HEALTH & SAFETY RISK ASSESSMENT
Replacement of Chilled
AL SHIRAWI FACILITIES HSE Ref No:
Facility/ Site/ Project Name: Scope of Work: water FCU 19253
MANAGEMENT
FAB Bank Building,
ROBIN ANTONY Assessment Date:
Assessment By: LOCATION Karama 04/06/2024
POOJA VIJAYAN Review Date:
Reviewed & Approved By: Signature: 04/06/2024
Functional Head: (indicating full NAVIN MICHEL Received Date:
Signature: 04/06/2024
understanding and compliance)
Insignificant Minor Moderate Major Catastrophic
Description Consequence (Table 1 – Area Impacted)
(1) (2) (3) (4) (5)
Likelihood Insignificant Minor Moderate Major Catastrophic Minor injuries, Injuries requiring Serious injuries Single Multiple
(1) (2) (3) (4) (5) which may on-site treatment requiring off-site fatality fatalities
Rare (1) 1 2 3 4 5 require self- by medical treatment by medical
administered practitioner. practitioner or
Possible (2) 2 4 6 8 10 first aid. Personnel unable to immediate evacuation
Injured continue to perform to hospital. Potential
Likely (3) 3 6 9 12 15
personnel can duties. long-term or
continue to permanently disabling
Often (4) 4 8 12 16 20 perform effects.
normal duties
Consequence (Table 1 – Area Impacted)
Frequent (5) 5 10 15 20 25
15-25 Extreme Risk Activity or industry should not proceed in current form.
Activity or industry should be modified to include Rare Possible Likely Often Frequent
8-12 High Risk
remedial planning and action. (1) (2) (3) (4) (5)
Moderate Activity or industry can operate subject to management Never Has occurred Has occurred more Occurs Occurs
4-6
Risk and / or modification. occurred than once several frequently
No immediate action required, unless escalation of risk is times
1-3 Low Risk
possible. per year
Risk Rating Likelihood
P.O BOX: 30771, AJMAN +971 67 490 988 [email protected]
UNITED ARAB EMIRATES +971 52 171 8000 www.excelacsys.com
THE TEMPERATURE EXPERTS
HEALTH & SAFETY RISK ASSESSMENT
Risk Rating Code: E - Extreme Risk, H – High Risk, M – Moderate Risk and L – Low Risk
Routine (R)/ Groups Exposed Residual
Hazards Risk Rating
Non-Routine (Including Numbers Existing Control Measures Additional Controls Required Risk Rating
(N) and Patterns) L C RL L C RL
N Falling from Height Workers Using appropriate ladder/Scaffolding 3 2 6 3 2 6
Co workers Personnel over 2m away from edges and
openings
Personnel should be trained in roof safety
Should be wearing appropriate PPE
Trip over of tools Workers Ensure all workers are aware where tools 2 2 4 2 2 4
N Co workers are Pack away tools
Trip Over of machines Workers Ensure all workers are aware how to load 2 2 4 Provide loading equipment by client 2 1 2
N Co workers and positioning the machine
Cut injury from tools or Workers Ensure all the workers aware how to use 2 2 4
N Co workers
machine parts the tools properly
Using Gloves while handling sharpened
edge machine parts or tools
Action By Action Date Date Completed Review Date Reviewed By Comment(s)
POOJA VIJAYAN 04/06/2024 04/06/2024 04/06/2024 NAVIN MICHAEL