8-16 MM VERTICAL BARS 6-16 MM VERTICAL BARS
GROUND FFL GROUND FFL GROUND FFL
NGL
TIES 10MM DIA. BAR TIES 10MM DIA. BAR
3@50MM,3@75MM,4@100MM,
REST @20MM O.C.
3@50MM,3@75MM,4@100MM,
REST @20MM O.C.
SCHEDULE OF BEAMS
SCALE 1:20 M.
FTB FTB FTB
1000
1200
AT SUPPORT AT MID SPAN
250 250
6-16 MM MAIN BARS 6-16 MM MAIN BARS
6-16 MM HOR. BARS
SPACED 170MM
300
O.C. BOTHWAYS
FTB1
350
350
8-16 MM HOR. BARS 10MM DIA. STIRRUPS 10MM DIA. STIRRUPS
SPACED 150MM 3@50MM,3@75MM,4@100MM REST 3@50MM,3@75MM,4@100MM REST
300
O.C. BOTHWAYS @200MM O.C. @200MM O.C.
AT SUPPORT AT MID SPAN
DET. SEC. OF C1-F1 DET. SEC. OF C2-F2 250
3-16 MM TOP BARS
250
3-16 MM TOP BARS
SCALE 1:20 M. SCALE 1:20 M. 10MM DIA. STIRRUPS
2-16 MM EXTRA BARS 2@50MM,3@75MM,4@100MM REST
B-1
350
350
@200MM O.C.
10MM DIA. STIRRUPS
WIDTH LENGTH DEPTH REINFORCING DEPTH OF 2@50MM,3@75MM,4@100MM REST 2-16 MM EXTRA BARS
MARK @200MM O.C.
(mm) (mm) (mm) BARS EXCAVATION
3-16 MM BOTTOM BARS 3-16 MM BOTTOM BARS
8 - 16mm Ø TOP OF FOOTING IS
F1 1200 1200 300 REBARS PLACED 1.20m BELOW THE
AT SUPPORT
O.C. BOTHWAYS NATURAL GROUND LINE AT MID SPAN
250 250
6 - 16mm Ø TOP OF FOOTING IS 3-16 MM TOP BARS 3-16 MM TOP BARS
F2 1000 1000 300 REBARS PLACED 1.00m BELOW THE
10MM DIA. STIRRUPS
O.C. BOTHWAYS NATURAL GROUND LINE 2-16 MM EXTRA BARS 2@50MM,3@75MM,4@100MM REST
B-2
300
300
@200MM O.C.
10MM DIA. STIRRUPS
SCHEDULE OF FOOTINGS RB2 3@50MM,3@75MM,4@100MM REST
@200MM O.C. 2-16 MM EXTRA BARS
N T S 2-16 MM BOTTOM BARS 2-16 MM BOTTOM BARS
AT SUPPORT AT MID SPAN
SCHEDULE OF COLUMNS 250 250
SCALE 1:20 M. 3-16 MM TOP BARS 3-16 MM TOP BARS
10MM DIA. STIRRUPS
2-16 MM EXTRA BARS 3@50MM,3@75MM,4@100MM REST
B3
C1 C2 C3
@200MM O.C.
400
400
10MM DIA. STIRRUPS
3@50MM,3@75MM,4@100MM REST 2-16 MM EXTRA BARS
@200MM O.C.
3-16 MM BOTTOM BARS 3-16 MM BOTTOM BARS
GROUND FLOOR
FOUNDATION TO
AT SUPPORT AT MID SPAN
200 200
VERTICAL BARS: 8-16 MM DIA. VERTICAL BARS: 6-16 MM DIA. VERTICAL BARS: 6-16 MM DIA.
COLUMN TIES: 10 MM DIA. 3@ 50MM, 3@75MM, 4@100MM,REST @ 200 MM O.C. COLUMN TIES: 10 MM DIA. 3@ 50MM, 3@75MM, 4@100MM,REST @ 200 MM O.C. COLUMN TIES: 10 MM DIA. 3@ 50MM, 3@75MM, 4@100MM,REST @ 200 MM O.C.
300
300
COLUMN SIZE: 250MM X 350MM COLUMN SIZE: 250MM X 300MM COLUMN SIZE: 250MM X 300MM
RB-1
GROUND FLOOR TO
SECOND FLOOR
AT SUPPORT AT MID SPAN
200 200
VERTICAL BARS: 6-16 MM DIA. VERTICAL BARS: 6-16 MM DIA. VERTICAL BARS: 6-16 MM DIA.
COLUMN TIES: 10 MM DIA. 3@ 50MM, 3@75MM, 4@100MM,REST @ 200 MM O.C. COLUMN TIES: 10 MM DIA. 3@ 50MM, 3@75MM, 4@100MM,REST @ 200 MM O.C. COLUMN TIES: 10 MM DIA. 3@ 50MM, 3@75MM, 4@100MM,REST @ 200 MM O.C.
COLUMN SIZE: 250MMX 350MM COLUMN SIZE: 250 X 300 COLUMN SIZE: 250 X 300
300
300
RB-1
SECOND FLOOR TO
ROOF BEAM
VERTICAL BARS: 6-16 MM DIA. VERTICAL BARS: 6-16 MM DIA.
COLUMN TIES: 10 MM DIA. 3@ 50MM, 3@75MM, 4@100MM,REST @ 200 MM O.C. COLUMN TIES: 10 MM DIA. 3@ 50MM, 3@75MM, 4@100MM,REST @ 200 MM O.C.
COLUMN SIZE: 250MMX 350MM COLUMN SIZE: 250 X 300