Curve Widening Estimate SH 216

1. The document is an estimate for curve widening work on the Solatharam - Srimushnam road including excavation, construction of a crash barrier median, laying of granular sub-base and wet mix macadam layers, and application of prime, tack and dense bituminous macadam coats. 2. The total estimated cost is Rs. 100 lakhs including provisions for GST, escalation costs, quality control charges, road furniture, shifting of utilities, and contingencies. 3. The main work items include excavation, construction of a concrete crash barrier median, laying of granular sub-base and wet mix macadam layers, and application of tack coats and dense bitumin

Uploaded by

veevimal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
99 views25 pages

Curve Widening Estimate SH 216

1. The document is an estimate for curve widening work on the Solatharam - Srimushnam road including excavation, construction of a crash barrier median, laying of granular sub-base and wet mix macadam layers, and application of prime, tack and dense bituminous macadam coats. 2. The total estimated cost is Rs. 100 lakhs including provisions for GST, escalation costs, quality control charges, road furniture, shifting of utilities, and contingencies. 3. The main work items include excavation, construction of a concrete crash barrier median, laying of granular sub-base and wet mix macadam layers, and application of tack coats and dense bitumin

Uploaded by

veevimal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

ABSTRACT ESTIMATE

Name of work: Curve Widening at 4/8, 4/10 & 5/2 of Solatharam - Srimushnam road (SH 216)

Estimate Amt.Rs. 100.00 Lakhs.


Sl.
Contents Details of work Rate Per Amount
No.
Providing cast in situ RCC M25 grade (Design
Mix) crash Barrier type centre Median of size
0.610M at Bottom, 0.250M at Middle and
0.150M at top to a total height of 1.250M using
HBG ISS graded metal including cost and
conveyance of all materials to site including
30.95kg cost of Reinforcements as per to steel
schedule in the appended drawing, fabrication
and placing in position of steel rods, cost of
1 200.00 RM Binding wire, laying the concrete, labour charges 6244.00 RM 1248800
for mixing, watering curing including centering
shuttering, rendering smoothness over the RCC
surface with 10Kg of cement per 10 Squre Metre
and painting two coat over the RCC surface with
best approved quality of enamel paint over the
primer coat, picking the existing BT surface
removal of debris etc. Complete as directed by
the department officer and as per MORTH
specification.
Excavation including removal and satisfactory
disposal of all materias necessary for the
construction of roadway and side drains in
accordance with the specifications and the lines,
2 1629.00m³ 96.60 Cum. 157361
grades and cross sections shown in the drawings
or as indicated by the Engineer for Box Cutting
for Wideneing Portion and as per MORTH No.
111, 112, 201, 202, 301, 302.
Providing and Laying Granular Sub-Base
Grade- III consisting of well graded Material
confirming to the grading given in Table No.400-
1, mixing in a mechanical mix plant at OMC,
3 270.00m³ carriage of mixed Material to work site, 1764.34 Cum. 476372
spreading in uniform layers with motor grader on
prepared surface and compacting with vibratory
roller to achieve the desired density, etc.,
complete as directed by the Engineer.
Sl.
Contents Details of work Rate Per Amount
No.
Providing and Laying Granular Sub-Base
Grade- V consisting of well graded Material
confirming to the grading given in Table No.400-
1, mixing in a mechanical mix plant at OMC,
4 459.00m³ carriage of mixed Material to work site, 1672.47 Cum. 767664
spreading in uniform layers with motor grader on
prepared surface and compacting with vibratory
roller to achieve the desired density, etc.,
complete as directed by the Engineer.
Sl.
Contents Details of work Rate Per Amount
No.
Provding and Laying Wet Mix Macadam
consisting of clean crushed aggregates
confirming to the grading given in Table No.400-
13, including premixing the Material with water
at OMC in mechanical mix plant carriage of
5 450.00m³ mixed Material by tipper to site, laying in 1896.49 Cum. 853421
uniform layers with paver on well prepared
surface and compacting with vibratory roller to
achieve the desired density, etc., complete as
directed by the Engineer. as per MORTH No.
111, 112, 406, 900.
Providing and applying Prime Coat over
granular Base with bitumen emulsion (SS-I
type) on prepared surface including preparing the
6 1800.00 m² road surface and spraying the primer at the rate of 73.80 sqm 132840
0.70 kg/sqm using bitumen sprayer as directed by
the Engineer - over WMM as per MORTH No.
111, 112, 502, 900
Providing and applying Tack Coat over
granular surface treated with primer using
Bitumen Emulsion (RS-I type) with mechanical
7 1800.00 m² 17.57 sqm 31626
sprayer at the rate of 0.25 kg per sqm as directed
by the Engineer as per MORTH
No.111,112,503,900.
Providing and applying Tack Coat over
existing bituminous surfaces with Bitumen
Emulsion (RS-I type) using mechanical sprayer at
8 4200.00 m² 23.39 sqm 98238
the rate of 0.20 kg per sqm on the prepared
bituminous surface as directed by the Engineer as
per MORTH No. 111, 112, 503, 900
Providing and laying Dense Bituminous
Macadam which work shall consist of
construction, using crushed aggregates, (Table
500-10) premixed with VG 30 Grade Bitumen at
the rate of minimum 4.50% by weight of the total
mix confirming to the aggregates and binder as
per the job mix formula in the Hot mix plant,
9 90.00m³ 10049.24 Cum. 904432
transporiting the mix to the worksite, laying with
paver finisher and compaction with smooth
wheeld and vibratory roller in accordance with
the requirements of the specification and in
confirmity with the drawing as directed by the
Engineer for DBM (Grade-II) as per MORTH
No. 111, 112, 505, 900
Sl.
Contents Details of work Rate Per Amount
No.
Providing and laying Bituminous Concrete
which work shall consist of construction using
coarse aggregates (Table 500-17) premixed with
VG 30 Grade Bitumen at the rate of minimum
5.40% by weight of the total mix confirming to
the aggregates and binder as per the job mix
formula in the Hot mix plant, transporiting the
10 240.00m³ 10970.35 Cum. 2632884
mix to the worksite, laying with paver finisher
and compaction with smooth wheeld and
vibratory roller in accordance with the
requirements of the specification and in
confirmity with the drawing as directed by the
Engineer for BC (Grade-II) as per MORTH No.
111, 112, 507, 900
Providing and laying Carted Earth having
minimum with an additional lead of km
including cost of earth, seniorage charges
11 120.00m³ conveyance, laying, watering and consolidation 159.41 Cum. 19129
etc., complete as directed by the Engineer for
forming the shoulders as per MORTH No.111,
112, 305, 900
7322767
Estimate including all Sub Estimate for CD works etc., C.V 7322767
12 Provision for GST 12% 878732
Total Contract Value including GST 8201499
13 Escalation 5.00 % for Construction & Upkeeping cost 410075

14 Provision for advertisement charges L.S 120000

15 Provision for Quality control 1% charges L.S 82015

16 Provision for Road Furniture 2% charges L.S 164030

17 Provision for shifting of EB Poles,Utilities. L.S 500000

18 Provision for Labour welfare fund 1.00% charges L.S 100000

19 Provision for P.S & Contingencies charges 2.50% L.S 422381

Total Amount Rs. 10000000

Assistant Divisional Engineer Assistant Engineer


Highways,C&M,Kattumannarkoil Highways,C&M,Kattumannarkoil
DETAILED ESTIMATE

Curve Widening at 4/8, 4/10 & 5/2 of Solatharam - Srimushnam


NAME OF WORK : -
road (SH 216)

Estimate Amt.Rs. 100.00 Lakhs


Sl. Measurement in Metre
Description of work No. Contents
No. L B D
Providing cast in situ RCC M25 grade (Design Mix) crash Barrier type centre Median
of size 0.610M at Bottom, 0.250M at Middle and 0.150M at top to a total height of 1.250M
using HBG ISS graded metal including cost and conveyance of all materials to site including
30.95kg cost of Reinforcements as per to steel schedule in the appended drawing, fabrication
and placing in position of steel rods, cost of Binding wire, laying the concrete, labour
1
charges for mixing, watering curing including centering shuttering, rendering smoothness
over the RCC surface with 10Kg of cement per 10 Squre Metre and painting two coat over
the RCC surface with best approved quality of enamel paint over the primer coat, picking the
existing BT surface removal of debris etc. Complete as directed by the department officer and
as per MORTH specification.
KM 4/8 1 X 1 200.00 - 200.00

KM 4/10 1 X 1 0.00 - 0.00

KM 5/2 1 X 1 0.00 - 0.00

200.00 m²
Excavation including removal and satisfactory disposal of all materias
necessary for the construction of roadway and side drains in accordance
2 with the specifications and the lines, grades and cross sections shown in the
drawings or as indicated by the Engineer for Box Cutting for Wideneing
Portion and as per MORTH No. 111, 112, 201, 202, 301, 302.
KM 4/8 1 X 1 200.000 3.000 0.905 543.000
KM 4/10 1 X 1 200.000 3.000 0.905 543.000
KM 5/2 1 X 1 200.000 3.000 0.905 543.000
1629.00 m³
Providing and Laying Granular Sub-Base Grade- III consisting of well
graded Material confirming to the grading given in Table No.400-1, mixing
in a mechanical mix plant at OMC, carriage of mixed Material to work site,
4
spreading in uniform layers with motor grader on prepared surface and
compacting with vibratory roller to achieve the desired density, etc.,
complete as directed by the Engineer.
Sl. Measurement in Metre
Description of work No. Contents
No. L B D

KM 4/8 1 X 1 200.000 3.000 0.150 90.000

KM 4/10 1 X 1 200.000 3.000 0.150 90.000

KM 5/2 1 X 1 200.000 3.000 0.150 90.000

270.00 m³
Providing and Laying Granular Sub-Base Grade- V consisting of well
graded Material confirming to the grading given in Table No.400-1, mixing
in a mechanical mix plant at OMC, carriage of mixed Material to work site,
5
spreading in uniform layers with motor grader on prepared surface and
compacting with vibratory roller to achieve the desired density, etc.,
complete as directed by the Engineer.
KM 4/8 1 X 1 200.000 3.000 0.255 153.000

KM 4/10 1 X 1 200.000 3.000 0.255 153.000

KM 5/2 1 X 1 200.000 3.000 0.255 153.000

459.00 m³
Provding and Laying Wet Mix Macadam consisting of clean crushed
aggregates confirming to the grading given in Table No.400-13, including
premixing the Material with water at OMC in mechanical mix plant carriage
6 of mixed Material by tipper to site, laying in uniform layers with paver on
well prepared surface and compacting with vibratory roller to achieve the
desired density, etc., complete as directed by the Engineer. as per MORTH
No. 111, 112, 406, 900.
KM 4/8 1 x 1 200.00 3.000 0.250 150.00

KM 4/10 1 x 1 200.00 3.000 0.250 150.00

KM 5/2 1 x 1 200.00 3.000 0.250 150.00

450.00 m³
Providing and applying Prime Coat over granular Base with bitumen
emulsion (SS-I type) on prepared surface including preparing the road
7 surface and spraying the primer at the rate of 0.70 kg/sqm using bitumen
sprayer as directed by the Engineer - over WMM as per MORTH No. 111,
112, 502, 900
KM 4/8 1x1 200.00 3.000 600.00

KM 4/10 1x1 200.00 3.000 600.00

KM 5/2 1x1 200.00 3.000 600.00


Sl. Measurement in Metre
Description of work No. Contents
No. L B D
1800.00 m²
Providing and applying Tack Coat over granular surface treated with
8 primer using Bitumen Emulsion (RS-I type) with mechanical sprayer at the
rate of 0.25 kg per sqm as directed by the Engineer as per MORTH
No.111,112,503,900.
Sl. Measurement in Metre
Description of work No. Contents
No. L B D

KM 4/8 1x1 200.00 3.000 600.00

KM 4/10 1x1 200.00 3.000 600.00

KM 5/2 1x1 200.00 3.000 600.00

1800.00 m²
Providing and applying Tack Coat over existing bituminous surfaces
with Bitumen Emulsion (RS-I type) using mechanical sprayer at the rate of
8
0.20 kg per sqm on the prepared bituminous surface as directed by the
Engineer as per MORTH No. 111, 112, 503, 900
KM 4/8 1x1 200.00 7.000 1400.00

KM 4/10 1x1 200.00 7.000 1400.00

KM 5/2 1x1 200.00 7.000 1400.00

4200.00 m²
Providing and laying Dense Bituminous Macadam which work shall
consist of construction, using crushed aggregates, (Table 500-10) premixed
with VG 30 Grade Bitumen at the rate of minimum 4.50% by weight of the
total mix confirming to the aggregates and binder as per the job mix
9 formula in the Hot mix plant, transporiting the mix to the worksite, laying
with paver finisher and compaction with smooth wheeld and vibratory roller
in accordance with the requirements of the specification and in confirmity
with the drawing as directed by the Engineer for DBM (Grade-II) as per
MORTH No. 111, 112, 505, 900
KM 4/8 1x1 200.00 3.000 0.050 30.00

KM 4/10 1x1 200.00 3.000 0.050 30.00

KM 5/2 1x1 200.00 3.000 0.050 30.00


90.00 m³
Providing and laying Bituminous Concrete which work shall consist of
construction using coarse aggregates (Table 500-17) premixed with VG 30
Grade Bitumen at the rate of minimum 5.40% by weight of the total mix
confirming to the aggregates and binder as per the job mix formula in the
10 Hot mix plant, transporiting the mix to the worksite, laying with paver
finisher and compaction with smooth wheeld and vibratory roller in
accordance with the requirements of the specification and in confirmity
with the drawing as directed by the Engineer for BC (Grade-II) as per
MORTH No. 111, 112, 507, 900
Sl. Measurement in Metre
Description of work No. Contents
No. L B D
KM 4/8 1x1 200.00 10.000 0.040 80.00

KM 4/10 1x1 200.00 10.000 0.040 80.00

KM 5/2 1x1 200.00 10.000 0.040 80.00

240.00 m³
Providing and laying Carted Earth having minimum with an additional
lead of km including cost of earth, seniorage charges conveyance, laying,
12
watering and consolidation etc., complete as directed by the Engineer for
forming the shoulders as per MORTH No.111, 112, 305, 900
Sl. Measurement in Metre
Description of work No. Contents
No. L B D
KM 4/8 1x2 200.00 1.00 0.100 40.00

KM 4/10 1x2 200.00 1.00 0.100 40.00

KM 5/2 1x2 200.00 1.00 0.100 40.00

120.00 m²

17 Provision for GST 12%

18 Upkeeping of Road

19 Provision for GST 12%

20 Escalation 5.00 % for Construction Cost

21 Escalation 5.00 % for Upkeeping Cost


Sl. Measurement in Metre
Description of work No. Contents
No. L B D

22 Provision for Labour welfare fund 1.00% LS

23 Provision for advertisement charges LS

24 Provision for Road Furniture 2.00 % LS

25 Provision for Shifting of Utilities, EB Poles. LS

26 Quality Control charges 1% LS

27 Contingencies and P.S.Charges 2.5% LS

Assistant Divisional Engineer Assistant Engineer


Highways,C&M,Kattumannarkoil Highways,C&M,Kattumannarkoil
BITUMEN LEAD PARTICULARS

Name of work : Curve Widening at 4/8, 4/10 & 5/2 of Solatharam - Srimushnam road (SH 216)

H.B.G. METAL FROM KM 3/2 OF A. SATHANUR-PUDHUKAZHANI ROAD

1 A. Sathanur – Pudukazhani Road Km 3./2 - 0./0 = 3.20

2 Chennai – Trichy – Dindugal (NH-45) Road Km 204./2 - 202./2 = 2.00

3 Mangalampettai – Elavasanurkottai Road Km 19./6 - 15./8 = 3.80

4 Vridhachalam – Ulundurpet – Villupuram Road Km 15./8 - 0./0 = 15.80

5 Cuddalore -Vridhachalam - Salem Road Km 54./0 - 54./4 = 0.40

6 Vridhachalam - Tholudur Road Km 0./0 - 6./2 = 6.20

7 Vridhachalam - Mathanathur Road (via)Jayankondam Km 0./0 - 6./4 = 6.40

8 Sozhatharam - Srimushnam Road Km 20./0 - 4./6 = 15.40


9 Average working distance 4./6 - 5./2 = 0./6 /2 = 0.30
53.50

(or) 54.00 KM

H.B.G. METAL QUARRY FROM KM 3/2 OF A. SATHANUR-PUDHUKAZHANI ROAD


TO CMP SITE AT KM 10/8 VRIDHACHALAM – ULUNDURPET – VILLUPURAM ROAD

1 A. Sathanur – Pudukazhani Road Km 3./2 - 0./0 = 3.20

2 Chennai – Trichy – Dindugal (NH-45) Road Km 204./2 - 202./2 = 2.00

3 Mangalampettai – Elavasanurkottai Road Km 19./6 - 15./8 = 3.80

4 Vridhachalam – Ulundurpet – Villupuram Road Km 15./8 - 10./8 = 5.00

14.00

Quarry to Worksite CMP to Worksite Quarry to CMP (or) 14.00 KM

54.00 KM -- 40.00 KM = 14.00 KM

BULK BITUMEN (60/70-VG 30) FROM THIRUVOTTIYUR TO CMP SITE


AT KM 10/8 VRIDHACHALAM – ULUNDURPET – VILLUPURAM ROAD

1 Factory to Ponneri - panchetty road Km 1./6 - 2./6 = 1.00


2 Manali to Mathur Road Km 0./0 - 5./7 = 5.70
3 Madavaram red Hills Road Km 0./0 - 4./6 = 4.60
4 N.H. 45 Chennai-Trichy-Dindugal Road Km 11./0 - 11./5 = 0.50
5 Chennai Byepass Km 0./0 - 32./2 = 32.20
6 N.H. 45 Chennai-Trichy-Dindugal Road Km 28./0 - 197./0 = 169.00
7 Vridhachalam – Ulundurpet – Villupuram Road Km 21./4 - 10./8 = 10.60

223.60

(or) 224.00 KM
BULK BITUMEN (80/100-VG 10) FROM THIRUVOTTIYUR TO WORK SITE .

1 Factory to Ponneri - panchetty road Km 1./6 - 2./6 = 1.00

2 Manali to Mathur Road Km 0./0 - 5./7 = 5.70

3 Madavaram red Hills Road Km 0./0 - 4./6 = 4.60

4 N.H. 45 Chennai-Trichy-Dindugal Road Km 11./0 - 11./5 = 0.50

5 Chennai Byepass Km 0./0 - 32./2 = 32.20

6 N.H. 45 Chennai-Trichy-Dindugal Road Km 28./0 - 149./8 = 121.80

7 Vikkiravandi - Kumbakonam - Thanjavur Road Km 0./0 - 75./2 = 75.20

8 Sozhatharam - Srimushnam Road Km 0./0 - 4./6 = 4.60


9 Average working distance 4./6 - 5./2 = 0./6 /2 = 0.30
245.90

(or) 246.00 KM
EMULSION FROM IRUNKATTUKOTTAI TO WORK SITE .
1 Factory to Sipcot road Km 2./0 - 0./0 = 2.00
2 Irunkattukottai Road Km 34./8 - 41./74 = 6.94
3 Sriperambudur - Singaperumalkoil Road Km 24./6 - 0./0 = 24.60
4 N.H. 45 Chennai-Trichy-Dindugal Road Km 47./8 - 149./8 = 102.00
5 Vikkiravandi - Kumbakonam - Thanjavur Road Km 0./0 - 75./2 = 75.20

6 Sozhatharam - Srimushnam Road Km 0./0 - 4./6 = 4.60


7 Average working distance 4./6 - 5./2 = 0./6 /2 = 0.30
215.64
(or) 216.00 KM

U.S.GRAVEL FROM PALAYANKOTTAI KM 6/4 OF SOLATHARAM- SRIMUSHANAM ROAD

1 Solatharam- Srimushnam Road Km 6./4 - 4./6 = 1.80


2 Average working distance 4./6 - 5./2 = 0./6 /2 = 0.30
2.10
(or) 2.00 KM
M-SAND FROM RAJASHREE INDUSTRIES QUARRY AT KM 1/6 OF PERAMBALUR -
MANAMADHURAI ROAD
1 CT = 1.00
2 Perambalur - ManamadhuraivRoad Km 1./6 - 15./0 = 13.40
3 kunam - Veppur - Vayalapadi Road Km 0./0 - 18./8 = 18.80
4 Mathur - Thittakudi Road Km 20./0 - 26./0 = 6.00
5 Panchayat Union Road Km 0./0 - 0./4 = 0.40

6 Vridhachalam - Tholudhur Road Km 31./6 - 6./2 = 25.40

7 Vridhachalam - Mathanathur Road Km 0./0 - 6./4 = 6.40

8 Sozhatharam - Srimushnam Road Km 20./0 - 4./6 = 15.40


9 Average working distance 4./6 - 5./2 = 0./6 /2 = 0.30
Total 87.10
(or) 87.00 KM

Assistant Divisional Assistant Engineer,


Engineer, Highways,C&M,
Highways,C&M, Kattumannarkoil.
Kattumannarkoil.
RCC CRASH BARRIER TYPE CENTRE MEDIAN OF SIZE 0.610M
Bottom 0.25M Middle, 0.150M top AT a Height of 0.985M From the
Road Level to Top of Median

150mm

485 mm 12 mm
6
2
985mm 5
250mm

250mm

110mm 2
dia 5
250 0

3
610mm 7
5
Cross-Section of RCC Crash Barrier
MODEL DATA

Name of work Junction Improvements at km 26/6 of Puduchathiram-Portonovo road

Providing cast in situ RCC M25 grade (Design Mix) crash Barrier type centre Median of size 0.610M at Bottom, 0.250M at Middle and 0.150M
at top to a total height of 0.985M using HBG ISS graded metal including cost and conveyance of all materials to site including 24.60kg cost of
Reinforcements as per to steel schedule in the appended drawing, fabrication and placing in position of steel rods, cost of Binding wire, laying the
concrete, labour charges for mixing, watering curing including centering shuttering, rendering smoothness over the RCC surface with 10Kg of
cement per 10 Squre Metre and painting two coat over the RCC surface with best approved quality of enamel paint over the primer coat, picking
the existing BT surface removal of debris etc. Complete as directed by the department officer and as per MORTH specification.

COST OF MATERIALS

Convey
Kind of Lead Cost of Total
Sl.No ance
materials in km Materials charge
20 mm ISS
1 54 1432.00 478.16 1910.16
metal
12 mm ISS
2 54 1329.00 478.16 1807.16
metal
M.Sand for
3 87 1280.00 723.25 2003.25
mortar

4 Quarry Dust 54 122.50 478.16 600.66

5 Cement - 6244.98 6244.98

6 Steel - 54324.48 54324.48

RATE OF LABOUR
Mazdoor I class (P-14) 562.00 each 562.00
Mazdoor II class (P-15) 461.00 each 461.00
Mason I class (P-12) 861.00 each 861.00
Mason II class (P-14) 804.00 each 804.00
Fitter I class (P-12) 747.00 each 747.00
Painter I class (P-12) 688.00 each 688.00
Carpenter I class (P-12) 842.00 each 842.00
Vibration charges for
RCC (P-30) 81.30 cum 81.30
(RMP) Iron
work Synthetic
225.40 Lt 225.40
Enamel Paint
page 51
White Led (Local rate) 38.50 kg 38.50
Boiled Linseed Oil
19.80 Lt 19.80
(Local rate)
Whiting (Local rate) 35.00 kg 35.00
1. Centering Area (for 1M length)
1 x 2 - 1.00 x 0.250 = 0.500
1 x 2 - 1.00 x 0.3125 = 0.625
1 x 2 - 1.00 x 0.490 = 0.980
2.095
Add sides on end L.S. 0.105
Total Area 2.20M2

2. Area of smoothening (for 1RM length)

1 x 2 - 0.25 = 0.500
1 x 2 - 0.3125 = 0.625
1 x 2 - 0.49 = 0.980
Top 1 x 1 - 0.15 = 0.150
2.255
sides on end - LS 0.095
2.35 M2

3. Area of painting = 2.35 M2

4. Materials requirement for mould

MS sheets 2 x 1 - 0.25 = 0.500


2 x 1 - 0.3125 = 0.625
2 x 1 - 0.49 = 0.980

sides in exp joints 2 x 1 - 0.61+0.25 / 2 x 0.23 = 0.10


- 0.25+0.15 / 2 x 0.49 = 0.10
= 2.350
Add sides on end LS 0.045
2.35 M2
Weight of MS sheet - 280cm x 60cm x 1.40mm 18.50 kg

18.50 = 11.012 = 11.012 kg/sqm


1.68

2.35M2 @ 11.012 kg / M2 = 25.88kg


MS angle - 50x50x40mm

2 x 1 - 2.00
4 x 0.86 - 3.44
5.44 RM

5.44 RM @ 3.00kg / RM = 16.32 kg

MS angle - 25x25x4mm - (0.075+0.485+0.30+0.25+0.305) x2 = 2.83


2 x 6 1 - =12.00
3 x 0.25 - =0.75
2 (0.485+0.30+0.225) x 2 =4.04
19.62 RM

19.62 RM @ 1.40kg / RM = 27.47 kg

5. Centering charges for centre median - 1RM

(i) Material

25.88 kg - MS sheet 20G 41.20 /kg - 1066.26


16.32 kg - MS sheet 50x50x4 41.20 /kg - 672.38
27.47 kg - MS angle 25x25x4 41.20 /kg - 1131.76
69.67 kg - Fabrication & welding charges 38.4 /kg - 2675.33
(25.88+16.32+27.47) -
Sundries for nut bolt - 154.27
for adopting 40uses 5700.00

Therefore 1 use 5700.00 / 40 142.50

(ii) Strutting

98.5 /RM Casurina props 10-13 cm @ 75cm c/c braces assuming 5


uses - 25.2 /RM - 2482.20
For One use 496.44

0.30 Nos Carpenter I class - 842.00 /E 252.60


0.30 Nos Mazdor I class - 562.00 /E 168.60
For 10M2 = Rs. 917.64
For 1M2 = Rs. 91.76

Therefore 1 RM = 2.20M2 centering required


2.2 x 91.76 201.88
1RM

Total Centering charges 201.88 + 142.50 = Rs. 344.38 /1 RM


6. Requirement of steel - 1 RM

Dia Spacing Nos Length Total Wt RM Total Weight


12mm dia 150mm 10 0.95 9.50 0.89 8.46
12mm stirupps 150mm 7 2.59 18.13 0.89 16.14
24.60
Total quantit = 24.60 kg

7. Requirement of RCC (M25)

Crash barrier 1 - 0.61 - 0.25 0.15


1 x (0.61+0.25) x 0.25 = 0.11
2
1 x (0.25+0.15) 0.485 = 0.10
2
Deduction for
1x1 x 0.00785 (-) 0.01
PVC pipe of 0.35 M3
110mm dia

8.Cement Mortar (M25)

0.845 MT Cement - 6244.98 - 5277.01


1m3 Sand - 1250+conveyance - 1973.25
7250.26

Cost of RCC (M25) Design Mix

6.30 m3 Cost of 20mm ISS 1910.16 m3 12034.01


2.70 m3 Cost of 12mm ISS 1807.16 m3 4879.33
4.50 m3 Cement Mortar (M25) 7250.26 m3 32626.16
3.5 Nos. Mason - II class 804.00 Each 2814.00
21.2 Nos. Mazdoor I class 562.00 Each 11914.40
35.3 Nos. Mazdoor II class 461.00 Each 16273.30
10 m3 Vibration charges 81.30 m3 813.00
1539 Lit. cost of water 130.00 KL 200.07
Sundries 0.78
Rate Rs. 81555.05 /10 m3
Rate Rs. 8155.51 / m3
9 Painting 2 coats

Prime coat

0.61 kg - white lead - 38.50 kg - 23.49


1.00 kg - whiting - 35.00 kg - 35.00
0.61 lit - Boiled linseed oil - 19.80 lit - 12.08
0.7 Nos - painter I class - 688.00 Each - 481.60
552.17

Main data for painting

10 m2 priming coat - 552.17 /10m2 552.17

2.55 lit Ready mixed paint - 225.40 /lit 574.77


1.2 nos Painter I class - 688.00 each 825.60

L.S. for brush, thinner etc., 8.78


Rate Rs. 1961.32 /10M2
Rate Rs. 196.13 /M2

10.Rendering Smoothness over the CC surfaces with 10kg of cement for 10 Sqm

10.00 Kg Cost of cement 6244.98 Kg 62.45


0.30 Nos Mason I Class 861.00 Kg 258.30
2.20 Nos Mazdoor II Class 461.00 each 1014.20
Rate per 10 Sqm 1334.95

Rate per 1 Sqm 133.49

11)Supply and fabrication of steel required for all RCC items

1.05 M.T Cost of steel 54324.48 1 Mt 57040.70

10.00 Kg Binding wire 50.30 1 Kg 503.00

35.00 No Fitter I clase 747.00 Each 26145.00

Rate per M.T 83688.70

Rate per 1 Kg 83.69

12. RCC centre median of size 0.610m bottom 0.25 m at middle 0.15m top at a height of 0.985 metre from the road
level to top of median

0.61 m2 picking the existing BT surface 17.15 m2 10.46


1 RM Form work for centering 344.38 RM 344.38
24.60 Kg steel 83.69 Kg 2058.77
0.35 m3 cost of RCC (M25) design mix 8155.51 m3 2854.43
2.35 m 2
Rendering smoothness 133.49 m 2
313.70
2.35 m2 painting 196.13 m2 460.91
1 RM 110mm PVC pipe 193.50 RM 193.50
sundries including curing removal of debris & etc., 6.91 1 RM
Rate Rs 6244.00
PROVIDING CARTED EARTH FOR BERMS INCLUDING COMPACTION
Providing and laying of Carted Earth including cost and conveyance of the same to work site
from approved quarry including stacking the same to departmental gauge for premeasurement
including all labour charges for laying, spreading etc.,complete and as directed by the
deparmental engineers for making up of low berms

Hire charge for machineries

Power Roller 8-10 tonne

Hire charges excluding fuel charges per day Rs. 985.00

Fuel charges per day (Diese 2.50x Lit / Hr 8.00 Hrs.x 90.17 / LitRs. 1803.40

Total Hire charges per day including Fuel Rs. 2788.40

Daily Out Turn 425 Cum


Hire charges of Power Roller per 10 sq = 2788.40 Rs. 6.56 /Cum
425

Water Sprinklers

Hire charges excluding fuel charge: 1383.00

Fuel charges per day (Diese 3.25x Lit / Hr 8.00 Hrs.x 90.17 / LitRs. 2344.42

Total Hire charges per day including Fuel Rs. 3727.42

Daily Out turn 1000 Cum


Hire charge of Water Sprinklers per 10 sqm = 3727.42 Rs. 3.73 /Cum
1000

Total Hire charges for Macheries per 1 = 6.56 + 3.73 = Rs. 10.29 /Cum

Labour charges for Laying U.S.Gravel for 100cum

2.00 Nos. of Mazdoor Ist Class Rs. 562.00 / Each = Rs. 1124.00

Total Labour charges for laying gravel per 100 Cum Rs. 1124.00

Total Labour charges for laying gravel per cum 1124.00 Rs. 11.24 /Cum
100

Total Hire and Labour charges 10.29 + 11.24 Rs. 21.53 /Cum
Name of
Curve Widening at 4/8, 4/10 & 5/2 of Solatharam - Srimushnam road (SH 216)
work

Kind of Cost of Conveyance Stacking


Km Name of Quarry Lead Total
Material Material Charge Charges

Km Palayankottai at Carted
2 96.60 22.26 - 118.86
4/6-5/2 km 6/4 Earth

PROVIDING CARTED EARTH FOR BERMS INCLUDING COMPACTION (100%)

Cost of Carted Earth


Qty Hire and Labour Total Rate per
Km
in Rate per Cum Amount Charges for 1 Cum. Cum at site
Cum.
Km
1.16 118.86 137.88 21.53 159.41
4/6-5/2

Assistant Divisional Engineer, Assistant Engineer,


Highways,C&M, Kattumannarkoil. Highways,C&M, Kattumannarkoil.
HIGHWAYS DEPARTMENT
CONSTRUCTION AND MAINTENANCE WING

CIRCLE

VILLUPURAM
DIVISION

CUDDALORE
SUB DIVISION

KATTUMANNARKOIL
JOB CODE
CRIDP 2021-2022
ROAD NO.
SH-216
NAME OF WORK

CURVE WIDENING AT 4/8, 4/10 & 5/2 OF


SOLATHARAM - SRIMUSHNAM ROAD (SH
216)

ESTIMATE AMOUNT

Rs.100.00 Lakhs