Satr A 2001

A pressure test was conducted on an 8-inch pipeline at the Dammam Crude & Gas Development Project. The test involved pressurizing the line to 937.5 psi for 4 hours with no observed leaks. Instrumentation used included several pressure gauges calibrated in June 2023 and a relief valve set to open at 984.5 psi. The test was witnessed and records were reviewed and approved, verifying the line passed the hydrotest.

Uploaded by

Naveed Shah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
333 views7 pages

Satr A 2001

A pressure test was conducted on an 8-inch pipeline at the Dammam Crude & Gas Development Project. The test involved pressurizing the line to 937.5 psi for 4 hours with no observed leaks. Instrumentation used included several pressure gauges calibrated in June 2023 and a relief valve set to open at 984.5 psi. The test was witnessed and records were reviewed and approved, verifying the line passed the hydrotest.

Uploaded by

Naveed Shah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

SAUDI ARAMCO ID/PIEU-28-Feb-2019 - Rev. 2019.02.00 (Standards Cutoff - Feb 28,2019) Rev.2019.02.

00 28-Feb-19

SAUDI ARAMCO TEST REPORT SATR NUMBER DATE APPROVED QR NUMBER

Pressure Test Report SATR-A-2001 30-May-19 MECH-RTR-RFI-0076


PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

Dammam Crude & Gas Development Project 10-00436 SICIM Saudi Arabia
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION TEST SYSTEM No./Test Pack No. PLANT NO.
SA006-00-5550-SC-RTR-HP- 336
001
DRAWING NUMBER (P&ID/ISO) / REV. No. PRESSURE TEST DIAGRAM NATURE OF TEST WORK PERMIT REQD?
ATTACHED ATTACHED HYDROTEST YES
SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME LOCATION OF TEST (PLANT NAME & NO.)
10-JUNE-2023 @ 3:00pm SA006- DS-B
SAUDI ARAMCO TIP (SATIP) NUMBER SATIP Activity No. TEST IN ACCORDANCE WITH: a) Procedure No. b) Supporting SAIC No.
SATIP-L-100-01 3.15 SAIC-L-2151
System Description: 8"-W-0200-99FE0W Test Details (Type): Hydrotest
Test/Service Fluid: Water MAOP: 750PSI Sys Mat'l Type: RTR Limiting Factor: Pipe
Flushing Cleaning Method Used: Piging Accepted: Rejected:
Lay-Up Method: None: Ambient: Wet: Dry: Other :

Pressure Gages/Recorder Temp Gage/Recorder Relief Valve


Test Instruments
PG- PG- PG- PG- PR- TG- TR- RV #
Serial No/Tag No. E1501021125 1502276148 1502276122 E1710401187 086587-62

Make A.M GAUGE A.M GAUGE A.M GAUGE A.M GAUGE Taylor

Range 0 To 1500 PSI 0 To 1440 PSI 0 To 1440 PSI 0 To 15 PSI 601-1200 PSI
MTE-CC- MTE-CC- MTE-CC- MTE-CC- MTE-CC-J80024196-
Certificate No. J80024196-5 J80024196-1 J80024196-2 J80024196-3 10
Date Calibrated June-07-2023 June-07-2023 June-07-2023 June-07-2023 June-07-2023

Set Pressure 984.5 PSI

Re-Calibration Due
July-06-2023 July-06-2023 July-06-2023 July-06-2023 June-21-2023
Date
ITEM Description of Test Parameters
Actual Pass Fail Remarks
No. (Complete Applicable Data Entry Prior to Test)
Test Medium Type/Quality (Indicate method of treatment if req'd in Clean
1 Remarks, i.e., Fluid type, ph, SRB count, O2 Scavenger, etc).
Water
2 SystemTemperature at test: Ambient
Test Pressure: Service Test/Others:________
3 Strength Test: ___________ Valve Body: ______________ 937.5 PSI
Tightness Test: ___________ Valve Seat: ______________

4 Preliminary Test Conducted at __________Psig 468.75 PSI


Area of interest (Indicate flange joints, weld joints, threaded, socket,
5
body)
Threaded

6 Method of leak detection (direct visual/remote) Visual


Test Duration : a. 30 minutes min for Plant Piping
7 b. 2 hrs. Pipeline strength test/ ______ Tightness Test 4hr
c. Others_____________
REPAIRS DURING TEST:

TEST RESULTS: Test Accepted. No leak or loss in pressure observed. State reasons in
Rejected Remarks Section.
AFFIX ANY TEST TAPE TO THIS REPORT (TEST EVIDENCE)

REMARKS:

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and
Name, Initials and Date:
Sayyed Waseem Date: Mr. Ibrahim Mobiyadh

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and
Name, Initials and Date:
Syed Sikandar Date: Mr. Muhammad Shakeel

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name,
Name, Sign and Date: Organization,
Muhammad Ishaque Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU-28-Feb-2019 - Rev. 2019.02.00 (Standards Cutoff - Feb 28,2019)

Saudi Aramco: Company General Use


Rev.2019.02.00

###

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU-28-Feb-2019 - Rev. 2019.02.00 (Standards Cutoff - Feb 28,2019)

Saudi Aramco: Company General Use


Rev.2019.02.00

###

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use