DV Hotel Network Infrastructure

The document outlines the hardware, software, project phases, activities, manpower, internet connectivity, physical topology, disaster recovery plan, maintenance strategy, and troubleshooting records for a DV Hotel network infrastructure project. The total estimated hardware cost is 3852500 Birr and the total estimated software cost is 11850 Birr. The project phases include planning, requirement identification, design, configuration, testing and maintenance. Responsible roles include the project manager, network administrator, lab technician, purchaser, and labor.

Uploaded by

Yenewub Damtea
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
800 views5 pages

DV Hotel Network Infrastructure

The document outlines the hardware, software, project phases, activities, manpower, internet connectivity, physical topology, disaster recovery plan, maintenance strategy, and troubleshooting records for a DV Hotel network infrastructure project. The total estimated hardware cost is 3852500 Birr and the total estimated software cost is 11850 Birr. The project phases include planning, requirement identification, design, configuration, testing and maintenance. Responsible roles include the project manager, network administrator, lab technician, purchaser, and labor.

Uploaded by

Yenewub Damtea
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

DV Hotel network infrastructure

Hardware requirement
NO Item Specification /description Quantity Unit Total
price price
1 Server computer Dell power Edge Cisco RAM 16 GB 5 300,000 1500000
Hard disk drive 5TR
2 Client Computer Dell core i7 8GB RAM 3.0GHZ 15 75,000 1125000
3 Printer HP 1400M 9 35000 210000
4 Access switch Cisco switch D_link 48 port 6 95000 570000
5 Distribution switch Cisco catalyst DS switch 1 200,000 200000
6 UPS 3000V 2 10,000 20000
7 Fan Fan/Ventilator 1 5000 5000
8 Tester Standard 5 1500 75000
9 crimper Standard 5 1500 75000
10 Jack connector Rj45 1000 5 5000
11 Cable UTP cat6 cable 5 role 8000 40000
12 well outlet 4 port 10 1000 10000
13 WAP 450MB 6 5000 30000
14 Firewall Cisco firewall 9010 1 75000 75000
15 Rack amount Server rack standard 1 50,000 50000
16 Total hardware cost = 3852500

Software requirement of the project

NO Item Specification /description Quantity Unit price Total


price
1 NOS Window server 2012R2 5cd 750 3750
2 Operating system Window 10 pro 5cd 500 2500
3 Utility software Kaspersky Antivirus 5cd 500 2500
4 Driver Driver pack solution 2cd 500 1000
5 Visio Microsoft Visio 2010 2cd 200 400
6 Browser Chrome ,Mozilla ,fire fox Free Free download free
7 SQL server SQL server 2012R2 5cd 500 2500
8 MS Office Microsoft office 2010 5cd 200 1000
Total software cost 11850
Project phase and Activity
NO Phase of the project Activity to be performed Duration Responsible body
1 Planning  Plan the project 2 week Project Manager
 visit site Network
Administrator
2 Identify requirement  Select appropriate 5 Week Lab Technician
device Network
 Purchas procurement Administrator
3 Design  Select best topology 4 Week Lab Technician
Network
Administrator
4 Configuration  Configure router cable 2 month Lab Technician
switch Access switch Network
Administrator
Labor
5 Testing & maintenance  Test cable test 2 week Lab Technician
network configuration Network
All device Administrator
6 Presentation and  Prepare Manual for 2 week Manager Network
documentation Users Administrator
 Prepare
troubleshooting
documentation

No Manpower/name Quantity Salary in birr


1 Project Manager Abebe 1 50000
2 Network Administrator Kebede & XYZ 2 15000
3 Lab Technician Selam , tedi, abe 3 10000
4 Labor Yonas,tedi,… 5 40000
5 Purchaser Tigsist,desta 2 15000
Total birr 130000

Internet connectivity
Internet service type Bandwidth Cost per month
Fiber optics 50MB 15000
Physical topology

Prepare disaster recovery

Introduction

DV hotel is implementing network infrastructure now any disaster is occur any time like man made
natural so be safe the data backup software incremental.

Prepare disaster recovery

R.n Expected Disaster Type category/ of Recovery plan action


disaster
1 Man made low Security gured install
CCTV camera crosstalk
2 Natural disaster High To build the
infrastructure cheek
environment place
3 Hybrid disaster Medium Cheek build
organization

Prepare maintenance strategy

Preventive maintenance

1. Clean pc
2. Defragmentation
3. Install antivirus
4. Scan computer

Corrective maintenance
1. Correct hardware failed
2. Correct expired SW(un Licensed)

 use backup software incremental in 6:0pM


Prepare phase security incident
 use licensed software
 protect and secure firewall
 use strong password
Prepare records
R.N Client name Assigned Experts Referred to Solution Remark
1 Aynalem Damena Restart the computer and S002
install new Software
2 Kebede Kedir Cheek HTTP,IP Browser S001
3 Solomon NIgist Configure Wireless Access s006
point check cable
4 Tsehay Alula Cheek the cable before S005
plug cut change cable
board
5 Tola aster Connect VGA cable or S003s004
check projector port
6 Sena Robera Check electric circuit and
change