ABB Installation: Low-Voltage Switchgear MNS
Topics covered
ABB Installation: Low-Voltage Switchgear MNS
Topics covered
and operation
MNS
ABB Installation
Low-voltage switchgear MNS is available with rated currents up to
5000 A (IP 31) and can be equipped with:
– starters and distribution units of withdrawable design (W units)
– distribution units and group boards of removable design (R units)
List of contents
Handling and unpacking page 3
Setting up switchgear cubicles 4
Laying of external cables 6
Connection of circuit-breaker cubicle and disconnector cubicle 7
Disconnector cubicle, cable connection from below 7
Disconnector cubicle, busbar connection from above 7
Circuit-breaker cubicle, cable connection from below 8
Circuit-breaker cubicle, cable connection from above 10
Circuit-breaker cubicle, busbar connection from above 12
Connection of apparatus units
Withdrawable units, main circuits 14
Removable units, main circuits 16
Screw-in fuse boards 17
MCB boards 20
Auxiliary circuits 21
Protective earthing 21
Withdrawable apparatus units, handling
Description 22
Operation 23
Withdrawing 25
Inserting 26
Extension 27
Withdrawable apparatus units, handling
Description 28
Operation 28
Replaceability, MNS – Center 5000/1600 28
Removing a unit 29
Mounting a unit 29
Extension 30
Measures to be adopted before applying voltage
Concluding work 31
Check list upon commissioning 31
2
Handling and unpacking
The switchgear cubicles are delivered in the form of ready
assembled complete units with horizontal busbars. Each
cubicle is protected with plastic wrapping and securely
attached to a loading pallet.
Check the delivery against the accompanying advice note.
Handle the cubicles carefully. They are most easily trans-
ported using fork-lift trucks.
When hoisting with an overhead travelling crane or other
hoists:
1. Use the lifting eye bolts attached to the top of the cubicles.
2. Insert the lifting sling shackles into the holes in the eye The cubicles are most easily Lifting with a hoist or overhead
bolts. transported using a fork-lift truck. travelling crane.
3. Adjust the length of the slings so that the angle between
them does not exceed 60°.
If the cubicles are not to be installed directly, they should be
Max. 3 mm
3
Setting up switchgear cubicles
Drilling of holes
The drawings show the holes that can be drilled for external cables under the
cubicles, in the base plate and in the roof plate. min 40 – 150
Distance to wall.
50 50
50 50
*) *)
FL 21
FL 21 FL 21
600
100 100 100
270 b – 100 50
100 100 100
D=16
Drilling of holes in floor and base plate: Drilling of holes in Drilling of holes in Drilling of holes in
Circuit-breaker cubicle, b = 600, 800, 1000, 1200 roof plate: roof plate: roof plate:
Disconnector cubicle, b = 600, 800 Apparatus cubicle, b = 400 Apparatus cubicle, b = 600 Apparatus cubicle, b = 800
Apparatus cubicle, b = 400, 600, 800
*) Not to be used when a cubicle is fixed to
a wall.
50 50
50 50
*) *)
FL 21 FL 21
600
100 100
270 300/500 50
100 100
Drilling of holes in floor and base plate: Drilling of holes in roof plate: Drilling of holes in roof plate:
Apparatus cubicle W, b = 600 + 400, 600 + 800 Apparatus cubicle W, b = 600 + 400 Apparatus cubicle W, b = 600 + 600
*) Not to be used when a cubicle is fixed to
a wall.
4
Setting up switchgear cubicles (cont.)
Alignment of cubicles
The flooring should be flat and even and carefully chosen for cubicle erection
so that several cubicles can be bolted together without necessitating further meas-
ures.
If the floor is not sufficiently flat, this may result in panels and doors jamming.
The height of the cubicles can be adjusted by inserting sheet metal shims between
base plate and floor.
Five distance bolts (article no. 1TSA2 21671-90) for bolting cubicles together are
provided in a plastic bag to be found attached in the cable compartment of each
cubicle.
Attachment
Placing against a wall
The cubicle furthest to the left in a row of cubicles is to be fixed to the wall with the
help of two wall attachment brackets and to the floor with a bolt through the front of
its base plate, positioned 200 mm from the right-hand side of the cubicle. Other Placing against a wall.
cubicles in the row are to be fixed to the wall with one wall attachment bracket and *) Only for the cubicle furthest to the left.
to the floor with a bolt through the front of their base plates.
Free-standing arrangement
The cubicle furthest to the left in a row of cubicles is to be fixed to the floor using
two bolts through the rear of its base plate (after removing the rear panel), 50 mm
from the sides of the cubicle, and with a bolt through the front of its base plate,
200 mm from the right-hand side of the cubicle. Other cubicles in the row are to be
fixed with one bolt through the rear of their base plates (after removing the rear
panel), 50 mm from the right-hand side of the cubicle, and with a bolt through the
front of their base plates, 200 mm from the right-hand side of the cubicle.
Recommended screw diameter: 10 mm.
Apparatus cubicle
All external cables to apparatus cubicles are to be laid in the area intended for
cables.
Main
cables *)
Control cables
Main cables
In the 400 mm cable compartment there are five rails on the right-hand cubicle Internal wiring
wall, for fixing of main cables using cable hangers. Slimmer cables are best fixed
Main cables
to the rails by crossing two smaller bunching straps.
In the 600 mm cable compartment there are in addition five rails on the rear wall,
for fixing of main cables.
Cable compartment.
Auxiliary cables *) Only with 600 mm cable compartment.
Internal wiring and operating voltage supply cables should be attached using
bunching straps in special attachment holes to the left at the rear of the cable
compartment. Control cables should be attached using strap attachments and
bunching straps on the rear wall. (Bunching straps are delivered with the cubicles.)
For withdrawable units, there is a strap attachment on the right hand side of the
cassette plate for supporting the weight of the operating cables.
Under the top door there is a cable duct intended for connections between
Cable clamping straps.
cubicles. The cable duct also serves as an attachment rail for cubicle terminal
boards.
Strap attachment. Cable duct for operating cables between cubicles. Attachment rail for cubicle terminal boards.
Auxiliary cables
Operating cables are supported with bunching straps in the cable brackets
fixed to the ends of the cubicle. Operating cables can be placed on either
side, depending on where the terminal board is placed.
6
Connection of circuit-breaker cubicles and disconnector cubicles
Fixed 4
Disconnectable 10
Disconnector cubicle, busbar connection from above
OETL 2500 A
7
Connection of circuit-breaker cubicles and disconnector cubicles (cont.)
Dimension drawings
Circuit-breaker cubicle, cable connection from below
8
Connection of circuit-breaker cubicles and disconnector cubicles (cont.)
Dimension drawings
Circuit-breaker cubicle, cable connection from below
9
Connection of circuit-breaker cubicles and disconnector cubicles (cont.)
Dimension drawings
Circuit-breaker cubicle, cable connection from above
*)
*)
*)
10
Connection of circuit-breaker cubicles and disconnector cubicles (cont.)
Dimension drawings
Circuit-breaker cubicle, cable connection from above
*)
*)
*)
11
Connection of circuit-breaker cubicles and disconnector cubicles (cont.)
Dimension drawings
Circuit-breaker cubicle, busbar connection from above
*)
*)
*)
12
Connection of circuit-breaker cubicles and disconnector cubicles (cont.)
Dimension drawings
Circuit-breaker cubicle, busbar connection from above
*)
*)
*)
13
Connection of apparatus units
Main circuit
terminal boards
A
B
D
14
Connection of apparatus units (cont.)
Connection unit Max. connectable Max. bolt Max. tightening Cable shields
size area dimension torque per phase
15
Connection of apparatus units (cont.)
Apparatus unit Connectable area, copper cable Connectable area, aluminium cable
Type Size Min. area Max. area Max. area Min. area Max. area Max. area
cable lug cable clamp cable lug cable clamp
mm2 mm2 mm2 mm2 mm2 mm2
16
Connection of apparatus units (cont.)
Fuse/switch OESA
160 A 50 120 120 70 120 120
250 A 95 300 300 150 240 300
400 A 240 2//300 2//240 300 240 300
630 A 2//150 3//300 2//300 2//240 3//240 2//300
800 A 2//240 3//300 2//300 2//300 3//240 2//300
Continued on page 16
17
Connection of apparatus units (cont.)
Thread II, 25 A
With neutral and protective earth busbars.
The groups are connected to a row of terminal Number of groups Height, modules
boards which also contain disconnectable neu- 1-pole 3-pole
tral boards for joint and individual disconnection
of the groups. Protective earth bar with single- 18 6 8
screw clamp and connection to the main neu- 9 3 6
tral board are included.
Connectable area:
max. 6 mm2, min. 1.5 mm2 for 3-pole
max. 4 mm2, min. 1.5 mm2 for 1-pole
Thread II, 25 A
With group circuit-breaker 40 A
Thread II, 25 A
With extra row of fuses.
Continued on page 17
18
Connection of apparatus units (cont.)
Thread III, 63 A
With row of terminal boards
Thread III, 63 A
With group circuit-breaker 80 A
Thread III, 63 A
With extra row of fuses
19
Connection of apparatus units (cont.)
MCB terminals
Internal cables from back-up circuit-breaker
Cable duct for external cable or from main busbar
Neutral bar
PE bar
PE + N placed in 5-conductor system PEN/PE +N placed in 4-conductor system (neutral bar optional)
20
Connection of apparatus units (cont.)
For withdrawable units, operating and signal cables are connected to terminal units
(sliding contact units).
Max. connectable area: 1 x 2.5 mm2 screw clamp + 2 x flat pin terminal 2.8 x 0.8.
Max. rated current/voltage: 10 A/500 V.
Connection of screened conductors is best done to an earthing bar located on the
left front post in the cable area (option).
Protective earthing
The vertical protective earth busbar (PE) has holes 50 mm apart for cable lug
connection down to 4 mm2 conductor area. Conductors with areas of 1 – 10 mm2
are to be connected to a smaller bar mounted on the large bar.
The PE busbar is located right at the back of the cable area to the left.
21
Withdrawable apparatus units, handling
Description
The withdrawable apparatus units have plug-in connection both for the incoming
supply from the vertical busbar system and for outgoing cables. The units can be
pulled out without having to unscrew any bolts. Interlocking takes place via the
group´s operating handle. The auxiliary circuits are connected via multi-pole plug-in
contact units. Unoccupied apparatus seats are screened off to minimise the risk of
unintentional touching of live parts.
Withdrawable starter.
22
Withdrawable apparatus units, handling (cont.)
23
Withdrawable apparatus units, handling (cont.)
24
Withdrawable apparatus units, handling (cont.)
4. For further movement inwards, turn the knob to the Move position.
26
Withdrawable apparatus units, handling (cont.)
Extension
Extension of the equipment can take place with the switchgear live, but it is
naturally preferable to work with the voltage switched off.
1. Remove the panel in question as well as the panel immediately below it.
Remove the panel bar as well (only at higher degree of protection).
Since the units are protected against adjacent units via cassette plates, and the ter-
minals are provided with cable shields, no further measures need be adopted when
carrying out extensions with the equipment live.
Before energising the equipment, see the instructions under ”Concluding work” and
”Check-list upon commissioning”.
In general, it is important when extending equipment that the relevant regulations
regarding measures that are to be adopted, such as marking with sign-plates, etc.,
are complied with. 27
Removable apparatus units, handling
Description
The removable apparatus units have plug-in connection for the incoming supply
from the vertical busbar system, whereas the outgoing cables are connected per-
manently direct to the apparatus terminals. The units can be taken out after the
outgoing cables have been disconnected and four fixing bolts removed. The auxil-
iary circuits are connected via multi-pole plug-in contact units.
Operation
The operating knob has two positions.
28
Removable apparatus units, handling (cont.)
Removing a unit
1. Set the knob in the 0 position (breaker off).
Mounting a unit
1. Open the panel.
29
Removable apparatus groups, handling (cont.)
Extension
Extension of the equipment can take place with the switchgear live, but it is
naturally preferable to work with the voltage switched off.
1. Remove the panel in question as well as the panel immediately below it.
Remove the panel bar as well (only at higher degree of protection).
Since the units are protected against the adjacent units via cassette plates, and
the terminals are fitted with screens against the cable cubicle, no further measures
need be adopted when extending the equipment in live conditions.
Before energising the equipment, see the instructions under ”Measures to be
adopted before energising”, page 29.
In general, it is important when extending equipment that the relevant regulations
regarding measures that are to be adopted, such as marking with sign-plates etc.,
are complied with.
30
Measures to be adopted before energising
Concluding work
Remove wire ends and debris from cable stripping, etc.
Wipe off any grease and dirt.
Check that tools and assembly material have not been left in the cubicles.
Vacuum-clean the cubicles.
Check-list upon
commissioning
There follows a list of points to be 7. ❐ Check the PE and N bars 10.6 Reconnect all relays , operating
observed when inspecting and testing voltages and circuits that were
a directly earthed system. Carry out a visual inspection to ensure
that the bolts in busbar joints between disconnected during the
In the case of indirectly earthed the cubicles are tight. insulation tests.
systems, a check must always be made
that all metallic parts are correctly 8. ❐ Check phase sequence and 11. ❐ Energising the equipment
earthed. Check the earth fault protec- marking 11.1 Check that incoming and
tion signal as well. outgoing circuit-breakers and
Apart from this check-list, local and disconnectors are off.
current national regulations and 11.2 Check that all doors and covers
instructions must be complied with. in the switchgear are closed.
11.3 Switch on the supply and
1. ❐ Insertion of fuses connect in the switchgear, if
Insert all necessary fuses in the main possible one cubicle or section
and auxiliary circuits. at a time.
2. ❐ Checking of fuses 11.4 Check the phase sequence of a
unit. It is enough to check one
Check that all fuses agree with the
unit since the phase sequence
apparatus list and the circuit diagram.
has already been checked
(point 8).
3. ❐ Setting of MCCBs
Set instantaneous and thermal tripping 11.5 Check the units one at a time
9. ❐ Check internal connections by:
of MCCB units, based on load and
selectivity. Check all internal connections between - switching on the circuit-breaker
the cubicles.
The instantaneous protection for incom- - checking the main circuit to
ing circuit-breakers and large distribu- 10. ❐ Carry out insulation tests the connected load
tion breakers can be temporarily set at 10.1 Check that incoming supply is - checking that all important
the lowest value to ensure the fastest switched off. interlocking measures agree
possible tripping in the event of a short with the circuit diagram.
circuit during commissioning. 10.2 Check that all operating
voltages are switched off.
12. ❐ Final inspection
4. ❐ Checking of current 10.3 Check that all relays are 12.1 Check that all voltmeters,
transformers switched off. ammeters and wattmeters are
Check that the secondary winding in all 10.4 Check that all large MCCBs in working order.
current transformers is connected (incoming circuit-breakers) are
(under load). Otherwise the secondary 12.2 Check that all instantaneous
disconnected. protections that have been
windings must be short-circuited.
10.5 Check the insulation on the turned down during
5. ❐ Setting of starters main busbars using a megger commissioning work are reset
with 1 or 0.5 kV. The insulation to their operating positions.
Set the thermal overload protection at resistance should be ≥ 1 Mohm.
the rated current of the motor. 12.3 Check that no vibrations or
Phase Insulation resistance noises occur in the busbar
N.B. Setting above or below the scale systems.
range is not permitted. Mohm
L1 – N
6. ❐ Check the main busbars L2 – N
Make a visual inspection to see that
the bolts in busbar joints between the L3 – N
cubicles are tight. L1 – L2
L2 – L3
L3 – L1
31
97414 ReklamCenter Västerås 1997 11/DocuTech 400ex
1TSC 234-EN
ABB Installation AB
Low Voltage Systems Division
S-721 62 Västerås, Sweden
Telefon: +46 21 34 60 00
Telefax: +46 21 34 61 10