Rajasthan Ganga Clean-Up Progress Report

This document provides a summary of the status of sewage and pollution management in the state of Rajasthan. It details the population and estimated sewage generation, existing and proposed sewage treatment plants and their capacities. It also summarizes the status of industrial pollution including numbers of industries and effluent treatment plants. Solid waste management details like generation and processing capacities are included. Bio-medical, hazardous and plastic waste management are also briefly outlined. Actions taken on groundwater regulation, irrigation practices, rainwater harvesting and other river rejuvenation efforts are referenced in annexures.

Uploaded by

Ashish Dongre
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
339 views65 pages

Rajasthan Ganga Clean-Up Progress Report

This document provides a summary of the status of sewage and pollution management in the state of Rajasthan. It details the population and estimated sewage generation, existing and proposed sewage treatment plants and their capacities. It also summarizes the status of industrial pollution including numbers of industries and effluent treatment plants. Solid waste management details like generation and processing capacities are included. Bio-medical, hazardous and plastic waste management are also briefly outlined. Actions taken on groundwater regulation, irrigation practices, rainwater harvesting and other river rejuvenation efforts are referenced in annexures.

Uploaded by

Ashish Dongre
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

National Mission for Clean Ganga

Format for submission of Monthly Progress Report in the NGT Matter OA


No. 673 of 2018 (in compliance to NGT order dated 24.09.2020)

For the State/ UT of Rajasthan

Overall status of the State:


I. Total Population: 6,86,21,012; Urban Population 1,10,80,776, Rural Population:
5,15,40,776 (As per census of 2011).

II. Estimated Sewage Generation (MLD): 1550.81 MLD

III. Details of Sewage Treatment Plant:


 Existing no. of STPs and Treatment Capacity (in MLD): 80 and 999.18 MLD
 Capacity Utilization of existing STPs: 694.54 MLD
 MLD of sewage being treated through Alternate technology: 17 KLD through
FSSM.
 Gap in Treatment Capacity in MLD: 304.64 MLD (existing Capacity – capacity
utilized)
 No. of Operational STPs: 80 and 999.18 MLD
 No. of Complying STPs: 22
 No. of Non-complying STPs: 39

Details of each existing STP in the State


No. Location Existing STP Capacity Being Operational Status Compliance
Capacity Utilized of STP Status of STP
As per Annexure_1

Details of under construction STPs in the State


No. Location Capacity of Physical Status of I&D or Incremental Completion
the plant in Progress in House sewer progress Timeline
MLD % connections
As per Annexure_2

1
Details of proposed STPs in the State
No. Location Capacity of Status of Project (at Incremental Likely Date of
the STP DPR Stage/ Under progress Completion
proposed in Tendering/ Work to be
MLD Awarded)
-

IV. Details of Industrial Pollution:


 No. of industries in the State: NA
 No. of water polluting industries in the State: 1199
 Quantity of effluent generated from the industries in MLD: NA
 Quantity of Hazardous Sludge generated from the Industries in TPD: 834.03 TPD
 Number of industrial units having ETPs: No. of ETPs-1167
 Number of industrial units connected to CETP: 4618
 Number and total capacity of ETPs (details of existing/ under construction / proposed)
o Total ETPs: 1167
o Total installed capacity: 3173.61 MLD
 Compliance status of the ETPs:
o Complying ETPs: 1129
o Non-Complying: 38
 Number and total capacity of CETPs (details of existing/ under construction /
proposed)
o Total CETPs: 16, (14 Operational, 01 under construction and 01 closed)
o Total installed capacity: 159.88MLD
 Status of compliance and operation of the CETPs
o Complying CETPs: 03
o Non-Complying: 11
 Status of compliance and operation of the CETPs
Complying CETPs: 03
Non-Complying: 11

Town No. of industries Industrial Status of ETPs Status of CETPs

2
discharge (existing, under
construction & proposed)
Ajmer NA NA 46 1
Alwar NA NA 443 1
Banswara NA NA 5 0
Baran NA NA 8 0
Barmer NA NA 112 3
Bharatpur NA NA 1 0
Bhilwara NA NA 35 0
Bikaner NA NA 78 0
Bundi NA NA 28 0
Chittorgarh NA NA 8 0
Dausa NA NA 1 0
Dholpur NA NA 7 0
Dungarpur NA NA 3 0
Hanumangarh NA NA 20 0
Jaipur NA NA 139 3
Jaisalmer NA NA 1 0
Jalore NA NA 4 0
Jhalawar NA NA 5 0
Jodhpur NA NA 11 1
Kota NA NA 43 0
Nagaur NA NA 05 0
Pali NA NA 48 7
Rajsamandh NA NA 4 0
Sawai NA NA 2 0
Madhopur
Sikar NA NA 16 0
Sirohi NA NA 22 0
Shri NA NA 19 0
Ganganagar
Tonk NA NA 8 0
Udaipur NA NA 45 0

V. Solid Waste Management:


 Total number of Urban Local Bodies and their Population : 196
 Current Municipal Solid Waste Generation: 6500 TPD

3
 Number, installed capacity and utilization of existing MSW processing facilities in
TPD (bifurcated by type of processing eg- Waste to Energy (Tonnage and Power
Output), Compost Plants (Windrow, Vermi, decentralized pit composting),
biomethanation, MRF etc
a. Running Centralized Plants-08 with capacity of 947 TPD
b. Running MRF- 66 Nos with capacity of 450 TPD
 Action plan to bridge gap between Installed Capacity and Current Utilization of
processing facilities (if Gap > 20%)
Installed capacity are running as full utilization
 No. and capacity of C&D waste processing plants in TPD (existing, proposed and
under construction)
a. 50 TPD Plant is running in Udaipur Municipal Corporation
b. 300 TPD plant LOI has been issue by Jaipur Municipal Corporation
 Total no. of wards, no. of wards having door to door collection service, no. of wards
practicing segregation at source
a. Total wards are 5389 and door to door collection is 99%.
 Details of MSW treatment facilities proposed and under construction (no., capacity,
and technology)
a. Details are attached at Annexure-1
 No. and area (in acres) of uncontrolled garbage dumpsites and Sanitary Landfills.
 No. and area (in acres) of legacy waste within 1km buffer of both side of the rivers
 No. of drains falling into rivers and no. of drains having floating racks/screens
installed to prevent solid waste from falling into the rivers
Status of ULB wise Management of Solid Waste
ULB Total MSW Total MSW Existing Utilization Proposed MSW
generation in being processed MSW Capacity of the Facilities &
TPD in TPD facilities existing MSW Completion
facilities Timeline
Details are attached at Annexure-1

VI. Bio-medical Waste Management:


 Total Bio-medical generation: 20685.65 kg/day
 No. of Hospitals and Health Care Facilities: 8584

4
 Status of Treatment Facility/ CBMWTF: Details are attached at Annexure-2

VII. Hazardous Waste Management:


 Total Hazardous Waste generation: 562463.96 MT
 No. of Industries generating Hazardous waste: 1633
 Treatment Capacity of all TSDFs: 760481 MTA
 Avg. Quantity of Hazardous waste reaching the TSDFs and Treated: 150462.41
MT
 Details of on-going or proposed TSDF: NIL

VIII. Plastic Waste Management:


 Total Plastic Waste generation:
 Treatment/ Measures adopted for reduction or management of plastic waste:

IX. Details of Alternate Treatment Technology being adopted by the State/UT

X. Identification of polluting sources including drains contributing to river pollution


and action as per NGT order on insitu treatment: Drain identified for contribution
in River Chambal in Kota Region.

XI. Details of Nodal Officer appointed by Chief Secretary in the State/UT:


XII. Details of meetings carried under the Chairmanship Chief of Secretary in the
State/UT: Chief Secretary Review is being held regularly.
XIII. Latest water quality of polluted river, its tributaries, drains with flow details and
ground water quality in the catchment of polluted river;

XIV. Ground water regulation: As per Annexure Action Plan


XV. Good irrigation practices being adopted by the State: As per Annexure Action
Plan
XVI. Rain Water Harvesting: As per Annexure_Action Plan
XVII. Demarcation of Floodplain and removal of illegal encroachments: As per
Annexure_Action Plan
XVIII. Maintaining minimum e-flow of river: As per Annexure_WRD
XIX. Plantation activities along the rivers: As per Annexure__Forest

5
XX. Development of biodiversity park: Development of Abheda Biological Park
Kota is under progress and is likely to be completed by March 2021
XXI. Reuse of Treated Water: As per Annexure_Action Plan
XXII. Model River being adopted by the State & Action Proposed for achieving the
bathing quality standards:
XXIII. Status of Preparation of Action Plan by the 13 Coastal States:
XXIV. Regulation of Mining Activities in the State/UT:
XXV. Action against identified polluters, law violators and officers responsible for
failure for vigorous monitoring.

*Note: Incremental progress made by the State/UT in each activity to be provided.

6
351 Polluter Stretches in the country
Name and designation of designated officer for ensuring compliance to provisions under statute: Compliance being made by co-
ordination among all concerned Departments with RSPCB. Matter does not fall under any statute.

Current Status Desirable level as per statutes Gap between Current status and desired Timeframe for
levels addressing the Gap

Contamination reaching 1. Characterization of runoff of Kota: Samples were collected from main Continuous
river stretch due to first main drains for first four storm drains (Municipal drain and nallah joining Process
flush water flows, Outcome would be: river Chambal) on 23/08/2019 and
I. Identification of most 09/09/2020. Analysis results reveal that
contaminated drains and drains carrying untreated domestic effluent.
level of contamination
II. Quantity of water to be Pali: Samples were collected on 14.08.2019.
handled, based on As per analysis results BOD level has been
available flow data found as 1.17 mg/l which is well within the
prescribed level i.e. more than 6 mg/l (10-20
mg/l) for polluted river stretches.

Jaipur: Samples were collected in June &


August 2019 and analysis report shows
pesticide below detection limit.
First meeting of Special Environment
Surveillance Task force was conducted on
02.04.2019 at District Collectorate Jaipur.
During meeting it was decided that

Rajasthan State information being submitted to CPCB Page 26


stakeholder departments will be informed to
work out for characterization of runoff of
main drains of nevta dam for first four storm
water flows.
i. For Kota UIT has started the
work. Nagar Nigam has collected samples
from various nallahs for sewerage
analysis and submitted to RSPCB for
analysis.
ii. Six drain are identified in municipal
area which is discharge into chambal
river. Two waste water treatment plant
proposed for treatment of drain water.
Land allotted for WTP & FSTP Plant
demarcation of land is done and leveling
sheet of exiting land topographical map of
town prepared. soil testing of proposed
land submitted to MNIT. Work order for
making DPR has been issued for the
establishment of Waste Water Treatment
Plant. DPR has been prepared and
submitted for Budget approval. 13 Crore
Fund will be required for construction of
integrated wastewater and Septage
management plant. Budget provision not
approved by Finance Department and
ULB doesn't have funds. ULB has
installed the gratings and regular cleaning
is being done at all 06 Drains. Timeline:-

Rajasthan State information being submitted to CPCB Page 27


2 Years after budget availablity. Budget:-
13 Crore required.
iii. RSPCB collects samples from the
identified water bodies for pre-monsoon
analysis. Samples have been collected in
Bharatpur on 26.06.2019 and Jaipur in
June 2019 at Nevta Dam.

2. Based on 1st step, design of i. Six drains have been identified by Feb. 2020
detention basin, if needed K'patan and action on detention plan will
be taken after DPR preparation. DPR has
been prepared and it is under submission.
13 Crore Fund will be required for
construction of integrated wastewater
and septage management plant.
Drains are chocked before Clearing of drains and disposal i. WRD Department: Being done as regular Before arrival of
monsoon of extracted material before activity pre-monsoon, every year by Water next monsoon (Till
monsoon. Resource Department, however, May 2019)
contamination still reaching rivers in first
flush.
ii. RIICO
In RIICO industrial area cleaning of drain
and disposal of extracted material is a
ongoing process.

For FY 2019-20:

 Expenditure = 38.26 Lacs

Rajasthan State information being submitted to CPCB Page 28


 Physical achievement= 22.0 km drain
length has been cleaned and repaired
with immediate lifting of sludge in
RIICO I/A located in Kota city .

For current FY 2020-21:

There is a financial provision of Rs 32.00


lacs for cleaning & repairing of 26.0 km
drains in RIICO I/A located in Kota City.

 For cleaning& repairing of drains


before coming monsoon , W/o of
amounting Rs 30.89 lacs has already
been issued for IA IPI, Chambal and
Electronic complex. Presently works
are under progress.
LSG Department:
iii. All drains of municipal area are
cleaned in month of May & June
2020.

Rajasthan State information being submitted to CPCB Page 29


Biomedical waste disposal Monitoring and technical Jaipur: Joint inspection of CBMWTDF by 12 months after
auditing of Bio-medical waste RSPCB & Health Department, GoR on award of work and
treatment and review/monitoring 31.07.2019. environmental
of processing plant.
clearance.
Kota:

 At present, there is no CBMWTDF at


Kota.
 Presently, M/s Hoswin Incinerator,
Jhalawar (CBWTDF) has been
authorised by Nagar Nigam, Kota (under
working arrangement) for disposal of
biomedical waste generated from HCFs
of Kota and Bundi districts. M/s Hoswin
Incinerator, Jhalawar was inspected on
25/06/2019 and 03/02/2020.
 Work order has been given to M/s Bio-
medical Waste Disposal Agency for
establishment of new common facility
(under working arrangement) by Nagar
Nigam, Kota. Lease deed is under
process.

Currently Bio Medical waste of Kota and


Bundi District is being treated at Jhalawar
Plant.
Runoff from agriculture Adopting water conservation i. Subsidy to the farmers is being granted One year
fields is reaching river practices like drip and sprinkler for the use of drip and sprinkler irrigation
stretches. irrigation systems Agriculture systems, by Agriculture Department.
department should collect

Rajasthan State information being submitted to CPCB Page 30


Also, fertilizers and information on irrigation water ii. Director, Agriculture Research Station,
pesticides are found in river used/hectare for different seasons Durgapura, Jaipur has been requested by
water for different crops for different RSPCB to do the same as per action plan.
areas and evaluate whether the iii. For preventing runoff from agriculture
use of irrigation water/hectare fields and increasing water use
has decreased or not. efficiency, some efforts are being made
to promote drip and sprinkler irrigation
systems in the region. During the year
2018-19, an area of 875 hectares and 261
hectares has been covered under
sprinkler and drip systems respectively.
An area of 2500 hectares and 900
hectares is proposed to be covered under
sprinkler and drip systems respectively
in Kota &Bundi region during the year
2019-20.
iv. In the region, 74 farm ponds on individual
farmer fields and 01 community farm pond
have been constructed to collect the runoff
and reuse it for irrigation purpose in
general and for life saving irrigation
purpose in particular.
RSPCB:
Samples were collected from:

a. D/s of Kota Barrage, Kota at Karbala


(Kota stretch);

Rajasthan State information being submitted to CPCB Page 31


b. Keshoraipatan U/s near Shri Raj
Rajeshwar Mahadev Temple
(Keshoraipatan stretch);
c. Keshoraipatan D/s near
Keshoraipatan (Keshraipatan
Stretch);
d. Kota Barrage at Kota at Karbala,
River Chambal;
e. Distt- Sawai Madhopur at
Rameshwar Ghat, Bathing Ghat,
River Chambal;
f. River Banas, Distt. Sawai Madhopur,
Nar Banas Bridge, Lalsoth to Sawai
Madhopur Road;
g. Nevta Dam, Jaipur, Rajasthan.

The analysis report shows all tested


pesticides below detection limit (Detection
limit was 0.1 ng/l,)
Adopting best management i. Agriculture department is already taking One year
practices for fertilizer and actions to minimize the use of fertilizers
pesticide usage. However, like and pesticides.
runoff spatial and temporal data ii. For minimizing the use fertilizer &
may be collected and analyzed pesticides, organic farming is being
promoted in the region. 100 clusters of
organic farming have been created
covering an area of 2000 hectares and
4864 farmers. 64 training programs for

Rajasthan State information being submitted to CPCB Page 32


promoting organic farming have also been
organized thus benefiting 4540 farmers.
iii. 115501 Soil health cards have been
distributed in Kota and 153423 Soil health
cards in Bundi district to the farmers for
balanced use of fertilizers. For
minimizing indiscriminate use of
pesticides, 30 training programs have
been organized for promoting integrated
pest & management practices.
Farmer education for reducing Designing of mass awareness program in Six months to
runoff, use of fertilizer and vernacular language for farmers is being design such
pesticides as well as reducing done. training workshops
groundwater over exploitation and then next one
etc. Also, organic farming must year for organizing
be encouraged in these stretched. such workshops at
regular interval
(twice every year)

Monitoring presence of
pesticides in water samples At regular interval
including analysis of other (suggested twice
groups also in addition to organo- every year)
chlorines
Agriculture department: The one time
sampling report available shows the presence
of DDT much below the standard limit.

Rajasthan State information being submitted to CPCB Page 33


RSPCB:
Samples were collected from:

a. D/s of Kota Barrage, Kota at Karbala


(Kota stretch);
b. Keshoraipatan U/s near Shri Raj
Rajeshwar Mahadev Temple
(Keshoraipatan stretch);
c. Keshoraipatan D/s near
Keshoraipatan (Keshraipatan
Stretch);
d. Kota Barrage at Kota at Karbala,
River Chambal;
e. Distt- Sawai Madhopur at
Rameshwar Ghat, Bathing Ghat,
River Chambal;
f. River Banas, Distt. Sawai Madhopur,
Nar Banas Bridge, Lalsoth to Sawai
Madhopur Road;
g. Nevta Dam, Jaipur, Rajasthan.

The analysis report shows all tested


pesticides below detection limit (Detection
limit was 0.1 ng/l,)

During SESTF meeting dated 07/01/2020


and 18/03/2020 at Kota, representative of
Agriculture Department, Kota informed that
they don’t have funds to get the samples

Rajasthan State information being submitted to CPCB Page 34


tested. He was advised to get the samples
tested at Agriculture Laboratory, Durgapura
Jaipur in the same way RSPCB got the
samples tested
Solid waste dumping sites Develop landfill site with LSG Department:
without proper sanitary leachate collection (with its i. In Kota, 04 time waste to energy
landfill sites scientific treatment before processing facilities tendering has
been done. Tender was not finalized
disposal) and monitoring well
because first time EMD forfeited and
in remaining case no bidder turned
up. 5th time waste to compost tender
was done but no bidder turned up.
ii. Again, Waste to Compost tender shall
be invited after preparation of DPR.
The tender has been invited for
preparing DPR.
iii. Ground water monitoring will be done
by concessionaire.
iv. Construction of MRF shade work is
complete. Door to Door collection is
happening. Tender invited to Solid
Waste Management facility and is under
approval. According to the rules of
Solid Waste Management Rules 2016,
for disposing of transported solid waste,
scientific landfill is required to be
developed at a distance of 500 meters
from the population area. Due to non-
availability of land at a distance of 500
meters from the population area near the
municipality, the proposal for allotment
of land has been sent to Tehsildar Tehsil

Rajasthan State information being submitted to CPCB Page 35


[Link] by selecting suitable land
Khasra number 1255 acre 6.64 ha and
Khasra number 1264 acre 5.16 ha. After
the allotment to the land municipality, a
tender will be invited for the
construction of Landfill Plant. Currently
waste is being segregated at dumping
site and RDF is being prepared.

RIICO:

i. For collection of industrial solid


waste from stone industry, RIICO
has earmarked dumping sites (12500
sqm.) In Indraprastha industrial area
Kota.
ii. At present SPV- Pashan Welfare
Society (created by stone based
industries of Kota) is utilizing waste
produced by Kota stone industries for
making of Tiles, Bricks, and
Interlocking Tiles etc.
Pashan Welfare Society is working
from 16 June 2018 and till date
approx. 7000 MT stone slurry and
about 9000 MT waste (Kota Stone
Pieces) has been utilized for making
Tiles, Bricks, Interlocking Tiles etc.

Industrial untreated/ Drains passing through industrial RSPCB: four times every
partially treated waste is area must be identified and

Rajasthan State information being submitted to CPCB Page 36


reaching river in Kota marker pollutants (based on  Samples of effluent from drains passing year monitoring by
stretch industries) should be regularly through industrial area were collected on RSPCB at regular
monitored. Steps should be taken 02/08/2019 and found compliant of interval
to prevent any violations and effluent standards.
 Samples of the treated effluent being
punitive action initiated on
recycled/ reused and being discharged by
continued violations. industries (M/s Shriram Rayons, Kota &
M/s DCM Shriram Limited, Kota) were
collected on 02/08/2019 and found
compliant of effluent standards.
 Samples from these points were re-
collected on 05.11.2019 and 06/08/2020.
 Ground water samples of non-PHED tube
wells/ hand pumps located on both the
bank of River Chambal (Kota District)
non-PHED tube wells/ hand pumps
located on the bank of River Chambal
(Bundi District) were collected on
08/04/2019 & 09/04/2019 (Kota) and on
17/05/2019 (Bundi) to identify infected
tube wells/hand pumps (if any).
 Analysis report revealed presence of
coliform in all the samples of non-PHED
tube wells/ hand pumps located on both
the bank of River Chambal.
 Analysis report revealed 4 out of 15 tube
wells of Kota and 2 out of 11 tube wells of
Bundi have potable water and rest are
infected and the infected tube wells are to
be either recovered or to be abandoned by
the PHED at Bundi and jointly by PHED
& Ground Water Department for Kota
District as decided in the SESTF Meetings

Rajasthan State information being submitted to CPCB Page 37


at Bundi and Kota respectively. Letters in
this regard have been issued to the PHED
& GWD on 16.03.2020.
 As decided in the SESTF Kota meeting
dated 16/09/2020 sampling of all the
borewells be again carried out post-
monsoon and be tested by PHED, samples
being collected.
 During SESTF meeting dated
01/07/2019, Chairman (Additional
District Magistrate -Administration,
Kota) directed Jr Hydrogeologist,
Ground Water Department to take
necessary action for recovery of these
ground water sources by the way
disinfection otherwise abandoned
these ground water sources.
 Meetings of Special Task Force of
Police Department:
 STF, Kota (Kota) – Last meeting was
held on dated 08/04/2019, 01/07/2019,
18.10.2019, 8/1/2020 & 18/03/2020,
17.06.2020, 16.09.2020.
 STF, Kota (Bundi) – Last meeting
was held on dated 16/05/2019 &
27/1/2020, 30.06.2020, 16.09.2020.
 STF, Jaipur (South) – Last meeting
was held on dated 02/04/2019,
02.09.2019, 05.08.2020.
 STF, Pali (Sirohi) – Last meeting was
held on dated 09/04/2019.
 STF, Bharatpur (SawaiMadhopur) –
Last meeting was held on dated

Rajasthan State information being submitted to CPCB Page 38


09/04/2019, 10.08.2020, 24.08.2020,
14.09.2020, 28.09.2020
Recycling of treated effluent by i. RIICO is agreeing to provide all Three months
industries itself by treating trade possible assistants to RSPCB for
effluent up to reuse level. Check motivating industries for reuse of
compliance. treated trade effluent. RSPCB has been
informed accordingly by RIICO vide
letter dated 07.03.2019.
ii. For environmental management and
pollution control in Industrial Areas,
RIICO incorporated various clauses in
RIICO lease deed.
iii. To bind the Lessee with term and
conditions imposed by RSPCB in
CTE/CTO, RIICO incorporated
following clause in lease deed.
iv. As per Lease Deed, clause (4a)……..
"The Lessee shall obtained all requisite
clearances/consent/
approval/authorization from the
competent authorities such as
MoEF&CC, SEIAA, CPCB, RSPCB,
CGWA etc. for the project/industry.
The lessee shall also observe and
comply with the terms and conditions so
imposed by aforesaid authorities and
shall also strictly adhere the
guidelines/directions/orders issued from
time to time in this regard.

Rajasthan State information being submitted to CPCB Page 39


v. Sample of treated effluent being
recycled/reused & being discharged by
M/S Shriram Rayons Kota & M/S DCM
Shriram Limited Kota have been
collected on 1.4.19 by RSPCB.

Identification of clusters of During the meeting dated 08.03.2019 Six months for
small-scale industries in the Kota under chairmanship of CS, after DPR preparation
city. CETP should be establish discussions it was informed that no CETP and tendering
for these clusters has been proposed for Kota industrial area process
as there is no requirement of the same at
present.

Out of 33 drains monitored Identify reason for high BOD Six drain are identified in municipal area Six months
one time in Kota, some have (open defecation, leaching from which is discharge into chambal river. Two
high BOD range. solid waste dump site, and waste water treatment plant proposed for
Similar in Keshoraipatan contributions from some small treatment of drain water. Land allotted for
area scale industrial/commercial WTP & FSTP Plant demarcation of land is
clusters). Take scientific done and leveling sheet of exiting land
measures to control that. Action topographical map of town prepared. Soil
based on analysis. testing of proposed land submitted to MNIT.
Work order for making DPR has been issued
for the establishment of Waste Water
Treatment Plant. DPR has been prepared and
submitted for Budget approval. 13 Crore
Fund will be required for construction of
integrated wastewater and septage
management plant. Budget provision not

Rajasthan State information being submitted to CPCB Page 40


approved by Finance Department and ULB
doesn't have funds. ULB has installed the
gratings and regular cleaning is being done at
all 06 Drains.
Low level of BOD in Explore possibility of closed A. Close conduits Six months to
sewage reaching existing conduit sewerage system for STP i. It is stated that the work of package RBS- identify sources of
STP. Microbial growth or identify sources of dilution and 02 regarding construction of 30 MLD & leakage and
would be adversely affected propose action plan for the same. related sewer lines is rescinded due to slow propose action on
due to low BOD. progress of work by the UIT Kota after the same.
prior approval of UDD on 3.8.2016.
ii. For completion of remaining work under
this package revised proposal has been
submitted to UDD.
iii. Till the rescind date closed conduit of
1000/1200 mm diameter RCC pipes NP4
is already laid in a length of about 1200 mtr
upstream of 30 MLD STP, which carries
flow of SajidehraNallah to receiving
chamber to 30 MLD. The low level of
BOD reaching 30 MLD is due to collection
of carries flow of SajidehraNallah as
sewerage network.
iv. After receiving revised A&F sanction of
remaining work balance sewer lines will
be laid & property connection will be done
to get raw sewage.
Water pipeline leakage.
v. As per MNIT report, low level of BOD in
sewage is also due to leakages in water

Rajasthan State information being submitted to CPCB Page 41


pipeline which would be controlled by
PHED.
Seepage from canal:
vi. The FSL of CRMC is at lower level as
compared to invert level of open drains.
Hence possibility of seepage from canal is
not practical.
In Kota additional 55MLD Ensure diluted sewage is not i. In Kota, two STP of 30 MLD and 20
+6 MLD STPs are under reaching planned STPs. MLD are working.
process. This would lead to Explore possibility of closed ii. Total 05 STP's are proposed under
65% population coverage conduit sewerage system for STP different scheme with the total
or else possibility of capacity of 78 MLD. Work of all 5
decentralized STPs to avoid STPs is under progress and will be
dilution by other streams than completed by 2022. After completion
domestic sewage of these STP's total coverage will
80% In Kota.
iii. Timeline:- June 2022.
iv. Budget:- Total cost is 584 Crore and
being executed From RUIDP Fund.
v. A&F sanction of remaining work,
balance sewer lines will be laid &
property connection will be done to
get raw sewage.
35% of Kota population is Faecal sludge characterization i. For remaining 35% population of
still not covered under lab may be established in any Kota the co-treatment of faecal sludge
sewerage system. existing institute/research lab. is proposed in existing STP by
Also, no sewerage system at Scientific management of faecal RUIDP.
Keshoraipatan. sludge should be carried out for ii. Two STP of 30 MLD and 20 MLD are
on-site treatment facilities. working.

Rajasthan State information being submitted to CPCB Page 42


For remaining 35% population in iii. Total 05 STP's are proposed under
Kota the co treatment of faecal different scheme with the total
sludge is proposed in existing capacity of 78 MLD. Work of all 5
STPs. STPs is under progress and will be
Similarly, in Keshoraipatan, completed by 2022. After completion
concept note for FSTP is made of these STP's total coverage will
but funds not allocated 80% In Kota.
iv. Timeline:- June 2022.
v. Budget:- Total cost is 584 Crore and
being executed From RUIDP Fund.
vi. For Keshoraipatan Work of DPR for
Integrated Wastewater and Septage
Management Plan has been given to
NIUA by LSG Department. NIUA
submitted the feasibility report for the
work and total cost of the project will
be Rs 10 crores made by MNIT. Due
to Non availability of land till April
2019 the DPR work could not started.
Land for Waste treatment plant and
for FSTP has been allotted at
Keshoraipatan by Collector Bundi in
June end. Direction has been issued to
ULB for preparing the DPR by
tendering process. DPR has been
prepared and it is under
submission. 13 Crore Fund will be
required for construction of

Rajasthan State information being submitted to CPCB Page 43


integrated wastewater and septage
management plant.

Poor ghat/temple Public toilets must be prepared. Three community toilet constructed [Link] Six Months
management leading to Proper solid waste management Chambal river bank & all are in functional
pollution of river at system should be developed. condition
Keshoraipatan (Also, at Rangpur, other side of
Chambal river)
It was discussed that Similar monitoring and action i. None of the sources have been found to Six months
periodic water quality must also be taken on non- be infected, in PHED’s database of water
assessment of all tube drinking water TW/HP of these quality assessment of TW/HP used for
wells/hand pumps stretches. Standard for non- drinking purpose, of the area suggested
(TW/HP) used for drinking drinking TW/HP must be framed. by MNIT (Akelgarh, Rangpur,
water purpose is made. Database of such reporting and Keshoraipatan & Nevta Dam)
Also, an immediate action taken must be available ii. Concerned District collectors are taking
remedial action of sealing action for the assessment of non-drinking
of infected TW/HP is taken. water TW/HPs.
Subsequently if it is
determined that infected
TW/HP could be recovered
by disinfection, it is
recovered, and otherwise it
is abandoned. However, no
database of such action is
easily available
Over exploited Many RWH structures RWH structures which had been constructed Maintenance for
groundwater regions in constructed. by WRD Department in Kota – next year must
Kota, Keshoraipatan and Keshaoraipatan stretches have been handed start from March
Nevta Dam stretches over to Gram Panchayat. Maintenance of 2019.

Rajasthan State information being submitted to CPCB Page 44


Regular monitoring and these structures is to be done by Panchayati
maintenance must be carried out Raj Department. No RWHS are constructed
before monsoon in the catchment of Nevta Dam by WRD.
Requirement of e-flow must E-flow of 5000 cusec released Compliance is being made. E-flow of 5000
be maintained for 35 minutes from Kota cusecs for 35 minutes in river Chambal is
Barrage every Monday during being released from Kota Barrage. on each
non-e-flow period only, i.e. all Monday.
Mondays during January to Date Water Remarks
onset of Monsoon. released in
cusec
06.1.20 5100
13.01.20 5128
20.01.20 5120
27.01.20 5128
03.02.20 5128
10.02.20 5128
17.02.20 5128
24.02.20 5128
02.03.20 5128
09.03.20 5128
16.03.20 5128
23.03.20 5128
30.03.20 5084
06.04.20 5034
13.04.20 5055
20.04.20 4970
27.04.20 4848
04.05.20 4874
11.05.20 4938
18.05.20 4862
25.05.20 4982

Rajasthan State information being submitted to CPCB Page 45


01.06.20 4894
08.06.20 5040
15.06.20 4996
22.06.20 4918
29.06.20 4996

122 Non-attainment cities


Name and designation of designated officer for ensuring compliance to provisions under statute: Matter does not fall under any
statute. Nodal department for monitoring is Department of Environment, GoR.;
The officials mentioned below are from RIICO:
Jaipur: Satish. K. Gupta (Sr. DGM), Ajay Gupta (Sr. DGM), Mahendra Singh (Sr. RM), [Link] Ruhela (Sr. RM).
Udaipur: Sanjay Nenavati (Sr. RM)
Kota: [Link] (Sr. RM)
Jodhpur: Sanjay K. Jha (Sr. RM),Kuldeep Dhadich (RM)
Alwar: [Link] (Sr. RM)
Sl. Item Source Current Status Desirable level Gap between Timefra
No group as per statutes/ Current status me for
approved action and desired addressi
plan levels ng the
Gap

Rajasthan State information being submitted to CPCB Page 46


owfdq alfrftfr sqrq gw dq slz76 (1-*"r1 vqvnn dqg(
.+tqi,
inrq-d ?ffq, gtclF
\rvqdt grenr g€m{iF. elr, qqgs_sozool Fr*n)
rqrenF-o Sa

ftFn, Ailq
w ftiero,
q-qt{ioT fr.,1rl
q-qg{ Rl-Renc.

ftEq :-submission of State Dossier and Monthly progress


Report (MpR) to
Central Monitoring Commitee in Matter of O.A. No. 673/20tg.
qr+f :-erqOf !:{ @-[Link] o6(31/Env/20r7
ftqiO_re rr zozo.
T6)qs,

Bq0-ff [Link] r4sffi-d q-r d o-q { qr+ftq [Link].O. o1 efR-w+o


\drdclq ;r1q\ 673/2018 d qrE$ i EilH q-qd c-fi G qq d ftqlt w o-qrt
Eefitu'r of qrft-f, [Link] Rfd gd rt s-gg-d o1 qr g+t B (cfr g{, e-f,q) asTr
Tw|fo droqs G-crrd-q) tnt Format eq-a-er orrit deir q6,ff erq,ro Orrii [Link]
G)fu'w d fu'c fr-gerI or r+qd$ fu-qr qrfl.t r

ro'q-sqoEeT{

TS-drqT,

,^St^.,,g-
(RTqT q6-{)
erfrftff cqFr gq c=r s{Ettn,
(,t-sqer"T) {K*en-q. qqg{

D:\All letter and file parewa\Tejendra pal singh\[Link]


orqfdq aftfu yqq
W Fr vwv (q.-lvt'ttrvr) wftn,n,
wirdl qrfi, flqnr riprtff.o eta, wqqc_gozooa ({rs.)
Cw 08( )Nar7t /\q./201647 / AUgs 22lq 2+
w ft*{rfi.
qq{svw ftqFT
-q'qgq clstTsr|;I,

ftT{l:-submission of Monthly progress Reports( I\IPR to Central


Monitoring Commitee in Matter of O.A. No. 673r ,::0
qEd{rTc"d orqfdq qrT q" @-[Link] 12(83)/Env/20: 15.07.18.
c-dcq,

scciffi ftvqmrf-d
riEffi-d tr{doqitftfs-{tfoq ix-{.fi.a. qft
3lifu-q-f, \'fr1'q TR-{ o7sl201s qW it qqm
d vq qq-d .'lql d frrflt c-{
m-trt W qe{ttq'ur of errrqn 2o2o da'.bt qfto. errfr ffid Trf,rr

$ct.1-$c|(trg$rt

qq:-

str
(Rret
oTfrfrfi qqn
(q-{i{eTor) c
-//

D:\All letter and file paqewa\[Link] pal singh\[Link]


clql hl
H (91I
qi TRet-6 ,T{I Glcl,
\r tq

1 [Link] T|qId 50 20r4-t5 r0000


2 n+dr -llq l'5 5(I 2014-t5 10000
3 erDrqN) -J
nqn* 5(l 20 t4-15 t0000
4 -l tq i.5
\111t '.] |
5(r 20t4-15 10000
Uq qi (l (tilq'1, q -tfullq
5
vr$q eE-f, qgvld R"a-qrel-q RDF' 5(, 2015-16 25000
6 ft-f,qlqT-fr RDF 5C 20r5-16 25000
7 \5lcli RDF 5C 20r5-16 25000
8 qcDerI{I ttqt.5
-.-_J 50 2015-16 10000
9 qr€Ef{f nrflrt 50 2015-r6 10000
]Tf,I .--.--'-_t
.l
10 t6t l{i 50 20t 6-17 I 000c1
s-t s{e 6,{al \rltq, a tc {
,.-'1 Sakatpura Campa 50 20l4-l5 27000
2 Sakatpura - A Cam pa 50 201 5- l6 25000
3 Sakatpula -B Campa J .18 20t6-t7
4
Tg E;I rwem, Tqffs Akelgarh
r7000

5
Tqflr {Sq serq, BoLkui
Nabar,l
Nabard
50
50
2013-14
2015-16
10000
Cptcl r0000
b Sakatpura - II Nabarrl 50 20r5-r6 r0000
7 Sakatpura - III Nabard 4< 2016-17 9000
8 Sakatpura - IV Nabard U 20t6-17 I 0000
q;I sftrd
1 uflft-qrdT Nabard 50 2013-14 10000
2 rTdqf{-1 Nabard 50 20t3-14 t0000
3 q\\5
-x-- Campei 50 2013-14 I0000
4 ddfqrdr tr{qrq -- r Nabald 50 2013-14 I 7000
5 TIGcIR_TI Nabarcl 50 20r4-15 I 0000
o d$ql-dT E-{qTq il Nabard 50 2014- l5 10000
7
gq zt{ ${effi , 6i-fr ]T6qT{-ITI Nabald 50 .20 I 5- 16 10000
8 gTR-T Nabard 50 201 5- 16 10000
9 gTR*TI Nabard 50 2015-16 10000
qR cci 6T
f6rtT{ oT [Link] 50 1016-17 25000
10 qilrq)q"oT
11 sq$r Nabard 50 20t6-17 t0000
'J.2
1\sll Campa 4 95: l0l6-17 3500
T.nq8-r
II 20 r0 7000

1l 20 r0 8500
1: 201 0
900
I. 20 r0
rsq
[. 201 0
$o
C 20t0 5000
! 20t 0 5000
5U 201 0 r0000
5 2010 r000
5 2011 r0000
5( 20il r0000
5( 201|
w ++ mao. utagr i2000
5C 201 1
500
50 20ll r000
50 20t2 r0000
r0c 20 t2 20000
50 2013 25000
50 20t3 2s000
50 20t3 25000
50 20 t3 25000
50 2014-15 35000
50 20t5-t6 3 5000
50 2016-17 10000
s0 20 t 6,t7 r0000
50 20 6-)7
t r0000
50 20 | 6-t7 r0000
ql TReffi q'q dq,
gq qq s{ero gq
w e}-a
fttpTo &-fiq wTsrer)-{
zvtJ-t4 r0000
eTq qRmq-fl ft*+fr

20t8-19

.^St.,'.i-.
(iPr?rr q-d-{r)
srft r. rT;r5Cq Tr FTerF,
1T Tiy,. $qi€n{, u-q!{
I
l:

1_
r;I. Uqqr

6.H. SI]I!'€NT OI flq o|fierd 6'r ilq qIvHl Hqs qlqi


sd al*qT
q{l a.r T{tt6 3ra{ l?
1
Ert'$Td RFBP 60 2006 I0000
2
rTdg-sr RFBP 50 2006 25000
3
4lRl FDA 50 2009 10000
qq{l I'DA 50 t0 r0 10000
5
clt19l FDA 50 2010 10000
6
Flt\rt6 Canpa AllR 50 20 r:l t0000
1
iq{rqr gs RFBP RDF^I i5 20 ll 17500
8
ffiqi RFBP [Link] 50 20t4 10000
9
snhifAqr RFt]P RDl].II 5U 2011 t0000
10 =.1+[Link] fiDA A^NR 50 2014 10000
't1
u9 ql n,(fl(f), tniliRqr S. Plan RDF 50 2014 25000
'12 m-c|4reT
cptcl RFBP RD.F-I 35 2015 17500
13 IErrT'r RFBP RDII-I1 50 20 t5 r0000
T4 IIq|lT{I RFB P-F\I/P 25 2015 20000
15
g\nt(sl S, Plan RDI. 50 2015 25000
1,6 cplcl [Link] 50 20t6 2 5000
!7 rrrorfr q-or S. Plan RDF 50 l0l6 25 000
18 qzlT;lrf{i
[Link] II' 50 2016 I0000
19 3nsr qftql S, Plan RDF 50 20t6 25000
20 oib-q Wr Canrpa A\lR 50 20t6 r0000
2r ordi re-rg i-{-{ za Crnrpa AlrlR l8 20 t9-20 5 600
22 r<{q o}-gr 2o1e-20 *r-{ 50 S. Plan Rl,F 50 20:0..: r 25 000

mrr tati6
1
Campa 50 20 t9-20 10000
2
Campa 50 2020-21 10000
3
Campa 50 3014.t5 10000
4

5
gq ?FI rl-{effi \rq F Nabard 50 20t4, t5 t0000
rtsd 3rffi (\a{.fr E6-f,Iq-r Nabard 50 20 t3- I.1 r0000
6
a)ea(mngr qFfitq-ll Nabard 50 20ti- i4 10000
7 Itfq{ T|{q [Link] 5 2017 - 18 t000
8 ItNl qTrr-T IVIJSA-iI 5 20t7- r8 1000
9 ffq irmt d^<T MJSA.I] 5 2017-r8 1000
10 fl-q uw q<t-n [Link] 5 2017-r8 1000
d{ tfieliF,
1
Vtl Ti g?8f.5 \l?uq? 5"n) or 1vr Nabard- | 45 20t5-t6 9000
2
3RR snt Nabard-i 50 2015- l6 10000
3 der ot] za{ Nabard-lll 50 20t6-17 10000

.,-SL't^-.*
{lfl'gl Tf,a)
oitclt(.tcl qqn Tct qi {erm( T-s{eT'r)

TqrcRarF,wrg{ 1-
Detail of each existing STPs in Rajasthan State
Annexure -1
Existing STP Capacity being
[Link]. Location Capacity utilized Operational Status of STP Compilance Status of STP
(MLD) (MLD)

1 Khanpura (Ajmer) 20 12.00 Operational (Upgradation work under AMRUT)

2 Anasagar (Ajmer) 13 10.00 Operational CTO applied on dated29.05.2019

3 Jerla (Balotra) 9 3.00 Operational CTO applied on dated_18.03.2020

4 Near Madela Road (Chirawa) 3 1.00 Operational CTO granted & complied

Pratappura (Bhoikhera)
5 5 1.00 Operational CTO granted & valid upto 31.10.2022
(Chitttorgarh)
Near Abhimanyu Park
6 3 1.00 Operational CTO applied on dated 03.01.2017 permission awaited
(Chitttorgarh)
7 Mela Maidan (Deedwana) 5 3.00 Operational CTE applied on dated_14.12.2016
Nari Bari Road (Fatehpur
8 7.5 6.00 Operational CTO Applied 30.09.2020.
Shekhawati)
Near Jaipur Highway (Gangapur CTO Not applied shall be applied with in 02 months
9 5.5 1.56 Operational
City)
Near Railway bridge over Ghaggar
10 5 4.28 Operational CTO granted & complied
river (Hanumangarh)
CTE expired on 30.11.2013 and fresh appliucation for CTE
11 Jadkiya Phatak (Hanumangarh) 7.5 5.00 Operational
shall be applied with in 02 months
12 Jaccha ki bawri (Hindaun City) 0.75 0.75 Operational CTO granted & complied

13 Brahmpuri STP (Jaipur) 8 8.00 Operational CTO granted & complied

14 Dehlawas unit I (Jaipur) 62.5 62.5 Operational (Upgradation work under AMRUT)

15 Paladi Meena (Jaipur) 3 0.80 Operational CTO granted & complied

16 Central Park (Jaipur) 1 0.70 Operational CTO granted & complied

17 Ralawta (Jaipur) 30 22.00 Operational CTO granted & complied

18 Gajdharpura (Jaipur) 30 22.00 Operational CTO granted & complied

19 Ram Niwas Bagh (Jaipur) 1 0.60 Operational CTO granted & complied

20 Jawahar Circle (Jaipur) 1 0.35 Operational CTO granted & complied

21 Swarnjayanti Park (Jaipur) 1 0.90 Operational CTO granted & complied


CTO Not applied
22 Sahkar Marg (Jaipur) 1 0.30 Operational
(will be applied with in 02 months
23 Kiro Ki Dhani (Jaipur) 1 0.50 Operational CTO granted & complied

24 Dravyawati River- PaniPech (Jaipur) 20 15.00 Operational CTO granted & complied
Dravyawati River- Mansarovar
25 15 12.00 Operational CTO granted & complied
(Jaipur)
Dravyawati River- Taruchya Nagar
26 100 70.00 Operational CTO granted & complied
(Jaipur)
Dravyawati River- Pratap Nagar
27 25 13.00 Operational CTO granted & complied
(Jaipur)
28 Dravyawati River- Goner (Jaipur) 10 5.00 Operational CTO granted & complied

29 Dehlawas unit II (Jaipur) 62.5 62.50 Operational Under upgradation

30 Jaisinghpura Khore (Jaipur) 50 50.00 Operational CTO granted & complied

31 Near Karolia village (Jaipur) 2 0.60 Operational CTO granted & complied
Near Indira Awas colony
32 1.5 0.68 Operational CTO granted & complied
(Laxmangarh)
33 Near Kidwai Stadium (Makrana) 6 3.50 Operational CTO applied on dated_13.07.2020.
Detail of each existing STPs in Rajasthan State
Annexure -1
Existing STP Capacity being
[Link]. Location Capacity utilized Operational Status of STP Compilance Status of STP
(MLD) (MLD)
CTE expired on 31.07.2018 and fresh application for CTE
34 Balwa Road (Nagaur) 8 3.50 Operational shall be applied with in 02 months
(Upgradation taken under AMRUT)
35 Suratgarh road (Sriganganagar) 10 1.73 Operational CTO Applied on dated_
CTO expired on 31.07.2015 and fresh application for CTO
Bharatpur Road near Agyarah Dam
36 20 14.00 Operational shall be applied with in Two month
(Alwar)
(Upgradation taken under AMRUT)
Near Vijay Nagar Private Bus Stand CTO Not applied
37 5 1.00 Operational
(Beawar) (will be applied with in 02 months)
CTO Not applied
38 Near Narsingh Pura (Beawar) 4 2.00 Operational
(will be applied with in 02 months)
CTO Not applied
39 Near Bichral Tank (Beawar) 1.5 0.30 Operational
(will be applied upto 31.03.2021)
CTO Not applied
40 Kundan Nagar (Beawar) 1 0.10 Operational
(will be applied upto 31.03.2021)
41 RHB (Bhiwadi) 1.5 0.70 Operational CTO granted & complied

42 MundenaMev (Bhiwadi) 2 0.15 Operational CTO granted & complied

43 Santhalka (Bhiwadi) 3 0.80 Operational CTO Applied dated 25.01.2019

44 Nr. Existing STP (Bhiwadi) 3 1.30 Operational CTO Applied dated 25.01.2019

45 Dhauheda (Bhiwadi) 4 4.00 Operational CTO Applied


CTO Applied on dated 14.09.2020.
46 Vallabgarden (Bikaner) 20 20.00 Operational
(Upgradation work under AMRUT)
CTO Not applied
47 Sareh Nathania (Bikaner) 12 8.35 Operational (will be applied with in 02 months)
(Upgradation work under AMRUT)
CTO Not applied
48 Tagawali (Dholpur) 10 7.75 Operational (will be applied upto 31.03.2021)
(Upgradation taken under AMRUT)
49 Shekhupur (Dholpur) 3 2.00 Operational CTO Applied
CTO Applied
50 Nandari (Jodhpur) 20 15.00 Operational
(Upgradation work under AMRUT)
51 Salawas Unit I (Jodhpur) 50 40.00 Operational CTO Granted

52 Salawas Unit II (Jodhpur) 50 30.00 Operational CTO Applied


Detail of each existing STPs in Rajasthan State
Annexure -1
Existing STP Capacity being
[Link]. Location Capacity utilized Operational Status of STP Compilance Status of STP
(MLD) (MLD)

CTE applied on 28.12.2020)


53 Nasirabad Highway (Kishangarh) 10 6.00 Operational

54 Goshala land (Sikar) 2 1.25 Operational CTO Granted

55 Near Shiv Colony (Sikar) 8 4.50 Operational CTO Granted


Near Shamshan Ghat, Kartana
56 2 0.8 Operational CTO Applied 30.07.2020.
(Nimbahera)
57 Near Panchayat Samiti (Kushalgarh) 1 1 Operational CTO Applied on dated 20.02.2020.

58 Kisanghat (Jaisalmer) 10 3.91 Operational CTO Applied on 20.04.2017 permission still awaited

59 Jalore 10 3.21 Operational CTE not applied, shall be applied with in 2 months.
Baga Road Near Agrasen Circle
60 8.5 0.00 Operational CTO Not applied
(Jhunjhunu)
61 Karauli 5 0.98 Operational CTO Applied
CTO Not applied shall be applied with in 02 months
62 Hetam Ji Village (Mt. Abu) 6 0.10 Operational

63 Village Sorwal (Sawai Madhopur) 10 2.91 Operational CTO Applied

64 Sumerpur 10 1.01 Operational

65 Village Kundla (Barmer) 10 4.00 Operational CTO Applied on dated 16.08.2016 permission is pending
Gopal Nangla (Rundhikiran)
66 8 1.20 Operational CTO Applied
(Bharatpur)
67 Devpura (Bundi) 8 4.00 Operational CTO granted and valid upto 31.03.2023.
CTE expired on dated 31.07.2016 and fresh application
68 Village Gajsar (Churu) 7 7.00 Operational
shall be apply within Two month Not applied
CTE expired on 31.10.2015, fresh CTE shall be applied
69 Gagrol Road (Jhalawar) 6 Operational
with in 2 months
4.00
70 Girdharpura (Jhalrapatan) 3 Operational CTE applied on 01.07.2020 for upgradation

71 Dhakarkhedi (Kota) 20 17.82 Operational CTO Not applied


Sajidhera (Kishorepura ladpura)
72 30 22.00 Operational CTO Applied
(Kota)
Mandia Road, Near ESI Hospital CTE expired on 31.12.2013 and fresh application shall be
73 7.5 2.00 Operational
(Pali) applied with in 2 Months
CTO Applied on 20.05.2017 under water act, application
74 Rajsamand 5 1.70 Operational
for DG set under Air act also required
75 Sardar Shahar 5 Operational CTO Not applied
2.45
CTO Not applied shall be applied with in 02 months
76 Sardar Shahar 2 Operational

77 Eklingpura (Udaipur) 20 12.00 Operational CTO Applied

78 Eklingpura (Udaipur) 25 25.00 Operational CTO granted & complied

79 Ghamaniya (banswara) 6.43 3.50 Operational CTO Not applied

80 Kewada (Bhilwara) 10 10.00 Operational CTO granted & complied

Total 999.18 694.54


Detail of under construction STPs in Rajasthan State
Annexure -2
Capacity Status of I&D
Physical
of the or House Incremental
[Link]. Location Progress Completion Timeline*
plant in Sewer Progress
(%)
MLD Connections

1 Pilani Road (Chirawa) 2 98% 2.00% Jan'2021


Near Existing Sedimentation tank
2 1 54% 7.67% June'2021
(Chittorgarh)
Near Abhimanyu Park
3 2 59% 6.83% June'2021
(Chittorgarh)
4 Near Gandhi nagar (Chittorgarh) 2 - - Work is yet to be started.
Near Mukhyamantri Jan Awas
5 1 59% 6.83% June'2021
Yojna (Chittorgarh)
6 Near Railway Station (Chittorgarh) 1 47% 8.83% June'2021

7 Near Kushal Lake (Gangapur City) 1.5 84% 5.33% March'2021


Near PHED campus (Gangapur
8 2.5 94% 6.00% Jan'2021
City)
Near Aliganj Tiraha (Gangapur
9 1.5 89% 3.67% March'2021
City)
10 Karauli road (Hindaun City) 3 85% 5.00% March'2021

11 Ragahv das Bagichi (Hindaun City) 5 90% 10.00% Jan'2021

12 Kartarpura Nallah (Jaipur) 1.3 -


Nil land allotment is pending.
13 Kartarpura Nallah (Jaipur) 2.4 -

14 Chaugan Stadium (Jaipur) 1 3% 4.04% Sep'2022

15 Dehlawas (Jaipur) 90 1% 2.75% March'2023


Payment issue with UIT, work with held
16 Khanpura (Ajmer) 40 95% due to financial crisis,. JnNURM schemen
closed in March 2017
17 Pushkar (Ajmer) 3.5 60% 1.67% March'2022
Near Basin Road Banjara Basti
18 1 95% 5.00% Jan'2021
(Laxmangarh)
19 TodhiKui (Laxmangarh) 3 99% 1.00% Jan'2021

20 Dulai Pond (Nagaur) 1.5 32% 6.80% Oct'2021

21 Idgah (Sriganganagar) 10 2% 10.89% Sep'2021

22 Sugarmill (Sriganganagar) 15 98% 0.67% March'2021


Near existing STP at Ikran Village
23 5 99% 1.00% Jan'2021
(Bharatpur)
Under litigation with Hon'ble High Court.
24 Khanpura (Bhiwadi) 2 61% -
Next hearing date is yet to be alloted.
25 Vallabh garden (Bikaner) 20 95% 2.50% March'2021
Near Kali Mata Mandir
26 20 72% 9.33% March'2021
Sujendarsar (Bikaner)
27 TajusaTakiya (Churu) 2.5 95% 2.50% Feb'2021
B/W Cremation ground
28 1 95% 2.50% Feb'2021
andAgarsen Nagar (Churu)
Detail of under construction STPs in Rajasthan State
Annexure -2
Capacity Status of I&D
Physical
of the or House Incremental
[Link]. Location Progress Completion Timeline*
plant in Sewer Progress
(%)
MLD Connections

29 Devi pura Beed (Sikar) 5 6% 18.80% May'2021

30 Near Mangri road (Badi Sadari) 1.5 99% 1.00% Jan'2021


Shamshan ghat (Ramgarh
31 2 99% 1.00% Jan'2021
Shekhawati)
32 Gogamedi (Ramgarh Shekhawati) 1 55% 15.00% March'2021

33 Gogamedi (Ramgarh Shekhawati) 1 55% 15.00% March'2021


Near Dashhera Maidan HSC shall be
34 4.5 5% 7.92% Dec'2021
(Nimbahera) completed
after
35 Kasod Basti Nalah (Nimbahera) 1 99% 1.00% Jan'2021
commissionin
Changedi village (Fatehnagar g of STPS
36 1 99% 1.00% Jan'2021
Sanwar)
37 Near subjail (Suratgarh) 2.5 99% 1.00% Jan'2021
Adarsh Kalyan Bhumi near
38 2.5 99% 1.00% Jan'2021
Anupgarh highway (Suratgarh)
39 Mahipaloka Mohalla (Bhadra) 1 97% 1.00% March'2021

40 Nathwana johad (Bhadra) 3.5 97% 1.00% March'2021

41 Near Fire station (Nawalgarh) 1 47% 17.67% March'2021

42 Bhakto Ka Johad (Nawalgarh) 1 6% 3.92% March'2022

43 Near Bus stand (Nawalgarh) 3 93% 7.00% Jan'2021

44 Gopalpura (Baran) 7 61% 7.80% May'2021


Gopal Gaushala on Thardaa Village
45 5.5 42% 6.44% Sep'2021
(Sujangarh)
Gaushala on Salasar Road
46 1.5 16% 9.33% Sep'2021
(Sujangarh)
Chaptia pond near F.C.I. Godown
47 1.5 12% 9.78% Sep'2021
(Sujangarh)
48 Near Kalkanda (Sujangarh) 2 41% 6.56% Sep'2021

49 FCI godown (Udaipur) 10 99% 1.00% Jan'2021

50 Kajrali house (Udaipur) 5 97% 1.50% Feb'2021


The STP was partially constructed in 2016.
Cost revision is under submission for
51 Balitalad pura (Kota) 6 48% -
approval. Matter is pending with GoI for
revised A&F.
52 Dhakar kheri (Kota) 40 20% 3.33% June'2022

53 Kala Talab (Kota) 15 16% 3.50% June'2022

54 IL Township (Kota) 2 Nil 4.55% Oct'2022

55 Balita (Kota) 15 Nil 4.55% Oct'2022


Detail of under construction STPs in Rajasthan State
Annexure -2
Capacity Status of I&D
Physical
of the or House Incremental
[Link]. Location Progress Completion Timeline*
plant in Sewer Progress
(%)
MLD Connections

56 Basni Bainda (Jodhpur) 40 35% 5.42% Dec'2021


Near RIICCO Bypass
57 4 10% -
(Hanumangarh) Contract terminated.
Near Railway bridge over Ghaggar matter is under arbitration.
58 2 10% -
river (Hanumangarh)
Detail of under construction STPs in Rajasthan State
Annexure -2
Capacity Status of I&D
Physical
of the or House Incremental
[Link]. Location Progress Completion Timeline*
plant in Sewer Progress
(%)
MLD Connections

59 Baga Road (Jhunjhunu) 7 99% - Jan'2021


Near Existing Jindal STP Kuwada
60 30 82% 6.00% Dec'2021
(Bhilwara)
61 Mandiya Road (Pali) 15 100% - HSCs will be completed by April'2022

62 Molai Pura (Tonk) 16 76% 3.43% Dec'2022

63 Dhaula Khera (Tonk) 4 82% 3.60% Dec'2022

64 South STP (Sardar Shahar) 2.3 Nil 3.57% June'2023

65 North STP (Sardar Shahar) 3.4 Nil 3.57% June'2023


Gandhi Vidhya Mandir (Sardar
66 1.6 Nil 3.57% June'2023
Shahar)
The unit of STP are not functinal as the flow
67 Ward No. 07 (Nokha) 1 100% - recahing at STP is higher than the designed
capacity.

Total 510 0
*Subject to availibility of funds.
Local Self Government Department

1. Compliance of SWM Rules 2016


Total MSW generation: ~ Approx 6500 TPD
Total Wards - 5464
Door to Door Collection: - 5464 wards
Bye laws have been finalized and issued.
State action plan has been approved and circulated and sent to RSPCB for
submission to Hon'ble NGT.

Solid Waste Management Plant Details


Plant Number of Plant Capacity (TPD)
Running Centralized 8 947
Processing Plant
Processing Plant Running 20 2337
under Pipeline
Processing Plant Under 5 760
Tendering Process
Tender Document Under 9 280
preparation
Operational MRF 66 450

1052 TPD is being processed by BWGs/ Recyclers and pit Composting,


garden composting and Remaining 674 TPD is being dumped unplanned
at landfill sites.
City wise Status of Processing & Disposal of waste:

[Link] City/Town Processing Plant Highest Name of Status


Technolog Capacity Royalty Firm
y (TPD) payable by
Contractor to
ULB
Running Centralized Processing Plant
1 Jaipur WtE 350 On PPP M/s Grasim Running full
(RDF) India Ltd capacity
2 Jaipur Compost 250 Royalty M/s IL&FS Running full
capacity
3 Pratapgarh Vermi 6 By ULB Fund By ULB Running
Compost
4 Dungarpur Vermi 7 By ULB Fund By ULB Running
Compost
5 Pali Compost+ 100 Royalty Rs M/s Rollz Construction
RDF 301/Ton on Material work has been
SLF input Handling finished and Plant
System Pvt. has been
Ltd. New commissioned.
Delhi
6 Bhilwara Compost+ 144 Royalty Rs M/s Rollz Construction
RDF 401/Ton on Material work has been
SLF input Handling finished and Plan
System Pvt. has been
Ltd. New commissioned.
Delhi
7 Udaipur MRF cum 30 By ULB Fund Running
RDF
8 Udaipur Compost 60 By ULB Fund M/s Sandal Running
+ RDF Buildcon Pvt.
limited
Total 947
Processing Plant Running under Pipeline
1 Bikaner Compost+ 258 Tipping fee Rs M/s IL&FS Firm has stopped
RDF 608 per ton on the work,
out put Termination letter
has been issued to
firm. BG has
been seized.
2 Sikar Compost+ 100 Tipping fee Rs M/s IL&FS Firm has stopped
RDF 1000 per ton the work, Final
on out put notice has been
issued to firm for
restart the work.
Hanuman Compost+ 60 Royalty Rs M/s Allied Firm has started
garh RDF 153/Ton on Energy the work of
SLF input Systems Pvt. boundary wall
[Link] City/Town Processing Plant Highest Name of Status
Technolog Capacity Royalty Firm
y (TPD) payable by
Contractor to
ULB
Ltd. New and commit to
Delhi finish the work
till Oct 2020.
4 Sheoganj+ Compost+ 40 Tipping fee on M/s Durga Boundary wall
Sumerpur RDF input for Impex work 80%
+ Processing is Udaipur Completed and
Takhatgar Rs 351/Ton approach road has
h been build. Lease
deed pending.
5 Bharatpur Compost+ 100 Royalty Rs M/s Rollz EC will be
RDF 101/Ton on Material granted after TPZ
SLF input Handling NOC.
System Pvt.
Ltd. New
Delhi
6 Karauli+H Compost+ 123 Tipping fee Rs M/s IL&FS Company didn't
indon+Ga RDF 1000 per ton submit the Lease
ngapur on out put deed fees.
7 Baran- Compost+ 60 Royalty Rs M/s Zonta CTE issued and
Anta RDF 38/Ton on SLF Infratech Pvt. work will be start
input Ltd. in
Bangalore August end.
8 Bundi Compost+ 42 Royalty Rs M/s Zonta New land has
RDF 59/Ton on SLF Infratech Pvt. been allotted.
input Ltd. Land Lease
Bangalore agreement has
been done. Firm
will apply for EC.
Notice has been
issued to expedite
the work.
9 Tonk- Compost+ 82 Royalty Rs M/s Zonta CTE issued.
Newai RDF 57/Ton on SLF Infratech Pvt. Notice has been
input Ltd. issued to expedite
Bangalore the work.
10 Jhunjhunu Compost+ 65 Royalty Rs M/s Allied Gram Panchayat
+ RDF 101/Ton on Energy refuse to transfer
Baggar+ SLF input Systems Pvt. the land. Letter
Udaipurw Ltd. New has been sent to
ati Delhi DM for resolving
the land dispute.
[Link] City/Town Processing Plant Highest Name of Status
Technolog Capacity Royalty Firm
y (TPD) payable by
Contractor to
ULB
11 Sri Compost+ 95 Royalty Rs M/s Allied Public Hearing
Ganganag RDF 230/Ton on Energy has been done.
ar SLF input Systems Pvt.
Ltd. New
Delhi
12 Jaipur Waste to 600 Royalty Rs M/s JITF Land allotment
Energy 66/Ton on Urban has been done.
processing Infrastructure Lease Deed
plant input Ltd. New Pending. PPA &
Delhi. Lease Deed is
pending
13 Jodhpur Waste to 400 Royalty Rs M/s JITF PPA & Lease
Energy 126/Ton on Urban Deed is pending.
processing Infrastructure
plant input Ltd. New
Delhi.
14 Alwar Compost 129 Royalty Rs M/s Rollz Construction
+ RDF 155/Ton on Material work started.
SLF input Handling
System Pvt.
Ltd. New
Delhi
15 Udaipur MRF 60 By ULB Fund Civil Work under
Facility + process.
Dry waste
processing
Centre
16 Udaipur Biometha 20 By ULB Fund M/s Work order
nation Mahindra Awarded
Plant
17. Jhalawar Compost 26 By ULB Fund M/s Ajay Civil Work
Plant Jain Started
Construction
Pvt. Limited
18 Churu MRF+Dry 30 By ULB Fund M/s Rupesh Work Order
waste Construction Awarded.
processing
centre
19 Churu Composti 15 By ULB Fund M/s Rupesh Work Order
ng Construction Awarded.
20 Kota Bio Gas 02 By ULB fund Work Order
Awarded.
Total 2337
[Link] City/Town Processing Plant Highest Name of Status
Technolog Capacity Royalty Firm
y (TPD) payable by
Contractor to
ULB

Processing Plant (Compost+RDF) Under Tendering Process


1 Kota Compost+ 400 Tender has been invited, no firm has participated.
RDF Re tender has to be done with modification in VGF
amount to be provided. DPR is being prepared for
installation of waste to compost and RDF plant.
2 Beawar Compost+ 61 Retendering has been done. No firm has
RDF participated.
3 Ajmer Compost+ 200 Under Tendering Process
RDF
4 Rajsmand Compost+ 44 Tender Evaluation process has been completed.
RDF Work Order shall be awarded soon.
5 Swai Compost 55 No bid received. Tender to be re-invited.
Madhopur + RDF
Total 760
Tender Document Under Preparation
1 Compost+ 37
Nagour
RDF
2 Compost+ 30
Dausa
RDF
3 Compost+ 47
Dholpur
RDF
4 Compost+ 34
Barmer
RDF
5 Compost+ 23
Jaisalmer
RDF
6 Compost+ 20
Jalore
RDF
7 Compost+ 14
Sirohi
RDF
8 Compost+ 36
Banswara
RDF
9 Compost+ 41
Chittorgarh
RDF
Total
280
Details of each existing STP in the State Annexure- A
S No. Location District Address Location coordinates Existing Capacity Operational Compliance Status of
STP Being Status of STP STP
Capacity (in Utilized (in
MLD) MLD)
1 JAIPUR DEVELOPMENT Jaipur Between Raiway Line and Lat: 26.891994 & Long: 2 2 Operational Complying
AUTHORITY STP SAHKAR MARG Road Boundary - 302005 75.793711

2 JAIPUR DEVELOPMENT Jaipur PALDI MEENA, JAIPUR - Lat: 26.875819 & Long: 3 3 Operational Non Complying
AUTHORITY STP PALDI MEENA 302031 75.967328

3 JAIPUR DEVELOPMENT Jaipur Rajeev Awas Yojana, Muhana, Lat: 26.797278 & Long: 1 1 Operational Complying
AUTHORITY STP RAJIV AWAS Jaipur - 302015 75.762717
YOJNA
4 JAIPUR DEVELOPMENT Jaipur Central Park, Jaipur - 302007 Lat: 26.901678 & Long: 1 1 Operational Complying
AUTHORITY STP CENTRAL PARK 75.812722

5 JAIPUR DEVELOPMENT Jaipur Ramnivash Bagh, Jaipur ,Tehsil- Lat: 26.912547 & Long: 1 1 Operational Non Complying
AUTHORITY STP RAMNIWAS Jaipur, Dist.-Jaipur - 302001 75.817822
BAGH
6 JAIPUR DEVELOPMENT Jaipur Jawahar circle, Tehsil- Jaipur, Lat: 26.840750 & Long: 1 1 Operational Complying
AUTHORITY STP JAWAHAR Dist.-Jaipur - 302018 75.799560
CIRCLE
7 JAIPUR DEVELOPMENT Jaipur Ralawata, Village-Goner, Lat: 26.768772 & Long: 30 6 Operational Non Complying
AUTHORITY STP RALAWATA Tehsil-Sanganer, Dist.- Jaipur - 75.930464
302002
8 JAIPUR MUNICIPAL Jaipur DELAWAS , PRATAP NAGAR Lat: 26.462567 & Long: 62.5 62.5 Operational Non Complying
CORPORATION STP DELAWAS ,SANGANER - 302033 75.838019
UNIT II
9 JAIPUR MUNICIPAL Jaipur DELAWAS, PRTAP NAGAR - Lat: 26.462567 & Long: 62.5 62.5 Operational Non Complying
CORPORATION STP DELAWAS 302033 75.838019
UNIT-I
10 Mundana Mev STP Alwar Khasra No 253, In front of Lat: 28.192686 & Long: 2 1 Operational Complying
madarsa, RIA, Kehrani, Ward 76.882373
No 43, Mundana Mev,
Bhiwadi - 301019
11 BIDA STP Alwar Near Star Hospital Bhiwadi - Lat: 28.208446 & Long: 4 2 Operational Non Complying
301019 76.810531
12 Sewage Treatment Plant (Unit Alwar Rajasthan Housing Lat: 28.205606 & Long: 1.5 0.75 Operational Complying
ID- 85899) Board,Arravali Vihar Bhiwadi - 76.819885
301019
13 Sewage Treatment Plant, Sawai Village- Surwal, Lat: 26.084166 & Long: 10 2.5 Operational Complying
Surwal Madhopur Sawaimadhopur - 322255 76.376388
14 Sewage Treatment Plant, Karauli Khasra No. 5931, Behind Lat: 26.505277 & Long: 5 1 Operational Complying
Behind Govt. College, Karauli Govt. College, Karauli - 77.009444
322255
15 Sewage Treatment Plant, Dholpur Village:- Thagawali, Tehsil:- Lat: 26.712981 & Long: 10 9 Operational Complying
Thagawali Rajakhera, DIstrict:- Dholpur - 77.907078
328001
16 Sewage Treatment Plant, Dholpur Village:- Shekhupura, Tehsil & Lat: 26.678200 & Long: 3 1.5 Operational Complying
Shekhupura District:- Dholpur - 328001 77.900791

17 Common sewage treatment Bundi Devpura, Bundi - Lat: 25.393725 & Long: 8 4 Operational Non Complying
plant 75.655106
18 Common sewage treatment Jhalawar Girdharpura Jhalawar - Lat: 24.526174 & Long: 3 2 Operational Non Complying
plant 76.216386
19 Municipal council, Alwar Alwar near village Agayara - 301030 Lat: 27.512308 & Long: 20 14 Operational Non Complying
76.766355
20 Common sewage treatment Kota Sajidhera, Kishorepura, Lat: 25.171204 & Long: 30 20 Operational Complying
plant Ladpura - 75.834113
21 Common sewage treatment Kota Dhakar Khedi, Near village Lat: 25.130772 & Long: 20 10 Operational Complying
plant dhakar khedi, Kota - 75.916476
22 UIT, Sriganganagar (Sewage Sri Near Suratgarh Road, Sri Lat: 29.881340 & Long: 10 10 Operational Non Complying
Tratment Plant) Ganganagar Gangnagar - 73.864290

23 Municipal Council (Sewage Hanumangar Near Railway Bridge on Lat: 29.595900 & Long: 5 5 Operational Complying
Treatment Plant) h Ghaggar River, Hanumangarh 74.299220
Town, Tehsil & Dist-
Hanumamngarh -

24 Sewage Treatment Plant of Jaipur Village Gajadharpura, Lat: 26.563100 & Long: 30 30 Operational Non Complying
Jaipur Development Autho Kalwar Road, Jaipur Sanganer 75.465200
JAIPUR
25 Sewage Treatment Plant (Cap. Churu village Gajsar, Churu - 331001 Lat: 28.332210 & Long: 7 7 Operational Non Complying
7 MLD) 74.942740

26 Sewage Treatment Plant (Cap. Sikar Khasra no. 380/446, Shiv Lat: 27.374000 & Long: 8 3 Operational Complying
8 MLD) Colony, Sikar - 332001 75.072640
27 M/s Sewage Treatment Plant Sikar Khasra No. 300, Gousala Land, Lat: 27.616415 & Long: 2 1.2 Operational Complying
(Cap. 2 MLD) Salasar Road, Sikar - 332001 75.127431

28 Sewage Treatment Plant Sikar Nari-Bari Road, Fatehpur, Lat: 27.999770 & Long: 7.5 6 Operational Non Complying
(Cap.7.5 MLD) Distt. Sikar - 332301 74.915000
29 Jaipur Municipal Corporation, Jaipur STP Campus Area, Brahmpuri, Lat: 26.563284 & Long: 8 8 Operational Non Complying
Deen Dayal Upadhaya Amber, Jaipur - 75.500780

30 Jaipur Development Authority Jaipur Khasra No. 1930 , Lat: 26.570248 & Long: 50 50 Operational Non Complying
(1 MLD Jaisighpura ST Jaisinghpura, Khor on Delhi 75.532952
Road, Jaipur -
31 Sewerage Treatment Plant, Chittorgarh Sewage Treatment Plant Near Lat: 24.422887 & Long: 1.5 1.2 Operational complying
Bari Sadari Idgah area at Kali mangari 74.477868
road, Bari Sadari , Chittorgarh -
312403
32 Municipal Council (Sewage Hanumangar Norht of Sriganganagar Lat: 29.687600 & Long: 7.5 5 Operational Non-Complying
Treatment Plant) h Abohar By Pass Road, Near 74.283400
Railway Track, Teh & Dist-
Hanumangarh -
33 Urban Improvement Trust Bikaner Vill-Sarai Nathania, Kharaa No Lat: 28.147690 & Long: 12 10 Operational Non Complying
(Sewage Treatment Plant) 05, Tehsil & Dist-Bikaner - 73.265790

34 Nagar Nigam (Sewage Bikaner Near Jorbeer, Jaipur Jodhpur Lat: 27.972800 & Long: 20 20 Operational Non- Complying
Treatment Plant) by Pass, Bikaner - 73.345990
35 Jindal Saw Limited (City Bhilwara Khasra No. - 338, Village- Lat: 25.363432 & Long: 10 3.8 Operational Complying
Sewage Treatment Plant) Kewara, Bhilwara - 311001 74.657060
36 Sewage Treatment Plant for Rajsamand Near Pratapura Village Lat: 25.063587 & Long: 5 1.7 Operational Non Complying
Rajsamand Rajsamand - 313324 73.930408

37 M/s Sewage Treatment Plant, Banswara Near Heera River City Lat: 23.190148 & Long: 1 0.8 Operational Non-Complying
Kushalgarh Kushalgarh Tehsil Kushalgarh 74.449367
District Banswara - 327801

38 Hindustan Zinc Limited Udaipur Eklingpura,Teh- Girwa, Lat: 24.567993 & Long: 25 19 Operational Complying
Udaipur - 313003 73.749862
39 Hindustan Zinc Limited Udaipur Eklingpura, Teh- Girwa, Lat: 24.567993 & Long: 20 14 Operational Complying
Udaipur - 313003 73.749862
40 STP BALOTRA Barmer Municipal Council Balotra Lat: 25.881388 & Long: 9 3 Operational Non Complying
,Pachpadra , Barmer - 344022 72.220000

41 Hindustan Zinc Limited Udaipur Near FCI Godown, Udaisagar Lat: 24.575950 & Long: 10 7 Operational Complying
road, Udaipur - 313001 73.734367

42 STP JALORE Jalore Municipal Council Jalore - Lat: 25.372222 & Long: 10 5 Operational Non Complying
343001 72.606388
43 STP , Kishanghat Jaisalmer Jaisalmer Kisanghat Road,Jethwai Lat: 26.943866 & Long: 10 6 Operational Non Complying
,Jaisalmer - 345001 70.941067
44 STP BARMER Barmer 10 MLD STP, Near Kurla Lat: 25.748055 & Long: 10 4 Operational Non Complying
Village, Barmer - 344001 71.473055
45 Sewage Treatment Plant Jodhpur STP phase -2 , Salawas Lat: 26.148198 & Long: 50 30 Operational Non Complying
(Phase 2) 50 MLD Jodhpur - 342001 72.986828
46 Sewage Treatment Plant Jodhpur Village Nandari, Banar Lat: 26.304873 & Long: 20 15 Operational Non Complying
Nandri Jodhpur Tehsil:Jodhpur 73.109863
District:Jodhpur - 342001
47 STP (50MLD) Phase-I, Salawas, Jodhpur Salawas - 342001 Lat: 21.150025 & Long: 50 40 Operational Non Complying
Jodhpur 72.985723
48 M/S Superintending Engineer Ajmer Khanpura Nasirabad Road, Lat: 26.413072 & Long: 20 12 Operational Non Complying
RUIDP Tehsil & Dist.- Ajmer - 305001 74.644853

49 Commissioner, STP (7.5 Pali Khasra no.943/3, 952/1, near Lat: 25.772363 & Long: 7.5 2 Operational Non Complying
MLD)ID-23924 Pali ESI Hospital,Mandiya Road 73.294749
Industrial Area,Punayata Road
Pali - 306401

50 Commissioner, Nagar parisad Pali Kh. No. 943/3,952/1, Mandia Lat: 25.771915 & Long: 15 15 Operational Complying
pali ,STP 15.0 MLD (ID Road Industrial Area, District- 73.290666
Pali - 306401
51 M/s , Sewerage Treatment Chittorgarh Sewerage Treatment Plant, Lat: 24.637193 & Long: 2 0.8 Operational Non Complying
Plant, Nimbahera Behind Karthana Samsan ghat, 74.697658
Nimbahera, Chittorgarh. -
312601
52 Sewerage Treatment Plant, Chittorgarh Sewerage Treatment Plant, Lat: 24.916647 & Long: 5 1 Operational Non Complying
Bhoikhera Bhoikhera, Chittorgarh - 74.641659
312001
53 Sewerage Treatment Plant Chittorgarh Sewerage Treatment Plant Lat: 24.887467 & Long: 3 1 Operational Non Complying
Abhiminyu Park Abhiminyu Park Chittorgarh - 74.627417
312001
54 M/s Municipal Council, Nagaur Khasra no. 661,Village Lat: 27.039827 & Long: 6 3.5 Operational Non Complying
Makrana Makrana ,Tehsil- Makrana, 74.702876
Dist.- Nagour - 341505
55 M/S Municipal Board, Didwana Nagaur Khasra no.818,822, Village- Lat: 27.385666 & Long: 5 3 Operational Non Complying
Didwana, Dist.-Nagaur - 74.551055
341001
56 M/S Municipal Board, Nagaur Nagaur Balwa Road Towards Bikaner, Lat: 27.238987 & Long: 8 3.5 Operational Non Complying
Tehsil & Dist.-Nagaur, - 73.687167
341001
57 M/S Commissioner Nagar Ajmer Ajmer - 305001 Lat: 26.476464 & Long: 13 9 Operational Non Complying
Nigam, RUIDP, PIU 74.612597
58 Sewage Treatment Plant, Bikaner Ward No. 7, Nokha, Bikaner - Lat: 37.470800 & Long: 1 Nil Non- Non Complying
Nokha 27.583880 Operational
59 Common sewage treatment Jhalawar near village faisalpura, Gagron Lat: 24.617662 & Long: 6 Nil Non- Non Complying
plant fort road Jhalawar - 76.173346 Operational
60 Jaipur Development Authority Jaipur Swarn Jayanti Park, Vidyadhar Lat: 26.580900 & Long: 1 Nil Operational Non Complying
(1 MLD) Nagar, Jaipur - 75.484900
61 M/S Ajmer Development Ajmer Khanpura Nasirabad Road, Lat: 26.413072 & Long: 40 Nil Non- Non Complying
Authority Tehsil & Dist.- Ajmer - 305001 74.644853 Operational

62 STP, Jaitaran Pali Jaitaran, Pali Not available 2 1 Operational Complying


63 STP-1 Suratgarh (2.5 MLD Sriganganag
STP) (Unit
Behind
ID 88194)
Sub-Jail, Suratgarh, Not available 2.5 2.5 Operational Non-complying
ar Dist- Sriganganagar
64 STP-1 Suratgarh (1.0 MLD STP)
Sriganganag
(Unit
Adarsh
ID 88194)
Kalyan Bhoomi, Not available 1 1 Operational Non-complying
ar Suratgarh, Dist- Sriganganagar

817 568.75
Details of under construction STPs in the State Annexure-B

Sl. Responsibl Address District Location of Status Capacit Physica Status of I Increment
No e authority STP with y of the l & D or al Progress
Coordinates Plant in Progres House
(Latitude MLD s in % sewer
and connection
Longitude, s
1 M/S Taal Jaipur if available)
Not under 1
Municipal Katora,Jaipur Available Constructio
Corporation n

NA NA NA
2 M/S Urban Village- Ajmer 26.4851 under 3.5
Improveme Ganahera, 74.5515 Constructio
nt Trust Khasra No.- n
1981
&1984,Tehsil-
Puskar,Dist.- NA NA NA
3 M/S Nasirabad Ajmer 74.898066 under 10
Municipal Bypass, 26.577198 Constructio
Council Kishangarh, n
RUIDP Ajmer

NA NA NA
4 M/S Near Vill- Bharatpur NA under 8
RUSDIP Gopal nangla, Constructio
Bharatpur Kharsa no. 44, n
STP T&D-
Bharatpur
NA NA NA
5 M/S Commissioner , Jhunjhunu 21.19571o under 8.5
municipal Municipal N 72.8084oE Constructio
Council Council, On n
Baggar Road,
Jhunhjunu
NA NA NA
6 M/S nagar Near Churu o under 9.6
28
palika , Gaushalla, 26’31’’N 74 Constructio
Sardarsahar Bikaner o 30’20’’E n
Road,Tahsil-
Sardharsahar,
Dist.-Churu NA NA NA
7 M/S nagar Near Churu o under 4
28
palika , Gaushalla, 26’31’’N 74 Constructio
Sardarsahar Giurgicha o 30’20’’E n
Road,Tahsil-
Sardharsahar,
Dist.-Churu NA NA NA
8 M/S Housing Board Tonk Not under 1.016
Rajasthan Colony Available Constructio
Housing n
Board

NA NA NA
9 M/S UIT Near Idgah Sri 29.55104 N, under 10
Srigangana Colony , Shri Ganganag 73.5115 E Constructio
gar Ganganagar, ar n
Rajasthan

NA NA NA
10 M/S UIT Near Sugar Sri 29.5531 N, under 15
Srigangana Mill Shri Ganganag 73.537 E Constructio
gar Ganganagar, ar n
Rajasthan

NA NA NA
11 M/S Jaipur Khasra no. Jaipur Not under 1
Developme 1930, Village- Available Constructio
nt Authority Jaisingpura, n
Khor on Dehli
Road, Tehsil-
Jaipur, Dist.- NA NA NA
12 M/S Jaipur Khasra no. Jaipur Not under 0.85
Developme 792, Village- Available Constructio
nt Authority Jaisingpuravas n
Bhakrota,
Tehsil-
Sanganer, Dist.- NA NA NA
13 M/S Jaipur Swapan lok-I, Jaipur Not under 0.38
Developme Sikar road, Available Constructio
nt Authority T&Dist.- n
Jaipur

NA NA NA
14 M/S Jaipur Anand lok-I, Jaipur Not under 0.41
Developme Sikar road, Available Constructio
nt Authority T&Dist.- n
Jaipur

NA NA NA
15 M/S Jaipur Anand Lok-II, Jaipur Not under 0.25
Developme 384 DUs Sikar Available Constructio
nt Authority Road, Tehsil- n
Amber, Dist.-
Jaipur
NA NA NA
16 Nagar Vill-Soran, Tonk 26°10'01.3"N under 4
Parisad, Near Ghanta 75°51'23.6"E Constructio
Tonk Ghar, Tonk n

NA NA NA
17 M/S Nagar Khasra no. 2, Tonk under 16
Parisad, Vill-Molaipura, 26°10'35.6"N Constructio
Tonk Tonk 75°44'42.3"E n

NA NA NA
18 M/S Near Existing Alwar Not under 3
Muncipal
STP, Planned Available Constructio
Council,
Area by UIT n
Bhiwadi Bhiwadi, In
front of Star
Hospital, Bus NA NA NA
19 M/S Khasra No. Alwar Not under 3
Muncipal 547,Near Shiv Available Constructio
Council, Mandir, n
Bhiwadi Santhalka
Bhiwadi
Tehsil:Tijara NA NA NA
20 M/S Khasra No. Alwar Not under 2
Muncipal 368/783,Khanp Available Constructio
Council, ur Tehsil:Tijara n
Bhiwadi

NA NA NA
21 M/S Khasra Jhunjhunu 21.19571 N, under 7
Jhunjhunu No.2082-2089 72.8084 E Constructio
Municipal and 2093-2094 n
Council Jhunjhunu

NA NA NA
22 M/S Sadulpura Hanuman Not under 3.5
Municipal Road,Bhadra , garh Available Constructio
Board,Bhad Hanumangarh n
ra

NA NA NA
23 M/S STP behind Sri Not under 2.5
Muncipal subjail,Shrigan Ganganag Available Constructio
Board, ganagar,Suratg ar n
Suratgarh arh

NA NA NA
24 Municipal Near Transport Hanuman 29.30990 N, under 1
Board,Surat Nagar, garh 73.88565 E Constructio
garh Hanumangarh, n
Bhadra

NA NA NA
25 STP of Near C.M Jan Chittorgar Not under 1
Nagar Aawas Yojana h Available Constructio
Parishad,Ch , Gandhi nagar n
ittorgarh. Chittorgarh.

NA NA NA
26 M/S Nagar STP of Nagar Chittorgar Not under 2
Parishad, Parishad,Abhi h Available Constructio
Chittorgarh manyu park, n
Near
Roadways Bus
Depot. NA NA NA
27 M/S Nagar Nagar Churu Not under 2.5
Parishad, Parishad, Available Constructio
Churu Churu n
Rajasthan

NA NA NA
28 Nagar Near Shree Churu Not under 1
Parishad, Ram Bharti Available Constructio
Churu Public School n
Churu

NA NA NA
29 M/S Nagar Railway colony Chittorgar Not under 1
Parishad chittorgarh h Available Constructio
n

NA NA NA
30 Near Nagar Bundi road Chittorgar Not under 1
Parishad h Available Constructio
n

NA NA NA
31 Nagar Gas Agency Churu Not under 5.5
Parishad, Dumping Yard, Available Constructio
Churu Sujangarh n
Churu,
Rajasthan
NA NA NA
32 M/S Nagar near Gularia Churu Not under 2
Parishad,Ch Hotel , Khasra Available Constructio
uru no. 787, 246 n
city Sujangarh

NA NA NA
33 Muncipal Near Basni Jodhpur 26.24250000 under 40
Corporation Benda Jodhpur , Constructio
Jodhpur 73.08666667 n

NA NA NA
34 Nagar Near Kali Mata Bikaner 27.5830 N, under 20
Nigam., Temple, 37.1655 E Constructio
Bikaner Sujandesar, n
Tehsil and
District-
Bikaner NA NA NA
35 STP, Nagar Khasara No 44, Bharatpur Not under 5
Nigam, Ikaran, Village- Available Constructio
Bharatpur Nagla Gopal , n
Bharatpur

NA NA NA
36 M/S STP Khasara No. Karauli Not under 3 MLD
Nagar 5430,Near Available Constructio
Nigam Ganesh Hotel, n
Hindaun City

NA NA NA
37 Commissio Jaccha Ki karauli Not under 0.75
ner Nagar Bawri, Tehsil- Available Constructio MLD
Parishad, Hindaun City, n
Hindaun district-
City, Karauli
Karauli NA NA NA
38 STP (2.5) Khasra No. Sawaimad Not under 2.5
MLD, 275, Gangapur opur Available Constructio
Nagar City, Sawai n
Parishad, Madhopur
Gangapur
City NA NA NA
39 M/S STP Khasara No. Sawaimad Not under 5.5
Nagar 167, Hingotia , opur Available Constructio
Parishad, Gangapur City n
Gangapur
City
NA NA NA
40 M/S STP behind Chittorgar Not under 2
for Pakage shamshan ghat h Available Constructio
4, Under Karthana Road n
RUDSICO STP ,
Nimbahera
NA NA NA
41 M/S STP near Kasod Chittorgar Not under 1
for Pakage Basti, h Available Constructio
4, Under Nimbahera n
RUDSICO Tehsil:-
Nimbahera
NA NA NA
42 STP, Nagar Gopal churu Not under 1.5
Parishad Goushala Land Available Constructio
Sujangarh Near Salasar n
Near Road, Khasra
Gandhi No. 202,
Chowk, Sujangarh, NA NA NA
43 Ambuja Ambuja Nagour 27.0409, under 0.3
Cement Cement Ltd., 73.4830 Constructio
Ltd., Marwar n
Marwar Mundwa,
Mundwa, Mundwa,
Mundwa, Nagaur NA NA NA
44 M/S Near Karjali Udaipur Near Alu under 5
Hindustan House Tehsil Factory - Constructio
Zinc Girwa, Udaipur Karjali n
Limited House, Pula,
Tehsil
:Girwa, dist : NA NA NA
45 Commissio Village- Bhilwara 25.361251,7 under 30
ner, Nagar Kuwada, 4.666631 Constructio
Parishad, District- n
Bhilwara Bhilwara

NA NA NA
46 M/S Nagar Gogamedi, Sikar 28 o under 1
Palika Ramgarh 10’11’’N 74 Constructio
Ramgarh Shekhawati o 58’8’’E n

NA NA NA
47 STP(Cap.2 At near Churu 28 o under 2
MLD ) Gaushala 26’31’’N 74 Constructio
Bikaner road o 30’20’’E n
Sardarshar

NA NA NA
48 Municipal Bhageniya Jhunjhunu 281455 N, under 2
Counci, Johda, 753834 E Constructio
Chirawa Chirawa, n
Jhunjhunu

NA NA NA
49 M/S STP near Chittorgar Not under 4.5
for Pakage Ambamata h Available Constructio
4, Under temple, n
RUDSICO neemuch
highway,
Nimbahera, NA NA NA
o
50 M.C, Near Todikui, Sikar 27 48’41’’ under 3
Laxmangar Sikar N 75 o Constructio
h 01’17.4’’ E n

NA NA NA
Details of Proposed STPs in the State Annexure- C
Sl. Responsible Address District Location of STP Status Capacit Status of Increment Likely Date of
No authority with Coordinates (Operational y of the Project(at al Progress Completion
(Latitude and /Non- STP DPR
Longitude, if operational/ propose Stage/Und
available) under d in er
construction MLD Tendering/
) Work to be
Awarded

1 M/S Nagar Devipura, Near Bus Sikar 273555.7 N Proposed 5


Parishad,Sikar Stand, Sikar 750901.9E
NA NA NA
2 M/S STP at Beawar, Near Vijaynagar Private Ajmer 26.097846 Proposed 5
Near Bus stand,Tehsil:- 74.324677
Beawar, Ajmer
NA NA NA
3 M/S Municipal STP (Bus Depot. Jhunjhunu 27.84951 N, Proposed 3
Council Jhunjhunu. Nawalgarh), Khasara No. 75.25335 E
174, Nawalgarh,
Jhunjhunu. NA NA NA
4 M/S Nagar Palika STP at Khasra No.1332 Jhunjhunu 27.8477377 N, Proposed 1
fire station , Nawalgarh, 75.2677945 E
Jhunjunu
NA NA NA
5 M.C, Chirawa STPNagar Palika, Jhunjhunu 28.1455 N, Proposed 3
Chirawa,( Mandrela 75.3834 E
Road), 1480/692,
Chirawa, Jhunjhunu. NA NA NA
6 M/S Nagar Palika, Khasara No. 421, Sikar 281015 N, 745815 Proposed 2
Ramgarh Shekhawati, Shamshan Ghat, Ramgarh E
Sikar Shekhawati, Sikar
NA NA NA
7 M/S Muncipal Khasara No. 1548/78/2 Sikar 27.84626 N, Proposed 1
Council, Banjara Basti, Basni 75.3509 E
Laxmangarh, Sikar Road, Laxmangarh, Sikar
NA NA NA
8 M/S Nager Palika, 1381/339/1, Indra Aawas Sikar 27.83094 N, Proposed 1.5
Laxmangarh, Sikar colony, Laxmangarh, 75.01857 E
Sikar NA NA NA
9 M.C, Beawar Vijaynagar Road, Bichrali Ajmer 26.094783 Proposed 1.5
Tank, Beawar 74.325388 NA NA NA
10 Narsinghpura, Nehru Narsinghpura, Nehru Ajmer 26.116714 Proposed 4
Bhawan, NH-8, Bhawan, NH-8, Beawar 74.327274
Beawar NA NA NA
11 M/S STP Fatehnagar, Changeri Village- Udaipur STP Fatehnagar, Proposed 1
Sanwar, RUDSICO Fatehnagar, Sanwar, Sanwar,
Tehsil-Mavli RUDSICO NA NA NA
12 M.C Kushalgarh Near Heera River Banswara Not Available Proposed 1
Kushalgarh, Banswara NA NA NA
13 STP (2.5) MLD, Khasra No 152, 153 STP Sawaimadopur Not Available Proposed 1.5
Nagar Parishad, (2.5) MLD, Nagar
Gangapur City Parishad, Gangapur City
NA NA NA
14 M/S Nagar Nigam , at Village - Sujadesar Bikaner Not Available Proposed 20
Bikaner (khasra
no.341,357,358,359,360)
Bikaner NA NA NA
15 Commissioner, Hanumangarh Town, Hanumangarh 29.5959 N, Proposed 2
Municiapl Council, District-Hanumangarh 74.29922 E
Hanumangarh NA NA NA
16 Commissioner, Hanumangarh Junction, Hanumangarh 29.6876 N, proposed 4
Municipal Council, Hanumangarh 74.2834 E
Hanumangarh NA NA NA
17 M/S Nagar Palika , Bibnawa Road,Tehsil:- Bundi Common sewage Proposed 0.5
Bundi Bundi treatment plant,
Bhinwa Road,
Bundi(25.429676
75.660378) NA NA NA
18 M/S Nagar Palika , near Gandhi Gram Tehsil:- Bundi Common sewage Proposed 0.5
Bundi Bundi treatment plant,
Gandhigram ,
Bundi(25.393725
75.655106) NA NA NA
19 M/S Nagar Parishad Kundan Nagar, Beawar, Ajmer 26.092024 Proposed 1
Beawar Ajmer 74.321139 NA NA NA
20 M.C. Kota Dhakar Kheri Kota Common sewage Proposed 40
treatment plan,
Dhakar Khedi,
Near village
dhakar khedi,
Kota(25.44025
75.67717) NA NA NA
21 M.C. Nagaur Khasra No. 405, STP Nagour 27.1955961 Proposed 1.5
station road, badi kuwa 73.730085 NA NA NA
22 Municipal [Link]. 1146, 1189, 1192, Kota (25°12'33.7647 Proposed 15
corporation, kota 1193, 1217, 1218, 1220, 75°55'57.4767)
1277, 1281-1284, 1286,
Kala Talab, Dhakar Kheri
NA NA NA
23 STP(Cap.1 MLD ) Khasra no.721,Bhagat Jhunjhunu Not Available proposed 1
Singh Joha
,Nawalgarh,Jhunjhunu NA NA NA
24 M.C Mount Abu Near Swaminarayan Sirohi Not Available Proposed 0.17
School Mount Abu
Sirohi NA NA NA
25 M.C Mount Abu Near Delwara Jain Sirohi Not Available Proposed 0.315
Temple Mount Abu
Sirohi NA NA NA
26 M.C Mount Abu Village- Naval Nagar, Sirohi Not Available Proposed 0.06
Infront of hotel Miskil
Asan Mount Abu
NA NA NA
27 [Link] Abu Village- Naval Nagar, Sirohi Not Available Proposed 0.07
aakash wani road,
Torna, Mount Abu
NA NA NA
28 M.C. Nimbahera Vill- Sigari, Tehsil, Chittorgarh Not Available Proposed 4.5
Nimbahera NA NA NA
29 M.C Khandela FSTP at, Khandela Sikar Not Available Proposed 0.01 NA NA NA
30 M.C. Lalsot FSTP at, Lalsot Dausa Not Available Proposed 0.02 NA NA NA
31 Rajasthan Housing Indira Gandhi Nagar Jaipur Not Available Proposed 3
Board NA NA NA
32 Rajasthan Housing Dastkar Nagar Jaipur Not Available Proposed 1
Board NA NA NA
33 M.C. Sambahar FSTP at Sambhar Jaipur Not Available Proposed 0.02 NA NA NA
34 M.C. Ratangarh Khasra No. 4, 28, NH- Churu Not Available Proposed
11, Derajsar 3.8 NA NA NA
35 M.C. Ratangarh Khasra no. 639, Churu Not Available Proposed
Gaushala Land,
Ratangarh 6.1 NA NA NA
36 M.C. Sardarsahar Near Girgichiya road, Churu Not Available Proposed
Sardarsahar 3.4 NA NA NA
37 M.C. Sardarsahar Near Bikaner Road, Churu Not Available Proposed
Sardarsahar 2.3 NA NA NA