Project Management Overview and Resources

The document outlines the project management plan for a Sales and Distribution System, detailing hardware and software requirements, including RAM, processor, operating system, and MySQL. It includes a work breakdown structure that defines roles such as customer, sales lady, cashier, and manager, along with their responsibilities. Additionally, it presents a project schedule with tasks, dependencies, and milestones, indicating the project timeline from June 20, 2011, to October 28, 2011.

Uploaded by

Neil Basabe
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
77 views6 pages

Project Management Overview and Resources

The document outlines the project management plan for a Sales and Distribution System, detailing hardware and software requirements, including RAM, processor, operating system, and MySQL. It includes a work breakdown structure that defines roles such as customer, sales lady, cashier, and manager, along with their responsibilities. Additionally, it presents a project schedule with tasks, dependencies, and milestones, indicating the project timeline from June 20, 2011, to October 28, 2011.

Uploaded by

Neil Basabe
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

Chapter II -Project Management

Hardware Resources

Random Access Memory(RAM)

Processor (Inter® Core)

Disk

Monitor(HP L1506)

Mouse and Keyboard(A4 tech and hp)

Software Requirements

Operating System

Programming Tools

MySQl 5.0
Work Breakdown Structure

Sales and Distribution System

Customer Sales Lady Cashier Manager

-Order -Assemble Order -Receive -Issue Invoice


Payment
-Pay -Pay Invoice
-Process
-Record Sales
Payment
Network Diagram
Project Schedule

Project Started: 06/20/11

Project End: 10/28/11

Task Dependencies Milestones

T1 -15 M1 7/1/11

T2- 10 T1

T3 -5 T2

T4-10 T3 M2 8/05/11

T5-5 T1, T2
T6-10 T5

T7-10 T6 M3 9/09/11

T8-10 T2, T5

T9-10 T8

T10-15 T9 M4 9/28/11

T1-Gathering information, interview

T2, T3-Making User Interfaces

T5, T7-Making documentation

T5, T10-Coding

M1-Gathered data and Information

M2-Produce User Interface

M3-Documentation

M4-Running program