ABB Consulting
Introduction to IEC61508 and
Functional Safety
© ABB Group
July 31, 2014 | Slide 1
Why have Functional Safety Systems?
To prevent risk to people, environment and business
HOW ?
By good management safety and quality systems
Design to standards / best practices
Using competent resources to deliver
WHAT HAPPENS IF THESE GO WRONG ?
Have You Been Asked This?
‘Regulator’
“How can you demonstrate that you are safe?”
Safety Issues for End User / Operators
How do you demonstrate that your operations are ‘safe’?
How do you demonstrate that your equipment is ‘safe’?
How do you demonstrate that your safety and protective
systems protect against your hazards?
You can answer these questions by demonstrating
compliance with Industry Safety Standards
IEC61508 - Functional safety of
electrical / electronic / programmable electronic
safety-related systems
What is IEC61508?
An international standard relating to the Functional Safety
of electrical / electronic / programmable electronic safety
related systems
Mainly concerned with E/E/PE safety-related systems
whose failure could have an impact on the safety of
persons and/or the environment
Could also be used to specify any E/E/PE system used
for the protection of equipment or product
It is an industry best practice standard to enable you to
reduce the risk of a hazardous event to a tolerable level
Features of IEC61508
Generic Standard which may be applied by all Sector variants
(machinery, process plant, medical, rail)
International standard - end users and suppliers operate
internationally
Guidance on use of Electrical, Electronic and Programmable
Electronic Systems which perform safety functions
Comprehensive approach involving concepts of Safety Lifecycle
and all elements of protective system
Risk-based approach leading to determination of Safety Integrity
Levels (S.I.Ls) - measures proportionate to the risk reduction
required
Considers the entire Safety Critical Loop
Aims to facilitate improvements in both safety and economic
performance through effective use of the (PES) technology
Overall Safety Lifecycle in IEC 61508
1 Concept
2 Overall Scope Definition
3 Hazard Risk Analysis
4 Overall Safety Requirements
5 Safety Requirements Allocation
Overall Planning Safety Related Systems: Safety Related Systems: External Risk
E / E / PES Other Technology Reduction Facilities
Overall Overall 9 10 11
Overall
Operational Installation and
6 7 Validation 8
and Maintenance Commissioning Realisation Realisation Realisation
Planning
Planning Planning
12 Overall Installation and Commissioning
Back to appropriate
13 Overall Safety Validation
overall safety lifecycle phase
14 Overall Operation and Maintenance 15 Overall Modification and Retrofit
16 Decommissioning
Why this lifecycle ?
Maps directly to the normal work pattern of the project in a ‘cradle-
to-grave’ process.
Maps directly to asset life cycle
Seen by the Regulatory Authorities as industry best practice
Can be used in any business, any sector.
Applies to all aspects of the end user supply chain relationship
Will be used to demonstrate regulatory compliance
Generates efficiencies in ‘cost of safety’
Common terminology
Defined document / responsibility interfaces throughout the
supply chain
Common practices
Summary of the Key Messages in IEC 61508
Safety Management System
Life cycle
Planning
Assessing compliance
Supply chain
Technical Requirements
Choice of technologies
Assessment of risk
Specifications of function & integrity level
Competencies
Roles & responsibilities
Skills & training
Benefits of a Safety Management System
A defensible method of managing risks
Coherent approach to the whole subject
Facilitates specification, design and purchase
Allows self regulation
What is Risk?
The probable rate of occurrence of a hazard causing harm
AND
the degree of severity of the harm
Qualitatively - Words
Quantitatively - Figures
Risk and Determination of Safety Integrity Levels
Basic
Design
Unacceptable
Increasing Severity
No
Protection
Increasing Likelihood
Levels of Risk and ALARP
Risk cannot be justified except in
Unacceptable Risk
extraordinary circumstances
Tolerable only if risk reduction is
The ALARP or
impracticable or if its cost is grossly
Tolerability Region
disproportionate to the improvement
gained
As risk is reduced, there is a proportional
(Risk is undertaken only if a
decrease in the cost of further reduction,
benefit is desired)
this concept of diminishing proportion is
represented by the triangle.
Broadly acceptable risk Necessary to maintain assurance that risk
remains at this level
(No need for detailed working
to demonstrate ALARP)
Negligible risk
Risk reduction: General concepts
Actual risk Risk to meet Plant under
remaining level of safety Control risk
Necessary minimum risk reduction Increasing risk
Actual risk reduction
Partial risk covered
Partial risk covered Partial risk covered
by other technology
by E/E/PES by External Risk
safety-related
protective systems Reduction Facilities
systems
Risk reduction achieved by all protective systems
and external risk reduction facilities
Technologies Under Consideration
Electrical
Electro-mechanical / relays / interlocks
Electronic
Solid state electronics
Programmable Electronic Systems
Programmable Logic Controllers (PLC’s);
Microprocessor based systems
Distributed Control Systems
Other computer based devices
(“smart” sensors / transmitters / actuators)
Extent of a E/E/PE safety-related system
Equipment Under Control
SENSOR PE ACTUATOR
PE = Programmable Element
Example method of calculating a Target Safety Integrity
Level
Hazard studies and HAZOPs
Evaluate possible consequences
Establish tolerable frequencies vs ALARP
Build event chain
Estimate demand rates
Define protection required
Specify required Safety Integrity Level
Risk Reduction Requirements
Safety Integrity Level Risk Reduction
1 10 - 100
2 100 - 1,000
3 1,000 - 10,000
4 10,000 - 100,000
Reliability, Failure Rate and Availability at each level
Probability of failure Trip Unavailable
Reliability
on demand (per year)
SIL 1 90% - 99% 0.1 to 0.01 876 to 87.6hrs
SIL 2 99% - 99.9% 0.01 to 0.001 87.6 to 8.76hrs
SIL 3 99.9% - 99.99% 0.001 to 0.0001 8.76hrs to 52.6 mins
SIL 4 99.99% - 99.999% 0.0001 to 0.00001 52.6 mins to 5.3 mins
Protective System Technology
SIL 1 Standard components, single channel or twin non-diverse channels
Standard components, 1 out of 2 or 2 out of 3, possible need for some
SIL 2 diversity. Allowance for common-cause failures needed
Multiple channel with diversity on sensing and actuation. Common-cause
SIL 3 failures a major consideration. Should rarely be required in process
industry
SIL 4 Specialist design. Should never be required in the Process Industry
Protective System Design, Test and Maintenance
Requirements
SIL 1 Relatively inexpensive to design, build and maintain
Test interval unlikely to be less than 3 months
Moderately expensive to design, build and maintain
SIL 2 Test interval unlikely to be more than 3 months
SIL 3 Expensive to design, build and maintain
Test interval likely to be 1 month
Extremely expensive to design, build and maintain
SIL 4 Test interval as for SIL 3 (diminishing returns below 1 month)
IEC 61508 - ownership of phases
PRE-DESIGN
(Phases 1 to 5)
End user / operator
DESIGN AND
Engineering Contractors
INSTALLATION
(Phases 6 to 13) / Equipment Supplier
OPERATION
(Phases 14 to 16)
End user / operator
Pre-Design: Phases 1 - 5
1 Concept
Can you demonstrate that you
2 Overall Scope Definition have identified all your hazards?
3 Hazard Risk Analysis
4 Overall Safety Requirements Can you demonstrate that
you are using adequate
and correct methods of
hazard protection?
5 Safety Requirements Allocation
Design & Implementation : Phases 6 - 13
How do you ensure competencies
for all these activities?
Overall Planning
Can you demonstrate that you pass the
Overall Overall
Operational
Overall
Installation and necessary information into these activities?
6 7 Validation 8
and Maintenance Commissioning
Planning
Planning Planning
Safety Related Safety Related External Risk
Systems: Systems: Reduction
E / E / PES Other Technology Facilities
9 10 11
Realisation Realisation Realisation
12 Overall Installation and Commissioning
Can you demonstrate that all necessary
information has been passed to you from these
activities?
13 Overall Safety Validation
© ABB Group
July 31, 2014 | Slide 25
Operation : Phases 14 - 16
Can you demonstrate that you
14 Overall Operation and Maintenance maintain / test / analyse your
protective systems correctly?
Can you demonstrate that you
15 Overall Modification and Retrofit are in control of your
modification process?
16 Decommissioning
IEC 61508 - Three Phases for Protective Functions
PRE-DESIGN
Set the Target SIL End user / operator
(Phases 1 to 5)
DESIGN AND
Engineering Contractors
Designed SIL INSTALLATION
/ Equipment Supplier
(Phases 6 to 13)
Demonstrate OPERATION
End user / operator
Achieved = Design = Target (Phases 14 to 16)
IEC 61508 Responsibilities: End Users / Operators
Functional Safety Specification Requirements
Contribution from all Safety Function Technologies and
Risk Reduction Methods
Target SIL for the E/E/PES contribution
Overall Responsibility for the Management of Functional
Safety
Functional Safety Plan at the outset of the work -
Identification of Functional Safety Assessments for the
project duration
Overall Validation and Verification
Commissioning and acceptance
Operations and Maintenance
Modification and Retrofit
© ABB Group
July 31, 2014 | Slide 29