RSL project remaining architectural & civil work report 18 8 2022
Main Building internal statsus Noted Remarks
Painting
1- Epoxy wall finishing (second coat)
2-Epoxy & self-level epoxy floors.
Commercial evaluation for remaining work vs payed money to
3-Ceiling paint. zidcon,
4- Wall painting (2 coats).
5-External paint of parapet
Flooring
Porcelain tiles in walk way at first floor. Delivered at site
Porcelain tiles rectification in main entrance hall. Delivered at site
Porcelain skirting. Delivered at site
Remaining ceramic wall tiles around door frames. Pending with engineer Ameen Eng. Ameen
Marble threshold. P.O issued under production ,(waiting Advance payment) [Link] Finance issue
Granite for main entrance & ramps, store room at roof floor. quantities review by eng. Ajentha Eng. Ajentha
Raised floor (13 m2). P.O issued, waiting advanced payment. [Link] Finance issue
Upstand of concrete stair. site work
Ceiling tiles
1- Installation of ceiling tiles after mep (phase 5). revised materials code c [Link]
DRAFT LETTER TO V3 IS READY
WAITING FOR ENGR HANY
Furniture
1- Kitchen cabinet. commercial evaluation under approval [Link]
PO UNDER PROCESS
2- Stainless steel laboratories cabinets. materials will be sent to consultant 21 /8/2022 then P.o issue [Link] MATERIAL TO RE SUBMIT THE
SAMPLE WITH CONSULTANT
COMMENTS
3- Installation of sinks & toilets. kinatecs [Link]
KINATICS NOT WORKING DUE
4- Mirrors in toilets. kinatecs [Link] TO PAYMENT ISSUE
5- Granite counter top for toilets. commercial evaluation under process [Link] WAITING FOR THE BUDGET
WAITING FOR THE
6- Signage in toilets & ( evaluation for offices signboards) . materials submittal code c [Link], QUOTATION
Aluminum works
1- External sunshades & entrance pergola. NAFCO P.O issued, waiting for advanced payment. [Link] Finance issue
2- Rectifying of plaster around windows. in progress to be finalized in 20 9 2022 Eng Hefnawy IN PROGRESS
3- Installation of aluminum doors. delivered to site ( bafco to submit delivery note) DONE
delivered to site, nafco to installed ready items,(only 2windows IN PROGRESS
4- remaining fire rated windows (pending due to invap). on phase 5)
5- Removing protection tap & installation of silicon for cladding. not start (nafco to start for approved RFI area) IN PROGRESS
Metal& wooden doors
remaining metal doors & frames of external doors ( 7 doors). wiating for delivery from alkuhaimi.
Installation of wooden door leafs. on hold (phase 5)
Grout for metal frames. in progress Eng Hefnawy. IN PROGRESS
Installation of doors hardware set. delivered to site (remining for external doors to review po) Eng Hefnawy.
Installation of main gate of reactor hall ( 4 x 4)m. materialssubmittal & shop drawing to be submitted next week Eng Hefnawy.
Gypsum walls
1- Gypsum wall of room (ventilation services 2) 35 m2& (2metal doors
inside) phase 5 .
Water proofing
WAITING FOR THE
remaining roof layers at roof floor level +12.73 m. waiting for po amedment issued. Eng. Kaleem CONFIRMATION FROM SITE
TEAM
Steel works & handrails
MATERIAL TO RE SUBMIT THE
SAMPLE WITH CONSULTANT
1- Handrail of walk way at first floor. (ALSHARQ) (material submittato be issued) Eng. Kaleem COMMENTS
2- Handrail of concrete stair
3- Handrail in reactor hall first floor.
waiting for final decesion for alshahine remaining work
4- Handrail of roof parapet level (+8.05 & level +12.73) .
5- Rectifying installed steel stairs & handrails defects.
6- Metallic covers (Alshahine) waiting for delivery
WAITING FOR THE QTY AND
SIZE FROM ENGR HEFNAWAY
7- Metallic ladder for vo06. material approved P.O to be issued. Eng. Kaleem
8- Crane for (Vo06) technical submittal in progress with invap Eng. Niazi Done
9- Replacing rusted corrugated sheet, & other corrugated sheet. briliant star ( eng hassan) advanced payment issued , eng hassan
will replay on sundat 21 8 2022
briliant star ( eng hassan) advanced payment issued , eng hassan
will replay on sundat 21 8 2022
10- Installation of sandwich panel (phase 3).
External rooms.
1- Steel doors & frames. security room approved , other roomspending with consultant. Eng Hefnawy.
2- Aluminum widows for security room. shop drawings to be resubmitted (pending with nafco) Eng Hefnawy.
Approved in submital RSL-
39-A7-DA-MP-0007
3- External & internal painting ( mockup for ext- painting). Eng Asad to prepare m.s to be submitted to consultant. Eng Asad
4- Granite for security room entrance quantities pending with Eng AJENTHA. Eng AJENTH
5- Epoxy floors painting. ZIDCONE ( Eng Ameen
6- Porcelain tiles for security room. Materials delivered to site ( to be rechceck ) Eng Ameen
7- Ceramic walls & floor for security room. p.o to be checked Eng Ameen
Waiting for Engr HANY for
8- Louver in generator room. no sub con asssigned. Eng Niazi budgt
9- metal covers (generator, elec & pump room). no sub con asssigned. Eng Niazi
10- Pvc coated steps for water tank. delivered. Eng Kaleem.
External site works
1- Site grading (back filling & excavation). in progress Eng Ameen IN PROGRESS
2- Casting ramps (for all entrances). after site grading Eng Ameen
3- Base concrete beam 20*40 cm for main building. start 1/9/2022 Eng Ameen
4- Hardscape including curbstone, interlock tiles, concrete tiles 50*50,
asphalt & gravel. mockup sample to be ready by next week (25/8/2022) Eng Ameen
CALRIFICATION REQUIRED
FROM ENGR NIAZI FOR GATER
5- Gate barrier & road blocker. , prequali. approved , materiasl to be submitted Eng Kaleem. BARRIER
6- Chain link fence foundation & installation. in progress
7- Rectifying sliding gates (defects & remaining motor). commercial evaluation to be approved. Eng Kaleem. PO UNDER PROCESS
8- Planting. shop drawings to be submitted. Eng niazi.