MOS Installation of 200A MCCB

The document provides instructions for installing a 200A MCCB at an existing LVAC board. It details the necessary tools, materials, safety procedures and steps to isolate the board, install the MCCB, terminate wiring and restore power. The work requires a 1 hour outage and coordination between SESB and Penulaju staff.

Uploaded by

Fadzli Maddy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
149 views4 pages

MOS Installation of 200A MCCB

The document provides instructions for installing a 200A MCCB at an existing LVAC board. It details the necessary tools, materials, safety procedures and steps to isolate the board, install the MCCB, terminate wiring and restore power. The work requires a 1 hour outage and coordination between SESB and Penulaju staff.

Uploaded by

Fadzli Maddy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

MOS FOR THE INSTALLATION OF THE 200A MCCB AT LVAC BOARD AT EXISTING 132/33 kV PMU DAM ROAD

Introduc on

To install 1 nos. 200A TPN MCCB at the Right Hand Side of the LVAC Board.

The 200A MCCB will be installed at the bo"om of the LVAC Board as per illustra&on in the picture.

The 1600A ACB from 132/33 kV 60/90 MVA TX No.2 shall be “OFF” (132/33 kV 60/90 MVA shall be remind “ON”)

The power supply at the RIGHT HAND side of the LVAC Board will be interrupted for a dura&on of 1 hour for the connec&on of
the wire from the 200A MCCB to the Main Busbar.

There is no outage require during the installa&on of the 200A MCCB and prepara&on of the wire work to minimise the outage
dura&on.

60/90 MVA 132/33 kV TX 1 was connected to the Right Hand side of the LVAC Board

There is the External LV connected to the Le; Hand side of the LVAC Board.

A visit to site to study for the outage plan is required for both SESB and Penulaju

The followings are the circuits and status of the MCCB and mcb at the Right Hand side of the LVAC Board at site.

No. MCCB Status No. MCCB Status No. MCCB Status


1 33 kV Oil Filtra&on OFF 7 Spare OFF 13 132/33 kV TX1 ON
2 100A 33 kV Oil Filtra&on OFF 8 Outgoing Chamber 14 H00-001 ON
3 No Nomenclature ON 9 Substa&on Aircon (DB-P) ON 15 132 kV Control Relay Panel ON
4 DC To Charger No.2 ON 10 Filtra&on ON 16 33 kV Swgr Panel (HS01) ON
5 Building DB ON 11 Spare ON 17 110VDC Charger 1 ON
6 mcb (no nomenclature OFF 12 132/33 kV TX 1 RTCC ON 18 110VC Charger 2 ON

Page 1 of 4
MOS FOR THE INSTALLATION OF THE 200A MCCB AT LVAC BOARD AT EXISTING 132/33 kV PMU DAM ROAD

During this 1 hour outage, Building Ligh&ng & Power will be without any power supply for 1 hour.

Substa&on Air Condi&oner (DB-P) will be without any power supply for 1 hour.

132/33 kV RTCC 1 will be without AC Power for 1 hour

110VDC Charger will be without power supply for 1 hour

Tools & Test Instrument

I. Drill & Metal Drill Bits


II. Jig Saw & Metal Jigsaw Plate
III. Safety Goggle
IV. Insula&on Glove
V. Mul&meter
VI. Phase Rota&on Meter

Material

I. 200A TPN MCCB


II. Short length 35mm2 CU/PVC (2 Wire Per Phase)
III. 35mm2 Cable Lugs
IV. Neutral Link
V. Small screw and small miscellaneous hardware

Page 2 of 4
MOS FOR THE INSTALLATION OF THE 200A MCCB AT LVAC BOARD AT EXISTING 132/33 kV PMU DAM ROAD

Method Of Statement

No. Descrip on Dura on SESB Penulaju Remarks


1 Safety Briefing by SESB 15 Minutes √ √
2 Issue/ Received Permit To Work 15 Minutes √ √
CuIng the front panel, install 200A TPN No outage is required
3 3 Hours √
MCCB and Neutral Link
Compressed the Cable Lug, bending the
4 1 Hour √
wire.
5 Measure the Voltage and record 5 Minutes √ No outage is required
6 Measure the Phase Rota&on 5 Minutes √
7 OFF DC Charger 1 1 Hour √ Outage
8 OFF DC Charger 2 1 Hour √
9 OFF DC Charger 2 1 Hour √
“OFF” Incoming 60/90 MVA 132/33 kV TX 60/90 MVA TX 132/33 kV ACB remain “ON”
10 5 Minutes √
#1 ACB at LVAC Board
11 “OFF” Bus Sec&on 5 Minutes √
Measure the Voltage to confirm that the
12 10 Minutes √
Right Hand Side Busbar is “OFF”
Installed the 35mm2 Wire and terminated Insulated Hand Glove shall be wore during
13 to the Right Hand Side Busbar and 200A √ the connec&on of the wire to the Main
TPN MCCB and Neutral Link 1 Hour Busbar
Physical check whether there is any
14 √
damage to the wire
“CLOSE” Incoming 60/90 MVA 132/33 kV
15 10 Minutes √
TX #1 ACB
Measure the voltage at the 200A TPN
16 5 Minutes √
MCCB
17 Test the Phase Rota&on 5 Minutes √

Page 3 of 4
MOS FOR THE INSTALLATION OF THE 200A MCCB AT LVAC BOARD AT EXISTING 132/33 kV PMU DAM ROAD

Page 4 of 4