<Project Name>: Change Management Process
1 Change request is raised and submitted to India Project Team (Om, Swati) via email. Send copy to the Impact Assessment Group
2 High level assessment by India Project Team
3 Impact assessers to meet every Monday and Thursday to discuss and take decisions on the CRs. Attached register to be shared ah
4 Email sign-off on the accepted changes by the sign-off authority group. Associated coomerical and timeline related impact to be
5 Team will make appropraiate amendments in the vendor contract (If applicable).
6 Project plan is updated with new timeline, resources and efforts
Sign-off Authority Group
A
B
C
D
E If budget exceeds Contingency
Summary of
CR Block (Iteration) Timeline Impact (Days) Effort Impact (person-Hours)
4,14 18 144
18,19,22,25 9 70
26 15 120
27,28,29,30,31 16 128
Total 58 462
il. Send copy to the Impact Assessment Group
ns on the CRs. Attached register to be shared ahead of meeting.
coomerical and timeline related impact to be signed off as relevant.
Impact assessment group
A J
B O
C V
F L
K
Summary of Timeline, Effort & Cost Impact
Cost Impact (USD) Milestone Dates Impact
3780 None
1838 None
3150 None
4404 None
13171
meeting.
ff as relevant.
e, Effort & Cost Impact
Remarks
Project: Change Control Register
Corr. Client Estimated Effort for
CR No. Date of request Description of Change Nature of Module/functionality Status Exp Dev & Testing Actual date of Actual Effort for Dev+
CR No. Requester Comments by Impact Assessment Group Dev+ Testing
Request Impacted date Implementation Testing (person-hrs)
(person-hrs)
CR01 2 4-Jan-12 Change Approved
Remarks Recieval date
4-Jan-12
<Project Name>: Change Iteration Impact on Timeline
Timelines:
Timelines (days) 1 2 3 4
Development
CR Testing
Regression testing
Development
CR Testing
Regression testing
Efforts:
Total Man hours required: 144 hrs for development and testing.
1st Change Iteration Total Person days required = 18
Testing would involved
· Test scenario and cases preparation for new functionality
· Test execution for new functionality
· Regression testing for existing functionality
For reference:
CR 4-Jan-12
CR 4-Jan-12
Timelines:
Timelines (days) 1 2 3 4
Development
CR18 Testing
Regression testing
Development
Testing
CR19 Regression testing
Development
Testing
CR22 Regression testing
Development
Testing
CR25 Regression testing
Efforts:
2nd Change Iteration
Total Man hours required: 70 hrs for development and testing.
2nd Change Iteration Total Person days required = 8.75
Testing would involved
· Test scenario and cases preparation for new functionality
· Test execution for new functionality
· Regression testing for existing functionality
For reference:
CR 18-Jan-12
CR 18-Jan-12
CR 25-Jan-12
CR 25-Jan-12
Timelines:
Timelines (days) 1 2 3 4
Development
Testing
Regression testing
Efforts:
Total Man hours required: 120 hrs for development and testing.
3rd Change Iteration
Total Person days required = 15
Testing would involved
· Test scenario and cases preparation for new functionality
· Test execution for new functionality
· Regression testing for existing functionality
For reference:
CR 14-Feb-12
5 6 7 8 9 10
for new functionality
5
for new functionality
5 6 7 8 9 10 11 12 13
for new functionality