100% found this document useful (1 vote)
360 views4 pages

BOM Is Not Exploding in P.O.

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
360 views4 pages

BOM Is Not Exploding in P.O.

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

2/3/23, 11:07 BOM Is Not Exploding In P.O.

| SAP Community

Community Topics Groups Answers Blogs Events Programs Resources What's New Explore SAP

Ask a Question Write a Blog Post Login

Search Questions and Answers

Former Member
02 Jan 2009 a 12: 52

BOM Is Not Exploding In P.O.


1210 Views
0
While creating subcontract order, BOM is not exploding in P.O even though we are maintaining BOM for end product. How to solve this problem?

Follow
Add a Comment | Alert Moderator

RSS Feed

Assigned Tags

MM (Materials Management)

Similar Questions 
subcontracting p.o & BOM explosion explode BOm in PO
Former Member Oct 16, 2008 Former Member Sep 05, 2007

https://answers.sap.com/questions/5296021/bom-is-not-exploding-in-po.html 1/4
2/3/23, 11:07 BOM Is Not Exploding In P.O. | SAP Community

1 Answer

Ordenar por Votos | Creado el | Oldest

Best Answer

Former Member
Jan 02, 2009 at 12:53 PM
2
Please check the following things :

1. In Material master MRP4 view - Field "Individual/Coll" should have value "2" or "Blank" & In BOM (Transaction code CS03) item detail section - Field "Explosion Type"
should have value "LB" ("Individual/Coll" should have value "2" or "Blank") .

2. PIR should have PIR Info category "3" , i.e., Subcontracting PIR must available for header material which we receive back from subcontractor.

3. Special Procurement Key must be "30" in material master MRP2 View.

4. Purchasing Item Category must be "L" and production BOM must be maintained, if you want to explode BOM in PO.

5. Please check BOM valid period is effective from in Tcode cs03

6. Please check your PO date against the valid date of the BOM valid period.

Add a Comment | Alert Moderator | Share

 1 comment

Former Member Jan 05, 2009 at 10:37 AM

Check the date when u created BOM it should be lesser than the date when ur creating PO.

This may help you

Mahesh M J

Like 0 | Share | Alert Moderator

https://answers.sap.com/questions/5296021/bom-is-not-exploding-in-po.html 2/4
2/3/23, 11:07 BOM Is Not Exploding In P.O. | SAP Community

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please
leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful
resources. Also, please make sure that your answer complies with our Rules of Engagement.

Rules of Engagement 

Know someone who can answer? Share a link to this question.

You must be Logged in to submit an answer.

Please provide a distinct answer and use the comment option for clarifying purposes.

10 characters required.

Submit your Answer

Find us on

https://answers.sap.com/questions/5296021/bom-is-not-exploding-in-po.html 3/4
2/3/23, 11:07 BOM Is Not Exploding In P.O. | SAP Community

Privacy Terms of Use

Legal Disclosure Copyright

Trademark Preferencias sobre cookies

Newsletter Support

https://answers.sap.com/questions/5296021/bom-is-not-exploding-in-po.html 4/4

You might also like