BOQ FOR CIVIL WORKS FOR IMPROVEMENT OF WATER SUPPLY AND
INFRASTRUCTURE FOR KISUMU GK WOMEN AND MEDIUM PRISONS IN KISUMU
COUNTY
RATE AMOUNT
ITEM DESCRIPTION QTY
UNIT (KShs) (KShs)
Provide lay and joint in trench as per drwg
(rate to include cutting to size, fixing and
jointing materials inclusive of sockets,
mechanical joints, or rubber rings where
applicable)
GI pipes to BS 1387 with threaded ends. All
HDPE pipes shall be manufactured to ISO
4427 Standard. All PPR pipes shall be
manufactured to DIN 8077 / ISO 15874.
Epoxy coated steel pipes to AWWA C210,
C213
All steel fittings shall be manufactured to
BS EN 10244/BS 3601. The working
pressures and wall thicknesses shall
conform to ISO 559 Series B. The flanges
shall conform to EN 1092-2
BILL
MOBILIZATION AND SIGN POST
1
Mobilization to Kisumu Women Prison in
1.01 LS
Kisumu County 1.0
Sign Post
Provide sign post as provided for in the
1.02 No.
drawings or as directed by the engineer 2.0
TOTAL FOR BILL 1
BILL EXCAVATION, BACK FILLING AND
2 PIPE WORKS
Excavation and Back Filling Works
Excavation and Backfilling in normal
2.01 M3 313.00
material for pipes to a depth n.e 1 m
E&O for Excavation of Rock Materials
2.02 M3 86.00
(Provisional)
2.03 Bush clearing M2 62.00
Pipe Works and Fittings
Provide lay and joint in trench as per drwg
(rate to include cutting to size, fixing and
jointing materials inclusive of sockets,
mechanical joints, or rubber rings where
applicable)
Page 56 of 102
Pipes (Rate inclusive of installation and
fittings)
110mm dia HDPE PN-8 pipe (SDR-17) for
2.04 M 108.00
river water to the medium prison
50mm dia HDPE pipe PN-8 (SDR-17) from
2.05 M
max prison to women prison 350.0
2.06 25mm dia PPR pipe (PN8) M
50.0
TOTAL FOR BILL 2
3M HIGH ELEVATED WATER TANK
BILL
WORKS FOR KISUMU WOMEN
3
PRISON
A Platform Construction
Excavation of foundation to firm ground
3.01 (provisionally 1.5m deep below ground) and M3 24.40
backfilling once curing is complete
Provide T12 reinforcement bars for pad
3.02 Kgs 101.00
footing foundation
3.03 Class 30 concrete in pad footing M3 1.60
3.04 T12 reinforcement bars in top slab @200 c/c Kgs 238.00
3.05 Class 30 concrete in top slab M3 2.20
Provide T16 main reinforcement bars for
3.06 Kgs 235.00
columns
Provide T8 link reinforcement bars for
3.07 Kgs 110.00
columns
3.08 Class 30 concrete in columns (300x300) M3 3.60
Provide T12 main reinforcement bars for
3.09 Kgs 108.00
main beams
Provide T16 main reinforcement bars for
3.10 Kgs 38.00
main beams
Provide T8 link reinforcement bars for beam
3.11 Kgs 88.00
beams
3.12 Class 30 concrete in main beams M3 1.79
Provide 20mm plaster class 1:3 on all
3.13 M2 63.00
concrete surfaces of the tank platform
Provide and install 40x40x2mm thick square
3.14 tube ladder and railing around the top slab as M 92.00
will be directed by the engineer
Supply and Install 10,000-liter uPVC Tank
3.15 (Kentank or equivalent approved by the No. 1.00
engineer)
Sub-Total for A
Page 57 of 102
Plumbing works to and from Elevated
B Kisumu Women Compound Water Tank
Works
Inlet to the elevated water tank
3.16 HDPE male threaded coupling (DN50) No 1.00
3.17 PPR female threaded elbow (DN50) No 1.00
3.18 PPR union (50) No 2.00
PPR gate valve (DN50). Must be approved
3.19 No 1.00
by the engineer
3.20 PPR male threaded elbow (50mm) No 2.00
3.21 GI long nipple with tank backnuts (1 1/2") No 2.00
3.22 1 1/2" GI Heavy Duty socket No 1.00
DN50 PPR pipe clips complete with fitting
3.23 No 8.00
accessories
Outlet from the tank
3.24 1" GI Nipple complete with tank backnuts No 1.00
3.25 1" GI union (H/D) No 1.00
3.26 PPR DN32 male threaded socket/bush No 1.00
3.27 PPR DN32 elbow No 2.00
3.28 PPR DN32 union No 2.00
PPR DN32 gate valve with GI handwheel.
3.29 No 1.00
Must be approved by the engineer
3.30 PPR DN32 socket No 34.00
DN32 PPR pipe clips complete with fitting
3.31 No 4.00
accessories
3.32 DN32 PPR Pipes (PN-8) M 100.00
Outlet to the Standpipe
3.33 PPR Reducing Tee (32x25mm) No. 1.00
3.34 DN25 PPR union No. 2.00
3.35 DN25 PN 8 PPR Pipe M 4.00
3.36 DN25 PPR gate valve with GI handle wheel No. 1.00
3.37 DN25 PPR female threaded adaptor No. 1.00
25mm GI Pipe of length 6m to be threaded
3.38 No. 1.00
on site according to engineer's specifications
3.39 25mm m/f bends No. 4.00
3.40 25mm hex nipples No. 2.00
3.41 25mm GI Sockets No. 4.00
3.42 25mm taps with padlock No. 2.00
3.43 25mm GI Union No. 2.00
Type B Stand and basin (See Drawing -
3.44 No. 1.00
Annex 1.2) with 3 taps as will be directed
Page 58 of 102
Provide provisional sum of KENYA
SHILLINGS THIRTY-FIVE
THOUSAND (Kshs. 35,000.00) for
Construction of soak pit (1mx1mx1m deep)
and connection of the new pipeline to
existing tanks and pipes and improvement of
3.45 Item 1.00
the kitchen water point. The soak pit must
be filled with hardcore rocks, covered with
16-gauge polythene sheet and natural soil.
Provide plumbing drainage to the soak pit
not more than 1m away from the water point
as will be directed by the engineer.
Sub-Total for B
TOTAL FOR BILL 3 (A+B)
BILL
AIR VALVES AND FITTINGS
4
25mm Dia Single-orifice Air "A.R.I model
701-040-L equivalent to ASTM A744/250
4.01 No 1.00
psi with 25mm isolating gate valve off
25x50mm HDPE saddle clamp
4.02 HDPE saddle clamp (50x32mm) No. 4.00
4.03 HDPE Male Coupling-50mm No. 4.00
4.04 GI MD Nipple - 1 1/2" No. 2.00
4.05 GI MD Union - 1 1/2" No. 1.00
4.06 GI HD Gate valve - 1 1/2" No. 4.00
4.07 HDPE Elbow coupling-50mm No. 2.00
4.08 GI HD Gate valve - 3/4" No. 4.00
4.09 HDPE Male Coupling-32mm No. 4.00
4.10 GI MD Nipple - 3/4" No. 2.00
4.11 GI MD Union - 3/4" No. 1.00
Provide provisional sum of KENYA
SHILLINGS FIFTY THOUSAND (Kshs.
4.12 Item 1.00
50,000.00) for any additional fittings as will
be directed by the engineer.
TOTAL FOR BILL 4
BILL CHAMBERS, ANCHOR BLOCKS AND
5 MARKER POSTS
Valve chambers (1x1m and depth not
exceeding 1m) including Air valve
chambers
Excavation of foundation to firm ground
5.01 (provisionally 1.5m deep below ground) and M3 2.20
backfilling once curing is complete
Page 59 of 102
E&O for Excavation of Rock Materials
5.02 M3 0.70
(Provisional)
Machine cut Masonry walls (Approved by
5.03 M2 6.20
the engineer)
Provide concrete on the bottom floor of the
5.04 M3 0.30
chamber
Provide and install door steel manhole cover
5.05 No. 1.00
with lockable padlocks
Provide 20mm plaster class 1:3 as will be
5.06 M2 13.00
directed
Sub-Total for 1
Sub-Total for 4 valve chambers
Concrete Anchor blocks
Provide and place reinforced concrete
C20/20 for thrust blocks and anchor blocks
5.07 M3 1.58
in bends etc Rate to include excavation and
necessary formwork (provisional quantity)
Sub Total for Concrete Anchor Blocks
Marker Posts
Marker posts at 30m intervals as per
5.08 No. 15.00
drawings or as directed by the engineer
Sub-Total for Marker Posts
TOTAL FOR BILL 5
BILL
PRIME COSTS
6
Provide provisional sum of KENYA
SHILLINGS ONE HUNDRED AND
FIFTY THOUSAND (Kshs, 150,000) for
6.01 Sum 1.00
improvement of the existing kitchen
including ventilation as will be directed by
the engineer.
Provide provisional sum of KENYA
SHILLINGS TWO HUNDRED
THOUSAND (Kshs. 200,000.00) for repair
of the water treatment system for medium
prison, modification of the water treatment
6.02 Item 1.00
system as will be directed by the engineer,
plumbing from the treatment system to the
pump, plumbing fittings from the pump to
the outlet pipe, reparing/replacing the pump
as will be directed by the engineer
TOTAL FOR BILL 6
Page 60 of 102
BILL
PAINTING
7
Provide painting for all metal surfaces.
Painting will also be done on some concrete
7.01 M2 172.00
surfaces as will be directed and with colours
approved by the engineer
TOTAL FOR BILL 7 0.00
SUMMARY
ITEM AMOUNT
TOTAL FOR BILL 1
1
TOTAL FOR BILL 2
2
TOTAL FOR BILL 3 (A+B)
3
TOTAL FOR BILL 4
4
TOTAL FOR BILL 5
5
TOTAL FOR BILL 6
6
TOTAL FOR BILL 7
7
TOTAL
10% Contingency
GRAND TOTAL
Page 61 of 102