0% found this document useful (0 votes)
17 views1 page

Golf Cart Path Grading Plan Review

Uploaded by

Nine Five
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views1 page

Golf Cart Path Grading Plan Review

Uploaded by

Nine Five
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Comments Sheet

Golf Cart Path Grading Plan Area 10, 11 & 12 @ Hole No. 05
QC911000-SLC-DRW-SDW-CIV-11A-11A-05010
Subject;
Workflow Ref. No. Date 21-May QC911000-SLC-DRW-SDW-CIV-11A-11A-05010 Comment Sheet Reference No. QC911000-SLC-DRW-SDW-CIV-11A-11A-05011
Document Reference;
QC911000-SLC-DRW-SDW-CIV-11A-11A-05011 QC911000-SLC-DRW-SDW-CIV-11A-11A-05012
QC911000-SLC-DRW-SDW-CIV-11A-11A-05012

Comments Status Definitions: Final Status Code: B

Closed - Comment Incorporated Pending - Response Pending Reviewed by:


No further action required
Agreed - Resolution to comment and timescale for action agreed Approved by:

Sn. No. Type (Discipline) Organisation Reviewer Date Drawing/Document Subject QIC Team Comments Contractor Response Comments / Clarifications From Review Close Out Date Status
Date Received by DT
page/sheet No Meeting

1 Salco 27-May-24 1. As per as build survey data, contractor has to reflect the cart path elevation,
DRW-SDW-CIV V Murugan slope and parking spots as per approved drawing.

2 Salco 27-May-24 2. Ensure the catch basin which was located in the lowest point and fall slope
DRW-SDW-CIV V Murugan should maintained towards catch basin.

3.Contractor is responsible for ensuring that all relevant MIRs related to catch
3 DRW-SDW-CIV Salco V Murugan 27-May-24 basins, wire mesh, concrete, base course aggregate, EJ & CJ filling material are
submitted and approved.

4 Salco 27-May-24 4.The cart path setting out to be followed with catch basin locations and top level of
DRW-SDW-CIV V Murugan cart path concrete.

5 Salco 27-May-24 5. The cart path's edge should align with the approved final shaping, and the
DRW-SDW-CIV V Murugan capping sand's FGL must be approved from GCA and Engineer.

6. The kerb stones requirements, curves and slopes should be determined and
6 DRW-SDW-CIV Salco V Murugan 27-May-24 marked out by a surveyor, as per approved drawing and subject to approval of GCA
and the Engineer.

7 DRW-SDW-CIV Salco V Murugan 27-May-24 7. Panel identification numbering is required.

10

11

12

13

14

15

16

17

18

19

20

21

22

23

758820956.xlsx Page 1 of 1