Flexstrong Installation Manual
Flexstrong Installation Manual
INSTALLATION MANUAL
FLEXSTRONG™
Installation Manual
FLEXSTRONG™
THERMOPLASTIC COMPOSITE PIPE (TCP)
INSTALLATION MANUAL
3
FLEXSTRONG™
Installation Manual
TERMS OF USE
All information was correct at the time of publication. However, we reserve the right to alter, amend
and update any of the products, systems and services described in this brochure.
This document contains confidential and proprietary information. Reproduction or disclosure of any
part of this document is only allowed with written authorization by Future Pipe Industries.
Occasionally, Future Pipe Industries will provide updates to this catalogue. In order to assure that the
reader is using the most current version, please visit our website at www.futurepipe.com
4
FLEXSTRONG™
Installation Manual
TABLE OF CONTENTS
1. INTRODUCTION 3
1.1 General Product Description Of Flexstrong™ 3
1.2 Product Identification 3
2. REFERENCES 4
4. EQUIPMENT 5
6. QUALITY 12
7. INSTALLATION TECHNIQUE 13
7.1 Pulling Methods 14
7.2 Unspooling from a Stationary Position 14
7.3 Unspooling from a Moving Reel 15
7.4 Joint Lowering 15
7.5 Bend and S Bend Deployment 16
7.6 Surface Laid Applications 17
7.7 Road Crossings 18
7.8 Pipe/Cable Crossing 19
7.9 Pulling Thru Steel Sleeves 19
7.10 Buried Applications 20
7.11 Buried Pipelines Berms 21
7.12 Underground to Above Ground Transition 22
8. JOINTING 23
8.1 External swaging Process 23
8.2 Dual Process 26
8.3 Additional Guidance While Doing Swaging and Crimping Jointing 30
8.4 Corrosion Coating 30
9. FIELD TESTING 32
9.1 Cleaning And Filling 32
9.2 Pressurisation 33
10.SHUTDOWN PROCEDURES 34
11.HSE REQUIREMENTS 34
1
FLEXSTRONG™
Installation Manual
2
FLEXSTRONG™
Installation Manual
1. INTRODUCTION
This document explains various aspects of the installation of the Flexstrong™ pipeline- a spoolable
pipeline. The adherence to the requirements, methods, and recommendations given in this guide
will contribute to a successful installation and operation. It is essential to have skilled labor for the
quality execution of the installation activity.
Besides, the contractor may consult FPI representative for any clarification of statements made in
this document. Any specific problem, which would be encountered on-site must be investigated
and resolved on a case-by-case basis.
3
FLEXSTRONG™
Installation Manual
2. REFERENCES
3.2 Tools
• Swaging or Crimping Kit* (Per the offered product)
• ID, and OD Peeler
• Forklift, cranes, etc
• A-Frame or Deployment Trailer (Optional)
3.3 Consumables
• MOLYKOTE™.
• Lithium Complex Grease.
• Rubber gloves, working gloves, safety goggles, etc.
• Overalls, safety shoes, safety helmet, etc.
• Cleaning rags.
* To be supplied by the Future Pipe Industries Ltd.
4
FLEXSTRONG™
Installation Manual
4. EQUIPMENT
The following are the equipment needed while deploying and connecting Flexstrong™ products;
Reels, A-Frame, Pulling Devices, Crimping kit, and Swaging Kit. Future Pipe Industries will supply those
items.
Equipment Illustrations
Reel
Flexstrong™ pipeline is typically packaged and
shipped on steel reels designed to spool the
required length of pipeline. The length of pipe
per reel varies depending on the pipe diameter
and dimensions of the reel.
A-Frames
An A-frame is a spooling frame suitable for
supporting and controlling the reel of the
pipeline. The design of the A-frame should
be suitable to hold the reel and to facilitate
the rotation/unspooling of the pipeline in a
controlled and safe manner.
Ideally, the A-frame should:
• Support the reel off the ground allowing it to
rotate in a controlled fashion.
• Have an integral braking device that allows
the operator to maintain tension on the
pipeline as it is pulled off the reel.
• Have spacers to Centre the reel onto the
A-frame.
• Be positioned as close to the ground as
possible to minimize the overturning moment
of the top-heavy reel.
Pulling Devices
The pulling devices must be capable of
“accommodating” the predicted load and
have a rated working load approximately
equal to the maximum allowable tensile
strength of the pipeline being installed.
Swaging Machine
The swaging machine consists of moving arm
and hydraulic mechanism that perform the
swaging process.
Part of Swaging Kit.
5
FLEXSTRONG™
Installation Manual
Equipment Illustrations
Swaging Dies
The swaging dies are installed on the swaging
machine arm to perform the swaging operation
and achieve the desired compression. Swaging
dies consist of two identical pieces. The size of
the swaging dies to be used depends on the
diameter and pressure class of the pipe.
Part of Swaging Kit.
Insertion Clamps
The insertion clamps are used to grip on
the pipe and maintain the roundness and
robustness during the insertion process.
Part of Swaging Kit.
Power Pack
The gasoline operated hydraulic power supply
Part of swaging kit.
Horseshoe Holder
The horseshoe holder is a component that holds
the steel fitting in place while performing the
swaging process.
Part of Swaging Kit.
6
FLEXSTRONG™
Installation Manual
Equipment Illustrations
Expansion Machine
The expansion machine is used to expand the
stem of the fitting. This is to push the inner sleeve
of the steel fitting to fully engage with the inner
portion of the pipe.
Part of Crimping Kit.
Crimping Machine
This machine is used to perform the last step of
the connection process which is: compressing
the outer sleeve of the fitting.
Part of Crimping Kit.
Insertion Clamps
The insertion clamps are used to grip to
the pipe and maintain the roundness and
robustness during the insertion process.
Part of Crimping Kit.
Expansion Dies
The expansion dies(dolly) are used to expand
the inner sleeve of the fitting during the
expanding process.
Part of Crimping Kit.
7
FLEXSTRONG™
Installation Manual
Equipment Illustrations
Crimping Jaws
The crimping jaws are used to compress the
outer sleeve of the fitting during the crimping
process. Jaw size depends on the pipe
diameter.
Holding Plates
The holding plates hold the fittings in place
during the expanding process.
Part of Crimping Kit.
8
FLEXSTRONG™
Installation Manual
When loading on the truck, reels must be “chocked” using wooden wedges on each side to avoid
any rolling movement. Three chains or slings must be placed: one at each side of the reel and one
placed through the drum of the reel and tied tightly to the trailer.
The speed of the vehicle should be carefully controlled, especially during turns. Upright reels are
“top-heavy” and can easily be overturned. During the transport, the speed of the vehicle should
be controlled, and the turns shall be handled with care. Reels may be moved for short distances
using a crane and a sling.
9
FLEXSTRONG™
Installation Manual
MOVING REELS BY ROLLING IS NOT RECOMMENDED. Rolling the reels may become unstable and out
of control. Upright reels are top-heavy and may tip over when rolling.
Lifting shall be performed using a spreader beam or a steel bar across the reel for loading and
unloading. Moving the reels using alternative means should be reviewed with Future Pipe Industries
Field Services to avoid potential damage to personnel, reel, pipeline, or other equipment.
10
FLEXSTRONG™
Installation Manual
In case of storing the pipe on site, avoid the rocky and rough terrain areas to protect the pipe from
sharp object/stone that can cause damage or dent.
If Flexstrong™ reels are being stored for an extended period, they should be protected from
ultraviolet (UV) exposure by being covered with a tarpaulin sheet.
11
FLEXSTRONG™
Installation Manual
6. QUALITY
Flexstrong™ pipeline shall be inspected on-site against kinks, scratches, and dents. Check for any
potential damage caused by reel and shipping straps. Need extra attention doing visual inspection
on the last layer of the pipe in the reel near the soil. If any damage is found after unloading,
record it on the checklist as this will be essential for FPI internal investigation. Any damage found on
Flexstrong™ product shall be communicated with the pipe manufacturer to advise on necessary
actions.
Note: Always record any damages observed, take pictures or video, and contact FPI.
Some deformation of the Flexstrong™ product including wrinkling, bulging, or sharp dent that occur
during delivery will be reported. Also, there are a few instances the reel can result in kinking of the
pipe, this can occur to Flexstrong™ Products when the minimum bend radius of the product is not
followed.
Repairing of Flexstrong™ pipeline is strictly not allowed. The only remedial action allowed in case
damage is observed and acknowledged by the pipe manufacturer is to cut the pipe 1 meter away
from the defective area, discard the part, and pull the free end to make a new connection: The
length to be connected must be straight to avoid misaligned pipe insertion thru the fitting.
12
FLEXSTRONG™
Installation Manual
7. INSTALLATION TECHNIQUE
Flexstrong™ pipeline is designed to be stored, handled, deployed, and installed using a reel. The
pipeline can be deployed using an “A – frame”. A truck can be used for the on-site transport
as well as unspooling activity. A crane and/or side boom can be used for the lowering activity,
this will ensure the flexibility for laying long continuous lengths and to reduce the impact and
possible damage during installation. A site evaluation should be performed prior to the delivery
of the pipeline, tools, and equipment to have a better deployment in the field. Considering the
site location and application of the pipeline, a suitable deployment method can be preferred as
described in this chapter.
A-frames are commonly used during deployment. The reel can be stationary, which is a “pull-
in” operation, or can be driven along the route as the pipeline is laid from a deployment trailer.
The equipment and the personnel necessary to support the installation depend on the project
characteristics (terrain, pipeline length, etc.).
While unspooling the Flexstrong™ pipeline, the below-mentioned methods must be followed. The
maximum allowable pulling force should be followed for the safe handling of the product. A load
indicator (load cell) should be fitted between Flexstrong™ pipeline and the pulling equipment so
that the axial load on the pipeline is monitored. If the maximum pull load exceeds the product’s
puling force rating, multiple pulling devices spaced along the length of the pipeline should be
used to ensure that the maximum allowable pull load is not exceeded. These multiple units must be
operated at the same speed, to avoid buckling of the pipeline.
Pulling force should always be maintained on the pipeline at the reel with a brake on the spooling
frame, to prevent bird’s nesting in several layers of a spooled pipeline. Bird nesting results when
an unrestrained pipeline is free to change its spooling diameter, and there is a rapid, uncontrolled
release of stored energy. Care must be exercised when removing a bird’s nest from a crossed
pipeline. Applying tension to pipelines that are crossed may result in pipe damage.
Note: Pulling force should be measured on site to prevent exceeding the maximum pulling force.
13
FLEXSTRONG™
Installation Manual
Generally, for short distances and straight pulling, a sling can be connected to the pipe by drilling a
hole on the pipe body and passing the sling. While pulling more than 300 meters of Flexstrong pipeline,
where passing a curve or a corner, use a sling roller to minimize excessive pull force on the pipe.
For long pipeline pull or, curved pulling, a puling device shall be used for pulling Flexstrong™ pipeline
to protect the integrity of the pipe’s structural wall.
Flexstrong™ pipeline may be pulled by a pickup truck, tractor, backhoe, or similar piece of
construction equipment. While unspooling, keep away from sharp objects / edges, to avoid any
pipe damage.
After the pull of the Flexstrong™ pipeline is complete, the section that was pulled should be cut off
and discarded for at least 1m (3 ft) from the pull point.
14
FLEXSTRONG™
Installation Manual
The pipeline reel represents a top-heavy load that may be prone to overturning when crossing
rough terrain. An overturned load can result in an injury to the personnel and/or damage to the
equipment and/or the pipeline. Be sure to evaluate the height of the centre of gravity of the
equipment with the reel and ensure the pathway of the vehicle is adequately smooth, wide, and
level to prevent overturning along the intended route.
15
FLEXSTRONG™
Installation Manual
In term of deployment thru a curve or bend, place straight the pipe near the trench. Then push/
drag carefully the pipeline towards the trench, and slowly lower it into the trench, using roller and
support bar strap or sling. In case of an obstruction, you need to push the pipe inside the trench
with extra support and within the maximum allowable bend radius (Table 2).
16
FLEXSTRONG™
Installation Manual
The surface laid pipelines shall be routed in a manner that no excessive movement occurs on the
pipes because of thermal expansion and/or contraction, internal pressure, and other design loads.
The axial and lateral expansions should be prevented by putting pipe support.
Flexstrong™ pipeline shall be properly supported at intervals no longer than 150m using berms,
sandbags, guide supports or any other proper means of support. The excessive movement of
Flexstrong™ pipeline shall be avoided while pressurizing, operating, or depressurizing the pipe. All
bends, mid joint, and proximity to the joints shall also be supported properly.
If the surface laid pipeline to be secured by means of berms, the height and length of the berm
should be 1m and 4m, respectively. Project-specific details should be referred for the implementation
of the right recommendation based on the terrain topography.
17
FLEXSTRONG™
Installation Manual
18
FLEXSTRONG™
Installation Manual
19
FLEXSTRONG™
Installation Manual
The bottom of the trench should be as uniform as possible and provide a smooth, firm bearing
surface to support the bottom quarter of the pipe circumference. This is often accomplished by
healing the bottom of the trench with a hoe bucket. High spots in the trench bottom can cause
uneven bearing on the pipe, damage due to localized stress during backfill, and unnecessary wear
at these points.
• It is important to remove all sharp rocks (larger than 50 mm) and other abrasive material from
the trench bottom.
• The pipe should be properly supported to prevent low spots, traps, or sumps.
• If the trench is excavated through rock or shale ledges, or through unstable soil, dig the trench
slightly deeper. Use a minimum of six inches of river sand or other clean backfill such as pea-
gravel in the bottom of the trench and over the pipe to protect the pipe from rocks.
• If multiple lines are installed in the same trench, they should be separated by a distance (A) of at
least six inches (150 mm) or one pipe diameter, whichever is greater. This is particularly important
if any lines in the trench will experience pulsation or movement.
20
FLEXSTRONG™
Installation Manual
Before backfilling the trench, make sure the pipeline is properly positioned and that any tools or
positioning jigs used during the installation are removed from the trench. Connections and joints
should be left exposed for inspection during hydro testing. The trench should be backfilled as soon
as possible after hydrostatic testing to eliminate the chance of damage to the pipeline, floating if
the trench floods, or shifting due to trench collapse. It is recommended that the material to be used
as backfill for Flexstrong™ pipeline be free from rocks, boulders, large clods of dirt, frozen dirt, and
other objects that could damage the pipe.
Caution should be taken to prevent voids (areas that do not contain backfill) under or around the
pipe. If frozen earth is used as backfill, it will eventually thaw and contract, leaving the pipe with
insufficient supports and voids around the pipe. Remove frozen lumps (solid lumps) from all backfill
materials before backfilling. For trenches excavated under roads or under structures, place backfill
in 6-inch (150 mm) layers till grade level and compact each layer to at least 95% of maximum
Standard Proctor Density. When compacting, avoid causing damage to the pipe. Vibrating
tampers should not be used until there is at least one foot (300 mm) of backfill over the pipe
Figure 19: Berm with environmentally friendly soil stabilization chemical cover
21
FLEXSTRONG™
Installation Manual
Figure 21: 45-degree transition Figure 22: 90-degree transition Figure 23: Transition using
S-Bend
Riser Assembly
1. Install steel pilings foundation to an appropriate depth determined by project parameters and in
line with riser chute design.
2. Keep a minimum of 1m pipe straight leading to the riser chute.
3. The steel frame shall be extended until the horizontal soil plane.
4. Place plastic protectors underneath the U-bolts to protect the pipe.
5. Neoprene rubber shall be placed between the pipe and the steel frame.
6. Protect the exposed pipeline to protect from excessive solar radiation.
7. Backfill the pipe after the installation is complete.
Note: In occasions where the difference in elevation of the underground to aboveground transition is comparatively less, the Flexstrong™
pipes can be connected directly to the tie-in without any riser chutes. The actual requirement shall be studied on a case-by-case basis, and
solutions shall be proposed, project-specific.
22
FLEXSTRONG™
Installation Manual
8. JOINTING
Flexstrong™ has three types of fitting connections. Pipe-to-pipe coupling, flange-end connector,
and weld-end connector. Pipe-to-pipe coupling is commonly used to join two lengths of line pipes,
whereas flange-end and weld-end connectors are used for tie-in connections.
The fitting material is selected based on fluid compatibility and corrosion resistance. Stainless
steel SS316 or SS304 is the standard material for fittings and is highly recommended for the best
performance in most common corrosive environments. Although, fitting material can vary based on
the product application and its end user requirement.
For each process, FPI supplies the right kit containing the relevant tools and equipment for
performing the intended process
The swaging machine will uniformly compress the outer jacket of the fitting resulting in a reliable,
permanent connection attached to the pipe end. The ferrule of the fitting is swaged down to
develop the clamping force that ensures fluid sealing and joint performance over the lifetime of
the pipeline.
Prior to performing the swaging process, the components of swaging kit shall be inspected, the fuel
tanks shall be filled with suitable gasoline, the engine oil level shall be checked and refilled with
suitable engine oil (10W30) if needed, the hydraulic oil level shall be checked and refilled with the
suitable hydraulic oil (HFO46) if needed, the hydraulic hoses and pressure gauges are properly
connected. Ensure the swaging machine is installed in a level and firm surface. The detailed
swaging process is described below with illustrations. Following the same procedure while doing the
swaging outside and inside the trench.
23
FLEXSTRONG™
Installation Manual
Step 1: Properly cut the pipe for at least 1m (3 ft.) Step 2: Mark the Home line for insertion length.
from the pulling device.
Step 3: Insert the O-ring in the groove. Step 4: Install the fitting on the proper
Horseshoe holder.
.
Step 5: Install the proper swaging die, the Step 6: Lock the upper securing cover.
steeper side facing opposite to the fitting.
24
FLEXSTRONG™
Installation Manual
Step 7: Attach the insertion clamps. Step 8: Apply Lithium Complex Grease on both
sides of the pipe.
Step 9: Start the insertion process until reaching Step 10: Dismantle the insertion clamps.
the Home line.
Step 11: Apply Molykote on the outer surface of Step 12: Start the swaging the process for the
the fitting and on swaging dies. fitting in both directions back and forth.
25
FLEXSTRONG™
Installation Manual
Step 13. Finally, strip the jacket of the pipe, 100mm from the sleeve edge of the fitting.
The Dual process consists of expanding the stem of the fitting by pulling a dolly through it. Then
crimping ferrule using the crimping machine to compress it towards the jacket of the pipe.
Prior to performing the crimping process, make sure that the electrical supply is connected and
of the required capacity. Hydraulic oil levels shall be inspected and refilled if needed.
Step 1: Properly cut the pipe for at least 1m (3 ft) Step 2: Mark the Home line for insertion length.
from the pulling device.
26
FLEXSTRONG™
Installation Manual
Step 3: Install the fitting on the proper holding Step 4: Install the expansion die(dolly) and
plate. secure nut.
Step 5: Apply grease on the expanding die and Step 6: install the pipe on clamps.
fitting. Ensure the alignment of the fitting.
Step 7: Start the insertion process till reaching Step 8: Expanding the fitting using the
the Home line. expansion die.
27
FLEXSTRONG™
Installation Manual
Step 9: Check the crimping machine if it is Step 10: Mark the fitting for crimping
function properly
Step 11: Install the crimping jaws according to Step 12: Check its functionality by moving
the required size inward and outwards
Step 13: Set the parameters” Close Die setting” Step 14: Keep the machine on auto mode and
according to pipe size operate to close manually to close the die for
crimping
28
FLEXSTRONG™
Installation Manual
Step 15: Open the swaging blocks and check Step 16: Repeat the procedure by increasing
the OD after crimping on marked area # 1 with gradually the parameter “ close Die setting”
OD tape until the required OD after crimping is achieved
Step 17: Repeat the same procedure for the Step 18: Remove the Pipe along with crimped
remaining marked areas(no. 3 and 2) fitting carefully from the machine
Step 19: After the jointing process is completed, Step 20: Finally, strip the jacket of the pipe,
a dimensional check should be carried out to 100mm from the edge sleeve of the fitting
ensure the end fitting is compressed well into
the pipe wall
29
FLEXSTRONG™
Installation Manual
2. Apply protective paste (Denso Paste) to the cut end to protect the reinforcement structure from
water, or contaminants.
3. Use the insertion clamps or crimping jaws that match the pipe size.
4. Use Pipe peeler only if the ID and OD do not conform to the required fitting dimension.
5. Ensure the swaged/crimped area is uniform, using the lever or measuring the OD after swaging/
crimping will be the best way to confirm it.
Remember:
Proper alignment of the pipe and connectors is critical for successful installation.
30
FLEXSTRONG™
Installation Manual
Note:
For Protection Coating
White Tape - For surface laid pipeline
31
FLEXSTRONG™
Installation Manual
9. FIELD TESTING
FField testing shall be conducted upon the completion of the pipeline installation to ensure the
performance of the installed systems. The supervisors or inspectors shall ensure all other activities are
completed before the pressure testing. Ensure all the requirements in the Inspection & Test Plan (ITP)
are met and the non-conformities have been completed.
Complex piping systems should be broken into smaller runs for testing. As a minimum, lines shall
be secured by backfill or sandbags before the hydrotesting. Surface laid pipelines shall also be
secured against any movement with soil or sandbags as stated in clause 6.4. Project specific
recommendations if any shall be implemented before the field-testing activity.
Cleaning: Cleaning the pipeline can be done using compressed air from one end to the other to
remove the dust or debris. Also flushing water from one end can clean the line from impurities and
external contamination.
Waterfilling: This can be done by pumping the test medium from one end to the other by ensuring
no entrapped air in the test section.
Dewatering: Dewatering after the testing can be done either by draining the line by gravity flow or
using compressed air to expel the water from one end to the other. Dewatering should be done
from the upstream end to the downstream end due to practical feasibility.
Cleaning: Pigs shall be propelled by compressed air at a maximum pressure of 7 bar. A 10bar
pressure gauge shall be installed at the launcher. The pressure set up on the piping shall be
fitted with a pressure relief valve set at 7bar. To assist and control the speed of the cleaning pig,
a constant back pressure of 2bar shall be maintained by suitable adjustment. The speed of the
cleaning pig shall be maintained between 0.2 to 0.8m/s.
Pigging shall continue until the volume of the received material is less than 5 liters and further
pigging will not result in a significant reduction in the material received.
Waterfilling: Pigging might be required to fill the line without air entrapment for the long stretch
pipelines and in special cases where a bigger elevation difference exists. The process shall be the
same as explained in the cleaning process above.
De-Watering: If the line needs to be dewatered after the testing pigs can be used in the same
manner as detailed in the cleaning.
32
FLEXSTRONG™
Installation Manual
Note:
1) Care shall be taken to ensure the line is pigable and the pig will not be stuck in the line during the process.
2) Cleaning, Water filling, Dewatering, etc. can be done either partially or fully depending on the site condition.
3) The standard method of cleaning, watering, and dewatering is not recommended if the line cannot be filled with a test medium without any
air entrapment.
9.2 Pressurization.
The test section shall be pressurized as detailed below.
• The pressure gauges are installed at the lowest and highest points in the pipeline. A minimum of
two pressure gauges is required for testing the system.
• The pipeline should be pressurized up to 60% of the test pressure with a rate of 6.9 Bar per minute
(100 psi per minute).
• Conditioning pressure should be held until the pressure stabilizes for a minimum duration of
30 minutes. It is normal to observe some slight decrease in the conditioning pressure over this
holding time.
• During the holding time, the line should be inspected for leaks, particularly at end connections.
• Once the conditioning pressure stabilizes, the pressure should be increased with a rate of 6.9 Bar
per minute (100 psi per minute) till 8-10% above the Hydrostatic Test Pressure for stabilization.
• It is expected to observe some slight decrease in the pressure over this stabilization process.
Hence, the pressure should be increased two more times up to 8-10% above the Hydrostatic
Test Pressure.
• After increasing the pressure two times, the pipeline should be left for a stabilization time of 8 hours.
• During the stabilization time, the line should be inspected for leaks, particularly at end
connections.
• After the stabilization time, the pipeline should be pressurized once more up to 8-10% above the
Hydrostatic Test Pressure. This marks the beginning of the 4-hour test period.
• If there is an indication of a leak, stop the test, bleed-off the pressure, and repair the line. After
repairing the leak, refill the pipeline with the hydrotest fluid and restart the testing procedure.
• Upon successful completion of hydrostatic testing, the line should be depressurized with a rate of
6.9 Bar per minute (100 psi per minute).
33
FLEXSTRONG™
Installation Manual
Note: The maximum test pressure shall not exceed 125% of the pressure class.
34