Structural Flow Chart

The document outlines the phases of a structural works project from planning through post-construction. The phases include drawing and specification, planning, bidding, construction, and post-construction. Key steps involve the design team creating drawings and specifications, planning and scheduling by the owner and general contractor, bidding by subcontractors, construction activities like inspection and testing, and warranty periods after completion.

Uploaded by

Angelo Endozo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
200 views1 page

Structural Flow Chart

The document outlines the phases of a structural works project from planning through post-construction. The phases include drawing and specification, planning, bidding, construction, and post-construction. Key steps involve the design team creating drawings and specifications, planning and scheduling by the owner and general contractor, bidding by subcontractors, construction activities like inspection and testing, and warranty periods after completion.

Uploaded by

Angelo Endozo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

FOR STRUCTURAL WORKS

DRAWING AND SPECIFICATION PHASE DRAWING AND SPECIFICATION PHASE PLANNING PHASE CONSTRUCTION PHASE POST CONSTRUCTION PHASE

DRAWINGS AND SPECS NEXT PHASE OWNER AND/OR


FROM DESIGN TEAM PLANNING AND CONSTRUCTION
FINAL BID GENERAL CONTRACTOR
SCHEDULING COMPLETION
TO APPLY PERMITS

REQUEST FOR INFO


CLARIFICATION

COORDINATION WITH
INSPECTION, TESTING
SUPPLIER, GENERAL GENERAL CONTRACTOR
REVISION AND BY OWNER OR
PERMITS SUBCONTRACTOR CONTRACTOR, - WARRANTY
VERIFICATION CONSTRUCTION
SUBCONTRACTOR AND
MANAGEMENT
DESIGN
BID DOCS

BIDDING

NEXT PHASE NEXT PHASE CONSTRUCTION/


BIDDING DEPARTMENT
FINAL BID DRAWINGS IMPLEMENTATION BY MAINTENANCE
(GENERAL MASTER SCHEDULE
AND SPECIFICATIONS GENERAL AND
CONTRACTOR)
(BID DOCS) SUBCONTRACTOR

FOR CONSTRUCTION
PLAN