI is raised and approved for technical clarification and modification
as/if required.
Ensure work area is clear and safe for working.
CONSTRUCTION ACTIVITIES:
Ensure that the installation of DX Split Unit is carried out in accordance with
manufacturer’s installation recommendations, requirement of applicable
standards and in accordance with recognized industrial practices and specified in
project specifications.
Special attention shall be paid to the condition of instruments and monitoring
devices supplied loose or installed along with the DX Split Units. Project
All the DX Split Units shall be fabricated and assembled complete at SPEC/
manufacturer’s works place, unless otherwise specified. PM/PE/SE/Q MSS/ITP/
The external air-cooled condensing units shall be installed at the perimeter of CM/HSEM RA/PTW/
the plant room floor such that they have direct intake of external air from ASD
outside and with level of direct discharge back to outside, so as to arrange the
discharge to minimize the risk of recirculation through the condensing unit.
All outdoor condenser units shall be installed on concrete plinths or wall
brackets, where installed above the finished floor level complete with neoprene
rubber pads and anti-vibration spring mountings.
Expansion valves shall be provided and installed at the condensing unit in
accordance with manufacturer’s instruction.
All indoor units shall have condensate connections to the nearest drain point or
as per the approved shop drawings.
Indoor units shall be of the decorative encased type. They shall be factory
assembled complete with fan, cooling coil, filter, condensate drain and controls.
Indoor units shall be provided with factory installed pre-wired terminal box to
IP44 with the fan motor wired to the box.
Refrigerant leak detection shall be provided in all voids and internal spaces
containing refrigerant pipework and plant.
Space temperature control shall be via a room thermostatic controller located
on the wall in the space being served and mounted at a suitable location to be
CONTRACTOR: ALEC Engineering and Contracting LLC
SUB - CONTRACTOR: SPECON LLC
Page 8 of 12
MSS Ref. No.: OZ31317-ZL6001-SPE-MST-0048
PROJECT : ONE ZA’ABEEL
METHOD STATEMENT FOR Rev : 00
INSTALLATION OF DX SPLIT SYSTEM, AC UNIT Date : 04-11-2018
& REFRIGERANT PIPE
Page 9 of 12
Reference
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK /Verifying
person
Document
agreed by the supervision consultant.
All DX Split units shall also be interfaced with the BMS to ensure full functionality
can be provided.
Ensure that all the relevant civil works are completed to intake the DX Split Unit
as per approved drawings.
Ensure that access is available from all sides for the installation of the unit,
placement of air filters and general servicing and maintenance of the DX Split
Unit.
Cut all banding (if applicable) loose from skid, but do not remove the skids until
the unit is shifted to the installation area.
Shift the DX Split Unit to the place of installation in a safe manner using fork lift
or crane as applicable.
Ensure that the correct unit is being shifted and installed in the correct location
as per the approved equipment schedule and unit reference number. Project
Ensure that the orientation of the units suits the supply and return air ducts. PM/PE/SE/Q SPEC/
Ensure the support sizes and spacing are in line with the approved shop CM/HSEM MSS/ITP/
drawings. RA/PTW/
Position support bracket and check for alignment with the unit. ASD
Lift and position the unit in a safe manner using suitable lifting gear.
Firmly secure the unit to the supports and make sure that the base of the unit is
levelled horizontally.
Ensure no damages occur during shifting, lifting and installation of the units.
Upon satisfactory positioning of the units, ensure all the openings shall be
temporarily protected until the final connections are made to the DX SPLITs.
Units will be carefully plumbed and aligned, then fully bolted and securely
anchored.
Refrigerant piping and accessories for all split air conditioning units shall be in
accordance with specification section 232113.
All refrigerant pipework shall be installed in accordance with manufacturer’s
instructions and approved shop drawings.
All refrigerant pipework shall be insulated in accordance with specification
section 230710, manufacturer’s instruction and approved material submittal.
Ensure that the unit power supply cables are connected to the isolators as per
approved shop drawings.
DX Split Unit earthing shall be done as per local authority regulation,
CONTRACTOR: ALEC Engineering and Contracting LLC
SUB - CONTRACTOR: SPECON LLC
Page 9 of 12
MSS Ref. No.: OZ31317-ZL6001-SPE-MST-0048
PROJECT : ONE ZA’ABEEL
METHOD STATEMENT FOR Rev : 00
INSTALLATION OF DX SPLIT SYSTEM, AC UNIT Date : 04-11-2018
& REFRIGERANT PIPE
Page 10 of 12
Reference
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK /Verifying
person
Document
specification and approved drawings.
All units shall be provided with connections to the BMS system for monitoring
the unit operation.
Work Inspection Request shall be initiated for consultant inspection and
approval.
Once the DX Split Units are inspected and approved, proper care will be taken to
protect the unit from dust by suitable covering until duct and chilled water pipe
connections are done and released for testing works.
Quality Control
All inspections will be performed by quality team in accordance with method
statements, review and approved by the Supervision Consultant.
The internal self-inspection shall be carried out as per the Hold, witness points as
identified in the inspection test plan for the installation and testing of
installation & testing of PPR pipes for domestic water supply (hot & cold).
instructed by the Commissioning Manager. Site Management and QA/QC
personnel should monitor the installation to ensure it is done according to the
approved drawings.
Site Supervision personnel must ensure that the work fully complies with the
norms laid down as per specification in all respects.
9. PROGRAMME
As per the site construction programme.
10. RISKS & CONTROLS:
i. Hazards / Risks
Please refer Attachment for the Risk Assessment
ii. Control Measures / Permits
Please refer Attachment for the Risk Assessment
CONTRACTOR: ALEC Engineering and Contracting LLC
SUB - CONTRACTOR: SPECON LLC
Page 10 of 12
MSS Ref. No.: OZ31317-ZL6001-SPE-MST-0048
PROJECT : ONE ZA’ABEEL
METHOD STATEMENT FOR Rev : 00
INSTALLATION OF DX SPLIT SYSTEM, AC UNIT Date : 04-11-2018
& REFRIGERANT PIPE
Page 11 of 12
iii. 3rd party Protection
Please refer Attachment for the Risk Assessment
11. TECHNICAL INFORMATION
In addition to the requirements indicated in the specification 238126, drawings, schedules, the work will be in
accordance with recommendations and requirements of the following standards, codes and bodies. The current
editions of publications being those applicable:
i. BSI Group, (BS) British Standards:
ii. BS EN 848, BS EN 779, BS EN 378 & BS EN 12735
iii. BS EN 4856 Parts 1, 2, 3 & 4, as applicable
iv. NFPA 90A – Standard for the installation of air conditioning and ventilating systems.
v. ARI Standards – Air Conditioning and Refrigeration Institute
vi. Dubai Municipality (DM) Requirements
vii. Dubai Green Building Regulations (DGBR)
viii. International Building Code (IBC)
ix. International Mechanical Code (IMC)
1. EMERGENCY ARRANGEMENTS
i. General
The Site HSE department to be responsible to arrange and coordinate with site execution teams in arranging
Day & Night emergency procedures
In case of any emergency the HSEM will be informed about the emergency
Emergency assembly point to be allotted and communicated to all the operatives involved in the job
Ensure clear access to the emergency assembly area with signage’s in place.
No construction activity shall block the access leading to the emergency assembly point. In case of any
deviation the access has to divert and the same to be communicated to all the operatives on site.
ii. Fire Precautions
Fire extinguishers to be put in place in each working zone and a clear access to be provided to the
location
All the operatives to be trained for fire precautions on site
A fire warden is appointed and trained from each team of operatives
CONTRACTOR: ALEC Engineering and Contracting LLC
SUB - CONTRACTOR: SPECON LLC
Page 11 of 12
MSS Ref. No.: OZ31317-ZL6001-SPE-MST-0048
PROJECT : ONE ZA’ABEEL
METHOD STATEMENT FOR Rev : 00
INSTALLATION OF DX SPLIT SYSTEM, AC UNIT Date : 04-11-2018
& REFRIGERANT PIPE
Page 12 of 12
iii. Communication
The communication on site to be through mobile provided by the contractor or by two-way wireless radio
systems
2. TRAINING
Necessary safety or operational training to be provided to the operatives involved in the activities
3. SUPERVISION
Adequate supervision to be provided for the executing each activity
Project QAQC Engineers shall monitor the workmanship and quality of the works
4. WORKING HOURS
Site working hours to be 06:30 AM to 05:30 PM. Authority regulations for the working hours will be
followed. Mid-day break between 12:30 PM to 3:00 PM will be followed during summer as per DM
regulation.
5. HOUSEKEEPING
The work areas to be clean and tidy.
No debris from construction activities is allowed to accumulate in the work area.
Work areas to be cleaned on daily basis at the end of the shift or on completion of the activity
Sufficient Waste collection bins to be provided at each working zone
Waste segregation area (where recyclable / landfill materials are segregated, usually as Steel, Wood,
Plastic, Concrete and Debris) to be established to control the waste generated on site due to
construction
6. OTHER INFORMATION
NA
7. ATTACHMENTS
1. Risk Assessment
2. Inspection Test Plan
3. Inspection checklist
CONTRACTOR: ALEC Engineering and Contracting LLC
SUB - CONTRACTOR: SPECON LLC
Page 12 of 12