Rural Electrification Design Guide
Rural Electrification Design Guide
162
162 NRECA International, Ltd.
Application of single-phase primary lines Compilation of available information on the
consisting of phase and neutral as a principal area to be electrified. The electric company
means of rural distribution. The use of single- or jurisdictional institution in charge of
phase lines, while providing adequate service supplying the electric service in the adjoining
for most uses and for the existing demand area should provide the initial information,
for electricity in the rural area. Three-phase especially if the project is connected with
lines are required to maintain system balance this entity and this entity will operate the
between phases in the system as well as to serve service once the project is executed. This
specific concentrated three-phase loads. information is necessary, but not sufficient
to characterize the area, for reasons to be
Application of single-phase transformers. explained shortly.
Application of
The application of single-phase 5-25 kVA
transformers is preferred, leaving the modules
single-phase
Analysis of the area to be electrified. This
of over 25kVA only for specific requirements means determining the location of consumer primary lines
such as three-phase banks. The use of a concentrations, based on the actual conditions consisting of
larger number of relatively small transformer of the project area. During this process the phase and
modules, as compared with a smaller number information gathered from the electric service
neutral as
of larger transformers used in an urban system, operator in the adjoining area should be
improves the quality of service for scattered confirmed, to the extent possible. a principal
users, reduces the investment in low-voltage means of rural
systems and reduces system losses, even though Analysis of the loads and configuration of distribution.
the transformers themselves may cost more. the proposed system. This step determines
the loads represented by the concentrations
Limit the length of low-voltage networks. of potential users and designs the system
This limited length reduces technical losses, configuration to supply them, including route
improves service quality, and reduces the design, the features of primary lines, and the
possibility of illegal connections. location of transformer points.
This design methodology for a rural electrification What follows are the details of the process of
project represents an integrated philosophy, and it analysis development and the use of the necessary
should be applied as a whole. Its presents a basis tools, and an example how the process applies to
for design and provides the professional user with a real project. The project used as an example is
the necessary tools for its application. an electrification project in the Tomoyo region,
near the city of Sucre in Bolivia.
comply with
Every distribution company has preferences as The electric company may have or know about an
the technical to the use of materials and line hardware. Some expansion plan for the present system, which would
criteria companies use wooden poles while others use affect the project being considered. Examples of
included in this concrete or metal or a mix of all. Normally, possible expansion plans are the construction
module. electric companies have standardized structures, of new sub-transmission lines, substations and/
often based on RUS standards. It is also usual to or generating plants. Such information would
have standardized conductor sizes for a company’s have great value for planning the new project.
distribution systems. Therefore, the project Take expansion plans into account with caution,
engineer should start the electric design from however, because most distribution companies’
the standards established by the electric company, expansion plans for rural areas are either overly
as long as they comply with the technical criteria general, without financing, or based on out-of-
included in this module. date information about major configurations
for transmission systems. Although taking into
Plans for Network Extensions in the Project account the plans of other companies may prevent
Area unnecessary expenditures in the development
of a project, it is important not to condition the
The electric company may have plans to extend design on the existence of other projects that may
its lines to the area contemplated in the project, not be executed in time.
and they might even have a final design for the
extension project. Many times these plans are When associated projects have received the
compiled by local governments, such as the necessary approval from financing sources and other
prefecture or the municipality,and can be highly approvals such as those related to environmental
politically motivated. The designs prepared under impact, it is valid to consider those projects in
these conditions usually have many serious flaws the planning of a rural electrification project.
164
164 NRECA International, Ltd.
Point of Origin or Supply for the Project and respect various design criteria. If no physical
neutral exists at the initial point, it is necessary
During the visit of the project designer to the to determine where the neutral of the existing
office of the electric company, obtain all available system ends, so as to take into account the costs
information on the source or supply point for of adding the neutral.
the new project. Whether or not the electric
company has all the necessary information, it Distance from Substation
is also necessary to pay a visit to the project site
to verify the data. The data to be obtained from If the electric company has updated and sufficiently
the electric company are the following. detailed maps, one can determine with their help
the distance from the substation to the initial point
Voltage Level of the Existing Distribution of the project. This information is necessary to
Lines model the voltage drop in the existing line, as
well as to simulate the power flow and the voltage
Existing voltage levels may be of the 15kV, 25kV, drop in the proposed project.
or 35kV class, each of which comprises a number
of options. For example, the 15kVvoltage class Existing Conductor Size from Substation to
includes 11kV, 12.47kV, 13.2kV, and 13.8kV. The the Project
25kV level includes 20kV, 22kV, and 24.9kV, etc.
The 35kV level includes voltages like 33kV and To carry out a power flow analysis, one needs to
34.5kV. An electric company must have more than know the cross-section of the existing conductor
one voltage level in its system, e.g., 12.5kV and in the line from the substation up to the initial
34.5kV. Then, even if a line is currently energized point of the project to be studied. The cross-
at a lower voltage, for example at 12.5kV, the section of the neutral conductor (if it exists) must
company may be willing to consider a conversion be determined, as well as the cross-section of
to 34.5kV, if this is technically justifiable. In phase conductors. If there are conductors of more
Bolivia, the system voltage used by distribution than one cross-section in the line between the
companies is in the process of being standardized substation and the initial point, record each cross-
at 35kV, 25kV, and 15kV. Few companies there are section of the conductor in the corresponding
still maintaining systems in other voltages. stretch, as well as its respective length.
Number of Phases Available
Load in the Existing Line
It is important to know how many phases are
available in the project sector: one, two or three The load in the existing line is another critical
phases. If three phases are not available at the component in defining the conductor cross-section
initial point (usually at the end of the existing line), and/or number of phases of the system that will
one must find out how far the three-phase line be analyzed in the power flow study in order to
goes, so as to take it into account if conversion determine the voltage drop in the existing line.
to a three-phase line is necessary. If there are important loads, record their location
so as to be able to model their effect in the power
Physical Neutral flow study. If the existing line has to be divided
into segments, for the reasons indicated in the
Some rural area distributors have adopted previous section, be sure to divide the existing
systems without a physical neutral. The system load among the same segments.
used for single-phase configurations without a
physical neutral, is referred to as Single Wire
Earth Return (SWER), must still comply with
166
166 NRECA International, Ltd.
demand of each transformer to be able to calculate of transformers and the way in which the neutral,
the capacity available for the proposed project. if any is grounded. This information is usually
If there is a lack of capacity in the substation presented on transformer name plates as %Z at
transformers, either an increase of capacity would the self cooled or OA rating. In the case of an
have to be budgeted at the existing substation or autotransformer or a three-winding transformer,
a new substation installed closer to the project record three impedances: primary secondary,
area. primary tertiary, and secondary tertiary. In
some substations, where it is necessary to limit
Voltages on Both Sides of the Transformer the magnitude of the fault current to ground,
an impedance may be installed in the ground
In every transformer at the substation, record the connection. If such an impedance exists, record its
Always record
rated (nameplate) voltage for both the high voltage value, so as to include it in the power flow model.
winding and the low volage winding. In many If the relation X/R of the transformer impedance
the presence
instances the nominal voltages of transformers is not specified, adopt the relation 10:1. of voltage
are not the same as the nominal voltages of the adjusting
system and the difference may influence the Transformer Connections taps on both
results of power flows.
sides of the
All three-phase transformers, or single-phase
Available Taps in the Transformer transformers connected in three-phase banks, can transformer,
be defined by the connection configuration of delta as they
Always record the presence of voltage adjusting or star windings, both on the high voltage side and influence the
taps on both sides of the transformer, as they on the low voltage side. Record the configuration transformation
influence the transformation relationship and of the connection on both sides of the transformer.
relationship
therefore the output voltage of the transformer. This configuration does not influence the power
There are usually five taps of +/- 5% on the high flow model, but it does influence the fault current and therefore
voltage side, i.e. +5%, +2.5%, 0% (nominal), model, which is normally calculated using the the output
-2.5% and –5%, but this varies according to the same model of the electric system. The calculation voltage of the
manufacturer and the purchase specification of of these fault currents influences the determination
transformer.
the transformer. Also determine the position of of the protection system that the project will need
the tap switch and therefore the tap position on so as to be reliable.
which the transformer is operating.
Characteristics of Overcurrent
Existence of Automatic Voltage Regulation Protection Devices
Another important factor to model in the power At every substation there should be overcurrent
flow is the presence or absence of devices for protective devices (such as fuses, reclosers,
voltage regulation. If the substation has voltage breakers, etc.) both on the high voltage side and
regulation equipment, verify whether it is low voltage side. For each device, record these
incorporated into the transformer or separated, characteristics:
along with whether it is automatic or manually
operated. the type of device,
the brand,
Impedance of the Transformer and
Ground Connection the pickup current,
There may be other equipment in the substation Georeference of All Sites with GPS
There may
that could have a great influence on the power flow
be other model, such as capacitors and reactors, so be sure During the visit to the site, the engineer should
equipment in to record their capacity and form of connection use the GPS to obtain georeferenced data for
the substation to the system. For capacitors, record the control the routes followed (and/or the probable route
that could mode, whether it is automatic or manual. For for electrical lines to be installed) and of all the
automatic capacitors, also record the operation points of interest, such as the substation, the end
have a great
criteria (voltage, phase current, power factor, or of the three-phase line, the initial point of the
influence on time of day). project and the center of each community to be
the power flow considered in the project.
model, such as Field Inspection
capacitors and Tracks or Routes
After compiling the available information at the
reactors, so be
office of the electric operator, it is necessary to All along the route, the GPS can mark out and
sure to record confi rm and complement that information by record the route followed. The engineer must
their capacity visiting the project area to establish the geographic make certain that the GPS is in the right mode to
and form of relationship between the loads to be electrified. mark and record the route, because upon returning
During this visit, the basic configuration of the to the office, this information will be very useful
connection to
system to be installed will take shape, subject to in determining the length of both the existing
the system. modification during the process of analysis. For lines and those to be installed.
this reason, during this visit, one needs some way
to establish distances and locations of towns and Waypoints
probable loads. The traditional way to perform
this task is to get the best map available of the The GPS capacity can also mark the location
area and measure the distance between key points of points of interest for the project, such as
using the odometer in the vehicle. Although the location of the substation, the end point of
this procedure meets the needs of the project, the three-phase line, the initial point and the
modern technology affords a more accurate and center of each community to be considered in
advantageous option through use of GPS satellites the project. Each such point should be recorded
for establishing geographic references. A GPS with an indicative name, which could be the
unit is portable and low cost, with geographic complete name of the community (according to
accuracy of +/- 7 meters in autonomous operation. the GPS capacity) or a simpler indicative name.
Additional technologies offer the capacity for In any case, keep a written file of all waypoints
greater accuracy, but for this kind of project with the indicative name, the real name of the
design they are not necessary. community, and the additional characteristics
of each point.
Apart from their ability to accurately locate key
168
168 NRECA International, Ltd.
Files vs. Active Memory Verify Key Data
During the registration of points and routes, the If visiting the substation, the engineer must verify
active memory of the instrument fills up. The all data compiled in the office and obtain all the
engineer must ensure that the memory does not missing data. The following table list shows the
become full, because the GPS then erases the minimum data to be obtained:
older data or simply stops recording new data.
In either case, data are lost. Depending on the Capacity of the transformer
model, the active memory may fill in half a day
or one whole day. When the memory is full, the Maximum load in the transformer
engineer must download the data to the computer,
so as to make room in the memory. If the GPS Nominal high voltage rating
model permits it, the instrument operator should
transfer the data of the active memory to a GPS Nominal low voltage rating
internal file, so as to empty the active memory
later, without losing data. Most GPS models have Existence of tap changer in the transformer
room in their memory for at least eight files of
route data, besides their active memory. Present position of the tap, if any
Although all the necessary data can be obtained Between Substation and Initial Point
in the office of the electric company, it is often
necessary to visit the substation and verify After obtaining the data on the substation and
personally all the data on the equipment name its georeferenced location, survey the existing
plates. If the engineer can obtain permission for line between the substation and the initial point
such a visit, it enables the collection of data that of the project. Along the way he must record the
are often not archived in the office, such as the route track with the GPS and mark the points of
voltage taps in the transformers. interest, such as the center of the communities
170
170 NRECA International, Ltd.
Figure 1. Sample graphic of GPS points and routes data (Tomoyo)
172
172 NRECA International, Ltd.
Table 2. Count of users by class for the Tomoyo project
Community Residence Shop School Mill Medical Center Phone kiosk Total
kWh/month 25 75 100 250 150 120
Molle Molle
54 1 1 1 – – 57
(Chuquisaca)
Molle Molle
146 2 1 1 1 1 152
(Potosi)
Sorojchi 105 2 1 – 1 1 110
Yoroca 98 3 1 1 – – 103
Tomoyo 114 4 1 3 1 1 124
Llajtapata 50 1 – – 1 – 52
Isluco 30 1 1 – – – 32
Jirota 60 1 1 – – – 62
Kasapata 50 1 – – 1 – 52
Sorocoto 160 2 1 – 1 – 164
Soroscopa 60 1 1 – – – 62
TOTAL 927 19 9 6 6 3 970
Calculation of Total Energy Consumption kWh factor (Factor B), where Factor A reflects the
per Community fact that diversity increases with increases in the
number of consumers, and Factor B reflects the
The next step is to calculate the total energy improvement in the load factor with the increase
consumption per community, by multiplying the in specific consumption.
number of potential users in each category by the
specific consumption of that category, as included
Table 3. Demand and Consumption of
in the demographic study described in Module 5:
Energy per community (Tomoyo)
Methodology for Evaluating Feasibility of Rural
Electrification Projects. Table 3, column 3 shows Community Users kWh kW
the results of this step, taking as an example the data
Molle Molle (Chuquisaca) 57 1,775 8
of the Tomoyo project, as recorded in Table 2.
Molle Molle (Potosí) 152 4,420 19
174
174 NRECA International, Ltd.
the project can supply the anticipated maximum i.e. at the client’s energy meter. Usually, the
demand under acceptable service conditions. regulations set a range of acceptable voltage, both
above and below a nominal value. Sometimes two
In addition to determing the voltage behavior ranges are included, one for normal conditions
of the project, the power flow study permits an and another for contingencies.
evaluation of losses and allows the engineer to
examine the required number of phases, the In Bolivia, for example, the acceptable range is
eventual need to reinforce the existing supply +4%/-7.5% for normal conditions and +7%/-10%
systems, or the requirement to establish a for emergencies. Where there are regulations on
distribution system with a different voltage level the voltage level, apply the regulated acceptable
from the existing one in the area. values for normal conditions for planning purposes, The engineer
leaving the additional margin for emergency
Criteria for Analysis conditions during the operation of the system.
should base
If there are no rules in a given country, use the the electric
To determine whether the study has met its values +5%/-10% for planning purposes. design of the
objective, it is necessary to establish criteria for system on an
the evaluation and acceptance of results. The It is important to point out that the limit values
analysis of
criteria normally used in planning studies relate for voltage level have been set at low voltage
to the level of voltage, the capacity of equipment at the point of delivery to the client, i.e. at the power flows or
and lines, the reliability of the service, and the meter. For planning studies it is not customary voltage drops.
level of losses. to perform the analyses down to this level, but
rather at a system level. Planning studies that
Voltage Level use the methods presented in this module are
based on the voltage at primary level, i.e., before
Minimum voltage levels are normalized in most the voltage drop represented by the distribution
countries, with the measuring point for purposes transformer, the low voltage (secondary) lines,
of application of regulations at the interconnection and the service drop. As reference criteria, use
node between the supply system and the client, the following values:
Service reliability, i.e. the frequency and duration For systems of 24.9kV phase to phase – 330
of interruptions, depends more on maintenance of amp.
the system during operations than on the decisions
made during the design, with one exception. For systems of 34.5kV phase to phase – 460
This exception is the provision for a coordinated amp.
protection system against faults. A coordinated
system ensures that for phase-to-phase faults, By applying the normal rules of uses the recloser/
as well as for phase-to-ground faults, there are fuse coordination system, one can derive the
protection elements sensitive enough to detect and maximum load allowable for the circuit and
176
176 NRECA International, Ltd.
branches to ensure a coordinated system. By However, the selection of the conductor cross-
applying a similar reasoning to various voltage section is within reach of the system designer.
levels and considering the features of commercially This selection process optimizes investment
available fuses and reclosers, the following results expenses and guarantees more efficiency in the
may be obtained: distribution of energy, considering both the cost
of construction and the cost of technical losses
For systems of 12.5kV between phases: resulting from the energy flow through the line.
The process consists of applying Equation 4 for
– Maximum load, main circuit – 70 amp several levels of loads and of line construction
costs with several alternative cross-sections of
– Maximum load, branches with fuses – 25 conductors.
amp
Equation 4: CA = K A*(Const) + K L*(Loss)
For systems of 24.9kV between phases:
Where:
– Maximum load, main circuit – 140 amp
CA = Total annual cost of one kilometer line
– Maximum load, branches with fuses – 65
amp K A = Fixed charge rate for investment costs,
typically = 0.15
For systems of 34.5kV between phases:
Const = Construction cost of one kilometer
– Maximum load, main circuit – 200 amp line with a specific conductor cross-
section
– Maximum load, branches with fuses – 80
amp K L = Acquisition cost of one kWh energy at the
beginning of the project
These limitations are substantial when dealing
with circuit loads, especially for systems of 12.5kV. Loss = Annual loss in kWh of one kilometer
While some devices for the electronic control line with the specific conductor cross-
of reclosers allow this range to be extended, section for a specific peak demand and
protection coordination should be an element in load factor.
the integral design of the system.
= (LLF)(n)(I2R)*8.76
Control of Technical Losses
Where:
The control of technical losses has many aspects
to be weighed, and not all of which are part LLF = Load factor of losses = (Load factor)2
of the system design process. An example of *0.84+ (Load factor) *0.16
an extraneous factor is limitation of losses in
the distribution transformers. When purchasing n = 3.0 if the line is three-phase, 2.0 if the line
distribution transformers and evaluating their is single-phase
cost, one must use a formula that determines a
financial value for losses, both for no load losses I = Phase current in amps for the specific load
and load losses. This procedure applieds during
the process of purchasing the equipment, not at R = resistance in ohms of one kilometer of the
the system design level. specific conductor
178
178 NRECA International, Ltd.
Annual fixed charge rate: 0.15 Code (NESC). 3 This rule, which requires
more horizontal separation for conductors
Cost of line construction based on 2005 prices smaller than #2 AWG ACSR, has the effect
of materials of making the spans shorter in primary lines
with conductors smaller than #2 AWG ACSR.
The gray values represent the minimum costs As a result, its cost per kilometer is higher
for the load indicated. A #4 ACSR conductor than the lines using #2 AWG ACSR or those
has an application range of only up to 400kW, of greater sections.
so it should not be considered as a conductor
for standard use. Instead, #2 ACSR has an After determining the cross-section of the phase
application range from 600kW to 1,600kW, conductor, the engineer must determine the cross-
which enables it to serve as a standardized section of the conductor in the neutral. If the line
conductor. A #1/0 ACSR conductor has an is single-phase, the neutral should be of the same
application range of 1,800kW to 2,500kW, cross-section as the phase conductor, because both
although its range of advantage over #2 is not conductors share the same current. For a three-
too marked below 2,000kW. A #2/0 ACSR phase line, consider the use of a conductor with
conductor has no preferred application range, a smaller cross-section for the neutral, because in
while the #4/0 conductor is preferred from a three-phase line with balanced loads, a reduced
3,000kW to 6,000kW. For loads over 6,500kW, current flows through the neutral.
the optimal conductor is 397.5 MCM. In this
example, the company would then remain with The RUS Bulletin #61-4 recommends that the
four normalized conductors, each one with a neutral conductor should have at least 20% of the
substantial application range, as follows: capacity of the phase conductor in three-phase lines
with balanced loads, and that they have similar
For loads up to 1,600kW: #2 AWG ACSR characteristics in their sagging. Considering all the
above, Table 6 shows a table of conductors with a
For loads of 1,601kW up to 3000kW: 1/0 AWG reduced cross-section for the neutral.
ACSR
Considerations in Power Flow Studies
For loads of 3001kW up to 6500kW: 4/0 AWG
ACSR A power flow study can be conducted with the
help of specialized software, with general-use
For loads of 6501kW and over: 397.5 MCM
ACSR 3
American National Standards Institute, National Electric Safety Code
(New York: Institute of Electrical and Electronics Engineers, 2002).
180
180 NRECA International, Ltd.
Coming back to the Tomoyo project, the feeder This graphic shows the points of interest, such as
for this project has 83% single-phase lines from communities included in the project and the routes
the substation. Therefore, trying to study this between them, along the line. In the lower corner
system with a power flow based on values of of the screen, the scale of the drawing appears
positive sequence would not give a reliable result. along with geographic coordinates of a selected
Thus the power flow program for a distribution point. Figure 4 shows the communities of the
system should always have the capacity to make Tomoyo project superimposed on GPS data.
calculations with unbalanced loads, either with
symmetrical components (an approximation) or Selection of Primary Voltage Level
with matrices (preferably).
After creating the geographic model, it is
necessary to determine the voltage to be used The reality
Capacity to Calculate Unbalanced
for the new extension. The choice of a voltage of rural
Impedances
level for a given project depends to a large extent
electrification
on the levels already used in the area. Selecting
Apart from their inability to model unbalanced lines,
a primary voltage that differs from the standard
loads, analysis programs using positive sequence especially
used in the project area requires the installation of
approximations have no capacity to model
substation, and possibly transmission, equipment. those with
unbalanced impedances. It is possible, though
This decision should be carefully examined prior long, single-
not very common, for a three-phase line to have
to final design. With that said, a voltage level
different conductors in the different phases. For phase
of the 25kV or 35kV class may be reasonably
instance, it might have been constructed originally branches,
introduced in the following circumstances:
as a single-phase line with a given conductor is that it is
cross-section and then converted into a three- If the existing voltage (whether 5kV or 15kV) difficult to
phase line with another conductor cross-section cannot be extended to serve the new project,
for the two new phases. A still more common case without investing in substations and sub-
achieve a
of unbalanced impedances is a bank of single- transmission lines balance of
phase transformers in which impedances are very currents.
similar but seldom exactly alike. Thus the power If the system has to serve large specific loads,
flow program for a distribution system should which are scattered over a wide area, such as
always have the capacity to calculate unbalanced an irrigation project, in which case a different
impedances, preferably by using matrices. voltage level from the existing one that serves
residential loads in the same area may be
Considerations for the Power Flow Model acceptable
for the Tomoyo Project
If the client or group of clients to be served
represents a pilot project for a more extensive
The power flow analyses for the Tomoyo project,
development of similar projects in the area
used as an example for this module, were
performed with the Windmil analysis package If a sub-transmission voltage within the same
(Milsoft Utility Solutions, Texas, USA). This company exists that may be used for distribution
package has all the required technical features (In those cases in which the electric company
for a power flow program and has an additional has historically utilized a 34.5kV or 22kV as
function called “LandBase,” which very usefully a sub-transmission voltage, these lines may
creates the model of the system by directly be converted to fit distribution applications at
importing the tracks and waypoints from GPS an attractive cost.)
units. Figure 3 shows the Windmil screen with
the GPS data of the Tomoyo project imported In the Tomoyo project, none of these considerations
by LandBase. applied, so the project was developed at 14.4 kV
182
182 NRECA International, Ltd.
(class 25kV) as an extension of the existing The need for alternative solutions to the extension
system. of single-phase lines must always be justified on the
basis of economic and/or regulatory considerations.
Determination of the Number of Phases Where the requirement for a three-phase service
is only potential and not immediate, the design
After determining the length of the proposed of the single-phase lines as standardized by
system and calculating the demand of potential RUS facilitates the conversion to a three-phase
loads in existing lines and those proposed for configuration, with the addition of a crossarm
the project, the engineer must determine the and two phase conductors. With the services of
number of phases required in the proposed lines a properly trained contractor and with adequate
of the project. As indicated at the start, the RUS equipment, it is possible to realize this conversion In situations
integrated design system assumes that rural lines without de-energizing the single-phase line. For
where loads
should be single-phase, for economic reasons, certain cases, it is possible to plan, initially, single-
i.e. phase and neutral. However, some situations phase construction, to be converted to three-phase are scattered,
require consideration of the extension of two- in the future, without losing the economic benefits and with little
phase lines (two phases and neutral) or three- of the initial single-phase solution. growth potential,
phase lines, for the following reasons:
some companies
The Tomoyo project did not require modification
and electric
The current in one of the single-phase branches of the initial design, and the system was designed
exceeds the limit established for a system of with single-phase lines. authorities have
coordinated protection. applied the SWER
Determine the Application of a system.
The result of the power flow studies indicates Physical Neutral
that using a single-phase system for the
projected loads will not maintain maintain In situations where loads are scattered, and
voltage levels within regulatory limits. with little growth potential, some companies
and electric authorities have applied the SWER
There are three-phase loads in the project area system, which consists of a single phase conductor
that are large enough to make a conversion into without physical neutral. This system also can
single-phase impossible. Generally, motors of be found in areas where there are problems with
over 10HP are three-phase, though the technology the theft of the neutral conductor. The SWER
exists to overcome this limitation. system has been successfully applied in many
countries, including Australia and Tunisia, among
The nature of the loads to be covered by others.
the project rules out the use of single-
phase systems. For example, a project to The main considerations in its application are
develop an extensive irrigation system with as follows:
electric pumps of over 10HP each should be
designed from the beginning with three- For situations with no anticipated hope of
phase lines. load growth beyond a very low initial level
(8 amperes per circuit), it is possible to use
There is a need to distribute the loads among steel conductors, long spans of around 250
phases to ensure a better balance of phase meters, and a narrow right of way. This
currents at the source. This is a necessary application achieves a 50% reduction in the
consideration in cases where the permissible construction cost of a conventional single-
percentage of current imbalance is regulated phase line with aluminum conductors steel
by law, as in Bolivia. reinforced (ACSR).
To limit the voltage gradient to adequately The conductor cross-section should be determined
ensure the safety of persons and pets, limit according to the criteria set forth in the section
the maximum value of the resulting voltage in on Criteria for Analysis, based on an economic
the grounding of the primary winding of the choice and limited by considerations of protection
transformer, to 20 volts. To obtain this value for coordination and voltage drops. For the conditions
transformers of different capacities, one must of energy costs, load factor, and power factor
ensure that ground resistances do not exceed described in the same section, the economic
the values indicated in Table 7. Particularly for matrix of conductors for 14.4kV single-phase
the 7.2kV MRT/SWER system, achieving these lines appears in Table 8.
values may increase the cost of grounding,
especially in difficult types of soil. Again, the gray results represent the most
economical conductors for the load indicated.
Another consideration is the separation The #4 conductor has an application range up
between the primary system grounding and to 200 kW, whereas the #2 conductor has an
184
184 NRECA International, Ltd.
application range of 250 kW to 550 kW, and the Minimum Voltage Calculation
#1/0, from 600 kW to 900 kW. As previously,
the #2/0 conductor has practically no application After selecting the number of phases and cross-
range and the #4/0 conductor is applicable only section of the conductor, run the power flow
above 1000 kW. Taking into account that the model to determine whether the selections made
limitation owing to the coordination of 14.4kV are adequate, or whether they have to be adjusted
single-phase branches is 65 amp, or nearly 1000 by increasing the number of phases and/or the
kW, a #4/0 conductor cannot be considered for conductor cross-section. Decisions should be
this application. Preferred conductors for 14.4kV based on the following criteria.
single-phase lines are clearly the #2 ACSR for
loads up to 550 kW and the #1/0 ACSR for loads Voltage in the First Year
If values under
from 600kW to the coordination limit of 1000kW.
Since the load projected for the Tomoyo project Upon running the program with the projected load 95% of the
is 124 kW for the first year, with a projection to for the first year, the result should show voltage nominal voltage
be increased up to 250 kW until the year 15, the levels of +5%/-5% with respect to the nominal are found at
standardized, utilized conductor for this project voltage. The loads applied come from the analysis any point in the
is the #2 ACSR. of the demand, which takes into account a certain
model, increase
either the number
Table 8: Comparison of total annual cost for 14.4 kV single-phase lines of phases or the
Conductor #4 ACSR #2 ACSR #1/0 ACSR #2/0 ACSR #4/0 ACSR
conductor cross-
Cost of Construction US$/km $5,668 $6,015 $7,138 $8,163 $9,839
section, according
Load kW Total Annual US$/km
to the parameters
100 $873 $917 $1,080 $1,232 $1,480
specified in
150 $902 $935 $1,091 $1,241 $1,486
previous sections.
200 $943 $960 $1,107 $1,253 $1,494
250 $995 $993 $1,128 $1,270 $1,504
300 $1,059 $1,033 $1,153 $1,290 $1,517
350 $1,134 $1,080 $1,183 $1,313 $1,532
400 $1,221 $1,135 $1,217 $1,341 $1,549
450 $1,319 $1,197 $1,256 $1,371 $1,569
500 $1,429 $1,266 $1,300 $1,406 $1,590
550 $1,551 $1,342 $1,348 $1,444 $1,614
600 $1,684 $1,426 $1,400 $1,486 $1,641
650 $1,828 $1,517 $1,457 $1,531 $1,669
700 $1,985 $1,615 $1,519 $1,580 $1,700
750 $2,152 $1,720 $1,586 $1,633 $1,734
800 $2,332 $1,833 $1,656 $1,689 $1,769
850 $2,523 $1,953 $1,732 $1,749 $1,807
900 $2,725 $2,081 $1,812 $1,813 $1,847
950 $2,940 $2,215 $1,897 $1,880 $1,889
1000 $3,165 $2,357 $1,986 $1,951 $1,934
Description of Item Historical Unit Price Taxes Inflation Projected Unit Price
186
186 NRECA International, Ltd.
Figure 5. Sample three-line diagram of the power flow at year 1 (Tomoyo)
This database
should include
the unit price
of each item
of material,
including
the cost of
shipment,
and the total
amounts for
each purchase.
because some items differ according to their voltage previous projects. The costs on this database
level (insulators, transformers, etc.). must be disaggregated by construction unit and
not by kilometer, to be able to differentiate lines
One must also consider taxes, if applicable to the with different features. To apply historical costs
project in question. Most projects financed with to future projects, the engineer has to apply an
external aid are exempt from local taxes, but in inflation rate. Table 10 shows a typical format
other cases, one must determine the applicability for a labor database.
of taxes and their amount. Another very important
factor, in being able to apply historical costs Database by Construction Unit
to future projects, is the projection of the cost
itself. The historical cost of materials may be The next step in determining project costs consists
projected to the future by using an inflation rate or in calculating the investment costs by construction
a percentage of change in the cost of metals.4 unit. Calculate these costs by adding the cost of
materials for all the items included in the unit,
Labor Database plus the cost of labor for that unit. Table 11
shows a typical format for the database on cost
Apart from a database for the cost of materials, by construction unit.
the designer should maintain a database for the
cost of labor, using the construction costs of Database on Previous Designs
4
A good database for metals is the London Metal Exchange at: The engineer in charge needs to maintain another
http://www.lme.co.uk.
database on construction units by kilometer of line,
188
188 NRECA International, Ltd.
Table 10. Format for a labor database
Description of the Unit Historical Unit Price Inflation Projected Unit Price
for the feeders between communities (called trunk electric lines differ greatly between these two
lines or main feeders), and on construction units for types of land. Then, when going to the field, the
distribution networks in the communities (i.e., taps engineer will evaluate the line to be built and will Apart from
off the primary line, transformation points, and low be able to determine its cost per unit. a database
voltage distribution networks). The database for
for the cost
feeders between communities must include poles, Table 12 shows a format for a database on
primary structures, conductors, anchors and all the construction units by kilometer/feeder. of materials,
primary line hardware. The database on distribution the designer
networks for the communities must include all Database on the Costs of Service Drops should
the units used in primary lines, underbuild, and
maintain a
secondary lines, and the transformation points in After developing the cost by kilometer of primary
the communities. lines for feeders between communities and the
database
cost by user for the distribution network in each for the cost
In the database on feeders between communities, community, develop cost estimations for the of labor,
distinguish between three-phase and single-phase service drops. As in the preceding steps, base using the
lines. Likewise, the database on feeders between these estimations on a database of historical
construction
communities must distinguish between lines in data, which includes the cost of materials and
flat, level areas and broken terrain or areas with labor. There are various types of service drops costs of
many line angles, because construction costs of to take into account, each with its particularities. previous
projects.
Table 11. Format for a database on cost by construction unit
Unit: ZA1
Description Quantity Unit Cost Total Cost
Square washer, 2-1/4”(5/8”) 3 $0.13 $0.39
Locknut, 5/8” 2 $0.11 $0.23
Spool insulator, 1-3/4” 1 $1.22 $1.22
Compression connector, ground to neutral 1 $0.33 $0.33
Preformed armor rods, single support, phase 1 $3.01 $3.01
Preformed armor rods, single support, neutral 1 $2.17 $2.17
Machine Bolt, 5/8” x 10” 2 $0.55 $1.10
Spool bolt , 5/8” x 10” 1 $2.43 $2.43
Pin-type insulator, ANSI 56-3 1 $30.22 $30.22
Pole top Pin , 20” 1 $3.68 $3.68
Aluminum tie wire, feet 15 $0.07 $1.04
Total Material Cost $45.81
Labor Cost $5.79
Total Unit Cost $51.60
Table 13 shows an example of a database on To have an idea of its cost, keep a database of
the distribution of different types of service the historical costs of staking in recent projects.
drops. This database must include the cost by kilometer
for feeders between communities and the cost
Database on the Cost of Staking by user for the staking of the distribution
network in each community. With this, the
The only cost component still to be determined engineer can make a projection of the annual
is that of staking (design) of the proposed project. cost, taking into account an inflation rate. Table
190
190 NRECA International, Ltd.
Table 14. Costs of electric line staking Tables of Indicative Line Costs
Add these costs to the Excel worksheet described Description of the Project
previously.
Keep the description simple, so it is useful for
the evaluation of the project’s feasibility. Table
Table 15 shows an example of a worksheet that
17 shows a scheme for clarifying the description
arrives at the total cost of the project.
Tomoyo km phases users KWh kW Staking Feeder Distribution Total Cost $/User
Molle Molle (ambos) 6.4 1 200 6,000 25 $4,723 $28,160 $94,000 $126,883 $634
Sorojchi 2.7 1 105 3,150 14 $2,240 $11,880 $49,350 $63,470 $604
Yoroca 2.5 1 98 2,940 13 $2,084 $11,000 $46,060 $59,144 $604
Tomoyo 4.2 1 114 3,420 15 $2,893 $18,480 $53,580 $74,953 $657
Llatapata 2 1 50 1,500 7 $1,326 $8,800 $23,500 $33,626 $673
Isluco 2 1 30 900 5 $1,086 $8,800 $14,100 $23,986 $800
Jiroja 1 1 60 1,800 8 $1,083 $4,400 $28,200 $33,683 $561
Kasapata 3 1 50 1,500 7 $1,689 $13,200 $23,500 $38,389 $768
Sorocoto 3.5 1 160 4,800 20 $3,191 $15,400 $75,200 $93,791 $586
Soroscopa 1 1 60 1,800 8 $1,083 $4,400 $28,200 $33,683 $561
28.3 10 927 27,810 121 $21,397 $124,520 $435,690 $581,607 $627
of the project. The numerical values correspond included when the study warrants the inclusion
to the Tomoyo project. of some voltage regulation equipment during the
life of the project, or during the time allowed for
Power Flow project analysis, so as to show where, when, and
with what capacity this equipment is required
The power flow proves that the design is adequate to be installed. In these cases, the power flow
for the project throughout the period evaluated. should include a table of results showing the
Consequently, there will be at least two power data for each point of the study and a three-line
flows: one for the fi rst year of the project and diagram that displays the results in a graphical
another for the last. A third power flow may be format.
192
192 NRECA International, Ltd.