0% found this document useful (0 votes)
58 views4 pages

Unity Lagi Aja

The document shows a table with details of activities like status, WBS code, task name, original duration, start date, end date and other details. It contains details of a few activities for a project with status, codes, names, dates and durations.

Uploaded by

safar bahari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
58 views4 pages

Unity Lagi Aja

The document shows a table with details of activities like status, WBS code, task name, original duration, start date, end date and other details. It contains details of a few activities for a project with status, codes, names, dates and durations.

Uploaded by

safar bahari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

status_codewbs_id task_code task_name target_drtn_hr_cnt

Activity Sta WBS Code Activity ID Activity Name Original Duration(h)


Not Started Gallaf Proj ML-CM-100Effective Date 10
In ProgressGallaf Proj ML-CM-101M1-Kick Off Meeting with Co4
start_date end_date delete_record_flag
(*)Start (*)Finish Delete This Row
11/12/2019 08:00 11/27/2019 16:00
2/27/2021 00:00 3/4/2021 14:30
user_data
UserSettings Do Not Edit
DurationQtyType=QT_HourShowAsPercentage=0SmallScaleQtyType=QT_HourDateFormat=M/d/yyyyCurrencyFormat=US D
ourDateFormat=M/d/yyyyCurrencyFormat=US Dollar