Presume Summary

The document provides a bill of materials for a proposed 4-storey boarding house construction project. It includes estimated costs for concrete and masonry works (PHP 1,135,000), rough hardware (PHP 993,700), carpentry and lumber works (PHP 1,106,000), and finishing hardware (PHP 527,500) for a total estimated building cost of PHP 9,801,200. The bill of materials lists in detail the quantities and costs of materials needed for each category.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
75 views4 pages

Presume Summary

The document provides a bill of materials for a proposed 4-storey boarding house construction project. It includes estimated costs for concrete and masonry works (PHP 1,135,000), rough hardware (PHP 993,700), carpentry and lumber works (PHP 1,106,000), and finishing hardware (PHP 527,500) for a total estimated building cost of PHP 9,801,200. The bill of materials lists in detail the quantities and costs of materials needed for each category.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

PRESUME SUMMARY

A. CONCRETE AND MASONRY WORK Php 1,135,000.00


B. ROUGH HARDWARES 993,700.00
C. CARPENTRY AND LUMBER WORKS 1,106,000.00
D. FINISHING HARDWARES (L) 527,500.00

Php 3,761,200.00

E. PLUMBING WORKS (L) 300,000.00


F. ELECTRICAL WORKS (L) 360.000.00
G. ROOFING AND TINSMITH WORKS (L) 350,000.00
H. GLASS DOORS AND WINDOWS (L) 380,000.00
I. CONCRETE AND FINISHING WORKS (L) 350,000.00

Php 5,581,200.00

J. STEEL WORKS (L) 300,000.00


K. CONTENGENCIES (15%) 650,000.00
L. PAINTING WORKS (L) 320,000.00

Php 6,901,200.00

DIRECT LABOR 2,200,000.00

PLANS AND SUPERVISION 700,000.00

___________________________

TOTAL ESTIMATED BUILDING COST Php


9,801,200.00

PREPARED BY:

_________________________
ARCHITECT

REG. No.

DATE

PTR. No.

DATE

TIN No .

APPROVED BY

_________________________
OWNER

PROJECT : PROPOSED 4 – STOREY BOARDING HOUSE WITH COVERED ROOFDECK


LOCATION : F. LLAMAS ST. PUNTA PRINCESA CEBU CITY
OWNER : JELBERT WONG
ARCHITECT : JUDITO TARIMAN
SUBJECT : BILL OF MATERIALS

A. CONCRETE AND MASONRY:


150 CU.M SAND Php 180,000.00
100 CU.M FIND SAND 150,000.00
50 CU.M (G1) GRAVEL 70,000.00
150 CU.M ¾” GRAVEL 210,000.00
15,000 PCS 4” THK CHB 165,000.00
1,800 BAGS CEMENT 360,000.00

Php
1,135,000.00
B. ROUGH HARDWARES:

600 LGTH 20MM DIA. X 6.00M DEFORM BARS Php 228,000.00


500 LGTH 16MM DIA. X 6.00M DEFORM BARS 160,000.00
500 LGTH 12MM DIA. X 6.00M DEFORM BARS 140,000.00
2,500 LGTH 10MM DIA. X 6.00M DEFORM BARS 400,000.00
250 LGTH 9MM DIA. X 6.00M DEFORM BARS 20,000.00
10 ROLLS NO.16 G.I TIE WIRE 13,000.00
5 BOX 4” COMMON NAIL 5,000.00
4 BOX 2 ½” COMMON NAIL 3,000.00
10 SQ M 1/8” SCREEN WIRE 2,000.00
20 KLS 1 ½” COMMON NAIL 1,600.00
5 DOZ HACKSAW BLADE 3,000.00
36 LGTH 3” DIA PVC PIPE (SERIES 1000) 12,600.00
100 PCS 3” X90 DEG.PVS PIPE ELBOW 3,200.00
30 PCS CONSTRUCTION PAIL 1,800.00

Php 993,700.00

C. CARPENTRY AND LUMBER WORKS


FORMS AND SCAFFOLDING
2250 PCS 2X2X12’ ROUGH COCO Php 168,750.00
2250 PCS 2X3X12’ ROUGH COCO 213,750.00
375 SHTS ¼”X4’X8’ PLY WOOD 103,125.00

CEILING JOIST, CEILING BOARDS AND FASCIA


2325 LGTH DOUBLE FURRING Php 162,750.00
1200 LGTH WALL ANGLE 36,000.00
427.50 SHTS 3.5MM X 4X8 FICEM BOARDS 128,250.00
75 SHTS 3/4” MARINE PLYWOOD 67,500.00
7.50 BOX ½” PAN HEAD SCREW 7,500.00
7.50 BOX ¾” HARDIFLEX SCREW 7,500.00
7.50 BOX ¼” X4’X8’ BLIND RIVETS 7,500.00

DOOR AND WINDOW JAMBS

87 PCS 2X2X14’ GOOD LUMBER Php 16,800.00

112.50 PCS 2X6X8’ GOOD LUMBER 56,250.00

45 PCS 2X6X10’ GOOD LUMBER 27,000.00

FLUSH DOORS FRAMES, SHELVES, AND CEILING VENTS

75 SHTS ¼”X4’X8’ PLYWOOD Php 22,500.00

127.50 PCS 2”X2”X12’ GOOD LUMBER 31,875.00

75 SHTS ¼”X4X8’ MARINE PLY WOOD 22,500.00


15 SHTS ½”X4’X8’ ORDINARY PLYWOOD 7,800.00

12 SHTS ¾”X4’X8’ ORDINARY PLY WOOD 11,760.00

45 PCS 1”X1”X10’ GOOD LUMBER 7,500.00

Php
1,106,610.00