Bituman Spray Rate Test

This document outlines the process for measuring the rate of spray of a prime coat in road construction. It lists the materials and equipment needed, including a sample tray, weighing balance, and details of the road and prime coat. It then provides a 12 step process: [1] Take a sample tray, [2] Weight the empty tray, [3] Place the tray where the prime coat will be sprayed and allow it to dry, [4] Weight the tray with the dried prime coat, [5-11] Make calculations using the weights, area of the tray, and specific gravity of the prime coat to determine the rate of spray in kg/sqm, [12] The unit of measure for the rate

Uploaded by

shekler
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
3K views2 pages

Bituman Spray Rate Test

This document outlines the process for measuring the rate of spray of a prime coat in road construction. It lists the materials and equipment needed, including a sample tray, weighing balance, and details of the road and prime coat. It then provides a 12 step process: [1] Take a sample tray, [2] Weight the empty tray, [3] Place the tray where the prime coat will be sprayed and allow it to dry, [4] Weight the tray with the dried prime coat, [5-11] Make calculations using the weights, area of the tray, and specific gravity of the prime coat to determine the rate of spray in kg/sqm, [12] The unit of measure for the rate

Uploaded by

shekler
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

Department Contractor Quality Controller

Bitumen Spray Rate Test

Project
Location
Material
Density
Temperature
Time Started
Time Ended
Length/Width/Area
Spray Speed
Pressure
Ambient Temperature
Design Spray Rate

Weight of Tray, g
Area of Tray, m2
Weight of Tray +
Spray Weight, g
Spray Weight, g Weight of Bitumen = (Total
Weight – Tray Weight)
Specific Gravity of Bitumen 1 g/mm3
Rate of Bitumen Spray Weight of Bitumen/area/1000,
kg/m2
Rate of Bitumen Spray Rate of Bitumen Spray kg/m2/
density, L/m2
Average Rate of Spray
Correction Factor for Temp at
C
Average Rate of Spray at 15.6
C
Bitumen %

Steps to measure the rate of Spray of Prime Coat in Road Construction are:

1. You have to take sample tray of suitable size. I would prefer use tray of Size 35 cm * 28 cm.

2. Weight the tray in weighing balance. Say initial weight of tray= A kg

3. Place the tray over the road on which prime coat is to be sprayed and hence the prime coat is sprayed
over the tray.

4. Let the prime coat dry for some time and weight the tray over which prime coat is sprayed. Say Final
weight of Tray(with the prime coat)= B kg
5. Calculations to be done:

6. Area of tray = 0.35 *0.28 =0.098 sq/m

7. Initial Weight of Tray= A kg

8. Final Weight of Tray= B kg

9. Specific Gravity of Prime Coat= 0.95

10. Calculate increase in Weight= (B-A) kg

11. Rate of Spray in Kg = (Increase in Weight)/(Area of tray)

12. Unit of Rate of Spray in kg/sqm.(Kilogram per square meter)