Peterhead - 11.097 Well Completion Concept Select Report
Peterhead - 11.097 Well Completion Concept Select Report
KEYWORDS
Goldeneye, CO2, Completion, Hydrates, Filtration, gravel pack, injectivity, pressure and temperature
calculation, minimum stress, lift performance, Joule-Thomson, single tubing, well elements, cement,
corrosion, materials.
IMPORTANT NOTICE
The information set out herein (the “Information”) has been prepared by Shell U.K. Limited and its sub-
contractors (the “Consortium”) solely for the Department of Energy & Climate Change in connection with the
Competition. The Information does not amount to advice on CCS technology or any CCS engineering,
commercial, financial, regulatory, legal or other solutions on which any reliance should be placed. Accordingly,
no member of the Consortium makes (and the UK Government does not make) any representation, warranty
or undertaking, express or implied, as to the accuracy, adequacy or completeness of any of the Information
and no reliance may be placed on the Information. Insofar as permitted by law, no member of the Consortium
or any company in the same group as any member of the Consortium or their respective officers, employees or
agents accepts (and the UK Government does not accept) any responsibility or liability of any kind, whether
for negligence or any other reason, for any damage or loss arising from any use of or any reliance placed on the
Information or any subsequent communication of the Information. Each person to whom the Information is
made available must make their own independent assessment of the Information after making such
investigation and taking professional technical, engineering, commercial, regulatory, financial, legal or other
advice, as they deem necessary.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 i
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT FRONT MATTER
Table of Contents
Executive Summary 1
1 Introduction 3
2 Completion requirements 6
2.1 Introduction 6
2.2 General completion considerations 6
Hydraulic Requirements 6
Well Integrity 7
Well Modifications 7
Operational aspects 7
Well Monitoring 7
Life Cycle Cost 7
2.3 Peterhead – Goldeneye CCS information 7
2.3.1 General information 7
2.3.2 Goldeneye field - main stratigraphy 8
2.3.3 Reservoir characteristics 10
2.3.4 Fluids characteristics 11
CO2 injection rates and condition 12
2.3.5 Existing wells summary 13
3 Injectivity 17
3.1 Initial injectivity 17
3.1.1 Reservoir characteristics of the Captain formation 17
3.1.2 Hydrocarbon Productivity Phase 19
3.1.3 Correction of hydrocarbon productivity for CO2 injection due to PVT changes 21
3.1.4 Relative permeability 26
3.2 Long Term Injectivity Management 27
3.2.1 Gravel pack and Formation plugging - Filtration 27
3.2.2 Discussion 27
3.2.3 Disbondment of pipeline coating (applicable to existing offshore pipeline) 28
3.2.4 Hydrates 29
3.2.5 Joule Thomson cooling upon CO2 injection into the reservoir 37
3.2.6 Halite Precipitation 37
3.2.7 Near Wellbore Asphaltene Deposition 39
3.2.8 Near Wellbore Wax deposition 39
3.3 Matrix or Fracturing conditions 39
3.4 Injection under fracturing conditions 40
3.4.1 Software 40
3.4.2 Model Input 41
3.4.3 Stress Regime 42
3.4.4 Injection conditions (matrix or fracturing) – The numbers 47
3.4.5 Summary of cases investigated for propagating fracture under injection 48
3.4.6 PWRI. Base case pressure and minimum stress 49
3.4.7 Fracture Geometry. Base Case Simulation results 51
3.4.8 Fracture Geometry. Injection rate sensitivity 52
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 ii
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT FRONT MATTER
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 iii
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT FRONT MATTER
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 iv
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT FRONT MATTER
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 v
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT FRONT MATTER
List of figures
Figure 2-1: Main stratigraphy for Goldeneye area, average depths of formation tops 9
Figure 2-2: GYA01 well schematic including formations (similar completion in
GYA05) [1ft = 0.3048m, 1'' = 25.4mm] 15
Figure 2-3: GYA03 Completion including completions (similar completion in
GYA02S1 and GYA04) [1ft = 0.3048m, 1'' = 25.4mm] 16
Figure 3-1: Subdivision of the Captain reservoir, Goldeneye area. Log data on left with
core faces log description on right. Note unit A is homogenous in parts
and highly variable in thickness (shown partial log). 17
Figure 3-2: Permeability histogram from available cores in the Captain D formation. 18
Figure 3-3: Goldeneye hydrocarbon production. Clean-Up performance. 19
Figure 3-4: GYA01. Productivity history 20
Figure 3-5: Productivity per well during long term production phase 20
Figure 3-6: Productivity. Jones representation. 21
Figure 3-7: CO2 downhole (in-situ) injection rate for given surface rate 22
Figure 3-8: Comparison of CO2 and hydrocarbon downhole rates 23
Figure 3-9: Comparison of Viscosity between CO2 and hydrocarbon gas. 23
Figure 3-10: CO2 injectivity in comparison to hydrocarbon productivity (GYA01,
GYA03 and GYA04) 25
Figure 3-11: CO2 injectivity in comparison to hydrocarbon productivity (GYA02S1
and GYA05) 26
Figure 3-12: Hydrate equilibrium curve for CO2 and Goldeneye hydrocarbon and
their mixtures in the presence of free water. 30
Figure 3-13: Hydrate equilibrium curve for CO2 at different water concentrations 30
Figure 3-14: Hydrate equilibrium curve and well conditions under normal CO2 injection
conditions 31
Figure 3-15: Hydrate equilibrium curve and well conditions during close-in operation 32
Figure 3-16: Hydrate equilibrium curve and well conditions during closed-in
conditions 33
Figure 3-17: Hydrate equilibrium curve and well conditions during start-up operations 34
Figure 3-18: Hydrate equilibrium curve and well conditions during first start of
injection (well filled with water) 35
Figure 3-19: Fracture propagation mechanism in PWRI 40
Figure 3-20: Original minimum stress conditions at isothermal conditions 44
Figure 3-21: Uncertainty in minimum stress in the Captain formation and injection
conditions at the start of injection. [1 psia = 0.06895bara] 48
Figure 3-22: Formation pressure in the Goldeneye area (pressure in the Captain
formation as an average pressure over the life of the project) 50
Figure 3-23: Isothermal minimum stress in the Goldeneye area for injection (reference
case Captain minimum stress) 50
Figure 3-24: Base case. Fracture depth to and depth bottom with time 51
Figure 3-25: Base case. Fracture length profile with time 51
Figure 3-26: Base case. Fracture length with time 52
Figure 3-27: Rate sensitivity. Fracture depth to and depth bottom with time 53
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 vi
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT FRONT MATTER
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 vii
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT FRONT MATTER
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 viii
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT FRONT MATTER
List of tables
Table 2-1: Existing hydrocarbon producer wells in Goldeneye platform 6
Table 2-2: Completion requirement. General information 7
Table 2-3: Completion requirement. Reservoir characteristics 10
Table 2-4: Completion requirement. Fluids characteristics 11
Table 2-5: Completion requirement. CO2 injection rates and condition 12
Table 2-6: Completion requirement. Existing wells summary 13
Table 2-7: Well deviation of the existing wells 13
Table 2-8: Suspension plugs – Setting depths [1ft = 0.3048m] 14
Table 3-1: Joule Thomson expansion calculation near wellbore for different injection
conditions. 37
Table 3-2: Base assumptions for the fracture modelling [1ft = 0.3048m, 1psia =
0.06895bara] 41
Table 3-3: Minimum horizontal stress at the Rodby formation [1psia/ft =
226.2mbara/m, 1 psia = 0.06895bara] 43
Table 3-4: Original minimum stress at the Captain formation [1psia/ft =
226.2mbara/m, 1 psia = 0.06895bara] 44
Table 3-5: Change of minimum stress in the Captain formation due to depletion
(during the hydrocarbon production phase) [1 psia = 0.06895bara] 45
Table 3-6: Change of minimum stress in the Captain formation due to pressure
increase (during the pre-CO2 injection and CO2 injection periods) [1 psia =
0.06895bara] 46
Table 3-7: Change of minimum stress in the Captain formation due to thermal effects 47
Table 3-8: Summary of change in minimum stress in the Captain formation - reference
case [1 psia = 0.06895bara] 47
Table 3-9: Considered PWRI cases for simulation 49
Table 3-10: Estimated fracture length for different reservoir sensitivities [1ft =
0.3048bara] 55
Table 3-11: Injectivity management. Risk reduction 59
Table 3-12: Injectivity test. Risk/Uncertainty comparison pre and post-test. 60
Table 4-1: Arrival CO2 temperature to the platform for different cases and subsequent
expansion to wellhead conditions 70
Table 4-2: Steel Roughness. 74
Table 4-3: Maximum injection due to velocity in tubing [1'' = 25.4mm] 80
Table 4-4: Results of transient calculations – design case (base oil in annulus) 85
Table 5-1. Low temperature threshold of current completion equipment 88
Table 5-2: Low temperature threshold after workover during injection 90
Table 5-3: Bottomhole pressure and downhole rate relation for Goldeneye wells 100
Table 6-1: Single tapered tubing. Advantages and disadvantages [1'' = 25.4mm] 105
Table 6-2: Insert string. Advantages and disadvantages [1'' = 25.4mm] 106
Table 6-3: Dual completion. Advantages and disadvantages [1'' = 25.4mm] 107
Table 6-4: Concentric completion. Advantages and disadvantages [1'' = 25.4mm] 108
Table 6-5: Downhole choke. Advantages and disadvantages [1'' = 25.4mm] 109
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 ix
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT FRONT MATTER
Table A0-1: Workover with the current friction concept and drilling new wells.
Advantages and disadvantages. 132
Table 11-1: Unit Conversion Table 138
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 x
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Executive Summary
Executive Summary
This report, Well Completion Concept Select Report, includes the rationale for selecting the preferred
completion from the range of options available considering the lifecycle of a well in the Peterhead
Goldeneye Carbon Capture and Storage (CCS) project.
The report considers the inflow performance (injectivity and matrix/fracturing conditions), the
vertical flow characteristics (pressure and temperature calculations) in relation to the phase behaviour
of the Carbon Dioxide (CO2).
Different completion concepts are analysed for the Goldeneye conditions and lifecycle
(installation/injection/abandonment) and a recommendation is done for the completion type to
mature in the define phase of the project (FEED). The Completion Concept for the upper
completion presented in this report is similar to the proposed for the Longannet project. Changes
related to flow rates, pressures and CO2 composition were included in the analysis.
The current upper completion was designed for hydrocarbon production. Analyses have shown that
injecting dense phase CO2 into a depleted reservoir has the risk of producing low temperatures in the
injection tubing. These low temperatures cause problems with the materials and fluids in the wells.
In order to avoid this, small injection tubing is being installed. This will introduce additional friction
and will maintain the injection column in dense phase from the well head to the sand face.
Limitations of the different well components were investigated for the expected well conditions
under CO2 injection. The Christmas tree and the tubing hanger will be replaced in the workover with
units having a lower minimum temperature. All completion equipment (i.e. attached to the tubing
string) will have 13Cr or s13Cr equivalent (or superior) metallurgy and will have working pressures in
excess of the expected final well pressures.
Based on the hydrocarbon production and the reservoir characteristics it is expected to have a good
initial injectivity in the Captain D. Filters will be installed on the platform to avoid particulates and
hence reduction of injectivity by plugging/erosion of the lower completion and formation. Batch
hydrate inhibitor is planned before well start-ups during the initial stage of injection to avoid hydrate
formation in the well. It is expected that matrix type of injection will occur at low reservoir pressures
changing to fracturing conditions with increase in reservoir, being the main uncertainty the thermal
effect on the rock.
The lower completion installed in the Goldeneye wells (screen and gravel pack) is considered fit for
purpose for CO2 injection. Filtration of the CO2 stream will reduce the risk of plugging and erosion
of the lower completion.
The installation of small bore tubing in the wells limits the operating envelope of each well. In order
to accommodate the range of injection rates at the different reservoir pressures during the injection
life, each well will be completed with a different tubing size/configuration tailored to a specific rate
range. The wells will then have overlapping operating envelopes and any rates specified in the
integrated basis-for-design will then be achievable through the choice of a specific combination of
wells.
In the completions, there will be permanent temperature and pressure monitoring gauges. There will
also be a distributed temperature sensing system - a fibre optic system providing temperature data at
specified intervals in the well, and distributed acoustic sending (DAS).
Three wells are planned to be converted as injector wells. GYA03 is planned to be a monitoring well.
The range of injection from the minimum to the maximum of the capture plant at the predicted
reservoir pressure evolution can theoretically be achieved with only two wells. In case of unforeseen
problems in a particular injector well, it is proposed to complete an additional or back-up well as a
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 1
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Executive Summary
CO2 injector to the number of wells required to cover the injection range. As such, at least three wells
are required to be completed as injectors. The well(s) not converted for CO2 injection will also need
to be considered for the Peterhead project. Options included are to complete as an injector/monitor
or to abandon the well.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 2
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Introduction
1 Introduction
General injection requirements
The Goldeneye platform features five suspended gas production wells, with an additional three spare
slots for potential future wells. Suspension plugs were installed in the existing producing wells after
the Cessation of Production (CoP) declaration.
The injector wells should be able to inject 10 million tonnes with a maximum rate of 138.3 tonnes/h.
Turn down of the surface facilities are estimated at 89.9 tonnes/h (65% of the design rate). The CO2
to be injected is almost pure (+99.9%) and it is arriving to the platform dehydrated (~20ppm weight
of H20) at temperatures similar to the seabed temperature and pressures above the critical point.
The reservoir will be depleted at the start of injection. The reservoir pressure will increase with CO2
injection; at the end the 10 million tonnes of injection, the reservoir pressure will be close to
hydrostatic conditions.
There is an aquifer attached to the formation. Completion design should consider the presence of
water and hydrocarbons (not only CO2). Water is present in currently present at the formation level.
The CO2 in presence of water is highly corrosive in carbon steel. Hydrocarbons are also present in
the current wells.
Injectivity
The initial CO2 injectivity is expected to be excellent (~200-400 psia [~13.8-27.6bara] above the
reservoir pressure) for the expected injection rates per well required for the project. This high
injectivity is based on the rock properties of the Captain D (storage formation) and the productivity
of the hydrocarbon production phase.
The expected CO2 injectivity under matrix conditions can be estimated from the hydrocarbon
productivity by considering the differences in (Pressure-Volume-Temperature) PVT between the
hydrocarbon and the CO2. The impact of the PVT correction is small in the injectivity as the high
viscosity of the CO2 is compensated by the low expansion factor of the CO2 with respect to the
hydrocarbon gas.
The risk of not being able to inject the desired amount of CO2 can be reduced by some proactive
measures such as filtration of the CO2 stream (5 micron) and hydrate inhibition (bath displacement of
methanol between the Xmas tree and the Sub Surface Safety Valve (SSSV) before opening the well).
There are other mechanisms, which are considered of very low risk to CO2 injectivity such as: Joule
Thomson cooling, Halite precipitation, and organic deposits like wax and asphaltenes.
Stress regime calculations in combination with the expected injection pressures indicate that the initial
phase of injection (for low reservoir pressure) will be under matrix injection. However, the late phase
of injection (as the reservoir pressure increases) is uncertain in terms of injection condition (matrix or
fracturing conditions). The main uncertainty in the calculations is the reduction in minimum stress
caused by the temperature contrast between the reservoir temperature and the bottom hole injection
temperature which effectively reduce the minimum stress of the formation.
Injection under fracturing conditions will propagate fractures in the Captain formation. These
fractures in the reservoir are not detrimental to the containment capacity of the primary reservoir seal
(Rodby/Hidra formations).
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 3
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Introduction
Analyses have shown that injecting cold liquid CO2 into a depleted reservoir has the risk of producing
low temperatures in the injection tubing due to the Joule-Thomson (JT) expansion.
CO2 expansion properties can be managed by a small diameter tubing resulting in temperatures
compatible with the materials in the existing wells. This will introduce enough friction and will
maintain the injection column in dense phase from the wellhead to the sand face. With appropriate
size in the tubing the wellhead pressure can be increased to the extent that it lies above the saturation
line. As such, the minimum wellhead pressure in the well is determined by the requirement of
operating the well in single phase. This will create a minimum rate limitation in each well.
The maximum CO2 pressure available (~120bara) will dictate the maximum injection rate per well for
a given tubing size.
Tubing sizes can be designed to accommodate variable flow rates from the platform by using
multiple wells.
Low temperatures for a short period of time can be encountered during transient operations (start up
and shut down). A procedure for testing the SSSV needs to be validated in the next phase of the
project.
For the Carbon Capture Plant (CCP) rates in the project, the expected bottomhole temperature is
estimated between 23°C to 35 °C.
Loss of control in a CO2 well can generate very low temperatures in the top of the well. In a CO2
well; with the rapid expansion of the CO2, correspondingly rapid cooling will occur. The top of the
well (wellhead, Xmas tree and tubing above the SSSV) will require special considerations due to the
potential low temperatures.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 4
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Introduction
Number of wells
The number of required injector wells depends mainly on the injection estimates (reservoir pressure
and injectivity), capture plant rates, CO2 management, monitoring requirements and life cycle risk
management.
The well(s) not converted for CO2 injection will also need to be considered for the Peterhead project.
Options included are to complete as an injector/monitor or to abandon the well.
The installation of small bore tubing in the wells limits the operating envelope of each well. In order
to accommodate the range of injection rates at the different reservoir pressures during the injection
life, each well will be completed with a different tubing size/configuration tailored to a specific rate
range. The wells will then have overlapping operating envelopes and any rates specified in the
integrated consortium basis-for-design will then be achievable through the choice of a specific
combination of wells.
The current plan is to recomplete the five existing production wells by means of a workover –
replacing upper completion. Whilst purely for CO2 injection, based on the latest scheduled volumes
of captured CO2 from the Peterhead power plant, there is a requirement for three injection wells
only. There is an additional requirement for one monitoring well (GYA03). There is a choice whether
the fifth well should be recompeted for injection or abandoned..
Drilling of new wells
New wells are not currently considered for the project. Drilling new wells to avoid the limitations of
eliminating the minimum rate dictated by the CO2 phase behavior is not justified.
Drilling new wells might only be justified in case of leak cases where the wellhead system needs to be
replaced based on consequences arising from a failure case. Experience in CO2 EOR and other CCS
projects under leak scenario indicated not to be an issue. Detailed thermal simulations of the
wellhead/Xmas tree system will be done in the FEED phase to evaluate the suitability of the system
under Goldeneye conditions.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 5
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Completion requirements
As a consequence, in the case of drilling new wells, they should be able to take low temperatures
(sub-zero) in the top part of the well (~2600ft [792.5m] under injection conditions and even lower
temperatures for leak scenarios in the very top of the well).
2 Completion requirements
2.1 Introduction
The Goldeneye platform features five suspended gas production wells, with an additional three spare
slots for potential future wells.
The five existing wells in the Goldeneye platform initially drilled and completed to produce
hydrocarbons form the Captain sands, Table 2-1 . The abbreviated well names are used in this
document. Well DTI 14/29a-A4Z (GYA02S1) is the sidetrack of DTI 14/29a-A4 (GYA02).
Table 2-1: Existing hydrocarbon producer wells in Goldeneye platform
The field was granted CoP (Cessation of Production) from DECC (Department of Energy and
Climate Change) in 2011. There are therefore no plans to produce the wells in the future.
These wells can be used for CO2 injectors or as monitor wells. Suspension plugs were installed in the
existing producing wells after the CoP declaration.
Hydraulic Requirements
• Management of the CO2 properties (Joule Thomson, JT expansion) and the resultant
temperatures in the existing platform wells.
• Flexible injection. The injector wells need to be able to cope with a range of CO2 arrival rates
within the limits of the capture plant and surface equipment. Facilities and their modus
operandi should be operated to have minimum impact in the wells.
• CO2 will be injected in a single phase with wellhead pressure kept above the saturation line.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 6
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Completion requirements
Well Integrity
• Avoid any leak path through the well.
• All well completion materials should be compatible with the injected fluid and expected
pressures and temperatures.
• Completion design should consider the presence of CO2, water and hydrocarbon. The
proportion will change depending on the well position and during the life of the project.
• Expected remaining well life after start of injection: minimum 15years.
Well Modifications
• A mobile jack-up rig will be required for Goldeneye platform due to the water depth.
• Minimise complexity of any well work. Uncomplicated well design.
Operational aspects
• Normally unattended platform.
• Maintain injectivity during the life cycle of the well.
• Optimise well life cycle cost..
Well Monitoring
• Able to monitor wells/reservoir. Facilitate intervention.
• In-well monitoring to be installed in the wells: Permanent Downhole Gauges (PDG) and
Distributed Temperature Sensing (DTS) (Distributed Acoustic Sensing (DAS) being
considered).
Name Goldeneye
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 7
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Completion requirements
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 8
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Completion requirements
Figure 2-1: Main stratigraphy for Goldeneye area, average depths of formation tops
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 9
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Completion requirements
Type Sandstone
Captain formation. Main formation is the Captain D
Formation ~83°C @ 8400ft [2560m] TVDss
temperature
Reduction of temperature around the injectors due to cold CO2 injection
(~20-35°C bottom hole injection temperature)
Formation Water Formation water present in the bottom of the well.
Water will be initially at the sand face. Evidence of water from downhole
pressure gauges in GYA03.
Formation water around the wellbore will reduce significantly after 6 to 9
months of continuous CO2 injection. However, water might come back to
the formation is not enough CO2 is injected in the well.
Average Reservoir ~25% porosity
(Captain D) ~790md permeability
Porosity and The Captain D is a clean sandstone with very high Net to Gross
Permeability
Captain D presented an excellent connectivity during the hydrocarbon
production phase.
Pressure Regime (The pressure regime is given as an indication for general well/completion
design selection. This will be re-calculated before any well operation and
before working over the wells).
An active aquifer supports the field. All the wells are currently shut in due
to water breakthrough and isolated with deep and shallow downhole plugs.
Original Reservoir Pressure ~ 3830psia [264bara] @ datum 8400 ft TVDss
Minimum Reservoir pressure after depletion ~ 2100psia [145bara] @ datum
Current pressure is ~2620psia [181bara] (@ end of December 2013 @
datum)
Minimum expected reservoir pressure before CO2 injection (~Year 2019):
2650psia [183bara], Pressure Gradient Range - 0.319 psia/ft [72mbara/m]
Maximum expected reservoir pressure after 10 million tonne of CO2–
(~Year 2031) 3450psia [238bara] @ 8400ft TVDSS, Pressure Gradient:
0.416psia/ft [94mbara/m]
Information is of enough quality for this analysis/report on completion
concept select.
This pressure information will be updated during FEED for the detail
design of the wells.
Different section of tubing (4½'' and 3½'' [114mm and 89mm]) to be
installed in each well will depend on this information.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 10
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Completion requirements
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 11
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Completion requirements
Total CO2 available The project requires to inject 10 million tonnes of CO2
Design Rate (capacity of the capture plant): 138.3 tonnes/h
equivalent to 63 MMscfd
Normal Operating Conditions ~ 130 tonnes/h (59 MMscfd)
Turndown Rate of surface facilities ~ 89.9 tonnes/h (65% of the
design case, 41 MMscfd)
It is estimated that the injection will take place over a period of 12
years for the 10 million tonnes (including downtime).
CO2 fluctuation For the first 5 years of the injection, project will operate with
turndown case of 75% (103.8 tonnes/h, 47 MMscfd)
For the rest of the injection years, the turndown case will be 65%.
All the surface equipment should be design to minimum
turndown of 65%.
The reference case is to operate the capture plant at based load
(i.e. continuous flow) during the first five years on injection.
Daily fluctuations between the design rate and the minimum (65%
of the design rate) might be carried out after year 5 of injection.
Frequent (daily) on and off periods of the capture plant are not
planned.
A limited packing capacity exists in the offshore pipeline operated
in dense phase CO2 (estimated to be between 2 to 4 hours of CO2
injection depending on the conditions of the pipeline).
Arrival Pressure and The CO2 will be transported to the platform in dense phase.
Temperature The maximum pressure of the offshore pipeline is 120bara. This
conditions is limited by the operating pressure of the offshore pipeline.
The CO2 will arrive cold to the platform according to the seabed
temperature with some changes of temperature in the platform
riser.
Variations in temperature exist between summer and winter.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 12
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Completion requirements
Attribute Data
On/Offshore Offshore
Well type Previously Hydrocarbon producer.
Currently closed in and suspended with deep set downhole plugs
To be converted to CO2 injection
DFE (ft) 152.5 [46.5m] (Drilling Rig)
Water depth (ft) 395 [120m]
Number of wells 5 existing, 3 slots available
Top reservoir (ft ~8300 [2530m]
TVDSS)
There are five existing wells (GYA01, GYA02S1, GYA03, GYA04, and GYA05) in Goldeneye field.
The upper and lower completion specifications of the current completion are:
• Upper Completion
SSSV 5.875'' [149mm], 7'' [178mm] tubing 6.184'' [157.1mm], 5'' [127] tubing 4.67'' [118.6mm],
PDG 4.576'' [116.23mm], Polished Bore Receptacle (PBR) 4.577'' [116.26mm], Packer 4.65''
• Lower Completion
Formation Isolation Valve (FIV) 2.94'' [74.68mm], Screens 3.548'' [90.12mm], X-over 3.515''
[89.28mm]
An intervention campaign was carried out in 2012 and suspension plugs were set in all the wells. At
the time some safety valve control line integrity issues were noted on wells GYA01 and GYA03 and
corrective measures were required to some tree valves.
In a number of wells (GYA02, GYA04 and GYA05) the lowermost suspension plug was set above
the downhole gauge thereby allowing the reservoir pressure and temperature to be monitored, Table
2-8.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 13
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Completion requirements
None of the wells are subject to any integrity issues of note (PCCS-05-PT-ZW-7180-00004 Well
Integrity Assessment Report, 2014).
The Figure 2-2 and Figure 2-3 capture the existing well construction elements with respect to the
different formations:
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 14
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Completion requirements
Figure 2-2: GYA01 well schematic including formations (similar completion in GYA05)
[1ft = 0.3048m, 1'' = 25.4mm]
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 15
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Completion requirements
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 16
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
3 Injectivity
This section is divided into initial injectivity, long term injectivity management and injection under
fracturing conditions.
Figure 3-1: Subdivision of the Captain reservoir, Goldeneye area. Log data on left with core faces
log description on right. Note unit A is homogenous in parts and highly variable in
thickness (shown partial log).
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 17
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
The Captain 'D' is the primary reservoir unit, into which all the development wells have been
completed as the primary target. The Captain 'D' unit has been cored in all of the exploration and
appraisal wells in the Goldeneye Field. It comprises medium grained massive sandstones that, with
the exception of a fining-upwards sequence at the top seen in all wells in the field, show only subtle
changes in grain size.
Average porosity of Captain 'D' reservoir is 25% and average permeability is ~790mD (
Figure 3-2). The average net to gross is 94%. The thickness of the Captain D is 75 to 225ft [22.9 to
68.6m] True Vertical Depth (TVD) with an average of 130ft [39.6m]. These are the primary
indicators that we can expect good CO2 injectivity in Goldeneye.
Figure 3-2: Permeability histogram from available cores in the Captain D formation.
All the available wells were completed in the top of the Captain D formation (60ft [18.3m] true
vertical). The 9-5/8'' [245mm] casing was set in the Rodby formation. The Captain D and E are
open to the gravel pack and screens. The Captain E characteristics are poor with average net to gross
of 61%, average net porosity of 21% and average permeability of only 150mD. Clearly the
contribution of the Captain E with respect to the Captain D is negligible.
The Captain D formation is well connected based on production and pressure information collected
during the hydrocarbon production phase.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 18
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
3800
3700
3600
BHP @ PDHG, psi
3500 GYA01
GYA02
3400 GYA03
GYA04
3300 GYA05
3200
3100
3000
0 10 20 30 40 50 60 70 80 90 100 110 120
Gas Rate, MMscfd
The high productivity was maintained during the production life of the wells. In general, low
drawdown levels have been required (150-200psia [10.3 – 13.8bara] drawdown for 60 million scf/d
[2.1 million sm3/d] production). The well productivity was stable during the production time,
demonstrating no impairment with time. This can be observed in the Figure 3-4 for GYA01 (note
that the other wells have similar performance). Similar productivity was observed for the five
producing wells.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 19
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
500
450
400
350
Drawdown, psi
300
250
200
150
100
50
0
- 20 40 60 80 100
Gas Rate, MMscfd
There are minor differences between the wells as can be observed in the following graph. GYA02S1
and GYA05 are a bit stronger than the rest of the wells (in line with the initial clean-up of the wells).
Goldeneye - HC Productivity
Productivity Information (excluding initial prod. data)
500
450
400
350
Drawdown, psi
300
250 GYA01
200 GYA02S1
GYA03
150 GYA04
100 GYA05
50
0
- 20 40 60 80 100
Gas Rate, MMscfd
Figure 3-5: Productivity per well during long term production phase
Inflow Performance from gas wells can be represented mathematically using the Jones equation, as
follows:
Preservoir2 – Pwf2 = Darcy coefficient * Q + Non-Darcy coefficient * Q2
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 20
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
Based on the well performance the wells can be grouped in two sets:
GYA01, GYA03 and GYA04
GYA02S1 and GYA05
Goldeneye - HC Productivity
Productivity Information (excluding initial prod. data)
500
450
400
350 GYA01
Drawdown, psi
GYA02S1
300
GYA03
250 GYA04
200 GYA05
GYA-01,03,04 Jones
150 GYA-02S1, 05 Jones
100
50
0
- 20 40 60 80 100
Gas Rate, MMscfd
hydrocarbon gas production was between 150 to 200psia, whilst for CO2 the injection would be
between 280psia [19.3bara] and 380psia [26.2bara] above the reservoir pressure depending on the
well.
The reservoir pressure just before the CO2 injection is estimated at 2650psia [183bara]. The required
bottom hole pressure is higher than the critical pressure of the CO2. At reservoir temperature, the
CO2 will be supercritical whilst at the injection temperature the CO2 can be considered as liquid or
supercritical fluid depending on the injection temperature. The viscosity of the CO2 will be higher
than the viscosity of the hydrocarbon gas.
The downhole in situ rate of the CO2 has a high dependency on the pressure and temperature, but
the effect is less pronounced in case of injecting at high pressures as encountered in the Goldeneye
reservoir. The downhole rate of the CO2 for a given surface rate is much smaller than the
hydrocarbon production. Both effects are illustrated in the following Figure 3-7 and Figure 3-8:
Goldeneye
16000
14000
CO2 83 degC 150bar
Downhole Rate, m3/d
0
0 20 40 60 80 100 120
Rate, MMscfd
Figure 3-7: CO2 downhole (in-situ) injection rate for given surface rate
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 22
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
Goldeneye
25000
0
0 20 40 60 80 100 120
Rate, MMscfd
The viscosity of the CO2 is higher than the viscosity of the hydrocarbon gas in Goldeneye (see Figure
below). This difference in properties will have a negative effect on the injectivity.
Viscosity Comparison
@ Injection conditions (~170 - 300bar)
0.14
0.12
0.10
CO2 20 degC
0.08
Viscosity, cP
CO2 30 degC
CO2 60 degC
CO2 80 degC
0.06
GYA HC 80 degC
0.04
0.02
0.00
150 200 250 300
Pressure, bar
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 23
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
The difference between CO2 and hydrocarbon gas in terms of equivalent downhole rate and viscosity
can be calculated with the previously calculated Jones equation as follows:
Pr2 − Pwf2 = Aq + Fq 2
µCO 2 Z CO 2 TCO 2
ACO 2 = Agas = Agas K A
µ gas Z gas Tgas
Z CO 2 γ CO 2 TCO 2
FCO 2 = Fgas = Fgas K F
Z gas γ gas Tgas
Where,
µCO 2 Viscosity relation CO2 / hydrocarbon gas
µ gas
Z CO 2 Compressibility Factor relation CO2/ hydrocarbon gas
Z gas
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 24
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
Figure 3-10: CO2 injectivity in comparison to hydrocarbon productivity (GYA01, GYA03 and
GYA04)
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 25
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 26
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
3.2.2 Discussion
The same offshore pipeline currently used for the hydrocarbon production will be used for the CO2
injection. During the production phase it is possible that corrosion products and / or formation
fines might have settled in the pipeline. On commencing CO2 injection there is the potential that any
solid debris present in the pipeline could become mobilised or dislodged and travel down the pipeline
to the wellbore, potentially impairing injectivity by physically obstructing the path of CO2 into the
reservoir. As the pipeline is 105km long 20'' [508mm] diameter, even a small film of debris may
represent a significant risk to injectivity.
In an injection system in the case of having particles bigger than a critical size the solids will start to
accumulate internally at the screens, gravel and the formation. Smaller solids can pass the screen but
can accumulate at the gravel. Still smaller solids can travel through the gravel and even smaller solids
can sail through the formation.
Very small particles can be accepted in the injection wells to avoid plugging at the screens / gravel
pack and formation. The accepted level is using the guidelines in the oil industry for flow in a porous
media:
o Particles larger than 1/3 of pore throat size will bridge
o Particles smaller than 1/7 of pore throat size will flow through the matrix without
plugging.
o Particles between 1/3 and 1/7 of pore throat size will invade and impair the porous
media
o Pore throat size is 1/6 of particle size in a packed sand matrix with reasonable sorting
Average pore throat analysis from capillary curves in Captain formation is between 35 to 40 microns.
Particles between 5-12 microns invades and impairs the formation (1/7 – 1/3 formation). Particles
smaller than 5 microns sails on through deep into the formation (1/7 formation).
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 27
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
Normally the value for the particle size compatible with the formation (under matrix injection) is
estimated using core flood lab experiments and experience in similar formations. The value in
Goldeneye was calculated using the average pore throat from petrophysical analysis (mercury
injection capillary pressures) and the normally accepted rules in the oil industry for particle
management. The average pore throat is in the order of 35-40 micron in line with the average
permeability of the formation.
During the hydrocarbon freeing operation in May 2013 (9 pigs sent from platform to beach), the
sludge collected contained approximately 1kg of solids. The sample analysis indicated 12% solids with
50% water & 25% condensate. The solids contained 50% iron oxides and the rest acid insoluble
compounds (silicates), carbon and other salts and trace materials. Sand was not detected. The only
material expected but not present in the samples was Iron Carbonate (FeCO3).
The main threat is perceived to be from the epoxy coating of the pipeline (section 3.2.3). Another
possible source of solids will be debris (corrosion products, sand/fines, scale) from the pipeline itself
and mol sieve, amine salts, etc. from the conditioning unit.
The quantity of solids that will be present during the injection operation is currently unknown.
The fact that the CO2 will be dry reduces the risk of having corrosion products injected into the wells.
Filtration will be provided at the Goldeneye platform. It is not expected to have large amount of
solids to be produced from the capture plant. Within the compressor package there will be a 5 micron
filter.
The current philosophy of the filters at the Goldeneye platform is to prevent exceptional situations
(de-bonding of epoxy coating) leading to remedial activities. In other words, the filters will be used to
prevent well workovers or stimulations with low chance of success. It is not designed for continuous
removal of sustained solids production. It is better to clog a surface filter than the filters (lower
completion/formation) downhole in the wells. If the filters clog up, it will be for no apparent reason,
and injection should be stopped until the root cause is identified and eliminated.
Filtration units for dense phase CO2 have been confirmed by the surface facilities to be available in
the market. Filtration package will be designed during FEED.
gravel pack / formation, thereby reducing injectivity. The mitigation for this case is to have a tight
control on the CO2 quality being injected into the wells using a filtration system on the platform.
3.2.4 Hydrates
The formation of hydrates is only possible when water is present in sufficiently significant quantities
and the temperature and pressure of the fluid is within the hydrate formation window. Hydrates will
be managed primarily during steady state injection by dehydration of the injection fluids to
sufficiently remove the water to inhibit the formation of hydrates.
Free water is not expected in an injection scenario. However, it is possible that water will enter back
the wellbore in case of an injection trip when not enough CO2 is injected to displace the water from
the wellbore.
During hydrocarbon production, water encroached into the Goldeneye gas cap and at least part of
the well gravel pack will be surrounded by water at the time that injection commences. As such
hydrocarbon gas and water will be present during the initial CO2 injection. The trapped gas
saturation is estimated to be 25%, so some methane will remain near the well. The methane is
miscible with CO2 and consequently will eventually be displaced by the injected CO2. The initial
injection of CO2 will drive water away from a well and cool the reservoir.
In order to reduce the initial risk of hydrate formation during the first years of injection (once water is
displaced from the wellbore) it is considered prudent to introduce batch hydrate inhibition prior to
operational opening of a well for injection purposes. If water is subsequently introduced into a well
and/or it is suspected that water is present in a wellbore, then batch injection should continue.
Methanol is currently preferred as an inhibitor and this will be supplied to the platform via the 4''
[102mm] piggybacked supply pipeline. Batch hydrate inhibition will feature as an instruction in the
well operational procedures that will be developed for the injection system.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 29
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
200
180
160
140 GYA HC
Pressure, bara
1GYA HC_0.1CO2
120
1GYA HC_1CO2
100
1GYA HC_10CO2
80 1GYA HC_100CO2
60 CO2
40
20
0
0 5 10 15 20 25 30
Temperature, degC
Figure 3-12: Hydrate equilibrium curve for CO2 and Goldeneye hydrocarbon and their mixtures in
the presence of free water.
The CO2 hydrate equilibrium curve will change due to the reduction of water as shown in Figure
3-13. For low concentrations of water in CO2, the hydrate equilibrium curve in the liquid CO2 phase
shifts to lower temperatures. This shift is attributed to a shift in solubility of water in the CO2 liquid
phase.
160
0.00005 mol water / mol fluid (CO2
spec 20 ppmw)
140
0.0001 mol water / mol fluid
Pressure, bar
120
0.0005 mol water / mol fluid
100
20
1 mol water / mol fluid
0
-50 -30 -10 10 30 Saturation
Temperature, degC
Figure 3-13: Hydrate equilibrium curve for CO2 at different water concentrations
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 30
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
200
180
160
120 Saturation
60
40
20
0
-30 -20 -10 0 10 20 30
Temperature, °C
Figure 3-14: Hydrate equilibrium curve and well conditions under normal CO2 injection
conditions
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 31
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
The CO2 in the top of the well will still be dehydrated during this operation. The top of the well will
be at saturation conditions (when the reservoir pressure is low) and some liquid CO2 will evaporate
causing a temperature drop. However, there is an insignificant risk of hydrate depositing, Figure 3-15,
as after a short time the content of the wellbore will increase in temperature again.
200
180
160
0.00005 mol water / mol fluid (CO2
spec 20 ppmw)
140
Saturation
Pressure, bar
120
100
Wellhead conditions - close-in
80
Well Profile - coldest during close-in
60
40
20
0
-50 -30 -10 10 30
Temperature, degC
Figure 3-15: Hydrate equilibrium curve and well conditions during close-in operation
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 32
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
With enough CO2 injection, water from the aquifer is pushed away by the CO2. The time where the
water is not coming back into the well (when it is closed in) is estimated to be between 6 months to 1
year of continuous injection (section 4.6.2 in the report (UKCCS-KT-S7.18-Shell-002 Injectivity
Analysis Preparation, 2010)).
After this continuous time of injection the water will tend to stay away from the wellbore. However,
in case that the well has injected for a short time then the water may enter the wellbore.
The discussion above is illustrated in the Figure 3-16 below. The top of the well under the presence
of free water will enter the hydrate deposition region.
200
140 Saturation
Pressure, bar
80
60
40
20
0
-50 -30 -10 10 30
Temperature, degC
Figure 3-16: Hydrate equilibrium curve and well conditions during closed-in conditions
Starting-Up Operation
Under certain conditions aquifer water has entered into the well during the close-in period (as
described above). Considering the cold injection conditions of the CO2 arriving to the platform and
the expansion of the CO2 during the starting-up operation, hydrate would be formed during this
operation in the presence of free water, Figure 3-17.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 33
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
200
180
0.00005 mol water / mol fluid (CO2
spec 20 ppmw)
160
0.1 mol water / mol fluid
140
Saturation
Pressure, bar
120
60
40
20
0
-50 -30 -10 10 30
Temperature, degC
Figure 3-17: Hydrate equilibrium curve and well conditions during start-up operations
The main risk during a well start-up operation is the hydrate deposition in the tubing and not in the
formation. The top of the well during the start-up operation will be in the hydrate region with a low
reservoir pressure. Expansion of the CO2 over the wellhead choke will result in low temperatures for
a period of time. The wellhead temperature of the steady state injection CO2 will be approximately
0.5°C -10.1°C, which is well to the left of the hydrate equilibrium curve considering the presence of
free water.
In the case that water is added to the well (e.g. well intervention) or suspected to be in the well (e.g.
initial injection conditions) then hydrate inhibitor should be used before starting-up the well.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 34
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
WH Steady State
Temperature, degC
Figure 3-18: Hydrate equilibrium curve and well conditions during first start of injection (well filled
with water)
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 35
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 36
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
3.2.5 Joule Thomson cooling upon CO2 injection into the reservoir
A Joule Thomson cooling effect can be expected when CO2 undergoes adiabatic expansion upon
entering the formation. The likelihood of encountering CO2 expansion problems in Goldeneye is
very low, due to the low JT coefficient based upon the injection pressure and temperature. Cooling
for Joule Thomson effects of less than 3°C is anticipated, due to the relatively high pressure of the
reservoir.
The injection conditions in Goldeneye: relatively high reservoir pressure, small delta pressure between
the well and the reservoir and low injection temperature are adequate to avoid cooling of the CO2 due
to CO2 expansion. This is demonstrated below:
Table 3-1: Joule Thomson expansion calculation near wellbore for different injection conditions.
A delta pressure of 500psia [34.5bar] was used as a worst case scenario in terms of JT effects on
temperature across the wellbore. Reference case is in the order of 280-380psia [19.3-26.2bara].
formation water (i.e. 100% water saturation) this would lead to a relative porosity reduction of only
26/1,000. Given the average porosity of 25% in the main reservoir sands (Captain D) this would
reduce porosity from 25% to 24.4%.
It should be noted that around most injectors the water saturation is likely to be lower, for two
reasons:
Initial water saturation in Goldeneye is only approx. 13% on average going down to 7% around
crestal wells. During the production phase this will have increased for some of the wells when
watering out, but at least the crestal wells will only have partially watered out at the end of
production.
Even for a fully watered out well, the initial water saturation upon injection is only (1-residual gas
saturation). Moreover, as has been shown in core flood experiments and modelling studies, dry-out
only starts to become significant after some of this water has been displaced by injected CO2. The
water saturation at the start of significant dry-out depends on the relative permeabilities, but
especially for a high permeability sandstone like in Goldeneye will be close to residual which for such
a sandstone is approx. 10-20%.
Therefore the relative porosity reduction is only [0.07-0.20]*26/1,000 = [2-5]/1,000, and therefore
the porosity only reduces from 25% to [24.88-24.96]%. This is a very small reduction. Even if much
of the salt deposition would occur in the pore throats (which have a relatively large diameter in
Captain D due to its high permeability) it is not expected to have a measurable effect on permeability
and therefore injectivity is expected to be unaffected by the build-up of the dry-out zone.
From field experience perspective, CO2 injection is ongoing in Sleipner in Norway and in Salah,
Algeria. These operations have a similar or higher likelihood than Goldeneye to exhibit injectivity
decline due to the build-up of a dry-out zone. This is for two reasons:
• These fields have a similar (Sleipner) or higher (in Salah) value of the product (salinity * water
saturation), primarily due to a similar or higher initial water saturation at start of dry-out, and
therefore a similar or higher amount of salt is available for deposition (per unit pore volume).
• These fields have similar (Sleipner) or much lower (in Salah) permeability and therefore (even
for the same amount of salt deposition per unit of pore volume) similar or higher risk of
deposition in the pore throats leading to permeability reduction.
However, no injectivity decline (besides decline due re-pressurisation of the formation) has been
reported for these operations during their injection period since start-up (14 and 6 years, respectively).
Therefore for Goldeneye the risk of injectivity impairment due to salt deposition in the dry-out zone
consider to be low.
Snohvit field in Norway presented injectivity issues at the beginning of the project. It was reported
(Hansen, 2013) that rapid increase in injection pressure during the initial stages of the project was
interpreted to be caused by halite precipitation in near the wellbore. A recipe of regular water with
MEG was pumped into the well on a weekly basis until the problem was overcome. Further
communication with Statoil clarified that the problem was attributed to the salt precipitation possibly
due to a high salinity (~150000 ppm TDS) and the presence of multiple perforation intervals
presented in the well. Production Logging (PLT) indicated cross-flow between the perforations at
well closed-in conditions. This facilitated water replenishing and further salt precipitation by water
dehydration with further CO2 injection then leaving more salt in the near wellbore area which lead to
injectivity deterioration. The water and MEG treatment possibly re-dissolve the salt present in the
wellbore.
In the case of halite precipitation bullheading of water can be applied in the wells to re-dissolve the
salt present in the well. Platform modifications to pump water into the wells are not justified due to
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 38
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
the low risk of having injectivity issues. Well intervention can be carried out in case of observing this
problem in the wells.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 39
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
matrix conditions. However, as the reservoir pressure increases and hence the injection pressure
increases, it is possible that the reservoir may be fractured during the injection process. There is
uncertainty in terms of the pressure at which the injection will move from matrix to fracturing
injection.
Injection under fracturing conditions can propagate fractures in the Captain formation. These
fractures in the reservoir are not detrimental to the containment capacity of the seal (Rodby/Hidra).
3.4.1 Software
The estimated length of the fracture in the case of injecting under fracturing conditions is calculated
using a Shell Proprietary software called PWRI-Frac.
The PWRI-Frac tool computes fracture dimensions, well injectivities, and flood front displacements
for injection above frac pressure. The software does not predict the starting point of the frac or
breakdown of the formation.
For injection of CO2 above frac pressure, the fracture propagation process is entirely steered by fluid
leak-off into the formation.
Leakoff
In-situ stress Pore pressure build-up
Formation cooling
Friction
Elastic opening
Figure 3-19: Fracture propagation mechanism in PWRI
The purpose of the program PWRI-Frac is to provide (i) an estimate of lateral and vertical extension
of induced fractures, (ii) of vertical fracture (non-)confinement and (iii) hydraulic requirements during
injection.
The software was developed for water injection purposes. The input has been modified to suit the
CO2 injection (viscosity, thermal properties, etc.).
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 40
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
The following data were used for this study in terms of rock characteristics:
Table 3-2: Base assumptions for the fracture modelling [1ft = 0.3048m, 1psia = 0.06895bara]
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 41
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
later due to the pressure increase process (section [Link]). The minimum stress is also affected by the
injection of cold fluid into the reservoir (section [Link]).
The original Captain D minimum stress is estimated to be 5993psia [413bara] at 8300ft [2530m]
TVD, based on 0.72 psia/ft [162.9mbara/m], typical of North Sea sandstones where the minimum
stress gradient in the sandstone shows an average of 95% value of the shales above.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 43
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
The reference case minimum stress at original conditions is represented in the Figure 3-20. The stress
contrast in the reference case between the bottom of the Rodby and the top of the Captain is
estimated at around 300 psia [20.7bara].
∆S h = Ap * ∆Ppore
Where Ap = depletion constant or poro-elastic constant (-)
∆Ppore is the depletion level (psia)
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 44
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
For soft rocks (like Captain D in Goldeneye) the expected poro-elastic constant is in the order of
0.55-0.70. A base value of 0.6 has been used in the calculations with sensitivities to 0.4 and 0.8 (
(PCCS-05-PT-ZP-9025-00004 Geomechanics Report, 2014). The following Table 3-5 illustrates the
change in minimum horizontal stress with change in reservoir pressure at different poro-elastic
constants for depletion scenarios under an isothermal scenario.
Table 3-5: Change of minimum stress in the Captain formation due to depletion (during the
hydrocarbon production phase) [1 psia = 0.06895bara]
P reservoir Depletion Change in Sh, psia Change in Sh, Change in Sh, psia
Level due to depletion psia due to due to depletion
depletion
0.6 Depletion 0.4 Depletion 0.8 Depletion
Constant (reference Constant Constant
case)
3830 0 0 0 0
3450 380 -228 -152 -304
3050 950 -570 -380 -760
2650 1180 -708 -472 -944
2100 1730 -1038 -692 -1384
(lowest
reservoir
pressure, psia)
[Link] Inflation process – Reservoir pressure recovery (aquifer strength and CO2 injection)
The reservoir pressure has increased from the lowest on depletion 2100psia [145bara] to the current
2620psia [181bara] (December 2013). The pressure will continue increasing to around 2650psia
[183bara] before injection to 3450psia [238bara] after CO2 injection.
One uncertainty is the ability of the formation to increase or recover the minimum horizontal stress
with the pressure inflation when the formation has previously been through a depletion phase. Data
suggest that some formations will not fully recover the minimum horizontal stress as calculated using
the poro-elastic constant.
The reference case for minimum stress recovery is estimated at 50% of the depletion constant.
Ranges vary from 0% recovery to 100%.
The 100% recovery indicates a totally elastic behaviour of the rock; the minimum stress
recovery is based on the depletion constant.
A 0% recovery in the minimum stress min indicates a totally inelastic behaviour where despite
of the pressure recovery the minimum stress will not recover from the minimum stress
estimated at the lowest reservoir pressure.
The change in minimum stress due to the inflation process is included in the Table 3-6.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 45
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
Table 3-6: Change of minimum stress in the Captain formation due to pressure increase
(during the pre-CO2 injection and CO2 injection periods) [1 psia = 0.06895bara]
P Inflation Level, Change Change in Sh, Change in Sh, Change in Sh, psia
reservoir in reservoir pressure from psia due to psia due to due to inflation
(psia) lowest after depletion, inflation (after inflation (after (after depletion)
psia depletion) depletion)
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 46
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
The typical coefficient of thermal expansion for sandstone is estimated at 10 E-6/°C (5.55 E-6 / °F).
The CO2 bottom hole temperature is estimated to be between 23°C to 35°C (section 4.3.10). As such,
there will be a difference of around 113°F (60°C difference). This will reduce the minimum stress in
the reference case in the order of 145bara [2000psia], Table 3-7.
Table 3-7: Change of minimum stress in the Captain formation due to thermal effects
Reservoir Original DSh, psia DSh, psia Isothermal DSh due Sh after
Pressure Sh, psia depletion inflation Sh (after to 60°C depletion,
(0.6 (50% depletion, cooling inflation and
depletion recovery inflation), cooling
factor @ P psia (60°C), psia
minimum)
2100psia 5993 -1038 0 5993 N/A N/A
(maximum
depletion)
2650psia 5993 -1038 +165 5120 -1905 3215
([Link] inj.)
3050psia 5993 -1038 +285 5240 -1905 3335
(mid Inj.)
3450psia end 5993 -1038 +405 5360 -1905 3455
of inj.)
The comparison of the bottomhole injection pressure and the minimum stress during injection will
determine the type of injection: under matrix conditions or fracturing conditions.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 47
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
The bottom hole injection pressure during the CO2 injection would be between 280psia [19.3bara]
and 380psia [26.2bara] above the reservoir pressure depending on the well. This indicates that the
initial conditions of injection (reference case) will be under matrix conditions and switching to
fracturing conditions with time (increase in reservoir pressure). However, the exact conditions of
when this will occur are uncertain given the uncertainty in the calculations.
The main factor affecting the injection under matrix and fracturing conditions is the level of cooling
of the reservoir. Under isothermal conditions the injection would be under matrix conditions during
the duration of the project. Equally and assuming a low effect on the minimum stress given by the
formation cooling then the injection condition will be under matrix condition. However, considering
the high value in the thermo-elastic constant then the injection would be under fracturing conditions.
This is illustrated in the Figure 3-21 at the start of injection for different cooling effects and variables
(stress gradient, depletion constant, and inflation recovery) on the minimum stress. As it can be
observed the main factor affecting the minimum stress is the thermo elastic properties of the rock
where the minimum stress changes dramatically (difference between the blue and green lines).
Depending on its value the injection might occur under injection conditions (Minimum stress to be
lower than the bottom hole injection pressure for injection under fracturing conditions).
5500
5000
Pressure / Sh, psi
2000
Reference High Low Low High Elastic on Inelastic All High All Low Sh
Case Original original Depletion Depletion inflation on Sh
Sh Sh Constant Constant inflation
Figure 3-21: Uncertainty in minimum stress in the Captain formation and injection conditions at
the start of injection. [1 psia = 0.06895bara]
Injection under fracturing conditions cannot be assumed to happen during the duration of the project
due to the uncertainty in terms of the effect of injection temperature in terms of minimum stress.
Matrix conditions should be used for the design of the injection system in terms of suspended solids.
However, injection under fracturing conditions in terms of fracture containment and potential issues
in the lower completion should be investigated due to the possibility of having this kind of injection.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 49
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
Figure 3-22: Formation pressure in the Goldeneye area (pressure in the Captain formation as an
average pressure over the life of the project)
Figure 3-23: Isothermal minimum stress in the Goldeneye area for injection (reference case
Captain minimum stress)
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 50
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
Figure 3-24: Base case. Fracture depth to and depth bottom with time
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 51
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 52
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
Figure 3-27: Rate sensitivity. Fracture depth to and depth bottom with time
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 53
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
Figure 3-29: CO2 quality sensitivity. Fracture depth to and depth bottom with time
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 54
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 55
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
Figure 3-31: Fracture geometry with time for different fracture initiation points
Figure 3-32: Fracture geometry with time assuming no changes in original minimum stress
(worst case for fracture containment)
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 56
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
• Flow back
Major operation for cleaning clogged solids on the screens. This might be applicable in case of
having problems with the pipeline coating disbondment. The planned platform configuration
will not allow a flow of the CO2 hydrocarbons mixture into the process facilities. Most likely a
well test package will be required.
• Others
Consideration should be given to new technologies in case of having injectivity problems. This
can be related to ultrasonic tools, heaters, etc.
• Side-track
It is always the last resort to restore injectivity. New formation is drilled with the formation
damage issues.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 58
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 59
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injectivity
The length of any productivity / injectivity test should be tailored to the main uncertainties / risks
considering the operational aspects of the test.
Another fluid (e.g. water, nitrogen, hydrocarbon) might be used, but the extrapolation of the results
should be taken into consideration.
Doing the test with water, hydrocarbon or nitrogen will only have benefits in terms of reducing the
uncertainty in terms of fines re-accommodation in the gravel pack.
In addition to the fines re-accommodation an injectivity test carried out with CO2 will have small
benefits with respect to the fluid change in terms of PVT, relative permeability and the risk of
hydrates. The phenomenon related to fluid change is relatively well understood with a very low
uncertainty. Reducing this further will not impact the project in terms of cost or decisions. There
will be a reduction in Hydrates uncertainty from low to zero. However, the current thinking calls for
batch hydrate inhibition.
The following Table presents the summary with the reduction of Risk / Uncertainty with respect to
the current understanding of the injectivity in Goldeneye and the planned mitigation options. The
table shows the value of the injectivity test over and above the current understanding.
Table 3-12: Injectivity test. Risk/Uncertainty comparison pre and post-test.
Current risk
uncertainty
Current View (including
Stage Factor (includes Risk/Uncertainty after Injectivity Test
planned mitigation)
planned
mitigation)
with CO2 with N2 with Water
Initial Reservoir Parameters High absolute permeability based Zero Zero Zero Zero
Injectivity on core and production
information.
Initial Skin High initial skin but stable VL VL VL VL
draw dow n during production. No added value No added value No added value
Fluid Change - PVT Different PVT from the current VL 0 VL VL
HC production to the CO2 Minor effect on Another fluid Another fluid
injection. Already included in the injectivity based on introduced in the introduced in the
calculations different PVT. Easy to system. system.
calculate
Relative Permeability Minor effect on injectivity in the VL 0 VL VL
long term. Scal analysis. Easy to Information added in Complications w ith Complications w ith
calculate the difference Different terms of permeability to different injection different injection
scenarios w ith simialr results CO2. fluids. fluids.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 60
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
For a CO2 injection test and based on the current knowledge of Goldeneye wells, injecting CO2 in the
wells without carrying any modification to the well completion could jeopardise the integrity of the
wells. This is related to the extremely low temperatures expected due to the Joule Thomson effect of
the CO2 and the related tubing shrinkage affecting the PBR in the well. Modifications in the well
completion would need to be carried out prior to the injectivity test.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 61
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
The Figure 4.2 shows the variation of density as function of Pressure and Temperature for CO2.
Especially for pressures and temperatures that are often encountered in CO2 injection, the CO2
density changes significantly for only relatively small variations in pressure and/or temperature. The
changes are more pronounced near the critical point conditions. The changes are less severe in the
liquid and vapour areas.
CO2 Density
350
300
100 Kg/m3
250 200 Kg/m3
300 Kg/m3
400 Kg/m3
500 Kg/m3
Pressure, bar
100
50
0
-50 -30 -10 10 30 50 70 90 110
Temperature, degC
Figure 4-2: Variation of CO2 density with pressure and temperature (NIST data)
The Figure 4-3 below shows the Joule Thomson coefficient of the CO2 at different pressure and
temperatures. The JT coefficient is very high (~9 to 14°C/Mpa or 0.9 to 1.4°C/bara) for the vapour
phase whilst in the liquid phase the JT coefficient is low (0 to 1.5°C/Mpa 0 to 0.15°C/bara).
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 62
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
2900
2175
Pressure (Psi)
1450
725
Well thermo-hydraulics are sensitive to the prediction of CO2 physical properties, heat transfer
between the fluid and the well bore and the frictional pressure drops.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 63
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 64
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
CITHP vs Preservoir
(Geothermal Gradient)
70
60
50
CITHP, bar
40
30
20
10
0
2000 2500 3000 3500 4000
Preservoir, psi
Figure 4-5: CITHP for a well filled with CO2 (at geothermal conditions)
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 65
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
-25.00
-455.00
-885.00
TDV
(m) -1315.00
TVD (m)
-1745.00
-2175.00
-2605.00
-30.00 -20.00 -10.00
Temperature (°0.00
C) 10.00 20.00
Figure 4-6: Temperature profile in the well considering CO2 injection in two phases in the top of
the well by expanding the liquid CO2 from the pipeline
The extreme reduction in temperature is due to the flashing of the liquid CO2 to gas/liquid CO2
caused by the low reservoir pressure. Even at relatively high reservoir pressures there will be a
flashing into two phases, mainly related to the high density of the CO2 in the bottom of the well.
A well might be operated with free CO2 expansion once the reservoir pressure increases to levels
close to hydrostatic as the density of the CO2 will be similar to the density of liquid water.
The general isenthalpic expansion from liquid CO2 (arrival CO2 conditions to Goldeneye platform) is
represented in the Figure 4-7. If the CO2 is kept in liquid phase then there will be a small reduction in
temperature for big pressure drops. If the liquid CO2 is expanded down to the saturation line, then
there will be an important reduction of temperature for a small change in pressure; the CO2 will
follow the saturation line.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 66
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
120
100
Pressure, Bara 80
60
20 Normal Expected
Downsrtream Choke
0
-40 -20 0 20 40
Temperature, Deg C
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 67
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
4.3.1 Software
Prosper (a commercial software marketed by Petroleum Experts, UK) is used for all calculations on
Steady State. The Shell proprietary software WePs© (Well Performance Simulator) (Copyright of this
program is vested in Shell International Exploration and Production BV, Rijswijk The Netherlands) has also been
used to confirm the Prosper calculations. The differences are negligible.
All the five wells (GYA01, GYA02S1, GYA03, GYA04 & GYA05) with proposed completion
options are modelled using Prosper/WePs.
The temperature change of the CO2 over a tubing section is governed by the energy balance which
dictates the change of the total energy. The change in temperature is caused by heat transfer, change
of potential energy, change of kinetic energy (acceleration) and change of enthalpy due to expansion.
The effect of adiabatic cooling, and Joule-Thompson cooling and phase changes are taken into
account. These calculations are implemented in Weps and Prosper considering the well construction,
the overburden description and the fluid description.
For each section, the pressure drop across the section is calculated using a multi-phase pressure drop
correlation. Based on the section properties, such as diameter and inclination angle, a multi-phase
pressure drop correlation is used to calculate the flow regime, gas and liquid hold ups, and
subsequently the pressure drop.
The vertical lift performance under steady state conditions is relatively simple to calculate considering
that there is only 1 phase of dense phase CO2. Prospers use the Peng Robinson equation of state to
model the CO2 properties. It is calibrated for the Goldeneye conditions (Appendix A in the report
(UKCCS-KT-S7.18-Shell-001 Temperature and Pressure Modelling (for CO2 injection wells -
Goldeneye CCS), 2010).
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 68
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
18
16
14
Temperature, °C
12
1%
10
50%
8 99%
6
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
18
16
14
Temperature, °C
12
1%
10
50%
8 99%
6
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
The minimum arrival CO2 temperature to the platform in winter of 2.3°C should be used for low
temperature calculations. The high temperature of 10.1°C should be used for limits of the injection
system. The temperature drop between the seabed and the CO2 arrival temperature is estimated at 1.7
°C for winter conditions and approximately 1 °C in summer.
The expected manifold conditions in winter would be 5.3°C considering an average seabed
temperature of 7°C and a temperature drop of 1.7°C at the riser. For an isenthalpic pressure drop in
the surface facilities to 115bara wellhead pressure, the wellhead temperature would be in the order of
5.2°C (3.1°C for 50bara wellhead pressure). These temperatures would be used for normal well
operational calculations. In summer the expected wellhead temperature is 5.5°C for 50bara tubing
head pressure and 7.9°C for 115bara.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 69
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
Table 4-1 summarises the expected temperatures for the operational and design cases to be used in
this report.
Table 4-1: Arrival CO2 temperature to the platform for different cases and subsequent expansion
to wellhead conditions
A temperature of 5°C will be used for reference case simulations as the injected CO2 temperature.
This is the average for the summer and winter design cases and also the average temperature of the
operational cases. Sensitivities will be carried out for the different cases in injected CO2 temperatures
when required.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 70
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
50
Pressure, bar 40
10
0
0 5 10 15
Temperature, degC
Figure 4-9: Wellhead pressure and pure CO2 saturation line. Difference in pressure between
minimum injection pressure and saturation curve.
It is important to mention that the expected injection range per well can be expanded by reducing the
minimum WH pressure but maintaining it above the saturation pressure. 50bara has been used at the
moment in the project as a conservative pressure considering the maximum manifold temperature in
summer. The WH temperature can be reduced with colder arrival temperature of the CO2. For
example, a way of operating the wells would be to reduce the minimum WH pressure in winter to a
lower value (43.5bara considering a CO2 manifold temperature 5.3°C and saturation pressure of
40bara).
The maximum WH pressure is limited by the maximum allowable pipeline pressure. A CO2 arrival
pressure to the platform of 120bara has been highlighted. Considering pressure drops in the surface
equipment (filters, meters, valves, etc.) a maximum available pressure of 115bara at the wellhead has
been used in the calculations.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 71
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
Water/Brine Packer fluid (or A-annulus fluid) is assumed in this report. New calculations of lift
performance will be done for the selected packer fluid.
5000
4500
Outflow 50bar WHP
4000 Inflow Pr 3450psi
3500
3000
Inflow Pr 2650psi
2500
CCP Rate
2000
0 10 20 30 40 50 60 70 80
Injection Rate, MMscfd
Inflow - P reservoir 2650psi Inflow - P reservoir 3450psi
Vertical Performance - 50bar WH Pressure Vertical Performance - 115bar WH Pressure
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 72
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
5000
4500
4 1/2" tubing
5 1/2" tubing
4000
3500
3000
2500 2 7/8" tubing 3 1/2" tubing
CCP Rate
2000
0 10 20 30 40 50 60 70 80
Injection Rate, MMscfd
Inflow - P reservoir 2650psi Inflow - P reservoir 3450psi
5.5" tubing 50bar 5.5" tubing 115bar
4.5" tubing 50bar 4.5" tubing 115bar
3.5" tubing 50bar 3.5" tubing 115bar
2 7/8" tubing 50bar 2 7/8" tubing 115bar
The 2 7/8'' [73mm] tubing is considered very small and the 5 ½'' [140mm] tubing seems very big for
the Peterhead CCP rates. The tubing size required for the CCP rates is a combination of 3 ½''
[89mm] and 4 ½'' [114mm] completion.
The operating envelope per well will be engineered/tailored well by well considering the lifecycle of
the project parameters (expected reservoir pressure, CCP rates, etc.).
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 73
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
5000
4500
4000
3500
3000
2500
0 10 20 30 40 50 60 70
Injection Rate, MMscfd
Winter design 50bar 0.5 °C Winter design 115bar 2.2 °C
Winter operational 50bar 3.1 °C Winter operational 115bar 5.2 °C
Summer operational 50bar 5.5 °C Summer operational 115bar 7.9 °C
Summer design 50bar 7.2 °C Summer design 115bar 10 °C
There is some variation in injection rate per well due to the CO2 temperature (when considering the
extremes for winter and summer) which needs to be considered for meeting the minimum and
maximum rates of the CCP.
Roughness, in /
micron
Bare 13Cr 0.0021654 / 55 Used as reference case
Electropolished bare - 13 Cr 0.00118 / 30 Low Value
Bare Carbon Steel 0.00138 / 35 Not to be used in the wells
Clean Carbon Steel 0.000787 / 20 Not to be used in the wells
Rusted steel 0.00394-0.0394 / Not to be used in the wells
100-1000
+ 25 % above Bare 13Cr 0.0027 / 69 High Value
roughness
Sensitivity was carried out for different average absolute roughness values, Figure 4-13. There are
some variation terms of injection rate per well. Variations in the order of ~+/- 3 MMscfd in injection
rate for the low and high roughness case with respect to the reference case are calculated.
5000
4500
4000
3500
3000
2500
CCP Rate
2000
0 20 40 60 80
Injection Rate, MMscfd
Inflow - P reservoir 2650psi Inflow - P reservoir 3450psi
50bar WHP, Roughness Ref. C 55microns 115bar WHP, Roughness Ref. C 55microns
50bar WHP, LowCase 30microns 115bar WHP, Low Case 30microns
50bar WHP, High 69microns 115bar WHP, High 69microns
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 75
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
Pressure and Temperature traverses in the well (based on GYA01) are presented in the figure below.
Total frictional losses of around 40 to 100bara will be encountered in the wells depending on flow
rate.
Pressure Traverse
Pressure, bar Temperature Traverse
0 50 100 150 200 250 300 Temperature, °C
0 0 10 20 30 40
1000 0
2000 1000
True Vertical Depth, ft
3000 2000
5000 4000
6000 5000
7000 6000
8000 7000
9000 8000
41 MMScfd 50bar FTHP 41 MMScfd 80bar FTHP 41 MMScfd 115bar FTHP
9000
63 MMScfd 50bar FTHP 63 MMScfd 80bar FTHP 63 MMScfd 115bar FTHP
41 MMScfd 50bar FTHP 41 MMScfd 80bar FTHP 41 MMScfd 115bar FTHP
63 MMScfd 50bar FTHP 63 MMScfd 80bar FTHP 63 MMScfd 115bar FTHP
The CO2 will be injected in the tubing of the well at single phase (dense phase). The PVT properties
of the CO2 are well defined in this region as observed in the Figure 4-15 where the CO2 density is
relatively stable travelling down the well. This will minimise the calculation error in terms of the
operating envelope of the wells and pressure traverses.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 76
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
100 Kg/m3
250 200 Kg/m3
300 Kg/m3
400 Kg/m3
200
500 Kg/m3
Pressure, bar
600 Kg/m3
0
-30 -20 -10 0 10 20 30 40 50 60 70 80 90 100
Temperature, °C
Figure 4-15: Pressure and Temperature prediction with respect to CO2 phase envelope and density
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 77
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
35
30
25
20
15
10
5 CCP Rate
0
30 35 40 45 50 55 60 65 70
Injection Rate MMscfd
Winter design 50bar 0.5 °C Winter design 115bar 2.2 °C
Winter operational 50bar 3.1 °C Winter operational 115bar 5.2 °C
Summer operational 50bar 5.5 °C Summer operational 115bar 7.9 °C
Summer design 50bar 7.2 °C Summer design 115bar 10 °C
Operators have reported using 10m/s in water injectors wells completed with carbon steel; the
velocity is increased to 17m/s for a duplex stainless steel or higher grade alloy.
Similarly 50m/s for gas hydrocarbon production has been used on a continuous basis. This is
equivalent to around 16m/s for CO2 injection using the C-factor for the ISO 13703 or APIRP14E
(Figure 4-17).
C factor ISO13703
50
45
40
Fluid velocity, m/s
35
Dense CO2 940 Kg/m3
30
HydroCarbon Gas 100Kg/m3
25
17 m/s water
20 50 m/s HC gas
0
0 100 200 300 400 500 600
C factor SI
Figure 4-17: C factor comparison (from ISO13703) for CO2 and hydrocarbon gas
Furthermore the erosion of the metal is not considered to be an issue. Erosion is not generally a
result of surface shear, but is usually a result of repeated, micro- (1) metal deformation or (2) fracture
damage as a result of a mass (solid in liquid or gas, liquid in gas) changing direction at a metal surface.
No ''mass'' changing direction equals no erosion.
Due to the high flow velocities and turbulent fluctuations in the fluid, pulsations and vibrations in the
tubing can be expected. Both the vibration of flow turbulence and the intrinsic instability of the
tubing due to large fluid momentum in the tubing were examined by TNO (TNO-RPT-DTS-2011-
00573, 2010). The tension in the tubing created during the installation and subsequent injection of
cold CO2 removed the chance of fluttering or oscillation of the tubing due to large flow velocity.
Instability is caused by an interaction between the flow-induced forces and bending waves of the
tubing. The part of the tubing in compression is more prone to instabilities than the part of the
tubing under tension. If there is no part in compression, there cannot be any instability in a vertical
pipe, for constant flow. The tubing above the packer on the full length will always be in tension. As
a result the instability is considered not an issue in this part of the completion. To avoid oscillations
in the tail pipe (or tubing below the production packer) a maximum length of 45.7m [150ft] is
calculated.
The acoustic forces, due to turbulence and created by the crossover installed in the completion will
not impact the tubing design.
In general, the TNO study recommended: to keep the tail pipe as short as possible, make sure the
tubing remains under tension during operation and use large diameter tubing near the packer.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 79
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
A maximum velocity in the tubing of 12m/s will be used in restricting the wells envelope. This value
includes a safety factor of 0.75 over the equivalent (C factor) experienced gas producing maximum
velocity in wells. This value is also in line with water injection values reported in the industry.
The 12m/s maximum velocity is equivalent in having the following injection rates in different tubing
sizes, Table 4-3. If the 3 ½'' [89mm] tubing is going to be used then the maximum injection rate per
well would be 68 MMscfd which is higher than the capacity of the capture plant (63 MMscfd).
Table 4-3: Maximum injection due to velocity in tubing [1'' = 25.4mm]
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 80
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
The pressure and temperature traverse can be represented in the Figure 4-19 for the downhole choke
case for an injection pressure of 3000psia (207bara). The Pressure traverse shows the required
pressure drop across the choke for the minimum (at 50bara wellhead pressure) and maximum rate (at
115bara WH pressure). The bottomhole temperature is similar to the tubing cases with bottom hole
temperatures varying from 22°C to 39°C. Due to the pressure drop at the choke depth there is
cooling of the CO2 due to the Joule Thomson effect.
Figure 4-19: Downhole choke pressure and temperature traverse (at 3000psia iBHP)
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 81
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
The pressure drop across the choke is very sensitive to the choke size. The pressure drop for
different choke sizes have been calculated and shown (Figure 4-20) before for an injection bottom
hole pressure of 2000psia (138bara).
Choke Size Vs Del P
400
350
300
250
Del P (Bar)
200
150
100
50
0
3 4 5 6 7 8 9 10 11 12
Choke Size (1/64 inch)
15 MMscfd, iBHP of 2000 Psi 20 MMscfd, iBHP of 2000 Psi 25 MMscfd, iBHP of 2000 Psi 30 MMscfd, iBHP of 2000 Psi
35 MMscfd, iBHP of 2000 Psi 40 MMscfd, iBHP of 2000 Psi 50 MMscfd, iBHP of 2000 Psi
Figure 4-20: Pressure drop across a downhole choke (at 2000psia iBHP)
Some general remarks can be drawn from the downhole choke calculations:
• The downhole choke can force the CO2 to stay in single phase at the well
• The required choke size is very small given the pressure drop required
• The operating range of a fixed size choke is very small
• Temperature drop caused by the Joule Thomson effect can be effectively managed by placing
the choke at the dense phase region under closed in conditions.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 82
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
The recommended procedure is to bring the well to the minimum rate (rate required to keep CO2 in
liquid phase at the wellhead, i.e. injection at 50bara WH Pressure) and then close the well at the
wellhead in 30 minutes. For bringing on a well on CO2 injection, the recommended procedure is also
to do it quickly. It is recommended to attain the minimum rate in 1 hour. Temperature as low as
-15°C can be reached inside the tubing in the top of the well during short periods of time. Due to
heat capacity/storage, this low temperature in the CO2 is not observed in the other well components
(tubing, annulus fluid, etc.), which will see less severe temperature drops. Calculated temperatures in
the top of the well for the recommended case at 2500psia [172bara] reservoir pressure are shown in
Figure 4-21.
At ~450m depth, the CO2 temperature in the tubing is 0°C (32°F). At reservoir depth, during CO2
injection steady-state conditions, the temperature is constant around 17-20°C for injection surface
fluid temperature of 4°C. When shut-in, this bottom hole temperature rises slowly (~2 weeks)
towards initial reservoir temperature.
The design case considers a longer time to open or close the wells in case of any operational problem.
Equally the reservoir pressure used in the calculations is 2500psia which is lower than the predicted
reservoir pressure at the start of the CO2 injection. For the design case, for a short period of time,
surface temperature drop in the CO2 can be in the order of -20°C during well start-up (see Figure
4-22).
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 83
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
Figure 4-22: Wellhead transient temperature. Wellhead conditions. 4°C IWHT (2500psia reservoir
pressure)
Figure 4-23 shows the traverse temperature profile of injection fluid, tubing and production casing at
13th hour of Figure 4-22 (the time where the coldest temperature is observed CO2 at the wellhead).
The top of the well is at low temperatures whilst the bottom of the well is close to steady state
injection temperature. It should be noted that the profile plot shown below is for lowest CO2
temperature and not for lowest tubing or production casing temperature. There is a time lag
observed for the lowest temperature in tubing and production casing with respect to injection fluid
temperature.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 84
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
Bottom of Top of
Figure 4-23: Traverse temperature profile design case: 13.5hr. 45bara WH pressure steady state
(2500psia P reservoir)
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 85
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 86
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Vertical Lift Performance
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 87
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injecting into Existing Wells
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 88
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injecting into Existing Wells
For this case, there will be a requirement to change the shallow well equipment (Xmas tree, hangers, a
portion of the tubing) for extremely low temperature service. There is also potential for integrity
issues associated with freezing of annuli fluids in the wells.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 89
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injecting into Existing Wells
Well Integrity
Should CO2 be injected into the existing Goldeneye completions, a consequence of the resulting low
temperatures (even managing the JT effect with small insert strings), is that the existing production
tubing will contract to such an extent that the PBR shear ring, rated to 120,000 lbs has the potential
to fail.
This being the case and given it is likely that regular movement of the PBR mandrel due to variations
in downhole pressure and temperature will cause the PBR seals to fail. Containment of the CO2 in
the tubing will be lost above the packer.
This will also allow CO2 to enter the A annulus and mix with water based completion brine. Should
this be allowed to happen, the resultant formation of Carbonic Acid would cause an immediate and
significant threat to the integrity of the production 9 5/8'' [245mm] carbon steel casing.
There are issues with existing control line in two wells on the platform: GYA01 and GYA03. As such
these wells cannot be used for long term CO2 injection with the currently installed completion.
Others
o Removal of the perforated pup joint below the production packer and the screen hanger.
o Setting the new production packer deeper, to be in front of the Hidra seal. Ideally the
production packer should be placed in front of the sealing formation. The current packer
in the wells GYA01 and GYA05 are across of the bottom of the Chalk; during the
workover operations there is an opportunity to set the production packer at the desired
position.
o Optimise in-well surveillance.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 90
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injecting into Existing Wells
Wellhead - Cameron 3 Stage -18°C Compact spool is made from 4130 Low
Compact Spool alloy steel and cannot be replaced
without adding complexity to the
workover operation.
Operation procedures during normal
transient events for the temperature to
be above the threshold of this
equipment.
Under investigation for a leak scenario.
Cameron Tubing Hanger -60°C Tubing hanger material to be upgraded
in line with the increased Xmas Tree
specification.
Production casing 10 ¾'' x 9 5/8'' -40°C Temperature OK for steady state
injection.
Potential complicated operation to
replace L80 casing in the upper section
of the well.
Production Tubing 13Cr L80 and S13Cr -60°C Top of the well with S13Cr which has a
S13Cr 13Cr -20 to - low temperature threshold of -60°C
30°C
(different
source)
A- Annulus Fluid __ An annulus fluid can be replaced with
different fluids. Being investigated.
TRSSSV (Current Supplier ) -7°C Temperature OK for steady state
injection at SSSV depth.
Further qualification to be carried out
in advance (one year) of workover
operations commencing
TRSSSV Control Line Fluid __ Temperature OK for steady state
injection.
Alternative control line fluid to -60°C
available
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 91
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injecting into Existing Wells
The Lower completion in the Goldeneye wells was selected considering hydrocarbon production.
The requirement for sand control was established considering the rock mechanics properties and the
well characteristics. The selection of the sand control method was done considering the rock
characteristics (e.g. grain size distribution), the understanding of the production phase and the
evaluation of the different sand control techniques. Installation operations and long term reliability
were also incorporated in the selection.
The Baker Alternate Pack system was chosen as the preferred lower completion. The following is a
summary of the operations carried out during the installation of the lower completion.
• Drill to TD (8.5'' [216mm] hole)
• Displaced to solids free mud
• Ran 7'' [278mm] pre-drilled liner (ensure formation stability during the gravel pack operation)
on drill pipe and washed down to the total depth
• Well displaced from mud (625pptf) to filtered completion brine (550pptf)
• Liner hanger set
• Ran 4'' [102mm] Excluder 2000 screen and liner assembly
• Set the gravel pack packer
• Gravel pack 20/40 pumped until screen-out
• Spotted MudSOLV–U820 with enzymes treatment (chelating agent U820 attacking the
CaCO3 and enzymes attacking the starch)
• FIV closed
• Well displaced to filtered and inhibited seawater
• POOH gravel pack assembly
• Continue with the Upper Completion installation
Formations
Figure 2-1 shows the main stratigraphy for the Goldeneye area with the main characteristics of the
individual formations.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 92
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injecting into Existing Wells
Related to the lower completion: The main reservoir is the Captain D. Captain E is sand with
relatively low permeability above the Captain D. The Rodby shale is the main seal above the Captain
formation. There are some Marls above the Rodby called Hidra and Plenus Marl. The Plenus Marl is
not present in all the Goldeneye producing wells.
Lower Completion description with respect of formation tops
The 9 5/8'' [245mm] casing shoe was set at the Rodby shale (with the exception of GYA05 which
was set at the Valhall formation). The bottom part of the Rodby and the Captain E layer was not
isolated with the casing and as such it is part of the open system of the screens.
The top of the screens is installed above the 9 5/8'' casing shoe. The top of the gravel pack is
estimated to be above the top of the screens in 10-15ft [3-4.6m].
The screen hanger is either set at the Rodby formation or the Hydra formation.
The production packer is either set at the Chalk (GYA01 and GYA05) or within the Marls
(GYA02S1, GYA03 and GYA04).
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 93
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injecting into Existing Wells
No issues have been identified for the long term operation of the CCS in this string.
FIV
A 5.00'' 15 lb/ft 13Cr Formation Isolation Valve (FIV) is installed as part of the lower completion in
all of the Goldeneye wells. In the case of Goldeneye the main purpose of the FIV was to isolate the
reservoir from the well bore post gravel pack operations, and to provide a positive mechanical barrier
to flow when running the completion tubing. The FIV would then have been opened by application
of pressure cycles down the production tubing. It is worth noting however, that remotely opening
the FIV by application of pressure is a feature that can be utilised one time only, repeated application
of tubing pressure will not operate the FIV once it has been opened. Subsequent manipulation of the
FIV requires that a shifting tool be run on coiled tubing or wireline tractor to engage in a shifting
profile inside the FIV. When the shifting tool is locked into the shifting profile a downward force of
circa 1,200 lbs is required to move the FIV in to the closed position. It is not possible to close the
FIV by application of pressure or if the FIV is exposed to large pressure differentials.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 94
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injecting into Existing Wells
Should Goldeneye wells be worked over for CCS operations the FIV will not be removed from the
well. The FIV is made from 13cr material and is considered to be compatible with CO2 providing
that there is no oxygen in the feed gas. The FIV in its current configuration simply becomes another
section of 13Cr tubing and poses no threat to the future integrity of the well. The minimum ID
through the FIV of 2.94'' [74.7mm] although reduced when compared with the proposed CO2
injection wells is sufficient to allow coiled tubing and 2.125'' [53.98mm] O.D wireline logging tools to
be run into the screen section.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 95
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injecting into Existing Wells
hole and the screens. In the CCS, the CO2 will be in contact first with the screen and then the gravel.
The gravel does not play an important role as in the production phase. As such, this limitation can be
lifted.
If the screen is covered with gravel then the pressure drop is significant to be able to inject through
the linear proppant plug. Assuming that a 50 ft/5'' [15.2m/127mm] screen is covered with proppant
of a permeability of 100Darcy then the pressure drop through the proppant plug to be able to inject
the minimum rate of the capture plant of 41 MMscfd (89.9 tonnes/h) would be in the order of 390
bara.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 96
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injecting into Existing Wells
[Link] Erosion
Erosion is one of the most common mechanisms of screen failure. Screen erosion is a progressive
failure that depends on fluid velocity, particle size and concentration and fluid properties. Erosion of
the screen can be caused by the high downhole flow of fluid through the screens. The presence of
solids will increase the erosion rate.
For erosion in the screens, it is normally accepted that particles above 30 microns will significantly
increase the erosion rate. As such, particle size above 30 microns should be avoided.
The aperture velocity (velocity at the slots or open space of the screens has been calculated (assuming
uniform distribution of the fluid in the screen, 10% of open space in the steel of the screens and
considers only the length of the screen at the Captain D) for the different wells considering the
downhole flow rate in the following picture.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 97
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injecting into Existing Wells
Goldeneye
Aperture Velocity (10% mesh area) - Across the Captain D
1
0.9
0.8
Aperture Velocity, ft/s
0.7
GYA01
0.6 GYA02S1
0.5 GYA03
0.4 GYA04
0.3 GYA05
0.2
0.1
0
0 5000 10000 15000 20000
Downhole Rate, m3/d
The gas production at downhole conditions has been estimated using the individual allocated flow
per well, information from the permanent downhole gauges as follows and the PVT properties of the
Goldeneye gas as follows
Goldeneye - HC production
Gas Downhole Production
30,000
25,000
20,000
Flow, m3/d
GY-A01
15,000 GY-A02
GY-A03
10,000 GY-A04
GY-A05
5,000
0
Jan-04
Jan-05
Jan-06
Jan-07
Jan-08
Jan-09
Jan-10
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 98
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injecting into Existing Wells
Goldeneye - HC production
Screens Aperture velocity
1.8
1.6
1.4
1.2
Speed, ft/s
1 GY-A01
GY-A02
0.8 GY-A03
0.6 GY-A04
GY-A05
0.4
0.2
0
Jan-04
Jan-05
Jan-06
Jan-07
Jan-08
Jan-09
Jan-10
Figure 5-3: Aperture velocity in the hydrocarbon production phase (assumes uniform distribution)
At downhole conditions and under steady state conditions the CO2 will be injected in single phase
with low temperatures (20 to 40°C) and bottom hole pressures above the critical point. The bottom
hole injection pressures range would be between 2,900psia [200bara] to 3,800psia [262bara] (250-
400psia [17.2-27.6bara] above the reservoir pressure).
At the expected downhole pressure and temperature conditions the downhole flow rate of the CO2
will depend mainly on the surface injection rate. The pressure and temperature will have a minor
impact considering the steady state conditions of injection. This is due to the relatively stable density
of the CO2 at the bottom hole injection conditions (~920-940 kg/m3).
Goldeneye
10000
9000
CO2 83 degC 150bar
8000
Downhole Rate, m3/d
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 99
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injecting into Existing Wells
injection pressures. However, in the case that the temperature is much higher (around reservoir
temperature 83°C) then the downhole rate will also be variable from 5,000 to 6,000 m3/d.
Table 5-3: Bottomhole pressure and downhole rate relation for Goldeneye wells
During the injection process the CO2 will contact first the screens (Excluder 2000). As such, the
restrictions for stand-alone screens (SAS) related to erosion should be applied (instead of the gravel
pack restrictions). Liquid limitations (instead of gas limitations) should be used as the density of the
CO2 at bottom hole injection conditions will be very high ~920-940 kg/m3. For liquid flow the
normally accepted industry velocity is 1 ft/s for production conditions.
It is clear that the aperture velocity (assuming uniform flow) during the hydrocarbon production
phase is much higher than the expected velocity during the CO2 injection case. In both cases the
aperture velocity is below the threshold velocity. In CO2 it is more variable depending on the
downhole conditions of pressure and temperature because of the CO2 variation with these properties.
However, the aperture velocity assumes uniform flow through the screens. Under production
conditions this can be considered a good approach due to the presence of gravel distributing the flow
– the flow is dispersed and distributed across the screen, which reduces the creation of hot spots.
Under injection conditions the CO2 will be first in contact with the screen increasing the susceptibility
to get plugged. If a large area of the screen is plugged or flow is going through a short interval such
as fractures, the erosion rate can be considerably higher creating a hot spot injection.
Even considering a reduction of the maximum aperture velocity from 1 ft/s to 0.25 ft/s (quarter of
the maximum recommended velocity) due to the reasons described above there will not be any
limitations in the wells with respect to the downhole injection velocity of the CO2 under steady state
conditions.
The main consequences of the calculations are in the well start up procedure. Start-up procedures in
the wells should be developed to be able to cope with the Joule Thomson effect in the top of the well
(rapid injection) and to avoid very high downhole rates created by high rates at warm CO2 conditions
at the screen level after some shut-in period.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 100
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injecting into Existing Wells
By reversing the flow, from the production hydrocarbon production phase to the CO2 injection
phase, there might be some re-accommodation of fines currently embedded in the gravel pack under
hydrocarbon production.
It is likely that sand failure has occurred in Goldeneye due to the level of depletion combined with
the rock strength. Fines have been trapped / embedded in the gravel pack, which is designed for this
function. The well productivity has not decreased with time.
Upon flow reversal the formation fines currently embedded in the gravel pack could be mobilized
and could then become trapped against the formation (like an external filter cake) and would then
create an additional pressure drop thereby reducing the injectivity in the well.
The effect of this pressure drop is considered low due to the following reasons:
- Well productivity stable with time.
Indication of a limited volume of fines being trapped with time as the pressure drop in the
wellbore has been stable.
- Captain D is well sorted sandstone
Completed in the top of the D sand where the sand sorting is better. Fines percentage in the
Captain D is very small
- Gravel pack designed considering the general criteria in the oil industry
- Industry experience in underground storage with sand control
This low risk can be further reduced with an injectivity test. However, the value of information of
carrying an injectivity test just for this cause is low, as the risk is considered manageable.
The mitigation were this issue to occur is to drill a side-track and to install a new gravel pack. This
avoids the trapping of solids in the lower completion during the production phase.
[Link] Filtration
In the event of injection under fracturing conditions, the CO2 quality specification in terms of
suspended solids may be relaxed. The injectivity is not affected as the fracture will grow longer.
In the case of Goldeneye, the lower completion, screens and gravel pack, also imply limitations in
terms of CO2 quality due to erosion / plugging.
To avoid formation impairment under matrix conditions, the CO2 should be filtrated to 5 microns
whilst to avoid blocking of the screens / gravel pack then the CO2 should be filtrated to 17 microns
to avoid lower completion erosion and plugging.
The initial period of CO2 injection will be most likely under matrix condition and 5 microns filtration
will be required. In the case of confirming injection under fracturing conditions, the CO2 quality
might be relaxed to higher value but not above 17 microns in size due to the lower completion
restrictions (erosion / plugging). An evaluation should be done to examine the predicted length of
the fracture once the solids content is known.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 101
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injecting into Existing Wells
In any case, under matrix or under fracturing conditions, the filtration is required and as such there
will not be a big cost difference in terms of the operation.
The drag forces of the injected CO2 might displace the gravel into the propagating fracture, leaving
the space between the hole and the screens without gravel. Some operators have expressed concerns
about formation sand entering the wellbore reducing the general injectivity as the gravel is no longer
between the hole and the screens. However, there is uncertainty in the industry as to whether it is
possible that displacement of gravel into the frac could possibly occur given the mitigating elements
described below:
• Experience gained from working with water injector wells in other developments demonstrates
that not all injection wells experience gravel displacement into the propagating fracture.
• The drag forces of CO2 compared with pure water are much less due to the lower viscosity of
the CO2. Viscosity of water at 20°C is in the order of 0.99cP and CO2 would be in the order
of 0.10cP.
• An “alternate gravel pack” system was used in the Goldeneye wells. Good packing of the
gravel during the initial completion operation was achieved.
• The 7'' [178mm] pre-perforated liner used in the alternate packing system will help with
distributing the CO2 over the screens in the event of fracturing conditions developing.
Even in the event that gravel is displaced into the propagating fracture, the amount of solids from the
formation passing the screens and depositing/filling the wellbore will be limited. The premium
screens have an aperture of 208 microns, which is similar to the average particle diameter (d50) of the
formation sand in the Captain D (d50=230 microns). In addition, the uniformity coefficient of the
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 102
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Injecting into Existing Wells
formation sand was estimated at 2.5. In summary, the screens were also purpose designed for the
formation sand and in the event that the gravel is displaced into the propagating frac, then the lower
completion will behave as a Stand Alone Screen, which is an acceptable completion situation.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 103
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Conceptual Upper Completion Selection
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 104
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Conceptual Upper Completion Selection
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 105
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Conceptual Upper Completion Selection
Well Design (-) Medium complexity. Experience in the gas industry with velocity strings
(+) Simple wellhead
Different tubing sizes required (4 ½” & 3 ½”) in the insert string
Hanger inside the tubing is critical. Pressure sealing required in the top of the
insert string. Extra stresses created by this configuration.
(-) Unable to fix leaking in the completion tubing
Injection Flexibility One string per well. A workover to remove the insert string might be executed
to expand the operating envelope of the well once the reservoir pressure
increases. More applicable to expansion storage projects.
(+) Combination of wells provide the required injection conditions for the
life cycle of the project.
(-) Limited range of injection conditions – depends on tubing size
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 106
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Conceptual Upper Completion Selection
Well Design (-) High complexity. Practically no experience in the North Sea with dual
strings
(-) Dual Xmas tree required. Long lead item. Goldeneye wellhead is not
designed for a dual Xmas tree and tubing hanger. A new build Xmas tree is
likely to be required.
(-) limited combinations in the dual tubings (2 x 2 7/8”, 2 x 3 ½” (?) and 2
7/8” – 31/2”)
Y-tool preferred over dual packer (stronger completion)
(-) impact of tubing stresses when injecting down in the a single string
(-) Mechanical barriers to be recovered through small tubing.
(-) Congested well bay (dual wellhead and dual flowlines)
Injection Flexibility Two string per well.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 107
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Conceptual Upper Completion Selection
(+) Increase flexibility per well (3 different injection sizes: tubing1, tubing 2,
tubing 1 + 2)
(-) Minimum rate required
(-) More difficult inflow calculation. Total capacity of the well should be
approximately ~ 0.85 of the tubing 1 + tubing 2 due to inflow restrictions.
(-) Congested well bay
Well Integrity (+) SSSV depth. 2 SSSV per well operating independently.
(+) PIT per string can be execute
(+) Corrosion log possible
(-) Multiple/complex leak paths
In case of a tubing failure, injection might continue in the well by isolating the
leaking string.
In-well monitoring (-) Limited space in the A-annulus. Ability to install devices depends on the
completion size
(-) PDG below Y-tool. DTS possible in one or both strings depending on
size. Number of penetration increase in the wellhead – confirmation required
of it doability
Well Intervention (+) Doable. Limited ID depending on tubing size and FIV (2.94”)
(+) 2 strings to get access to the wellbore. However, Y-tool will cancel this
option (only one string normally has access to the wellbore)
Life Cycle Cost As a minimum 2 injectors required and 1 back up. Not possible to meet
injection expectations with only one well
(-) Very expensive initial workover
(-) Expensive integrity workover (if required)
(+) no late workover required to meet CCP rates
(-) Expensive abandonment
Well Design (-) High complexity completion. No major experience in the hydrocarbon
industry with concentric completions
(-) Special dual wellhead required (Horizontal tree). Special design required
and long lead item. The current wellhead at Goldeneye is not suitable for
running a concentric completion from surface to require depth.
Different tubing sizes required (4 ½” & 3 ½”) in the inner string
(-) Unable to fix leaking in the completion tubing
(-) Deep set SSSV
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 108
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Conceptual Upper Completion Selection
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 109
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Conceptual Upper Completion Selection
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 110
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Well Construction Elements
reservoir. The number of potential leak paths is high for dual completions. Pressure integrity test in
the downhole choke would be challenging below the valve in case of not able to retrieve the choke.
The single completion tubing and the downhole choke completion present the best option for in-well
monitoring. The in-well monitoring is not ideal in the insert and concentric strings as the temperature
information is from the outer tubing string. Depending on tubing size there might not be enough
space for accommodating all the required devices in a dual completion.
The well intervention for the friction dominated completion concepts is similar. Dual completion
options presents a slightly less than ideal conditions due to the intervention being possible in only
one string if Y-tool options is selected. In the single tapered tubing the only restriction for well
intervention is related to the tubing size (potential landing nipples) and deep in the well by the FIV.
The downhole choke option will have limitations in easy intervention as the restriction would require
to be removed prior to any intervention.
A traffic light can be used to visualise the advantages and disadvantages of the different completion
systems. Green represents ideal conditions and red represent a major concern of the option.
Concern
Small Tubing Big tubing +
Doable (Tapered) Insert String Dual completion Concentric Downhole choke
(Smart)
Ideal
Well Design
Injection Flexibility
Well Integrity
In-well monitoring
Well Intervention
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 111
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Well Construction Elements
• temperature
Limitations of the different well components were investigated for the expected well conditions
under CO2 injection. The Christmas tree and the tubing hanger will be replaced in the workover with
units having a lower minimum temperature rating. All completion equipment (i.e. attached to the
tubing string) will have 13Cr or S13Cr equivalent metallurgy and will have working pressures in
excess of the expected final well pressures.
It is proposed to standardise the top (from surface down to the SSSV) and the bottom (up to the
PDG) of the upper completion for the CO2 injection. The planned well design for CCS is shown in
Figure 7-1.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 112
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Well Construction Elements
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 113
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Well Construction Elements
7.1.3 Elastomers
Elastomers can also absorb gas and suffer explosive decompression when pressure is reduced. Any
elastomers to be in contact with CO2 have been checked for compatibility. Where needed these
elastomers will be changed out.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 114
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Well Construction Elements
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 115
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Well Construction Elements
Even in the scenario of having casing failure and axial cement degradation, the risk of leaking CO2 is
very low. This is based on the estimated matrix properties and the absence of fractures at the Hidra
level. Additionally, during most of the injection period, the pressure of the CO2 downhole will be
lower than the hydrostatic pressure. As such, there is no reason to plan a side-track for the potential
of out of zone injection of the CO2 as the marls above the Rodby also present adequate sealing
characteristics.
In the current well completion, a perforated pup joint is present below the production packer and the
top of the screen hanger; this section creates a dead volume (stagnant) between the tubing and the
production casing. CO2 fluid could find its way through the perforated pup and contact the carbon
steel production casing in the dead area between tubing and casing and potentially cause high levels
of corrosion in the casing. Although this section is below the existing production packer, it is
recommended to remove the perforated tubing section during the workover operations to give more
protection to the casing and to be able to run the new production casing across the Hidra.
Due to injection of cold CO2, the load cases are driven towards tensile loading due to thermal
contraction.
Normal CS (''LT0'') is adequate down to 0°C. For lower temperatures, carbon steel should be impact
tested. Available certificates that supported the quality of the installed production casing were
analysed and recorded Charpy values at different temperatures demonstrating adequate toughness
down to -40°C, well below the worst case lowest casing temperature on injection conditions. If such
information would not have been available, then the next step would be to assess the suitability based
on the design code used, the materials specification and the wall thickness.
7.3 Cement
This section is a summary of the Chapter 4 and Appendices 4 & 5 of the report (PCCS-05-PT-ZW-
7180-00002 Conceptual Completion and Well Intervention Design Report, 2014) where detail
analysis on the cement is presented.
The primary cement sheath of the production casing is a barrier to capture the CO2 downhole in the
well. The cement used in the cementation is normal Portland class G cement.
The theoretical top of the cement (TOC) in the B-annulus between 9 5/8'' [245mm] production
casing and the 10 ¾” [273mm] hole has been estimated for all five wells during the cementing
operations. The cement column from the 9 5/8in casing shoe to the theoretical TOC is calculated at
1,500ft [457m] AHD above the shoe, well above the formation seals of the reservoir. Cement
evaluation logs were not run during the drilling phase of the wells, but are scheduled for the
workover operations.
The cement is considered of good quality, based on well operation records. The historical records
show that the casing integrity is good as a successful pressure test was achieved after bumping the top
of the cement plug during the production casing section. The historical records of top well annuli
pressures also show that no anomalies have been reported in the B annulus pressures during the
production history of Goldeneye.
The distance between the currently installed production packer and the theoretical TOC is between
1,190 and 1,351ft [363m and 412m] AHD depending on the well. The cement is covering the
primary seal formations (Rodby and Hidra) in all five wells up into the Chalk formation. This is
enough cement height to ensure a barrier in the B annulus above the production packer.
Given that the TOC is theoretical, it is recommended to run a cement evaluation tool to better assess
the condition of the cement in the B-annulus during the proposed workovers of the upper
completion.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 116
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Well Construction Elements
The long term effect of CO2 on cement has been investigated. Cement degradation by CO2 in the
form of carbonic acid is a process that produces an insoluble precipitate that slows degradation.
Several recently published papers examine various experiments or case studies that examine the
potential degradation of Portland based cements when exposed to high CO2 environments.
Degradation rates are proportional to temperature, pressure and the square root of time. From
literature, estimates for cement degradation vary from 0.05 m in 10,000 years to 12.36 m in 10,000
years. Goldeneye conditions ~2m in 10,000 years.
Diana software, a specialist mechanical cement model has been run to ascertain the thermal effects of
CO2 injection on Goldeneye. The injection model simulates the thermal effects on the mechanics of
the system (casing / formation / cement). Diana results indicate that the remaining integrity of the
cement is sufficient for CO2 injection in the Goldeneye Platform wells. The remaining capacity of
the cement sheath for various simulated operational scenarios is sufficient for CO2 injection in the
Goldeneye Platform wells.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 117
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Well Construction Elements
As part of the workover operations, the tubing hanger and tree will be installed and pressure tested.
This will then allow for final well hook up and flow of CO2 through the pipeline to the platform.
7.5.1 Tubing
Re-completion of the wells will incorporate changing out of the 7'' [245mm] tubing to a smaller size.
As pressure and CO2 rates will vary during the duration of the project, the injection rates will be
accommodated by different tubing sizes in the injection wells - low rates with smaller tubing and
higher rates with larger tubing, considering the well deviation.
The tubing sizes will be optimised in the later stages of the project when more information is
available, especially regarding the reservoir pressure, injection rates and powerplant power generation
cycles.
The intention is to standardise the top and bottom part of the upper completion. Currently the
preferred tubing size in the top of the well (from the wellhead to the SSSV) is 4½'' [114mm].
The upper completion tubing will be a 13Cr steel tubing material to provide protection of CO2
corrosion. The current view is to install Super 13Cr tubing in the top of the well (from wellhead to
SSSV) which gives more resistance to lower temperatures than 13Cr. For both materials 13Cr and
Super 13Cr, impact testing will be required. In the case 13Cr is resistant to temperatures below the
minimum expected CO2 temperature in the top of the well, 13Cr might be used instead of the Super
13Cr.
Tubing hanger material can be upgraded in line with the increased Xmas tree specification.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 118
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Well Construction Elements
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 119
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Number of Wells
7.7.1 Pressure containment between the lower completion (top of the screens)
and upper completion (tail pipe)
There is the possibility to install a seal assembly in the tail pipe to seal off the casing between the
production packer and the SC-2R screen hanger. This will reduce the exposure of the 9 5/8in casing
to CO2 to below the SC-2R packer. A closed space with stagnant fluid between the packer and the
SC-2R packer (top of the screens) will be created. The main concern is that the cold injection of CO2
will contract the fluid installed in this confined space leading to vacuum conditions, generating loads
to the casing (collapse), tubing (burst) and packer (high differential pressure) which might jeopardise
the well integrity with time.
The other option is to stab the tail pipe into the SC-2R without the sealing mechanism. In this case
more casing is exposed to CO2. There will not be a closed space between the packer and the top of
the screens. This option is preferred as the production packer will be installed at the Hidra level,
which is part of the CO2 subsurface seal and it is expected that dry CO2 will displace and evaporate
water from the wellbore, reducing the corrosion rate of the production casing.
This will be explored in detail in the FEED phase. The options to install pressure relief valves in a
close system will also be investigated.
8 Number of Wells
The Peterhead CCS bid submission, made in mid-2012, included four wells converted for
injection/monitoring, with the recommendation to decide the way forward of the fifth well during
further stages of the project.
The number of require injector wells depends mainly on the injection estimates (reservoir pressure
and injectivity), capture plant rates, CO2 management, monitoring requirements and life cycle risk
management.
The well(s) not converted for CO2 injection will also need to be considered for the Peterhead project.
Options included are to complete as an injector/monitor or to abandon the well.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 120
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Number of Wells
The installation of small bore tubing in the wells limits the operating envelope of each well. In order
to accommodate the range of injection rates at the different reservoir pressures during the injection
life, each well will be completed with a different tubing size/configuration tailored to a specific rate
range. The wells will then have overlapping operating envelopes and any rates specified in the
integrated consortium basis-for-design will then be achievable through the choice of a specific
combination of wells.
The five existing wells will be recompleted for the Peterhead CCS project. Two wells are the absolute
minimum injectors for the life cycle of the project. Two additional wells are required: a back-up and a
monitoring well. The fifth well in the platform will be re-completed based upon a project decision.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 121
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Number of Wells
75% of max.
Minimum (65%) Maximum
89.9 tonnes/h 138 tonnes/h
41 MMscfd 63 MMscfd
GYA_01_02_04
75% of Maximum
GYA01 to cover maximum rate at high P reservoir
GYA02 in the middle of the range at initial P reservoir
GYA04 to cover minimum rate at initial Preservoir
2650psi Resevoir Pressure
GYA01 GYA02 GYA04 GYA05
P reservoir
Minimum Maximum 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66
1 53 76 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
1 44 63 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
1 38 55 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
1
2650psi
1 1 97 139
1 1 91 131
1 1
1 1 82 118
1 1
1 1
1 1 1 135 194
1 1 1
1 1 1
1 1 1
1 1 1 1
2800psi
29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66
1 49 74 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
1 42 61 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
1 37 54 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
1
1 1 91 135
1 1 86 128
1 1
1 1 79 115
1 1
1 1
1 1 1 128 189
1 1 1
1 1 1
1 1 1
1 1 1 1
1 45 72 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
1 39 59 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
2950psi
1 34 52 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
1
1 1 85 131
1 1 80 124
1 1
1 1 73 111
1 1
1 1
1 1 1 119 183
1 1 1
1 1 1
1 1 1
1 1 1 1
1 42 70 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
1 36 57 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
3100psi
1 32 50 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
1
1 1 78 127
1 1 74 120
1 1
1 1 68 107
1 1
1 1
1 1 1 110 177
1 1 1
1 1 1
1 1 1
1 1 1 1
3250psi
1 38 67 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
1 33 57 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
1 29 50 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
1
1 1 71 122
1 1 67 115
1 1
1 1 62 103 xxx xxx xxx xxx xxx
1 1
1 1
1 1 1 100 170
1 1 1
1 1 1
1 1 1
1 1 1 1
1 33 63 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
1 29 53 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
3400psi
1 25 46 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
1
1 1 62 116 xxx xxx xxx xxx xxx
1 1 58 109 xxx xxx xxx xxx xxx xxx xxx xxx xxx
1 1
1 1 54 99 xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
1 1
1 1
1 1 1 87 162
1 1 1
1 1 1
1 1 1
1 1 1 1
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 122
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Number of Wells
A single well will not be able to inject from the minimum to the maximum CO2 injection rate for the
duration of the project. This is due to the limited injection envelope per well and the increase in
reservoir pressure with injected CO2.
The range of injection from the minimum to the maximum of the capture plant at the predicted
reservoir pressure evolution can theoretically be achieved with only two wells. A small well might
likely be injecting during the initial years of the project when the reservoir pressure is relatively low. A
big well will likely be used when the reservoir pressure exceeds 2950psia [203bara].
In case of unforeseen problems in a particular injector well, it is proposed to complete an additional
or back-up well as a CO2 injector to the number of wells required to cover the injection range. As
such, at least three wells are required to be completed as injectors (observed in the “Organ Pipe”).
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 124
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Other Production Technology Aspects
CITHP vs Preservoir
(Geothermal Gradient)
70
60
50
CITHP, bar
40
30
20
10
0
2000 30002500 3500 4000
Preservoir, psi
Figure 9-1: CITHP for a well filled with CO2
In case that the well is full of hydrocarbon gas then the CITHP at the same 3500psia reservoir
pressure would be in the order of 205bara (assuming methane filling the tubing), see Figure 9-2
200
150
CITHP, bar
100
50
0
2500 2700 2900 3100 3300 3500 3700 3900
Bottom Hole Pressure, psi
CITHP
below.
Figure 9-2: CITHP for a well with Methane in the tubing
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 125
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Other Production Technology Aspects
9.2.2 Scenarios
The tubing will be left after the commissioning/workover operations with water/brine and probably
a N2 cushion in the top of the well. The reservoir currently has gas and water and the reservoir
pressure is increasing with time even without CO2 injection due to the aquifer strength. The reservoir
pressure will increase faster with CO2 injection.
CO2 will be injected into the wells displacing initially the water/N2 from the well. If CO2 continues
for long time in the same well then the expected fluid inside the well is CO2 when the well is closed
in.
However, if the well is left closed-in for a long time and because of the increase of reservoir pressure
(by the aquifer or CO2 injection in another well), fluid segregation in the reservoir (gas moving to the
top of the reservoir) and a potential arrival of a hydrocarbon bank displaced by the CO2 plume
(injected into another well) then the CO2 inside the tubing can be displaced to hydrocarbon. Under
this scenario the wellhead pressure will increase to the hydrocarbon case.
The monitoring well will be left closed-in for a long time. It is likely in this well to have a scenario
where the water left in the well after the workover is displaced by hydrocarbon gas considering the
increase in reservoir pressure (with / without CO2 injection), segregation of fluids in the tubing and
the arrival of a hydrocarbon bank into the well before the CO2 breakthrough. CO2 breakthrough will
take place in the monitoring well at around 10 Mt of injection, near the end of injection.
If the wells are filled with hydrocarbon gas then CO2 cannot be injected in the wells due to the higher
CITHP than the available CO2 pressure.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 126
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Other Production Technology Aspects
Captain sandstone: Formation receiving the CO2. It will contain hydrocarbon, water and CO2.
Hydrostatically pressured (~3500-3800 psia [~241-262bara]) or slightly depleted after CO2
injection. The primary seal for the Captain reservoir is the Rodby shales/Hidra marl. These
formations are impermeable, strong and about 500ft [152m] in vertical thickness. In Goldeneye,
these formations are positioned right above the Captain reservoir.
Tertiary sandstones (Balmoral, Dornoch): water bearing, hydrostatically pressured. However, in
case of CO2 leakage into this formation then CO2 will need to be considered for the
abandonment. The Balmoral sandstone formation is contained by the Lista shales.
• Number of cement plugs
Over-pressured permeable zones (both water and hydrocarbon bearing) and normally
pressured permeable zones containing hydrocarbons require a minimum of two Permanent
(abandonment) barriers between the permeable zone and seabed/surface.
Normally pressured permeable zones containing water require one Permanent (abandonment)
barrier between the permeable zone and seabed/surface.
• Cement
The reference case for cement plugs is Portland cement. The type of cement to be used will be
reviewed later and may include CO2 resistant additives. Some alternatives to cement (like resins,
etc.) may be considered as well. This will be influenced by the best practices and standards of
the day at the time of abandoning.
• Geometry of cement plug
Two options exist for the primary seal: rock to rock cement plug or internal and external with
pipe.
The reference case for cement plugs is Portland cement. The type of cement to be used will be
reviewed later and may include CO2 resistant additives. Some alternatives to cement (like resins,
etc.) may be considered as well. This will be influenced by the best practices and standards of
the day at the time of abandoning.
Different options exist for abandoning the injection wells. The reservoir abandonment will be
selected close to the time of abandonment.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 127
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT References
References
Baklid, Alan. 1996. SPE 36600, Sleipner Vest CO2 disposal, CO2 injection into a shallow underground aquifer.
1996.
Bellarby, Jonathan. 2009. Well Completion Design. s.l. : Elseiver, 2009. 978-0-444-53210-7.
Dendy Sloan, Jnr. 2000. Hydrate Engineering. Monograph Volume 21 SPE. 2000.
Haigh, M.J. 2009. SPE 124274 Well Design Differentiators for CO2 Sequestration in Depleted Reservoirs.
2009.
Hansen, Olav. 2013. Snohvit: The history of injecting and storing 1 Mt Co2 in the fluvia Tuaben formation.
2013. Paper presented in the GHGT-11.
Paterson, Lincoln. 2008. SPE115946 Numerical Modeling of Pressure and Temperature Profiles including
phase trasnitions in Carbon Dioxide wells. 2008.
PCCS-05-PT-ZG-05800-00004 Static Model (Field) Report. 2013. Peterhead Goldeneye CCS. 2013.
Key Knowledge Deliverable 11.108.
PCCS-05-PT-ZP-9025-00004 Geomechanics Report. 2014. Peterhead Goldeneye CCS. 2014. Key
Knowledge Deliverable 11.115.
PCCS-05-PT-ZW-7180-00001 Abandonment Concept for Injection Wells. 2014. Peterhead
Goldeneye CCS. 2014. Key Knowledge Deliverable 11.100.
PCCS-05-PT-ZW-7180-00002 Conceptual Completion & Well Intervention Design Report.
2014. Peterhead CCS Project. 2014. Key Knowledge Deliverable 11.093.
PCCS-05-PT-ZW-7180-00003 Well Completion Concept Select Report. 2014. Petehead CCS.
2014. Key Knowledge Deliverable 11.097.
PCCS-05-PT-ZW-7180-00004 Well Integrity Assessment Report. 2014. Peterhead Goldeneye CCS.
2014. Key Knowledge Deliverable 11.113.
Skinner, Lee. 2003. CO2 blowouts: An emerging problem. s.l. : World Oil Magazine, January 2003, 2003.
TNO-RPT-DTS-2011-00573. 2010. CCS Vibration Study: An assessment for Shell UK Ltd on tubing
vibrations due to high velocity fluid CO2 injection. 2010.
UKCCS-KT-S7.18-Shell-001 Temperature and Pressure Modelling (for CO2 injection wells -
Goldeneye CCS). 2010. ScottishPower Consortium UKCCS Demostration Project. 2010.
UKCCS-KT-S7.18-Shell-002 Injectivity Analysis Preparation. 2010. Scottish Power Consortium
UKCCS Demostration Competition. 2010.
UKCCS-KT-S7.18-Shell-003 Flowline Well Interactions. 2011. Scottish Consortium UKCCS
Demonstration Comnpetition. 2011.
UKCCS-KT-S7.18-Shell-005. 2011. Scottish Consortium UKCCS Demostration Competition. 2011.
UKCCS-KT-S7.19-Shell-001 - Wells Fluid Assurance & Technical Design. 2010. Scottish Power
Consortium UK CCS Competition. 2010.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 128
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS [Link] of new wells: CO2 expansion in the tubing
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 129
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS [Link] of new wells: CO2 expansion in the tubing
A1.2.1 Drilling
No changes are expected in the undepleted overburden in the case of drilling of new wells. Learning
from the previous Goldeneye wells should be included.
The degree of depletion in the reservoir will depend on the time that the well is drilled. Drilling of
the undepleted overburden with the depleted Captain needs to be properly managed to avoid well
drilling issues and impairment to the formation.
The Rodby shale should ideally be isolated from any sand control devices to avoid high skin in the
wells as observed in the existing platform wells. This needs to be evaluated with respect to the
position of the casing points and well control.
In case of drilling deeper of the Captain D then reservoir pressure uncertainty should be considered
in the drilling design. This will impact the selection of the lower completion.
A1.2.4. Cement
The primary cement sheath of the production casing is a barrier to contain the CO2 downhole in the
well. Portland cement (installed in the existing wells) is suited for CO2 conditions. Choice between
the use of Portland cement and CO2 resistant cement should be evaluated during considering the
advantages, disadvantages of both system and the operational experience worldwide.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 130
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS [Link] of new wells: CO2 expansion in the tubing
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 131
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS [Link] of new wells: CO2 expansion in the tubing
Table A0-1: Workover with the current friction concept and drilling new wells. Advantages and
disadvantages.
Existing Platform Wells New Platform Wells
Workover with single tapered tubing (for two phase injectors)
(+) Green project. Re-use of the existing (-) More penetrations in the overburden.
General
infrastructure. Increases the risk of a leak.
(+) Reduced uncertainty. Wells (+) Might increase flexibility in injection
completed in the top part of the Captain point.
D. (-) Low temperature in the top of the well
(down to -2600ft at low reservoir pressure)
and the Xmas tree area.
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 132
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS [Link] of new wells: CO2 expansion in the tubing
(-) limitations of -18°C in the wellhead (+) wellhead / Xmas tree can be installed to
Integrity
system -60°C
(+) Xmas tree can be changed to -60°C
(+) Known hydrocarbon production (-) More uncertainty in injectivity. High skin
Injectivity
properties. might be expected due to drilling in
Filtration required to ensure long term depleted reservoir.
injectivity
(+) Easy access to the wells (+) Easy access to the wells.
MMV / WRM
(+) Ability to design the well for the
instrumentation to be closer to the
formation than existing wells.
(-) Any injector well will have a (+) No minimum rate. Variable flow might
Well Operations
minimum rate dictated by the CO2 be accommodated in a single well.
phase management.
(+) Management of CO2 rate optimized
with the number of wells
5 wells to be worked over. (2 required Requires the abandonment of the existing
Well Requirement
for injection, 1 back up, 1 monitoring wells + the cost of drilling at least 2 wells.
well and 1 conversion to injector
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 133
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Glossary of terms
10 Glossary of terms
Term Definition
′′ Inches [1′′ = 25.4mm]
13Cr 13 percent chrome content metallurgy
1D, 2D, 3D One, two, three Dimensional
'A' annulus Annulus between the production tubing and production casing string
Annuli The space between adjacent strings of tubing or casing
'B' annulus Annulus between the production casing and intermediate casing string
bara Standard measure of pressure [1bara = 100,000Pa]
Barrier Barriers prevent of mitigate the probability of each threat or prevent, limit the extent of, or
provide immediate recovery from the Consequences
Base oil Oil with carcinogenic elements removed
BHP Bottom Hole Pressure
BHP&T Bottom Hole Pressure and Temperature
Cap rock The shale layers above a reservoir that provide geological isolation to upward migration
and provide the primary seal
CBIL Circumferential Borehole Imaging Log
CBL Cement Bond Logging
CCP Carbon Capture Plant
CCS Carbon, Capture and Storage
CDT Conductivity Depth and Temperature
Cement Injection of cement to isolate a leak in the cement behind casing
squeeze
CITHP Closed in Tubing Head Pressure
CO2 Carbon Dioxide
Completion The conduit for production or injection between the surface facilities and the reservoir.
The upper completion comprises the tubing and packer, etc. The reservoir completion is
the screens, etc., across the reservoir interval.
CoP Cessation of Production
CRA Corrosion Resistant Alloys
CTU Coil Tubing Unit
DAS Distributed Acoustic Sensing
DECC Department of Energy and Climate Change
DIANA Software package from TNO that solves, with the aid of FEM, problems relating to design
and assessment activities in concrete, steel, soil, rock and soil-structure.
DP Differential Pressure
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 134
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Glossary of terms
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 135
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Glossary of terms
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 136
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Glossary of terms
Seepage Migrated CO2 out of the containment that seeps into the biosphere (shallow subsurface
and atmosphere). In contrast to leakage, seepage involves low fluxes and low
concentrations
SEM Scanning Electron Microscope
Sh Minimum Horizontal Stress
SITs Non-flow wetted tests
SRM Static Reservoir Model
SSSV SubSurface Safety Valve
Straddle A device comprising two packers and tubing designed to isolate leaking tubing or casing
TDS Total Dissolved Solids
Threat Means by which a hazard can be released and thus cause the top event
TNO Netherlands organization for applied scientific research
Nederlandse Organisatie voor Toegepast Natuurwetenschappelijk Onderzoek
TOC Top of Cement
Top Event Incident that occurs when a hazard is realized, or the release of the hazard. The Top Event
is typically some type of loss of control or release of energy. If this event can be prevented
there can be no effect or consequence from the hazard
TVD True Vertical Depth
TVDss True Vertical Depth sub-sea
UCS Unconfined Compressive Strength
UGS Underground Gas Storage
UKCS United Kingdom Continental Shelf
Under ream To mill out a section of casing / cement by the use of an expandable milling bit
USIT Ultrasonic Imaging Tool
VIT Vacuum Insulated Tubing
VOI Value of Information
WFS Well Functional Specification
WITs Well Integrity Tests
XLOT Extended Leak Off Test
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 137
The information contained on this page is subject to the disclosure on the front page of this document.
PETERHEAD CCS PROJECT Glossary of Unit Conversions
Doc. no.: PCCS-05-PT-ZW-7180-00003 – Well Completion Concept Select Report Revision: K02 138
The information contained on this page is subject to the disclosure on the front page of this document.