August Cost Estimate, AOC and BOQ of DPR Ward-2 Office Building
August Cost Estimate, AOC and BOQ of DPR Ward-2 Office Building
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Insurance premium for the works and materials damage for contract
1 work for all risk including riot, strike, damage, malicious damage for job 200,000.00
project 1.5 mairitenace peroid.
3 Provide personal protective equipments, first aid kits, fire extinguishers LS 15,000.00
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 2 of 2
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
ABSTRACT OF COST OF BUILDING,
LANDSCAPING, SANITARY AND
ELECTRICAL WORKS
8/11/2024 1 of 14
ABSTRACT OF COST
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 2 of 14
ABSTRACT OF COST
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Centering and shuttering with water proof 12mm plywood material for foundations, MTM Building Rate
beams and slabs including all necessary propping, scaffolding, staging, analysis FY
Sq.m 3,170.34 1,357.28 4,303,037.21
supporting etc. all complete as per drawing, specification, and instruction of site 80/81Samuha
engineer. Cha,51ka
Centering and shuttering with water proof 12mm plywood material for RCC band,
MTM Building Rate
sill and lintel band and other structures including all necessary propping,
Sq.m 497.70 900.00 447,931.35 analysis FY
scaffolding, staging, supporting etc. all complete as per drawing, specification,
80/81Samuha Cha,43
and instruction of site engineer.
2.05 Reinforcement
Reinforcement work including straightening, cleaning, cutting, bending, binding
MTM Building Rate
with 20 SWG of Fe500 TMT bars annealed wire & fixing in position as per
MT 119.11 149,749.50 17,835,971.34 analysis FY
drawing, bar bending schedule for raft foundation column, beam, wall, stair, slab
80/81Samuha Nka,42
in all R.C.C. works as per specification, drawing & instruction of site engineer.
Sub Total (B) 51,988,000.00
3.00 MASONRY WORK
Providing & laying local First class chimney made brick masonry work in cement,
MTM Building Rate
sand mortar (1:6) in substructure finished in perfect line & level including
3.01 cu.m 1.96 16,103.00 31,532.49 analysis FY
scaffolding, wetting the bricks, packing the joints & curing the work for atleast 7
80/81Samuha Ga,25
days complete in all thickness of walls as per drawings.
Providing & Laying First class chimney make brick masonry work OF 230mm and
100mm thk with 1:4 cement sand mortar including the cost of RCC band of 50mm MTM Building Rate
3.02 Thk. at every 1m height level and including lead up to 30m with scaffolding, cu.m 238.19 17,048.00 4,060,725.06 analysis FY
wetting the bricks, joints packing and curing the work for atleast 7 days as per 80/81Samuha Ga,24
drawing, specification & instruction all complete .
KTM Building Rate
Providing & Laying dry stone masonry work with 1:4 cement sand mortar
analysis FY
3.03 including the scaffolding, cleaning stones, joints packing and curing the work for cu.m 70.98 14,588.75 1,035,559.26
80/81Samuha
atleast 7 days as per drawing, specification & instruction all complete .
Gha,41
Sub Total (C) 5,127,000.00
4.00 OPENING WORKS
Preparation of agrakh wood Door (chaukos) as per drawing and specification
MTM Building Rate
including supply of materials,labours,making as per design/details,fixing it to
4.01 cu.m 0.29 324,649.00 92,719.75 analysis FY
perfect position, moulding on edges, grooves for plasters, fixing with necessary
80/81Samuha Ja,63
MS, steel hook locks and screws all accessories as per drawing all complete.
Preparation of Double leaf wooden core readymade Double panel Door shutter
as per drawing and specification including supply of materials, labours, making as MTM Building Rate
4.02 per design/details,fixing it with medium quality locks,handles,hinges etc with Sq.m 11.88 17,258.00 205,025.04 analysis FY
necessary MS, steel hook locks and screws all accessories as per drawing all 80/81Samuha Ja,64
complete.
Providing, fabricating & fixing aluminium curtain Windows frame using
MTM Building Rate
(100X50X1.2)mm (under ISO 9001:2000, ISO 1401:2004), thick anodized
analysis FY
4.03 Chinese section with 5mm clear float glass, U-shaped both side plastic gasket, Sq.m 168.02 6,866.00 1,153,611.59
80/81Samuha Ja, A,
steel hook locks and screws including 2mmx2mm mosquito proof fly wire mesh all
ka
accessories as per drawing all complete.
Supplying,fabricating and fixing aluminium Framed panel single leaf Door with
MTM Building Rate
anodized Colour in the Section of 101 x 45 x 1.5 mm (under ISO 9001:2000, ISO
analysis FY
4.04 1401:2004), thick anodized Chinese section with 5mm clear float glass (7.3 kg. Sq.m 74.24 7,181.00 533,081.54
80/81Samuha Ja, A,
per Sqm), U-shaped both side plastic gasket, steel hook locks and screwsas per
Ga
specifiaction and as directed by Engineer
Providing, fabricating & fixing aluminium sliding ventilation frame using
MTM Building Rate
(100X50X1.2)mm (under ISO 9001:2000, ISO 1401:2004), thick anodized
analysis FY
4.05 Chinese section with 5mm clear float glass, U-shaped both side plastic gasket, Sq.m 14.31 6,866.00 98,252.46
80/81Samuha Ja, A,
steel hook locks and screws including 2mmx2mm mosquito proof fly wire mesh all
ka
accessories as per drawing all complete.
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 3 of 14
ABSTRACT OF COST
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Supplying,fabricating and fixing rolling shutter with aluminium Framed panel with
MTM Building Rate
shutter Door with anodized Colour in the Section of 101 x 45 x 1.5 mm (under ISO
analysis FY
4.06 9001:2000, ISO 1401:2004), thick anodized Chinese section with 5mm clear float Sq.m 73.31 11,635.00 852,985.12
80/81Samuha Na,
glass (7.3 kg. per Sqm), U-shaped both side plastic gasket, steel hook locks and
196
screwsas per specifiaction and as directed by Engineer
MTM Building Rate
Supplying,fabricating and fixing 3.0x22mm metal grill in windows of basement, GF
analysis FY
4.07 and FF with one coat of lead oxide paint and enamel paint per specifiaction and Sq.m 82.76 2,654.22 219,657.94
80/81Samuha ANa,
as directed by Engineer
19
Sub Total (D) 3,155,000.00
5.00 FLOOR FINISHINGS WORKS
MTM Building Rate
Providing, laying, compacting and curing average 75mm thick screed with 1:4
analysis FY
5.01 cement sand mortar in perfect lines & level as per design, specification and Sq.m 1,761.36 1,292.00 2,275,672.81
80/81Samuha Jha,
instruction of the site engineer
89
MTM Building Rate
Providing, laying, compacting and curing average 2mm thick punning with 1:1
analysis FY
5.02 cement sand paste in perfect lines & level as per design, specification and Sq.m 522.73 327.00 170,931.51
80/81Samuha Jha,
instruction of the site engineer
112
Providing & laying glazed non skid ceramic, porcelain/granamite wall & tiles of
MTM Building Rate
Johnson, Cotto or equivalent brand in 1:4 cement sand mortar in perfect lines &
analysis FY
5.03 level finishing the joint with white cement with or without pigments where Sq.m 412.93 3,705.96 1,530,306.85
80/81Samuha Jha,
necessary all complete as per design drawings, patterns, specifications and
96
instruction of the site engineer.
Providing & laying /semi glazed skid ceramic, porcelain/granamite floor tiles of
MTM Building Rate
Johnson, Cotto or equivalent brand in 1:4 cement sand mortar in perfect lines &
analysis FY
5.04 level finishing the joint with white cement with or without pigments where Sq.m 125.95 3,640.97 458,593.55
80/81Samuha Jha,
necessary all complete as per design drawings, patterns, specifications and
95
instruction of the site engineer.
Providing, laying, grinding & polishing 9-10 mm thick Vetrified Terracota
MTM Building Rate
terrace Tiles of 2'x2' or 2'x4' of approved colour and quality (Jonshon or
analysis FY
5.05 Somany) in floor with 1:3 c/s mortar over already screed surface in perfect line & Sq.m 308.62 3,707.00 1,144,051.79
80/81Samuha Jha,
level all complete as per design, patterns, specification and instruction of site
96
engineer. (Terrace,Balcony)
Providing, laying, grinding & polishing 9-10 mm thick Vetrified Floor Tiles of
MTM Building Rate
2'x2' or 2'x4' of approved colour and quality (Jonshon or Somany) in floor with 1:3
analysis FY
5.06 c/s mortar over already screed surface in perfect line & level all complete as per Sq.m 400.28 3,707.00 1,483,838.87
80/81Samuha Jha,
design, patterns, specification and instruction of site engineer. (Floor, Foyer,
96
Lobby)
5.07 WATER PROOFING WORKS
Providing, mixing & applying two coat of acrylic polymer waterproofing using MTM Building Rate
RHEOCREAT, CRETOPROOF or equivalent with surface preparation,chipping analysis FY
Sq.m 733.36 480.76 352,568.70
and removing adhesive on floor/roof slab/wall as per manufacturer's specification 80/81Samuha Da,
and instruction of site engineer. 176
5.08 GRANITE WORKS
Providing, laying, grinding & polishing 16 mm thick granite of approved colour MTM Building Rate
and quality in staircase and lobby with 1:3 c/s mortar over already screed surface analysis FY
Sq.m 8.00 7,921.00 63,392.15
including polishing and moulding in perfect line & level all complete as per 80/81Samuha Da,
design, patterns, specification and instruction of site engineer. 226
5.09 PARQUETING WORKS
Providing, laying 12mm thick laminated parquet with polishing of approved colour
Kathmandu District
and quality in rooms over 1:3 c/s mortar over already screed surface in perfect
Sq.m 80.60 3,217.76 259,350.85 rate 80/81 samuha
line & level all complete as per design, patterns, specification and instruction of
jha, 149
site engineer.
5.10 FALSE CEILING WORKS
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 4 of 14
ABSTRACT OF COST
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Eco friendly Green certified minimum 12 mm thick gypsum false ceiling with water
Kathmandu District
proof aluminium foil on top of Armstrong,Boral or equivalent with necessary
Sq.m 553.27 1,175.53 650,380.02 rate 80/81 samuha
provisions for light fittings,light boxes with painting works, all completed as per
Tha, 309
technical drawings,specification and instructions of site engineer.
5.11 MARBLE WORKS
Providing, laying, grinding & polishing 14 mm thick marble of approved colour MTM Building Rate
and quality in staircase and lobby with 1:3 c/s mortar over already screed surface analysis FY
Sq.m 243.56 5,425.77 1,321,496.20
including polishing and moulding in perfect line & level all complete as per 80/81Samuha Jha,
design, patterns, specification and instruction of site engineer. 94
Providing, laying, grinding & polishing 14 mm thick marble skirting of 100mm on MTM Building Rate
staircase and lobby of approved colour and quality in floor with 1:3 c/s mortar over analysis FY
Sq.m 211.88 4,340.62 919,674.90
already screed surface including polishing and moulding in perfect line & level all 80/81Samuha Jha,
complete as per design, patterns, specification and instruction of site engineer. 94
5.12 BRICK CLADDING WORKS
KTM Building Rate
Providing, laying, grinding & polishing 100 mm thick brick cladding in exterior
analysis FY
wall with 1:3 c/s mortar polishing and moulding in perfect line & level all Sq.m 346.63 3,206.13 1,111,332.74
80/81Samuha Jha,
complete as per design, patterns, specification and instruction of site engineer.
162
Sub Total (E) 11,741,000.00
6.00 PLASTERING WORKS
Providing, laying & curing cement sand (1:4) Plastering on internal and external MTM Building Rate
wall to perfect plumb, lines & level icluding raking the mortar joints and wetting the analysis FY
6.01 Sq.m 3,489.87 470.28 1,641,213.89
masonry surface all complete as per design drawings, specifications and 80/81Samuha Ya,
instrcution of the site engineer all complete: 127
Providing, laying & curing cement sand (1:3) Plastering on ceilings to perfect MTM Building Rate
plumb, lines & level icluding raking the mortar joints and wetting the masonry analysis FY
6.02 Sq.m 1,879.36 553.08 1,039,438.89
surface all complete as per design drawings, specifications and instrcution of the 80/81Samuha Ya,
site engineer all complete: 126
Sub Total (F) 2,680,000.00
7.00 PAINTING WORK
MTM Building Rate
Providing and laying 2mm thick plain white Putty on internal walls Ceilings and
analysis FY
7.01 False ceiling surfaces with proper finishing , work all complete as per specification Sq.m 4,438.22 279.12 1,238,797.20
80/81Samuha Tha,
and approval of site Engineer.
ka
Providing and applying washable emulsion paint with primer coat with specified MTM Building Rate
and approved shadein two coats over wall putty inclusive of surface preparation of analysis FY
7.02 Sq.m 4,438.22 249.00 1,105,117.88
providing puttying sanding surface, watering(if necessary), cleaning as per 80/81Samuha Ta,
specifications, drawings and instruction all complete. 146
Providing and applying over wall putty surface with specified Weather Coat paint MTM Building Rate
of approved shadein two coats inclusuive of primer coat, surface preparation of analysis FY
7.03 Sq.m 919.51 296.00 272,175.63
providing puttying sanding surface, watering(if necessary), cleaning as per 80/81Samuha Ta,
specifications, drawings and instruction of the site engineer 147
Sub Total (G) 2,616,000.00
8.00 HAND RAILING WORKS
Supplying and fixing 50 mm wooden hand railing in staircase with vertical post at MTM Building Rate
2 m c/c spacing and three layers of 25 mm wooden pipes to the height of 2'-6" to analysis FY
8.01 R.m 46.72 11,465.00 535,644.80
3' in perfect line and level all complete as per design, drawings , specifications 80/81Samuha 226,
and approval of site Engineer 229
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 5 of 14
ABSTRACT OF COST
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
1.1 cPVC pipe ½" (15 mm) (SDR-11) Rm 5.50 547.40 3,010.70
1.2 cPVC pipe ¾" (20 mm) (SDR-11) Rm 52.13 650.90 33,934.12
1.3 cPVC pipe 1" (25 mm) (SDR-11) Rm 162.00 918.85 148,853.70
1.4 cPVC pipe 1¼" (32 mm) (SDR-11) Rm 38.41 1,038.45 39,891.68
1.5 cPVC pipe 1½" (40 mm) (SDR-11) Rm 27.44 1,146.55 31,460.21
Soil,Waste and Rain Water Drainage Pipe Line(from toilets/roofs to the duct and
2
then to the nearest manholes)
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 6 of 14
ABSTRACT OF COST
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Soil,Waste, Vent and Rain Water Pipe Line having Unplastisied Poly Vinyl
Chloride (upvc) Pipes conforming to nepal standard (NS :206) of panchkanya or
Janta of nepal of the following sizes in upvc Adhesive cement solvent and/or 'O'
Ring Socket Joints with necessary upvc pipe fittings conforming to indian
standard (IS) of prince or supreme of india with or without clean outs as per the
condition, cutting the pipes to the required lenghts and fixiing pipe sleeves in thte
wall, clamps ,hangers,brackets,supports etc of approved type including making
holes/pockets in walls or floor and making good the same to the original condition,
testing the pipe line by Smoke Test, rectifying the leakage , if any, all complete as
per the specification and instruction
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 7 of 14
ABSTRACT OF COST
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
4 Urinal
a)Supply and commissioning of white glaze poreaselin clayurinal (46.5 X 35.3 X
26.5cm) with complete accessories. 15 mm stianless steel angle valve, 15 mm
set 20.00 4,371.15 87,423.00
flush cock push type and 15 mm spread etc as per drawings, specification and
instruction all complete.
5 Partition
a) Supply and commissioning of white glaze porcelain clay urinal partition (68 X
30 cm) with complete accessories as per drawings, specification and instruction set 12.00 3,455.75 41,469.00
all complete.
6 Grab Bar Bend type
a) Supply, delivery and commissioning of Grab Bar bend type made of stainless
set 8.00 10,842.20 86,737.60
steel 60 CM long tightness as per Schedule.
7 Sanitary assosaries
Supply & commissioning of Types LM consisting of bevelled edged Mirror 55 X
7.1 40 X cm, back CP clamps, screws & CP cap all complete etc. complete. nos 4.00 2,094.15 8,376.60
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 8 of 14
ABSTRACT OF COST
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
* The point wiring under this item shall be measured from the switch box to the
light/fan/sockets. cost shall include with The wiring from the respective DB's to
switch box and looping points to Light/Fan/Socket etc.. No separate payments for
point wirings and circuit wiring shall be paid. All wiring should confirm to IS: 732-
1982.
1 1 way Light points by means of 2x1.5 sq. mm; COCOND single core Multistrend
pts 270.00 1,400.34 378,092.40
wire with modular type gang switches within 20 mm conduit.
2 2 way Light points by means of 3x1.5 sq. mm; COCOND single core Multistrend
pts 30.00 1,915.52 57,465.50
wire with modular type gang switches with 20 mm conduit.
Wiring for General power outlets wiring with 2x 2.5 + 1x 1.5sq.mm PVC insulated
multi strand, 1100 V grade copper wire through 20/25mm grade HDP conduit in
3 walls, ceilings, false ceiling and floors including ,bends ,GI metal Box saddle and pts 180.00 2,207.43 397,336.50
all neceesary accessories for conduit as per drawing and instruction all complete.
AC Point Wiring for General power outlets wiring with 2x 4 + 1x 2.5sq.mm PVC
insulated multi strand, 1100 V grade copper wire through 20/25mm grade HDP
4 conduit in walls, ceilings, false ceiling and floors including ,bends ,GI metal Box pts 15.00 4,133.48 62,002.25
saddle and all neceesary accessories for conduit as per drawing and instruction
all complete.
5 Switches and Sockets ( Modular Type )
Supply, Delivery, Installation Testing and Commissioning of following Modular
type Switches/Sockets with all applicable accessories such as Heavy Duty GI
Metal Box /PVC Box, Junction Box all complete.(Make: ABB,Schneider,
North west or equivalent )
5.1 1 Gang 1 way switch nos 42.00 348.45 14,634.90
5.2 2 Gang 1 way switch nos 15.00 512.90 7,693.50
5.3 1 Gang 2 way swtich nos 10.00 381.80 3,818.00
5.4 2 Gang 2 way swtich nos 7.00 579.60 4,057.20
5.5 3 Gang 1 way switch nos 15.00 707.25 10,608.75
5.6 4 Gang 1 way switch nos 2.00 917.70 1,835.40
5.7 6 Gang 1 way switch nos 5.00 1,466.25 7,331.25
5.8 6/13 A , 3 Pin Universal Switch Socket . nos 55.00 877.45 48,259.75
5.9 6/16 A , 6 Pin Switch Socket . nos 125.00 951.05 118,881.25
Sub-total for Light and Power Point Wiring= 1,112,000.00
B Lighting Fixtures with all required fixing and mounting
accessories all complete:
(Fixtures Make: Jaquar, Legro, Wipro, Brilliant, or eqv.)
1 Supply and install wall mounted Up Down Light, 12 Watts, 3000K, IP 65 luminaire
made of high grade aluminium extrusion & die cast aluminium heatsink for
effective heat dissipation with high efficient COB for better output, including all
set 15.00 7,500.00 112,500.00
accessories and connecting, fixing and insulating materials as per the drawings,
site conditions, list of approved manufacturer, and direction of Engineer.
2 Supply, installation and testing of Mirror Light with 6/9 Watt LED Lamp and Inbuilt
LED Driver, all complete as per the drawings, site conditions, list of approved set 15.00 1,275.35 19,130.25
manufacturer, and direction of Engineer.
3 Supply, installation and testing of 9 watt Ceiling LED Panel Light (surface/recess)
all complete as per the drawings, site conditions, list of approved manufacturer, set 45.00 1,735.35 78,090.75
and direction of Engineer.
4 Supply, installation and testing of 12 watt Ceiling LED Panel Light
(surface/recess) all complete as per the drawings, site conditions, list of approved set 80.00 2,091.85 167,348.00
manufacturer, and direction of Engineer.
5 Supply, installation and testing of 600mm x 600mm Concealed/Surface
BACKLIT LED (36/40W, 6000k) luminaire with high efficient flat
set 90.00 6,706.80 603,612.00
PMMA low glare diffuser, all complete as per design, list of
approved make and direction of Engineer.
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 9 of 14
ABSTRACT OF COST
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
6 Supply, installation and testing of 20 watt 4 feet led batten light , all complete as
set 32.00 1,672.10 53,507.20
per design, list of approved make and direction of Engineer.
7 Supply, installation and testing of 12 Watt LED Gate light. set 2.00 6,500.00 13,000.00
8 Supply, installation and testing of 12 Watt LED Bulkhead light all complete. set 18.00 3,289.00 59,202.00
Sub Total of Light Fixtures= 1,106,000.00
C Power and Feeders Cable:
Supply, installation and inter connection of following sizes of 1100 volt grade PVC
insulation XLPE cable in Tray/cable trench/buried in ground/clamped to wall with
suitable clamps / trefoil clamps for single core cable, saddles and fixing bolts and
including testing and commissioning as required complete as per IS 7098 Part I,
IS 1554 and IS - 694 required. The costs shall include for all cables to be provided
suitable cable Sockets, Lugs, Double compression Glands, Metal/PVC tags, PVC
ties, dressing clamps or GI strips as per specification and as required. Cable
installation shall be carried out as per relevant IS codes and standards. Cables:
Janta/Pioneer/Litmus; Cable Terminals and Accessories- Jainson / Dowells or
equivalent. Note-The quote of the cable shall include the required and suitable
cable terminations lugs and accessories.
1 3.5 core 95 sq. mm; Arm. Aluminium conductor XLPE PVC cable mtr 30.00 1,181.05 35,431.50
2 3.5 core 70 sq. mm; Arm. Copper conductor XLPE PVC cable +1x 25 sq mm cu
mtr 50.00 605.02 30,250.75
wire with conduit
3 (4Cx25+1x10) sq. mm; arm. Copper conductor PVC cable r mt 50.00 370.65 18,532.25
4 (4Cx16+1x6) sq. mm; arm. Copper conductor PVC cable r mt 55.00 1,293.24 71,128.14
5 (4Cx10+1x6) sq. mm; Unarm. Copper conductor PVC cable r mt 100.00 958.59 95,858.89
6 (4Cx6+1x4) sq. mm; arm. Copper conductor PVC cable r mt 60.00 684.01 41,040.43
7 (4Cx4+1x2.5) sq. mm; Unarm. Copper conductor PVC cable r mt 50.00 409.07 20,453.39
8 (2Cx10+1x6) sq. mm; Copper PVC cable r mt 40.00 591.74 23,669.56
9 3Cx4) sq. mm; Copper PVC cable r mt 50.00 310.50 15,525.00
10 (2x4+1x2.5) sq. mm; Copper PVC cable r mt 100.00 409.07 40,906.78
11 (3x2.5) sq. mm; Copper PVC cable r mt 200.00 236.90 47,380.00
12 300x40x2 Cable Ladder with horizontal & vertical bends, reducers, Tee's, Cross
over member and other accessories as required and duly suspended from the
ceiling with supports confirming to IEC-61537. The Cable Ladder shall be made of
2 mm thick sheet steel hot dip galvanised (confirming to ISO 1461). The cable
ladder should be tested for safe working load of 200 Kg / Mtr with a span distance
of 2 Mtr the deflection should be within the limits as per the standards. The cable mtr 20.00 3,769.70 75,394.00
ladder shall be supplied in standard length of 3000/6000 mm. The rung size shall
be of 30x15mmm size suitable for fixing the cable clamps the space between the
rungs shall be 300mm. It shall be UL and VDE tested and approved and shall be
EMC Compliance.
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 10 of 14
ABSTRACT OF COST
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
9. All MCCB’s shall be with thermal magnetic releases up to 250 amps and
microprocessor based above 250 amps capacity, unless specified otherwise.
1 Main Switchgear consisting of: (MDB) located at Sub Station set 1.00 306,744.10 306,744.10
160 A, 4P MCCB 25KA 1 nos
250 amps 4 pole (35 KA) with Earth (minimum 50% of Phase cross section)
copper bus bars with colour coded heat shrinkable insulating sleeves - 1 set
63 A, TP MCCB 1 nos
50 A, TP MCCB 5 nos
32-40 A, TP MCCB 5 nos
32-25A, DP MCB 6 nos
6/16 A, SP MCB 6 nos
Required Indicating Devices - 1 lot
Multifunctional meter (conzerv – EM 6100 or equivalent) of accuracy class-I, with
3 Nos. /5 amps 15VA CTs to measure VAF and PF - 1 set
20KA Surge protection device-1set
2 Electric Vehicles DB set 1.00 180,259.05 180,259.05
Incoming
50 amps TP MCCB - 1 set
150 amps 3 pole (25 KA) with Earth (minimum 50% of Phase cross section)
copper bus bars with colour coded heat shrinkable insulating sleeves - 1 set
Under/Over Voltage Protection Relay with required Contactor and timer
Outgoing
4 no 25 A TP MCB
12 Nos. 25 A DP ,MCB
Multifunctional meter (conzerv – EM 6100 or equivalent) of accuracy class-I, with
3 Nos. /5 amps 15VA CTs to measure VAF and PF - 1 set
20KA Surge protection device-1set
Required Indicating Devices - 1 lot
3 Ground Floor DB set 1.00 64,207.95 64,207.95
Incoming
40 amps TP MCCB - 1 set
100 amps 3 pole (25 KA) with Earth (minimum 50% of Phase cross section)
copper bus bars with colour coded heat shrinkable insulating sleeves - 1 set
Outgoing
1 Nos. 25 A TP ,MCB
6 Nos. 25 A DP ,MCB
3 Nos. 6 A SP ,MCB
3 Nos. 16 A SP ,MCB
Required Indicating Devices - 1 lot
4 First Floor DB set 1.00 110,351.70 110,351.70
Sec A
Incoming
32 amps TP MCCB - 1 set
100 amps 3 pole (25 KA) with Earth (minimum 50% of Phase cross section)
copper bus bars with colour coded heat shrinkable insulating sleeves - 1 set
Outgoing
6 Nos. 6 A SP ,MCB
6 Nos. 16 A SP ,MCB
Required Indicating Devices - 1 lot
UPS Sec
Incoming
20 amps DP MCB - 1 set
100 amps 2 pole (25 KA) with Earth (minimum 50% of Phase cross section)
copper bus bars with colour coded heat shrinkable insulating sleeves - 1 set
Outgoing
4 Nos. 10 A SP ,MCB
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 11 of 14
ABSTRACT OF COST
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 12 of 14
ABSTRACT OF COST
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Incoming
25 amps DP MCB - 1 set
100 amps 2 pole (25 KA) with Earth (minimum 50% of Phase cross section)
copper bus bars with colour coded heat shrinkable insulating sleeves - 1 set
Outgoing
3 Nos. 6 A SP ,MCB
6 Nos. 16 A SP ,MCB
Required Indicating Devices - 1 lot
8 HVAC DB set 1.00 57,199.85 57,199.85
Incoming
40 amps TP MCCB - 1 set
100 amps 3 pole (25 KA) with Earth (minimum 50% of Phase cross section)
copper bus bars with colour coded heat shrinkable insulating sleeves - 1 set
Outgoing
5 no 32 A TP MCB
Required Indicating Devices - 1 lot
9 UPS DB set 1.00 24,610.00 24,610.00
Incoming
32 amps DP MCB - 1 set
100 amps 2 pole (25 KA) with Earth (minimum 50% of Phase cross section)
copper bus bars with colour coded heat shrinkable insulating sleeves - 1 set
Outgoing
2 no 25 A DP MCB
2 no 20 A DP MCB
2 no 16 A DP MCB
Required Indicating Devices - 1 lot
10 Outdoor Lighting DB set 1.00 22,588.30 22,588.30
Incoming
25 amps TP MCB - 1 set
100 amps 3 pole (25 KA) with Earth (minimum 50% of Phase cross section)
copper bus bars with colour coded heat shrinkable insulating sleeves - 1 set
Outgoing
3 Nos. 6 A SP ,MCB
6 Nos. 16 A SP ,MCB
Required Indicating Devices - 1 lot
11 Lift DB set 1.00 30,411.75 30,411.75
Incoming
50 amps TP MCCB - 1 set
100 amps 3 pole (25 KA) with Earth (minimum 50% of Phase cross section)
copper bus bars with colour coded heat shrinkable insulating sleeves - 1 set
Outgoing
6A, SP MCB 3 nos
16A, SP MCB 3 nos
Required Indicating Devices - 1 lot
Sub Total for Distribution Boards= 1,152,000.00
E Earthing System
1 Earthing system including earth works in excavation and back filling as per IS
3043-1966 specifications and instruction such that the earth resistance should not
set 1.00 26,667.35 26,667.35
exceed 3 ohm as per Specification and drawings , with following accessories:
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 13 of 14
ABSTRACT OF COST
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 14 of 14
ABSTRACT OF COST
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
4 Wiring of Router with CAT 6, 4 pair cable in HDPE conduit for wireless networking
Points 3.00 3,808.47 11,425.41
purpose.
Sub Total for Computer Network System= 112,000.00
J Attendance System and Multimedia Projection
1 8 c x 0.75 Sq.mm in PVC Conduit with Accessories and GI Sadel spacers in
point 1.00 4,500.00 4,500.00
Every 0.3 meter with 2c X 1mm Power Cable in HDPE Pipe with accessory
Sub Total for Attendance System and Multimedia Projection= 4,500.00
Total Cost of Electrical and Allied works= 4,298,000.00
(Note: Rate analysis is based on Madhyapur Thimi Municipality of Bhaktapur Fiscal year 2080/81 BS and some rates which are not included in MTM i.e parqueting
works(5.08), false ceiling works(5.09), cladding works (7.04)and gardening works(9.03),, those are taken from Kathmandu District rate 2080/81 BS
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
BILL OF QUANTITIES OF BUILDING,
LANDSCAPING, SANITARY AND
ELECTRICAL WORKS
8/11/2024 1 of 16
BILL OF QUANTITIES
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 2 of 16
BILL OF QUANTITIES
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Centering and shuttering with water proof 12mm plywood material for all kinds of
work including all necessary propping, scaffolding, staging, supporting etc. all Sq.m 497.70
complete as per drawing, specification, and instruction of site engineer.
2.05 Reinforcement
Reinforcement work including straightening, cleaning, cutting, bending, binding
with 20 SWG of Fe500 TMT bars annealed wire & fixing in position as per
MT 119.11
drawing, bar bending schedule for raft foundation column, beam, wall, stair, slab
in all R.C.C. works as per specification, drawing & instruction of site engineer.
Sub Total (B)
3.00 MASONRY WORK
Providing & laying local First class chimney made brick masonry work in
cement, sand mortar (1:6) in substructure finished in perfect line & level
3.01 Cu.m 1.96
including scaffolding, wetting the bricks, packing the joints & curing the work for
atleast 7 days complete in all thickness of walls as per drawings.
Providing & Laying First class chimney make brick masonry work of 230mm and
100mm thk with 1:4 cement sand mortar including the cost of RCC band of
3.02 50mm Thk. at every 1m height level and including lead up to 30m with Cu.m 238.19
scaffolding, wetting the bricks, joints packing and curing the work for atleast 7
days as per drawing, specification & instruction all complete .
Providing & Laying dry stone masonry work with 1:4 cement sand mortar
3.03 including the scaffolding, cleaning stones, joints packing and curing the work for Cu.m 70.98
atleast 7 days as per drawing, specification & instruction all complete .
Sub Total (C)
4.00 OPENING WORKS
Preparation of agrakh wood Door (chaukos) as per drawing and specification
including supply of materials,labours,making as per design/details,fixing it to
4.01 Cu.m 0.29
perfect position, moulding on edges, grooves for plasters, fixing with necessary
MS, steel hook locks and screws all accessories as per drawing all complete.
Preparation of Double leaf wooden core readymade Doublepanel Door shutter
as per drawing and specification including supply of materials, labours, making
4.02 as per design/details,fixing it with medium quality locks,handles,hinges etc with Sq.m 11.88
necessary MS, steel hook locks and screws all accessories as per drawing all
complete.
Providing, fabricating & fixing aluminium curtain Windows frame using
(100X50X1.2)mm (under ISO 9001:2000, ISO 1401:2004), thick anodized
4.03 Chinese section with 5mm clear float glass, U-shaped both side plastic gasket, Sq.m 168.02
steel hook locks and screws including 2mmx2mm mosquito proof fly wire mesh
all accessories as per drawing all complete.
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 3 of 16
BILL OF QUANTITIES
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 4 of 16
BILL OF QUANTITIES
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 5 of 16
BILL OF QUANTITIES
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Providing and applying over wall putty surface with specified Weather Coat
paint of approved shadein two coats inclusuive of primer coat, surface
7.03 Sq.m 919.51
preparation of providing puttying sanding surface, watering(if necessary),
cleaning as per specifications, drawings and instruction of the site engineer
Sub Total (G)
8.00 STAINLESS STEEL RAILING WORKS
Supplying and fixing 50 mm wooden hand railing in staircase with vertical post at
2 m c/c spacing and three layers of 25 mm wooden pipes to the height of 2'-6" to
8.01 R.m 46.72
3' in perfect line and level all complete as per design, drawings , specifications
and approval of site Engineer
50 mm dia SS wall hand rail, 50mm dia 0.45 mtr ht. vertical steel pipe placed at
8.02 1.5 mtr c/c , 25 mm dia 2 layer horizontal steel pipe placed between vertical pipe R.m 44.51
for Verandah and ramp Railing as per specification and as directed by Engineer.
Sub Total (H)
9.00 LANDSCAPING WORKS
9.01 INTERLOCKING BLOCKS PAVEMENT WORKS
Providing and laying hexagonal 2" thick interlocking blocks on footway in perfect
plumb, lines & level icluding all complete as per design drawings, specifications Sq.m -
and instrcution of the site engineer all complete:
9.02 OPEN SURFACE DRAIN WORKS
Providing and laying open surface drain on periphery of building in desired
longitudinal and cross slope with designed brickwork, plaster and punning works
R.m 81.40
in perfect plumb, lines & level icluding all complete as per design drawings,
specifications and instrcution of the site engineer all complete:
9.03 GARDENING WORKS
Providing and laying the natural green grass,bushes and dubos in the well
compacted earth soil in required lines and level as per design, specification and Sq.m 5.40
instruction of the site engineer.
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 6 of 16
BILL OF QUANTITIES
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Soil,Waste and Rain Water Drainage Pipe Line(from toilets/roofs to the duct and
2
then to the nearest manholes)
Soil,Waste, Vent and Rain Water Pipe Line having Unplastisied Poly Vinyl
Chloride (upvc) Pipes conforming to nepal standard (NS :206) of panchkanya or
Janta of nepal of the following sizes in upvc Adhesive cement solvent and/or 'O'
Ring Socket Joints with necessary upvc pipe fittings conforming to indian
standard (IS) of prince or supreme of india with or without clean outs as per the
0
condition, cutting the pipes to the required lenghts and fixiing pipe sleeves in
thte wall, clamps ,hangers,brackets,supports etc of approved type including
making holes/pockets in walls or floor and making good the same to the original
condition, testing the pipe line by Smoke Test, rectifying the leakage , if any, all
complete as per the specification and instruction
2.1 1½" (50mm) (4 kgf/sq cm) RM 68.29
2.2 2½" (75mm) (4 kgf/sq cm) RM 102.34
2.3 4" (110mm) (4 kgf/sq cm) RM 102.34
2.4 6" (140mm) (6kgf/sq cm) RM 67.51
2.5 PVC Floor Trap 110/75 nos 37.00
2.6 PVC greating 4" nos 37.00
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 7 of 16
BILL OF QUANTITIES
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
3 Ball Valve for CPVC or Upvc Pipe line of ASTRAL,india of the following pipe size
3.1 ¾" dia CPVC Ball Valve, CTS Socket nos 2.00
3.2 1" dia CPVC Ball Valve, CTS Socket nos 6.00
3.3 1¼" dia CPVC Ball Valve, CTS Socket nos 2.00
3.4 1½" dia CPVC Ball Valve, CTS Socket nos 3.00
B. Sanitary Fixture
1 Water Closet Set :
a) Supply, delivery and commissioning of white vitreous One Piece Commod
made of sanitary ceramics 61.5 X 37 X 70 CM with intended use of Personal
Hygiene assessment and verification of contancy of performanceof Capacity of
0 set 13.00
flushing water, Angle valve dia ½", Connector pipe 24" long, Backflow
Prevention, Cleanability, Load Resistance , Durability, Water/Leak tightness as
per Schedule.
b) Supply, delivery and commissioning of white vitreous Commod made of
sanitary ceramics 61.5 X 37 X 70 CM with intended use of Personal Hygiene
0 assessment and verification of contancy of performanceof Capacity of flushing set 4.00
water, Backflow Prevention, Cleanability, Load Resistance , Durability,
Water/Leak tightness as per Schedule.
2 Flush Valve
Supply, delivery, installation, testing and commissioning of flush valve divoter
0 set 4.00
with complite set 1¼" etc as per Schedule
3 Wash Basin Set :
Supply and commissioning of white vitreous ovel Basin 53 X 41 X 20.5 CM
made of sanitary ceramics with intended use of performances of Capacity of
0 overflow, Cleanability, Load Resistance, Durability, Single lever Piller cock, set 21.00
Plastic bottle trap, Angle valve dia ½" 2 nos, Connectin pipe dia ½" 24" long as
per Schedule.
4 Urinal
a)Supply and commissioning of white glaze poreaselin clayurinal (46.5 X 35.3 X
26.5cm) with complete accessories. 15 mm stianless steel angle valve, 15 mm
0 set 20.00
flush cock push type and 15 mm spread etc as per drawings, specification and
instruction all complete.
5 Partition
a) Supply and commissioning of white glaze porcelain clay urinal partition (68 X
0 30 cm) with complete accessories as per drawings, specification and instruction set 12.00
all complete.
6 Grab Bar Bend type
a) Supply, delivery and commissioning of Grab Bar bend type made of stainless
0 set 8.00
steel 60 CM long tightness as per Schedule.
7 Sanitary assosaries
Supply & commissioning of Types LM consisting of bevelled edged Mirror 55 X
7.1 nos 4.00
40 X cm, back CP clamps, screws & CP cap all complete etc. complete.
Supply, delivery, installation, testing and commissioning of Essential health
7.2 set 13.00
fauset (water spray) etc as per Schedule
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 8 of 16
BILL OF QUANTITIES
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
8 Kitchen Sink
Supply and commissioning of Stineless steel sink bowl with diamond board
8.1 ordinary 37" long made of stainlessl steel with intended use of Personal Hygiene set 2.00
(PH) system, Single lever long handle tap, Plastic bottle trap as per Schedule.
9 Plastic Water Storage Tank Set :
Over Head Water Storage Tank Set - 'Type-WT' consisting of 2'000 liters
capacity Molded High Density Polyethyiene Water Storage Tank having,
9.1 set 2.00
Lockable Cover and necessary connection for Inlets,Out lets, Over Flow & Drain
Pipe Line, etc as per Schedule
10 Water pump
Supply, delivery,installation, testing and commissioning of Essential 1 HP
10.1 set 1.00
Submersible water pump etc as per Schedule
11 Manholes
Manhole having Inside size 450mmX450mm up to 450mm deep including
11.1 nos 6.00
450mm x450mm double seal iron (CI) frame cover as per drawing
Manhole having Inside size 450mmX450mm up to 600mm deep including
11.2 nos 2.00
450mm x450mm double seal iron (CI) frame cover as per drawing
Cast iron Manhole cover and Reserve tank cover 450 X 450 Medium Duty (14
11.3 nos 10.00
kg)
Uunderground RCC reserve tank of 20000 lts with 2 comppartment including all
11.4 nos 1.00
civil, finishing works with water proofing as per drawing
C ELECTRICAL WORKS WITH EQUIPMENTS
A Light and Power Point Wiring (all complete with
switches/Regulators/Indicator/Bell push/sockets etc.)
(switches and sockets make: modular type Orange, ABB ,
Legrand , Schneider or eqv. with prior approval)
(Wire Make: Rathi, Pioneer, Mahalxmi, Litmus)
Point Wirings
* The point wiring under this item shall be measured from the switch box to the
light/fan/sockets. cost shall include with The wiring from the respective DB's to
switch box and looping points to Light/Fan/Socket etc.. No separate payments
for point wirings and circuit wiring shall be paid. All wiring should confirm to IS:
732-1982.
1 1 way Light points by means of 2x1.5 sq. mm; COCOND single core Multistrend
pts 270.00
wire with modular type gang switches within 20 mm conduit.
2 2 way Light points by means of 3x1.5 sq. mm; COCOND single core Multistrend
pts 30.00
wire with modular type gang switches with 20 mm conduit.
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 9 of 16
BILL OF QUANTITIES
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 10 of 16
BILL OF QUANTITIES
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
1 3.5 core 95 sq. mm; Arm. Aluminium conductor XLPE PVC cable mtr 30.00
2 3.5 core 70 sq. mm; Arm. Copper conductor XLPE PVC cable +1x 25 sq mm cu
mtr 50.00
wire with conduit
3 (4Cx25+1x10) sq. mm; arm. Copper conductor PVC cable r mt 50.00
4 (4Cx16+1x6) sq. mm; arm. Copper conductor PVC cable r mt 55.00
5 (4Cx10+1x6) sq. mm; Unarm. Copper conductor PVC cable r mt 100.00
6 (4Cx6+1x4) sq. mm; arm. Copper conductor PVC cable r mt 60.00
7 (4Cx4+1x2.5) sq. mm; Unarm. Copper conductor PVC cable r mt 50.00
8 (2Cx10+1x6) sq. mm; Copper PVC cable r mt 40.00
9 3Cx4) sq. mm; Copper PVC cable r mt 50.00
10 (2x4+1x2.5) sq. mm; Copper PVC cable r mt 100.00
11 (3x2.5) sq. mm; Copper PVC cable r mt 200.00
12 300x40x2 Cable Ladder with horizontal & vertical bends, reducers, Tee's, Cross
over member and other accessories as required and duly suspended from the
ceiling with supports confirming to IEC-61537. The Cable Ladder shall be made
of 2 mm thick sheet steel hot dip galvanised (confirming to ISO 1461). The cable
ladder should be tested for safe working load of 200 Kg / Mtr with a span
distance of 2 Mtr the deflection should be within the limits as per the standards. mtr 20.00
The cable ladder shall be supplied in standard length of 3000/6000 mm. The
rung size shall be of 30x15mmm size suitable for fixing the cable clamps the
space between the rungs shall be 300mm. It shall be UL and VDE tested and
approved and shall be EMC Compliance.
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 11 of 16
BILL OF QUANTITIES
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 12 of 16
BILL OF QUANTITIES
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 13 of 16
BILL OF QUANTITIES
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 14 of 16
BILL OF QUANTITIES
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 15 of 16
BILL OF QUANTITIES
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 16 of 16
BILL OF QUANTITIES
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
QUANTITY SUMMARY SHEET
8/11/2024 1 of 3
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Total
I/No. Description of Works Unit Remarks
Quantity
1.00 EARTHWORK AND ALLIED WORKS
1.01 Site clearance Sq.m 316.91 Cad measured
1.02 Earthwork in excavation Cu.m 1,059.41
1.03 Filling with associated Earth Cu.m 334.21
1.04 Disposal of excavated earth in safe dumping site Cu.m 725.19
1.05 Filling with one layer flat brick soling Sq.m 30.41
1.06 Filling with one layer dry stone soling Cu.m 325.36
1.07 Filling with 25mm dry fine sand Cu.m 27.14
2.00 CONCRETE AND REBAR WORKS
2.01 M10 PCC Works Cu.m 49.04
2.02 RCC Works (M20) Cu.m 553.50
2.03 RCC Works (M25) Cu.m 686.30
2.04 Formworks
Column and RCC wall Sq.m 1,121.89
Slab, beam and staircase Sq.m 3,170.34
RCC band, sill, lintel band and Other RCC structures Sq.m 497.70
2.05 Reinforcement MT 119.11
3.00 MASONRY WORK
3.01 Brick Masonry Sub Structure Cu.m 1.96
3.02 Brick Masonry Super Structure Cu.m 238.19
3.03 Stone Masonry works Cu.m 70.98
4.00 OPENING WORKS
4.01 Agrakh wood Door frame(chaukos) Cu.m 0.29
4.02 Double leaf wooden core readymade Doublepanel Door shutter Sq.m 11.88
4.03 Aluminium curtain Windows frame with shutter Sq.m 168.02
4.04 Aluminium Framed panel single leaf Door with shutter Sq.m 74.24
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 2 of 3
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Total
I/No. Description of Works Unit Remarks
Quantity
4.05 Aluminium sliding ventilation frame with shutter Sq.m 14.31
4.06 Rolling shutter with aluminium Framed panel with shutter Door Sq.m 73.31
4.07 Grillworks in Opening works Sq.m 82.76
5.00 FLOOR FINISHINGS WORKS
5.01 75mm thick screed Sq.m 1,761.36
5.02 2mm thick punning Sq.m 522.73
5.03 Glazed skid ceramic, porcelain/granamite wall tiles Sq.m 412.93
5.04 Semi glazed non skid ceramic, porcelain/granamite floor tiles Sq.m 125.95
5.05 9-10 mm thick VetrifiedTerracota Tiles of 2'x2' or 2'x4' Sq.m 308.62
5.06 9-10 mm thick Vetrified Floor Tiles of 2'x2' or 2'x4' Sq.m 400.28
5.07 WATER PROOFING WORKS Sq.m 733.36
5.08 GRANITE WORKS Sq.m 8.00
5.09 PARQUETING WORKS Sq.m 80.60
5.10 FALSE CEILING WORKS Sq.m 553.27
5.11 MARBLE WORKS
14 mm thick marble works. Sq.m 243.56
14 mm thick marble skirting Sq.m 211.88
5.12 BRICK CLADDING WORKS Sq.m 346.63
6.00 PLASTERING WORKS Sq.m
External and Internal walls Sq.m 3,489.87
Ceilings Sq.m 1,879.36
7.00 PAINTING WORK
7.01 2mm thick plain white Putty on internal walls and celings Sq.m 4,438.22
7.02 Washable emulsion paint Sq.m 4,438.22
7.03 Weather Coat paint Sq.m 919.51
8.00 STAINLESS STEEL RAILING WORKS
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 3 of 3
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Total
I/No. Description of Works Unit Remarks
Quantity
8.01 Wooden hand rail R.m 46.72
8.02 Stainless steel handrails R.m 44.51
9.00 LANDSCAPING WORKS
9.01 INTERLOCKING BLOCKS PAVEMENT WORKS Sq.m 180.40
9.02 OPEN SURFACE DRAIN WORKS R.m 81.40
9.03 GARDENING WORKS Sq.m 5.40
10.00 MISCELLANEOUS WORKS
10.10 Gravel Piling works R.m 114.00
10.2 Sheet Piling works Sq,m 92.50
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 1 of 1
1 Foundation Kg 19,095.94
2 Shear and Lift wall Kg 4,925.71
3 Column Kg 22,716.79
4 Main Beam Kg 34,484.04
5 Slab Kg 28,709.03
6 Staircase Kg 2,853.62
7 RCC Wall Kg 1,915.70
8 Sill/Lintel & RCC Band Kg 4,372.29
Total 119,073.13
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
DETAIL QUANTITY ESTIMATE
8/11/2024 1 of 1
ESTIMATE OF EARTHWORKS
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 1 of 6
ESTIMATE OF CONCRETING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
2.4 Column
C1 2.0 0.510 0.510 17.987 Cu.m 9.357
C2 5.0 0.510 0.510 17.987 Cu.m 23.392
C3 2.0 0.510 0.510 17.987 Cu.m 9.357
C4 4.0 0.510 0.510 17.987 Cu.m 18.714
C5 6.0 0.510 0.510 21.494 Cu.m 33.544
Cu.m 94.363
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 2 of 6
ESTIMATE OF CONCRETING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
3.99x3+5.13x3+
Longitudinal direction 1.0 47.805 0.254 0.281 5.105x3+5.13
Cu.m 3.412
4.75*3+5.51*3
Traverse direction 1.0 39.820 0.254 0.281 Cu.m 2.842 +4.52*2
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 3 of 6
ESTIMATE OF CONCRETING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
3.2 Staircase
3.2.1 1st Staircase of GF
1st flight 1.0 1.200 1.630 0.150 Cu.m 0.293
2nd Flight 1.0 1.200 3.730 0.150 Cu.m 0.671
Landing 1.0 1.200 1.200 0.150 Cu.m 0.216
Steps 14 1.200 0.254 0.175 Cu.m 0.747
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 4 of 6
ESTIMATE OF CONCRETING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 5 of 6
ESTIMATE OF CONCRETING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
100mm wall
Maintenance room north 2.0 3.353 0.100 0.075 Cu.m 0.05
Maintenance room east 2.0 8.839 0.100 0.075 Cu.m 0.13
Revenue room east 2.0 7.010 0.100 0.075 Cu.m 0.11
Revenue room north 2.0 5.339 0.100 0.075 Cu.m 0.08
Data Chalani east 2.0 4.443 0.100 0.075 Cu.m 0.07
Data chalani north 2.0 4.877 0.100 0.075 Cu.m 0.07
Planning room west 2.0 5.283 0.100 0.075 Cu.m 0.08
store room 2.0 5.500 0.100 0.075 Cu.m 0.08
pantry room 2.0 5.553 0.100 0.075 Cu.m 0.08
Passage west 2.0 1.702 0.100 0.075 Cu.m 0.03
passage south 2.0 10.490 0.100 0.075 Cu.m 0.16
Men toilet room south 2.0 2.821 0.100 0.075 Cu.m 0.04
Men toilet room east 2.0 3.454 0.100 0.075 Cu.m 0.05
Men shower room 2.0 8.14 0.100 0.075 Cu.m 0.12 2.79*2+1.28*2
Women toilet 2.0 6.52 0.100 0.075 Cu.m 0.10 2.661+3.863
Janitor room 2.0 2.30 0.100 0.075 Cu.m 0.03 0.825+0.737*2
Women shower 2.0 4.78 0.100 0.075 Cu.m 0.07 2.972+1.803
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 6 of 6
ESTIMATE OF CONCRETING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 1 of 4
ESTIMATE OF FORMWORK
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
3.76+4.98+4.875
Grid A,B,C 3.00 18.595 0.433 Sq.m 48.310 +4.98
3.99x3+5.13x3+
Longitudinal direction 1.00 47.805 0.281 Sq.m 26.866 5.105x3+5.13
4.75*3+5.51*3
+4.52*2
1st,2nd,3rd Floor
3.76+4.98+4.875
Grid A,B,C 9.00 18.595 0.433 Sq.m 144.929 +4.98
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 2 of 4
ESTIMATE OF FORMWORK
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
3.99x3+5.13x3+
Longitudinal direction 3.00 47.805 0.281 Sq.m 80.599 5.105x3+5.13
4.75*3+5.51*3
Traverse direction 3.00 39.820 0.281 Sq.m 67.137 +4.52*2
4th Floor
3.76+4.98+4.875
Grid A,B,C 3.00 20.425 0.433 Sq.m 53.064 +4.98+0.915x2
3.76+4.98+4.875
Grid D 1.00 15.445 0.433 Sq.m 13.375 +0.915*2
4.52+5.285+4.37
Grid 1,2,3,4 4.00 16.005 0.433 Sq.m 55.441 +0.915*2
4.52+5.285+0.915
Grid 5 1.00 11.635 0.433 Sq.m 10.076 *2
3.99x3+5.13x3+
Longitudinal direction 1.00 47.805 0.281 Sq.m 26.866 5.105x3+5.13
4.75*3+5.51*3
Traverse direction 1.00 39.820 0.281 Sq.m 22.379 +4.52*2
22.96+18.035+
13.155+
17.475+4.875+5.4
Edge beam 1.00 81.985 0.230 Sq.m 37.713 85
Top Floor
4.98x2+4.875x2+
Grid C,D 2.00 21.540 0.433 Sq.m 37.307 0.915x2
Grid 2,3,4 3.00 6.200 0.433 Sq.m 16.108 4.37+0.915*2
Longitudinal Sec beam 1.00 9.855 0.281 Sq.m 5.539 4.98+4.875
Traverse Sec beam 2.00 4.370 0.281 Sq.m 4.912
Edge beam 1.00 40.850 0.230 Sq.m 18.791 13.21*2+7.215*2
Staricase Z- beam
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 3 of 4
ESTIMATE OF FORMWORK
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 4 of 4
ESTIMATE OF FORMWORK
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
First floor
230mm wall 2.00 48.440 0.300 Sq.m 58.128 Sum of all wall
100mm wall 2.00 48.161 0.150 Sq.m 28.897 length
Second floor
230mm wall 2.00 72.490 0.300 Sq.m 86.988 Sum of all wall
100mm wall 2.00 90.402 0.150 Sq.m 54.241 length
Third floor
230mm wall 2.00 72.490 0.300 Sq.m 86.988 Sum of all wall
100mm wall 2.00 95.578 0.150 Sq.m 57.347 length
Fourth floor
230mm wall 2.00 24.077 0.300 Sq.m 28.892
497.702
Column,shear wall,RCC wall,Lift wall Sq.m 1,121.886
Foundation, Beam,slab and staircase Sq.m 3,170.339
Other RCC structures Sq.m 497.702
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 1 of 6
ESTIMATE OF REBAR
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
3.2 C2
All floors 5.00 8 17.84 713.41 25 3.85 2,749.05
5.00 8 17.84 713.41 20 2.47 1,759.39
Stirrups 5.00 119 2.03 1,207.15 8.00 0.39 476.32
10.00 119 1.57 1,870.54 8.00 0.39 738.09
3.3 C3
All floors 2.00 16 17.84 570.73 20.00 2.47 1,407.51
Stirrups 2.00 119 2.03 482.86 8.00 0.39 190.53
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 2 of 6
ESTIMATE OF REBAR
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
3.4 C4
All floors 4.00 4 17.84 285.37 25.00 3.85 1,099.62
4.00 12 17.84 856.10 20.00 2.47 2,111.27
Stirrups 4.00 119 2.03 965.72 8.00 0.39 381.06
8.00 119 1.57 1,496.43 8.00 0.39 590.47
3.5 C5
All floors 6.00 4 21.04 504.88 25.00 3.85 1,945.48
6.00 12 21.04 1,514.63 20.00 2.47 3,735.32
Stirrups 6.00 140 2.03 1,708.58 8.00 0.39 674.18
12.00 140 1.57 2,647.53 8.00 0.39 1,044.68
Total 22,716.79
4 Main Beam
5.1 Grid A and B
GF to 3rd floor 8.00 10 21.14 1,691.20 16 1.58 2,669.29
8.00 2 14.09 225.49 16 1.58 355.91
4th floor 2.00 10 22.97 459.40 16 1.58 725.09
Stirrups 1.00 1,720 1.98 3,409.49 10 0.62 2,102.08
1.00 1,720 0.71 1,222.17 10 0.62 753.52
5.2 Grid C
GF to 4th floor 5.00 10 21.14 1,057.00 16 1.58 1,668.31
5.00 4 14.09 281.87 16 1.58 444.88
Top floor 1.00 10 13.21 132.10 16 1.58 208.50
Stirrups 1.00 951 1.98 1,885.16 10 0.62 1,162.27
1.00 951 0.71 675.76 10 0.62 416.63
5.3 Grid D
GF to 4th floor 5.00 10 15.65 782.25 16 1.58 1,234.66
5.00 3 10.43 156.45 16 1.58 246.93
Top floor 1.00 10 13.21 132.10 16 1.58 208.50
Stirrups 1.00 731 1.98 1,449.58 10 0.62 893.72
1.00 731 0.71 519.62 10 0.62 320.37
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 3 of 6
ESTIMATE OF REBAR
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
5.6 Grid 4
GF to 4th floor 5.00 12 18.04 1,082.10 16 1.58 1,707.92
5.00 3 12.02 180.35 16 1.58 284.65
Top floor 1.00 10 7.22 72.20 16 1.58 113.96
Stirrups 1.00 232 1.98 459.54 10 0.62 283.33
1.00 232 1.57 364.81 10 0.62 224.92
5.7 Grid 5
GF to 3rd floor 4.00 12 11.33 543.84 16 1.58 858.36
4.00 3 7.55 90.64 16 1.58 143.06
4th floor 1.00 10 13.16 131.60 16 1.58 207.71
Stirrups 1.00 468 1.98 927.12 10 0.62 571.61
1.00 468 1.57 735.99 10 0.62 453.77
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 4 of 6
ESTIMATE OF REBAR
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
6 Slab
Ground floor 1.00 108 21.14 2,283.28 10 0.62 2,815.47
1.00 141 16.21 2,283.28 10 0.62 2,393.15
1st floor 1.00 108 21.14 2,283.28 10 0.62 2,815.47
1.00 141 16.21 2,283.28 10 0.62 2,393.15
2nd,3rd floor 2.00 108 21.14 4,566.57 10 0.62 5,630.94
2.00 141 16.21 4,566.57 10 0.62 4,786.30
4th floor 1.00 120 22.96 2,760.56 10 0.62 3,403.98
1.00 153 18.04 2,760.56 10 0.62 2,893.39
Top floor 1.00 48 13.21 635.40 10 0.62 783.50
1.00 88 7.22 635.40 10 0.62 665.97
Basement entry ramp 1.00 33 4.98 161.85 8 0.39 63.86
1.00 33 4.88 161.85 8 0.39 63.86
East ramp 1.00 24 1.68 40.87 8 0.39 16.13
1.00 11 3.66 40.87 8 0.39 16.13
Total 28,709.03
7 Staircase
7.1 1st Staircase of GF
1st flight 1.00 22 1.2 26.08 16.00 1.58 41.16
1.00 16 1.6 26.08 10.00 0.62 16.08
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 5 of 6
ESTIMATE OF REBAR
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
9 RCC Sill/Lintel band (Check sum of all length of wall in formwork sheet)
Basement floor
230mm wall 2.00 4 11.5 91.84 10.00 0.62 56.62
100mm wall 2.00 2 9.9 39.62 10.00 0.62 24.43
Stirrups 2.00 143 0.8 217.33 8.00 0.39 85.75
Ground floor
230mm wall 2.00 4 46.9 374.90 10.00 0.62 231.14
100mm wall 2.00 2 50.2 200.84 10.00 0.62 123.82
Stirrups 2.00 647 0.8 986.50 8.00 0.39 389.26
First floor
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 6 of 6
ESTIMATE OF REBAR
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Second floor
230mm wall 2.00 4 72.5 579.92 10.00 0.62 357.54
100mm wall 2.00 2 90.4 361.61 10.00 0.62 222.95
Stirrups 2.00 1,086 0.8 1,655.41 8.00 0.39 653.20
Third floor
230mm wall 2.00 4 72.5 579.92 10.00 0.62 357.54
100mm wall 2.00 2 95.6 382.31 10.00 0.62 235.71
Stirrups 2.00 1,120 0.8 1,708.01 8.00 0.39 673.95
Fourth floor
230mm wall 2.00 4 24.1 192.62 10.00 0.62 118.76
Stirrups 2.00 161 0.8 244.68 8.00 0.39 96.55
Total 4,372.29
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 1 of 5
3.00 Brickwork
3.10 Basement floor
230mm wall
Grid A 1.00 11.480 0.230 3.407 Cu.m 8.996 2.692+4.978+3.81
100mm wall
Staricase South 1.00 4.521 0.100 3.840 Cu.m 1.736
Store room east 1.00 3.200 0.100 3.840 Cu.m 1.229
Wall around void 1.00 2.184 0.100 3.840 Cu.m 0.839
3.804
3.20 Ground Floor
230mm wall
Grid A 1.00 11.474 0.230 2.642 Cu.m 6.972 2.692+4.972+3.81
Grid 1 1.00 12.141 0.230 2.642 Cu.m 7.3783.505+5.283+3.353
Grid 4 1.00 2.337 0.230 2.642 Cu.m 1.420
Grid 5 1.00 9.300 0.230 2.642 Cu.m 5.651
Staircase west 1.00 4.369 0.230 2.642 Cu.m 2.655
2.286+2.058*2+0
Lift wall 1.00 7.242 0.230 2.642 Cu.m 4.401
.42*2
28.477
100mm wall
Rental space north 1.00 20.345 0.100 3.075 Cu.m 6.26 16.586+3.759
Rental space east 1.00 1.851 0.100 3.075 Cu.m 0.57
Men toilet room south 1.00 2.821 0.100 3.075 Cu.m 0.87
Men toilet room east 1.00 3.454 0.100 3.075 Cu.m 1.06
Men shower room 1.00 8.140 0.100 3.075 Cu.m 2.50 2.79*2+1.28*2
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 2 of 5
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 3 of 5
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 4 of 5
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 5 of 5
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 1 of 7
ESTIMATE OF PLASTERING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 2 of 7
ESTIMATE OF PLASTERING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 3 of 7
ESTIMATE OF PLASTERING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 4 of 7
ESTIMATE OF PLASTERING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 5 of 7
ESTIMATE OF PLASTERING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 6 of 7
ESTIMATE OF PLASTERING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 7 of 7
ESTIMATE OF PLASTERING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
7.00 Ceiling
Ground floor 1.00 21.14 16.21 Sq.m 342.49
1st floor 1.00 21.14 16.21 Sq.m 342.49
2nd,3rd floor 2.00 21.14 16.21 Sq.m 684.99
4th floor 1.00 22.96 18.04 Sq.m 414.08
Top floor 1.00 13.21 7.22 Sq.m 95.31
Sq.m 1,879.36
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 1 of 7
ESTIMATE OF PAINTING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ...............................
Prepared by: Approved By:
ARENA ARCHITECTS DEVELOPERS .....................
8/11/2024 2 of 7
ESTIMATE OF PAINTING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ...............................
Prepared by: Approved By:
ARENA ARCHITECTS DEVELOPERS .....................
8/11/2024 3 of 7
ESTIMATE OF PAINTING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ...............................
Prepared by: Approved By:
ARENA ARCHITECTS DEVELOPERS .....................
8/11/2024 4 of 7
ESTIMATE OF PAINTING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ...............................
Prepared by: Approved By:
ARENA ARCHITECTS DEVELOPERS .....................
8/11/2024 5 of 7
ESTIMATE OF PAINTING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ...............................
Prepared by: Approved By:
ARENA ARCHITECTS DEVELOPERS .....................
8/11/2024 6 of 7
ESTIMATE OF PAINTING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ...............................
Prepared by: Approved By:
ARENA ARCHITECTS DEVELOPERS .....................
8/11/2024 7 of 7
ESTIMATE OF PAINTING
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ...............................
Prepared by: Approved By:
ARENA ARCHITECTS DEVELOPERS .....................
7/30/2024 1 of 2
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
7/30/2024 2 of 2
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 1 of 6
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 2 of 6
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 3 of 6
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 4 of 6
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 5 of 6
9.0 Railing
Wooden Staircase Railing 2.00 5.360 R.m 10.720
5.00 7.200 R.m 36.000
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 6 of 6
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 1 of 2
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 2 of 2
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 1 of 2
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
8/11/2024 2 of 2
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
7/30/2024 1 of 5
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of
ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
7/30/2024 2 of 5
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of
ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
7/30/2024 3 of 5
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of
ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
7/30/2024 4 of 5
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of
ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
B. Sanitary Fixture
1.00 a) Water Closet nos 13.00
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
7/30/2024 5 of 5
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of
ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
7/30/2024 1 of 4
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
7/30/2024 2 of 4
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
7/30/2024 3 of 4
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
7/30/2024 4 of 4
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
.................................... ....................................
Prepared by: Approved by:
ARENA ARCHITECTS DEVELOPERS Mr.Mrs............................
RATE ANALYSIS SHEET OF
SANITARY AND ELECTRICAL
WORKS
7/30/2024 1 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
B DIESEL GENERTOR
4 3.5cx150 sq.mm Al armoured cable
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.1 nos 1200.00 120.00
Semi skilled 0.15 nos 900.00 135.00
Un Skilled 0.1 nos 900.00 90.00
345.00
Aluminium
materials a. 3.5c150 sq.mm Al armoured cable 1 mtr. 1209.00 1209.00 cable c 7
b. Minor Materials 1 LS 50.00 50.00
1259.00
Actual rate 1604.00
15% conctractor overhead 240.60
Total (Rs.) 1844.60
Rate per set Rs. 1844.60
C.1 Light Point and Power Point Wiring
1 Light Point Wiring
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.1 nos 1200.00 120.00
Semi skilled 0.15 nos 900.00 135.00
Un Skilled 0.15 nos 900.00 135.00
390.00
materials a. 1.5 sq mm Cu wire 16 Rm 18.86 301.69 2
b. pvc Conduit 8 Rm 47.00 376.00 pvc conduti 2
c. Minor Materials 1 LS 150.00 150.00
827.69
Actual rate 1217.69
15% conctractor overhead 182.65
Total (Rs.) 1400.34
Rate per set Rs. 1400.34
7/30/2024 2 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
2 2way Point Wiring
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.1 nos 1200.00 120.00
Semi skilled 0.2 nos 900.00 180.00
Un Skilled 0.2 nos 900.00 180.00
480.00
materials a. 2.5 sq mm Cu wire 30 Rm 18.86 565.67 2
b. pvc Conduit 10 Rm 47.00 470.00 pvc conduti 2
e. Minor Materials 1 LS 150.00 150.00
1185.67
Actual rate 1665.67
15% conctractor overhead 249.85
Total (Rs.) 1915.52
Rate per set Rs. 1915.52
3 Power Point Wiring
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.1 nos 1200.00 120.00
Semi skilled 0.2 nos 900.00 180.00
Un Skilled 0.2 nos 900.00 180.00
480.00
materials a. 2.5 sq mm Cu wire 18 Rm 27.71 498.80 3
a. 1.5 sq mm Cu wire 9 Rm 18.86 169.70 2
b. pvc Conduit 9 Rm 69.00 621.00 pvc conduti 3
c. Minor Materials 1 LS 150.00 150.00
1439.50
Actual rate 1919.50
15% conctractor overhead 287.93
Total (Rs.) 2207.43
Rate per set Rs. 2207.43
4 AC Point Wiring
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.2 nos 1200.00 240.00
Semi skilled 0.2 nos 900.00 180.00
Un Skilled 0.2 nos 900.00 180.00
600.00
materials a. 4 sq mm Cu wire 30 Rm 44.79 1343.67 4
a. 2.5 sq mm Cu wire 15 Rm 27.71 415.67 3
b. pvc Conduit 15 Rm 69.00 1035.00 pvc conduti 3
c. Minor Materials 1 LS 200.00 200.00
2994.33
7/30/2024 3 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Actual rate 3594.33
15% conctractor overhead 539.15
Total (Rs.) 4133.48
Rate per set Rs. 4133.48
5 Switch and Sockets
5.1 1 Gang 1way switch
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0 nos 1200.00 0.00
Semi skilled 0.015 nos 900.00 13.50
Un Skilled 0.015 nos 900.00 13.50
27.00
Modular type
materials a. 1 gang switch 1 nos 143.00 143.00 switch 1
Modular type
b. 1 module plate 1 nos 74.00 74.00 switch 25
c. metal box 1 nos 54.00 54.00 Metal box 1
d. Minor Materials 1 LS 5.00 5.00
276.00
Actual rate 303.00
15% conctractor overhead 45.45
Total (Rs.) 348.45
Rate per set Rs. 348.45
5.2 2 Gang 1way switch
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0 nos 1200.00 0.00
Semi skilled 0.015 nos 900.00 13.50
Un Skilled 0.015 nos 900.00 13.50
27.00
Modular type
materials a. 1 gang switch 2 nos 143.00 286.00 switch 1
Modular type
b. 2 module plate 1 nos 74.00 74.00 switch 25
c. metal box 1 nos 54.00 54.00 Metal box 1
d. Minor Materials 1 LS 5.00 5.00
419.00
Actual rate 446.00
15% conctractor overhead 66.90
Total (Rs.) 512.90
Rate per set Rs. 512.90
5.3 1 Gang 2way switch
7/30/2024 4 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0 nos 1200.00 0.00
Semi skilled 0.015 nos 900.00 13.50
Un Skilled 0.015 nos 900.00 13.50
27.00
Modular type
materials a. 1 gang switch 1 nos 172.00 172.00 switch 4
Modular type
b. 1 module plate 1 nos 74.00 74.00 switch 25
c. metal box 1 nos 54.00 54.00 Metal box 1
d. Minor Materials 1 LS 5.00 5.00
305.00
Actual rate 332.00
15% conctractor overhead 49.80
Total (Rs.) 381.80
Rate per set Rs. 381.80
5.4 2 Gang 2way switch
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0 nos 1200.00 0.00
Semi skilled 0.015 nos 900.00 13.50
Un Skilled 0.015 nos 900.00 13.50
27.00
Modular type
materials a. 1 gang switch 2 nos 172.00 344.00 switch 4
Modular type
b. 2 module plate 1 nos 74.00 74.00 switch 25
c. metal box 1 nos 54.00 54.00 Metal box 1
d. Minor Materials 1 LS 5.00 5.00
477.00
Actual rate 504.00
15% conctractor overhead 75.60
Total (Rs.) 579.60
Rate per set Rs. 579.60
5.5 3 Gang 1way switch
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0 nos 1200.00 0.00
Semi skilled 0.02 nos 900.00 18.00
Un Skilled 0.02 nos 900.00 18.00
36.00
7/30/2024 5 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Modular type
materials a. 1 gang switch 3 nos 143.00 429.00 switch 1
Modular type
b. 3 module plate 1 nos 87.00 87.00 switch 27
c. metal box 1 nos 58.00 58.00 Metal box 3
d. Minor Materials 1 LS 5.00 5.00
579.00
Actual rate 615.00
15% conctractor overhead 92.25
Total (Rs.) 707.25
Rate per set Rs. 707.25
5.6 4 Gang 1way switch
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0 nos 1200.00 0.00
Semi skilled 0.03 nos 900.00 27.00
Un Skilled 0.03 nos 900.00 27.00
54.00
Modular type
materials a. 1 gang switch 4 nos 143.00 572.00 switch 1
Modular type
b. 4 module plate 1 nos 92.00 92.00 switch 28
c. metal box 1 nos 70.00 70.00 Metal box 4
d. Minor Materials 1 LS 10.00 10.00
744.00
Actual rate 798.00
15% conctractor overhead 119.70
Total (Rs.) 917.70
Rate per set Rs. 917.70
5.7 6 Gang 1way switch
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0 nos 1200.00 0.00
Semi skilled 0.05 nos 900.00 45.00
Un Skilled 0.05 nos 900.00 45.00
90.00
Modular type
materials a. 1 gang switch 6 nos 143.00 858.00 switch 1
Modular type
b. 6 module plate 1 nos 167.00 167.00 switch 29
c. metal box 1 nos 140.00 140.00 Metal box 6
d. Minor Materials 1 LS 20.00 20.00
7/30/2024 6 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
1185.00
Actual rate 1275.00
15% conctractor overhead 191.25
Total (Rs.) 1466.25
Rate per set Rs. 1466.25
5.8 3 pin Universal Socket
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0 nos 1200.00 0.00
Semi skilled 0.05 nos 900.00 45.00
Un Skilled 0.05 nos 900.00 45.00
90.00
Modular type
materials a. 13A universal Socket 1 nos 278.00 278.00 switch 17
Modular type
b. 13/16A switch 1 nos 230.00 230.00 switch 2
Modular type
c. 3 module plate 1 nos 87.00 87.00 switch 27
d. metal box 1 nos 58.00 58.00 Metal box 3
e. Minor Materials 1 LS 20.00 20.00
673.00
Actual rate 763.00
15% conctractor overhead 114.45
Total (Rs.) 877.45
Rate per set Rs. 877.45
5.9 6 pin Power Socket
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0 nos 1200.00 0.00
Semi skilled 0.05 nos 900.00 45.00
Un Skilled 0.05 nos 900.00 45.00
90.00
Modular type
materials a. Power Socket 1 nos 342.00 342.00 switch 14
Modular type
b. 13/16A switch 1 nos 230.00 230.00 switch 2
Modular type
c. 3 module plate 1 nos 87.00 87.00 switch 27
d. metal box 1 nos 58.00 58.00 Metal box 3
e. Minor Materials 1 LS 20.00 20.00
737.00
Actual rate 827.00
7/30/2024 7 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
15% conctractor overhead 124.05
Total (Rs.) 951.05
Rate per set Rs. 951.05
D LIGHT FIXTURE
2 Mirror Light
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.05 nos 1200.00 60.00
Semi skilled 0.1 nos 900.00 90.00
Un Skilled 0.1 nos 900.00 90.00
240.00
materials a. Mirror light 1 nos 849.00 849.00 Dome light x
b. Minor Materials 1 LS 20.00 20.00
869.00
Actual rate 1109.00
15% conctractor overhead 166.35
Total (Rs.) 1275.35
Rate per set Rs. 1275.35
3 9 watt ceiling light(recess/surface)
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.05 nos 1200.00 60.00
Semi skilled 0.1 nos 900.00 90.00
Un Skilled 0.1 nos 900.00 90.00
240.00
materials a. 9 watt ceiling light(recess/surface) 1 nos 1249.00 1249.00 Dome light vii
b. Minor Materials 1 LS 20.00 20.00
1269.00
Actual rate 1509.00
15% conctractor overhead 226.35
Total (Rs.) 1735.35
Rate per set Rs. 1735.35
4 12 watt ceiling light(recess/surface)
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.05 nos 1200.00 60.00
Semi skilled 0.1 nos 900.00 90.00
Un Skilled 0.1 nos 900.00 90.00
240.00
materials a. 12 watt ceiling light(recess/surface) 1 nos 1559.00 1559.00 Dome light xii
b. Minor Materials 1 LS 20.00 20.00
1579.00
Actual rate 1819.00
7/30/2024 8 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
15% conctractor overhead 272.85
Total (Rs.) 2091.85
Rate per set Rs. 2091.85
5 600mm x 600mm ceiling light(recess/surface)
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.05 nos 1200.00 60.00
Semi skilled 0.1 nos 900.00 90.00
Un Skilled 0.1 nos 900.00 90.00
240.00
materials a. 600mm x 600mm ceiling light(recess/surface) 1 nos 5572.00 5572.00 k
b. Minor Materials 1 LS 20.00 20.00
5592.00
Actual rate 5832.00
15% conctractor overhead 874.80
Total (Rs.) 6706.80
Rate per set Rs. 6706.80
6 20watt 4 feet light
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.05 nos 1200.00 60.00
Semi skilled 0.1 nos 900.00 90.00
Un Skilled 0.1 nos 900.00 90.00
240.00
materials a. 20watt 4 feet light 1 nos 1194.00 1194.00 e
b. Minor Materials 1 LS 20.00 20.00
1214.00
Actual rate 1454.00
15% conctractor overhead 218.10
Total (Rs.) 1672.10
Rate per set Rs. 1672.10
9 Bulk Head Light
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.05 nos 1200.00 60.00
Semi skilled 0.1 nos 900.00 90.00
Un Skilled 0.1 nos 900.00 90.00
240.00
materials a. Bulk Head Light 1 nos 2600.00 2600.00 Down light 6.9
b. Minor Materials 1 LS 20.00 20.00
2620.00
Actual rate 2860.00
15% conctractor overhead 429.00
7/30/2024 9 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Total (Rs.) 3289.00
Rate per set Rs. 3289.00
E POWER and Feeder cable
1 3.5cx95 sq.mm Al armoured cable
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.05 nos 1200.00 60.00
Semi skilled 0.05 nos 900.00 45.00
Un Skilled 0.05 nos 900.00 45.00
150.00
Aluminium
materials a. 3.5c95 sq.mm Al armoured cable 1 mtr. 827.00 827.00 cable 3.5core 5
b. Minor Materials 1 LS 50.00 50.00
877.00
Actual rate 1027.00
15% conctractor overhead 154.05
Total (Rs.) 1181.05
Rate per set Rs. 1181.05
2 3.5cx70 sq.mm CU armoured cable +25 sq mm cu cable
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.05 nos 1200.00 60.00
Semi skilled 0.05 nos 900.00 45.00
Un Skilled 0.05 nos 900.00 45.00
150.00
Arm copper
materials a. 3.5c 70 sq mm cu cable 0.1 mtr. 3183.00 318.30 cable 3.5core 4
unarm copper
b. 1c 25 sq mm cu cable 0.1 mtr. 78.00 7.80 cable 1core 3
c. Minor Materials 1 LS 50.00 50.00
376.10
Actual rate 526.10
15% conctractor overhead 78.92
Total (Rs.) 605.02
Rate per set Rs. 605.02
3 4cx25 sq.mm CU armoured cable +10 sq mm cu cable
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.05 nos 1200.00 60.00
Semi skilled 0.05 nos 900.00 45.00
Un Skilled 0.05 nos 900.00 45.00
150.00
7/30/2024 10 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Arm copper
materials a. 4c 25 sq mm cu cable 0.1 mtr. 1379.00 137.90 cable 4core 7
unarm copper
b. 1c 10 sq mm cu cable 0.1 mtr. 44.00 4.40 cable 1core 1
c. Minor Materials 1 LS 30.00 30.00
172.30
Actual rate 322.30
15% conctractor overhead 48.35
Total (Rs.) 370.65
Rate per set Rs. 370.65
4 4cx16 sq.mm CU armoured cable +6 sq mm cu cable
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.02 nos 1200.00 24.00
Semi skilled 0.04 nos 900.00 36.00
Un Skilled 0.04 nos 900.00 36.00
96.00
Arm copper
materials a. 4c 16 sq mm cu cable 1 mtr. 928.00 928.00 cable d 4core 6
b. 1c 6 sq mm cu cable 1 mtr. 70.56 70.56 Multi strand 5
c. Minor Materials 1 LS 30.00 30.00
1028.56
Actual rate 1124.56
15% conctractor overhead 168.68
Total (Rs.) 1293.24
Rate per set Rs. 1293.24
5 4cx10 sq.mm CU armoured cable +6 sq mm cu cable
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.02 nos 1200.00 24.00
Semi skilled 0.04 nos 900.00 36.00
Un Skilled 0.04 nos 900.00 36.00
96.00
Arm copper
materials a. 4c 10 sq mm cu cable 1 mtr. 637.00 637.00 cable d 4core 5
b. 1c 6 sq mm cu cable 1 mtr. 70.56 70.56 Multi strand 5
c. Minor Materials 1 LS 30.00 30.00
737.56
Actual rate 833.56
15% conctractor overhead 125.03
Total (Rs.) 958.59
Rate per set Rs. 958.59
7/30/2024 11 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
6 4cx6 sq.mm CU armoured cable +4 sq mm cu cable
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.02 nos 1200.00 24.00
Semi skilled 0.04 nos 900.00 36.00
Un Skilled 0.04 nos 900.00 36.00
96.00
Arm copper
materials a. 4c 6 sq mm cu cable 1 mtr. 424.00 424.00 cable d 4core 4
b. 1c 4 sq mm cu cable 1 mtr. 44.79 44.79 Multi strand 4
c. Minor Materials 1 LS 30.00 30.00
498.79
Actual rate 594.79
15% conctractor overhead 89.22
Total (Rs.) 684.01
Rate per set Rs. 684.01
7 4cx4 sq.mm CU unarmoured cable +2.5sq mm cu cable
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.01 nos 1200.00 12.00
Semi skilled 0.02 nos 900.00 18.00
Un Skilled 0.02 nos 900.00 18.00
48.00
unArm copper
materials a. 4c 4 sq mm cu cable 1 mtr. 260.00 260.00 cable e 4core 3
b. 1c 2.5 sq mm cu cable 1 mtr. 27.71 27.71 Multi strand 3
c. Minor Materials 1 LS 20.00 20.00
307.71
Actual rate 355.71
15% conctractor overhead 53.36
Total (Rs.) 409.07
Rate per set Rs. 409.07
8 2cx10 sq.mm CU armoured cable +6 sq mm cu cable
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.02 nos 1200.00 24.00
Semi skilled 0.04 nos 900.00 36.00
Un Skilled 0.04 nos 900.00 36.00
96.00
Arm copper
materials a. 2c 10 sq mm cu cable 1 mtr. 318.00 318.00 cable b 4core 5
b. 1c 6 sq mm cu cable 1 mtr. 70.56 70.56 Multi strand 5
c. Minor Materials 1 LS 30.00 30.00
7/30/2024 12 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
418.56
Actual rate 514.56
15% conctractor overhead 77.18
Total (Rs.) 591.74
Rate per set Rs. 591.74
9 3cx4 sq.mm CU unarmoured cable
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.01 nos 1200.00 12.00
Semi skilled 0.02 nos 900.00 18.00
Un Skilled 0.02 nos 900.00 18.00
48.00
unArm copper
materials a. 3c 4 sq mm cu cable 1 mtr. 202.00 202.00 cable c 3core 3
b. Minor Materials 1 LS 20.00 20.00
222.00
Actual rate 270.00
15% conctractor overhead 40.50
Total (Rs.) 310.50
Rate per set Rs. 310.50
10 2cx4 sq.mm CU unarmoured cable +2.5sq mm cu cable
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.01 nos 1200.00 12.00
Semi skilled 0.02 nos 900.00 18.00
Un Skilled 0.02 nos 900.00 18.00
48.00
unArm copper
materials a. 2c 4 sq mm cu cable 1 mtr. 260.00 260.00 cable b 2core 3
b. 1c 2.5 sq mm cu cable 1 mtr. 27.71 27.71 Multi strand 3
c. Minor Materials 1 LS 20.00 20.00
307.71
Actual rate 355.71
15% conctractor overhead 53.36
Total (Rs.) 409.07
Rate per set Rs. 409.07
11 3cx2.5 sq.mm CU unarmoured cable
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.01 nos 1200.00 12.00
Semi skilled 0.02 nos 900.00 18.00
Un Skilled 0.02 nos 900.00 18.00
48.00
7/30/2024 13 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
unArm copper
materials a. 3c 2.5 sq mm cu cable 1 mtr. 138.00 138.00 cable c 3core 2
b. Minor Materials 1 LS 20.00 20.00
158.00
Actual rate 206.00
15% conctractor overhead 30.90
Total (Rs.) 236.90
Rate per set Rs. 236.90
12 150 x 40 x 2 mm hot dip cable tray
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.1 nos 1200.00 120.00
Semi skilled 0.15 nos 900.00 135.00
Un Skilled 0.15 nos 900.00 135.00
390.00
materials a. cable tray 1 mtr. 1358.00 1358.00 cable tray 4
b. Minor Materials 1 LS 300.00 300.00
1658.00
Actual rate 2048.00
15% conctractor overhead 307.20
Total (Rs.) 2355.20
Rate per set Rs. 2355.20
13 300 x 40 x 2 mm hot dip cable tray
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.1 nos 1200.00 120.00
Semi skilled 0.15 nos 900.00 135.00
Un Skilled 0.15 nos 900.00 135.00
390.00
materials a. cable tray 1 mtr. 2588.00 2588.00 cable tray 8
b. Minor Materials 1 LS 300.00 300.00
2888.00
Actual rate 3278.00
15% conctractor overhead 491.70
Total (Rs.) 3769.70
Rate per set Rs. 3769.70
F Distribution Board
1 Main DB(MDB)
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 2 nos 1200.00 2400.00
Semi skilled 10 nos 900.00 9000.00
Un Skilled 10 nos 900.00 9000.00
7/30/2024 14 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
20400.00
materials a.160 A 4P MCCB 1 nos 23870.00 23870.00 MCCB n
b.63 A 3P MCCB 1 nos 6578.00 6578.00 MCCB n
c.50 A 3P MCCB 5 nos 6578.00 32890.00 MCCB n
d.32-40 A 3P MCCB 5 nos 6578.00 32890.00 MCCB n
e.25-32 A 2P MCB 6 nos 1061.00 6366.00 10.1 MCB 2
f.6/16 A, SP MCB 6 nos 212.00 1272.00 10.1 MCB 1
g. Miltifunction Meter 1 nos 7500.00 7500.00
h. 250 A TPN Cu Bus Bar 1 set 25000.00 25000.00
Panel Board
i. Phase Indicators 3 set 244.00 732.00 measurement c
j. Copper Ground Bus Bar 1 nos 3500.00 3500.00
k. Surge Protection 1 LS 22000.00 22000.00
l. Distribution Box 1 set 43736.00 43736.00 Panel Board d
m. Minor Materials as cable glands, cable ties, expansion1 bolts etc LS 15000.00 15000.00
n. Testing and Comissioning 1 LS 25000.00 25000.00
246334.00
Actual rate 266734.00
15% conctractor overhead 40010.10
Total (Rs.) 306744.10
Rate per set Rs. 306744.10
2 Electric Vehicles
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 2 nos 1200.00 2400.00
Semi skilled 5 nos 900.00 4500.00
Un Skilled 5 nos 900.00 4500.00
11400.00
materials a.50 A 3P MCCB 1 nos 6578.00 6578.00 MCCB n
b.U/O voltage protection 1 nos 32000.00 32000.00
c.25 A 3P MCB 4 nos 1761.00 7044.00 10.1 MCB 3
d.25 A, 2P MCB 12 nos 1061.00 12732.00 10.1 MCB 2
e. Miltifunction Meter 1 nos 7500.00 7500.00
f. 100 A TPN Cu Bus Bar 1 set 10000.00 10000.00
Panel Board
g. Phase Indicators 3 set 244.00 732.00 measurement c
h. Copper Ground Bus Bar 1 nos 2000.00 2000.00
i. Surge Protection 1 LS 22000.00 22000.00
j. Distribution Box 1 set 36761.00 36761.00 Panel Board c
k. Minor Materials as cable glands, cable ties, expansion1bolts etc LS 3000.00 3000.00
l. Testing and Comissioning 1 LS 5000.00 5000.00
7/30/2024 15 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
145347.00
Actual rate 156747.00
15% conctractor overhead 23512.05
Total (Rs.) 180259.05
Rate per set Rs. 180259.05
3 Ground Floor DB
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 1 nos 1200.00 1200.00
Semi skilled 2 nos 900.00 1800.00
Un Skilled 2 nos 900.00 1800.00
4800.00
materials a.40 A 3P MCCB 1 nos 6578.00 6578.00 MCCB n
b.25A 3P MCB 1 nos 1761.00 1761.00 10.1 MCB 3
c.25 A 2P MCB 6 nos 1061.00 6366.00 10.1 MCB 2
d.6/16 A, SP MCB 6 nos 212.00 1272.00 10.1 MCB 1
e. 100 A TPN Cu Bus Bar 1 set 7500.00 7500.00
f. Copper Ground Bus Bar 1 nos 1000.00 1000.00
g. Distribution Box 1 set 22056.00 22056.00 Panel Board a
h. Minor Materials as cable glands, cable ties, expansion1bolts etc LS 2000.00 2000.00
i. Testing and Comissioning 1 LS 2500.00 2500.00
51033.00
Actual rate 55833.00
15% conctractor overhead 8374.95
Total (Rs.) 64207.95
Rate per set Rs. 64207.95
4 First Floor DB
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 2 nos 1200.00 2400.00
Semi skilled 4 nos 900.00 3600.00
Un Skilled 4 nos 900.00 3600.00
9600.00
materials a.32 A 3P MCCB 2 nos 6578.00 13156.00 MCCB n
b.25A 2P MCB 9 nos 1061.00 9549.00 10.1 MCB 2
c.10 A SP MCB 4 nos 212.00 848.00 10.1 MCB 1
d.6/16 A, SP MCB 12 nos 212.00 2544.00 10.1 MCB 1
e. 100 A TPN Cu Bus Bar 1 set 10000.00 10000.00
f. Copper Ground Bus Bar 1 nos 3500.00 3500.00
g. Distribution Box 1 set 36761.00 36761.00 Panel Board c
h. Minor Materials as cable glands, cable ties, expansion1bolts etc LS 5000.00 5000.00
i. Testing and Comissioning 1 LS 5000.00 5000.00
7/30/2024 16 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
86358.00
Actual rate 95958.00
15% conctractor overhead 14393.70
Total (Rs.) 110351.70
Rate per set Rs. 110351.70
5 Second and Third Floor DB
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 2 nos 1200.00 2400.00
Semi skilled 4 nos 900.00 3600.00
Un Skilled 4 nos 900.00 3600.00
9600.00
materials a.40 A 3P MCCB 1 nos 6578.00 6578.00 MCCB n
b.25-32A 3P MCB 3 nos 1761.00 5283.00 10.1 MCB 3
c.20 A DP MCB 4 nos 1061.00 4244.00 10.1 MCB 2
d.6/16 A, SP MCB 19 nos 212.00 4028.00 10.1 MCB 1
e. 100 A TPN Cu Bus Bar 1 set 10000.00 10000.00
f. Copper Ground Bus Bar 1 nos 3500.00 3500.00
g. Distribution Box 1 set 36761.00 36761.00 Panel Board c
h. Minor Materials as cable glands, cable ties, expansion1bolts etc LS 10000.00 10000.00
i. Testing and Comissioning 1 LS 10000.00 10000.00
90394.00
Actual rate 99994.00
15% conctractor overhead 14999.10
Total (Rs.) 114993.10
Rate per set Rs. 114993.10
6 Second and Third Floor SUSB DB
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 1 nos 1200.00 1200.00
Semi skilled 2 nos 900.00 1800.00
Un Skilled 2 nos 900.00 1800.00
4800.00
materials
b.25-32A 3P MCB 2 nos 1761.00 3522.00 10.1 MCB 3
c.20 A DP MCB 6 nos 1061.00 6366.00 10.1 MCB 2
d.6/16 A, SP MCB 12 nos 212.00 2544.00 10.1 MCB 1
e. 100 A TPN Cu Bus Bar 1 set 7500.00 7500.00
f. Copper Ground Bus Bar 1 nos 3500.00 3500.00
g. Distribution Box 1 set 7959.00 7959.00 DB 9
h. Minor Materials as cable glands, cable ties, expansion1bolts etc LS 5000.00 5000.00
i. Testing and Comissioning 1 LS 5000.00 5000.00
7/30/2024 17 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
41391.00
Actual rate 46191.00
15% conctractor overhead 6928.65
Total (Rs.) 53119.65
Rate per set Rs. 53119.65
7 TOP FLOOR DB
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 1 nos 1200.00 1200.00
Semi skilled 1 nos 900.00 900.00
Un Skilled 1 nos 900.00 900.00
3000.00
materials
c.20 A DP MCB 1 nos 1061.00 1061.00 10.1 MCB 2
d.6/16 A, SP MCB 9 nos 212.00 1908.00 10.1 MCB 1
e. 100 A DPN Cu Bus Bar 1 set 1500.00 1500.00
f. Copper Ground Bus Bar 1 nos 500.00 500.00
g. Distribution Box 1 set 5973.00 5973.00 DB 8
h. Minor Materials as cable glands, cable ties, expansion1bolts etc LS 500.00 500.00
i. Testing and Comissioning 1 LS 2500.00 2500.00
13942.00
Actual rate 16942.00
15% conctractor overhead 2541.30
Total (Rs.) 19483.30
Rate per set Rs. 19483.30
8 HVAC DB
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 1 nos 1200.00 1200.00
Semi skilled 2 nos 900.00 1800.00
Un Skilled 2 nos 900.00 1800.00
4800.00
materials a.40 A 3P MCCB 1 nos 6578.00 6578.00 MCCB n
b.25-32A 3P MCB 5 nos 1761.00 8805.00 10.1 MCB 3
e. 100 A TPN Cu Bus Bar 1 set 2500.00 2500.00
f. Copper Ground Bus Bar 1 nos 1000.00 1000.00
g. Distribution Box 1 set 22056.00 22056.00 Panel Board a
h. Minor Materials as cable glands, cable ties, expansion1bolts etc LS 1500.00 1500.00
i. Testing and Comissioning 1 LS 2500.00 2500.00
44939.00
Actual rate 49739.00
15% conctractor overhead 7460.85
7/30/2024 18 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Total (Rs.) 57199.85
Rate per set Rs. 57199.85
9 UPS DB
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 1 nos 1200.00 1200.00
Semi skilled 1 nos 900.00 900.00
Un Skilled 1 nos 900.00 900.00
3000.00
materials
c.32 A DP MCB 1 nos 1061.00 1061.00 10.1 MCB 2
d.16-25 A, DP MCB 6 nos 1061.00 6366.00 10.1 MCB 2
e. 100 A DPN Cu Bus Bar 1 set 1500.00 1500.00
f. Copper Ground Bus Bar 1 nos 500.00 500.00
g. Distribution Box 1 set 5973.00 5973.00 DB 8
h. Minor Materials as cable glands, cable ties, expansion1bolts etc LS 500.00 500.00
i. Testing and Comissioning 1 LS 2500.00 2500.00
18400.00
Actual rate 21400.00
15% conctractor overhead 3210.00
Total (Rs.) 24610.00
Rate per set Rs. 24610.00
10 OUTDOOR DB
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 1 nos 1200.00 1200.00
Semi skilled 1 nos 900.00 900.00
Un Skilled 1 nos 900.00 900.00
3000.00
materials
c.25 A TP MCB 1 nos 1761.00 1761.00 10.1 MCB 3
d.6/16 A, SP MCB 9 nos 212.00 1908.00 10.1 MCB 1
e. 100 A DPN Cu Bus Bar 1 set 1500.00 1500.00
f. Copper Ground Bus Bar 1 nos 500.00 500.00
g. Distribution Box 1 set 5973.00 5973.00 DB 8
h. Minor Materials as cable glands, cable ties, expansion1bolts etc LS 1500.00 1500.00
i. Testing and Comissioning 1 LS 3500.00 3500.00
16642.00
Actual rate 19642.00
15% conctractor overhead 2946.30
Total (Rs.) 22588.30
Rate per set Rs. 22588.30
7/30/2024 19 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
11 LIFT DB
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 1 nos 1200.00 1200.00
Semi skilled 1 nos 900.00 900.00
Un Skilled 1 nos 900.00 900.00
3000.00
materials
a.50 A TP MCCB 1 nos 6578.00 6578.00 MCCB n
b.6/16 A, SP MCB 9 nos 212.00 1908.00 10.1 MCB 1
c. 100 A DPN Cu Bus Bar 1 set 1500.00 1500.00
d. Copper Ground Bus Bar 1 nos 500.00 500.00
e. Distribution Box 1 set 7959.00 7959.00 DB 9
f. Minor Materials as cable glands, cable ties, expansion1bolts etc LS 1500.00 1500.00
g. Testing and Comissioning 1 LS 3500.00 3500.00
23445.00
Actual rate 26445.00
15% conctractor overhead 3966.75
Total (Rs.) 30411.75
Rate per set Rs. 30411.75
G EARTHING
1 Plate Earthing
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 1 nos 1200.00 1200.00
Semi skilled 1 nos 900.00 900.00
Un Skilled 1 nos 900.00 900.00
3000.00
materials
a.Copper Plate 10 Kg 945.00 9450.00 Earthing a
b.GI Pipe 2 mtr 260.00 520.00 Earthing g
c. Cover 1 set 637.00 637.00 Earthing h
d. copper strip 4 mtr 1114.00 4456.00 Earthing b
e. salt 25 kg 12.00 300.00 Earthing m
f. Charcol 3 bora 318.00 954.00 Earthing l
g. Funnel 1 LS 372.00 372.00 Earthing k
h. Testing and Comissioning 1 LS 3500.00 3500.00
20189.00
Actual rate 23189.00
15% conctractor overhead 3478.35
Total (Rs.) 26667.35
Rate per set Rs. 26667.35
7/30/2024 20 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
3 Strip
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.03 nos 1200.00 36.00
Semi skilled 0.05 nos 900.00 45.00
Un Skilled 0.05 nos 900.00 45.00
126.00
materials
a. copper strip 1 mtr 1114.00 1114.00 Earthing b
b. Minor Materials 1 LS 200.00 200.00
c. Testing and Comissioning 1 LS 50.00 50.00
1364.00
Actual rate 1490.00
15% conctractor overhead 223.50
Total (Rs.) 1713.50
Rate per set Rs. 1713.50
4 4sq mm earth wire
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.01 nos 1200.00 12.00
Semi skilled 0.01 nos 900.00 9.00
Un Skilled 0.01 nos 900.00 9.00
30.00
materials
a. wire 1 mtr 148.00 148.00 Earthing f
b. Minor Materials 1 LS 5.00 5.00
c. Testing and Comissioning 1 LS 5.00 5.00
158.00
Actual rate 188.00
15% conctractor overhead 28.20
Total (Rs.) 216.20
Rate per set Rs. 216.20
I Telephone System
1 20 pair TDB
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.5 nos 1200.00 600.00
Semi skilled 0.5 nos 900.00 450.00
Un Skilled 0.5 nos 900.00 450.00
1500.00
materials
a. 20 Pair db 1 nos 1999.85 1999.85 e
b. Minor Materials 1 LS 500.00 500.00
7/30/2024 21 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
c. Testing and Comissioning 1 LS 2000.00 2000.00
4499.85
Actual rate 5999.85
15% conctractor overhead 899.98
Total (Rs.) 6899.83
Rate per set Rs. 6899.83
2 10 pair TDB
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.5 nos 1200.00 600.00
Semi skilled 0.5 nos 900.00 450.00
Un Skilled 0.5 nos 900.00 450.00
1500.00
materials
a. 10 Pair db 1 nos 1999.85 1999.85 e
b. Minor Materials 1 LS 250.00 250.00
c. Testing and Comissioning 1 LS 1000.00 1000.00
3249.85
Actual rate 4749.85
15% conctractor overhead 712.48
Total (Rs.) 5462.33
Rate per set Rs. 5462.33
3 Telephone socket
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0 nos 1200.00 0.00
Semi skilled 0.015 nos 900.00 13.50
Un Skilled 0.015 nos 900.00 13.50
27.00
Modular type
materials a. telephone socket 1 nos 164.00 164.00 switch 18
Modular type
b. 1 module plate 1 nos 74.00 74.00 switch 25
c. metal box 1 nos 54.00 54.00 Metal box 1
d. Minor Materials 1 LS 5.00 5.00
297.00
Actual rate 324.00
15% conctractor overhead 48.60
Total (Rs.) 372.60
Rate per set Rs. 372.60
4 Telephone Point Wiring
sources Level Qty Unit Rate/unit cost Total Cost Remarks
7/30/2024 22 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
labour Skilled 0.1 nos 1200.00 120.00
Semi skilled 0.1 nos 900.00 90.00
Un Skilled 0.1 nos 900.00 90.00
300.00
materials a. telephone wire 12 Rm 14.00 168.00 3
b. pvc Conduit 12 Rm 47.00 564.00 pvc conduti 2
c. Minor Materials 1 LS 150.00 150.00
882.00
Actual rate 1182.00
15% conctractor overhead 177.30
Total (Rs.) 1359.30
Rate per set Rs. 1359.30
5 20 pair Telephone wire
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.02 nos 1200.00 24.00
Semi skilled 0.02 nos 900.00 18.00
Un Skilled 0.02 nos 900.00 18.00
60.00
materials a. 20 pair telephone wire 1 Rm 123.00 123.00 8
b. pvc Conduit 1 Rm 69.00 69.00 pvc conduti 3
c. Minor Materials 1 LS 20.00 20.00
212.00
Actual rate 272.00
15% conctractor overhead 40.80
Total (Rs.) 312.80
Rate per set Rs. 312.80
6 10 pair Telephone wire
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.02 nos 1200.00 24.00
Semi skilled 0.02 nos 900.00 18.00
Un Skilled 0.02 nos 900.00 18.00
60.00
materials a. 10 pair telephone wire 1 Rm 64.00 64.00 6
b. pvc Conduit 1 Rm 69.00 69.00 pvc conduti 3
c. Minor Materials 1 LS 20.00 20.00
153.00
Actual rate 213.00
15% conctractor overhead 31.95
Total (Rs.) 244.95
Rate per set Rs. 244.95
7/30/2024 23 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
7 pabx
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 1 nos 1200.00 1200.00
Semi skilled 1 nos 900.00 900.00
Un Skilled 1 nos 900.00 900.00
3000.00
materials a. pabx 1 nos 51056.00 51056.00 14
b. Minor Materials 1 LS 1000.00 1000.00
c. Testing and Comissioning 1 LS 3500.00 3500.00
55556.00
Actual rate 58556.00
15% conctractor overhead 8783.40
Total (Rs.) 67339.40
Rate per set Rs. 67339.40
J CCTV SYSTEM
1 Outdoor Bullet Camera
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.1 nos 1200.00 120.00
Semi skilled 0.1 nos 900.00 90.00
Un Skilled 0.1 nos 900.00 90.00
300.00
materials a. camera 1 nos 7380.70 7380.70 cctv system h
b. Minor Materials 1 LS 100.00 100.00
c. Testing and Comissioning 1 LS 500.00 500.00
7980.70
Actual rate 8280.70
15% conctractor overhead 1242.11
Total (Rs.) 9522.81
Rate per set Rs. 9522.81
2 indoor dome Camera
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.1 nos 1200.00 120.00
Semi skilled 0.1 nos 900.00 90.00
Un Skilled 0.1 nos 900.00 90.00
300.00
materials a. camera 1 nos 7380.70 7380.70 cctv system i
b. Minor Materials 1 LS 100.00 100.00
c. Testing and Comissioning 1 LS 500.00 500.00
7980.70
Actual rate 8280.70
7/30/2024 24 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
15% conctractor overhead 1242.11
Total (Rs.) 9522.81
Rate per set Rs. 9522.81
3 16 channel NVR
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 1 nos 1200.00 1200.00
Semi skilled 1 nos 900.00 900.00
Un Skilled 1 nos 900.00 900.00
3000.00
materials a. nvr 1 nos 52515.00 52515.00 cctv system e(ii)
b. Minor Materials 1 LS 500.00 500.00
c. Testing and Comissioning 1 LS 1500.00 1500.00
54515.00
Actual rate 57515.00
15% conctractor overhead 8627.25
Total (Rs.) 66142.25
Rate per set Rs. 66142.25
4 8 port poe switch
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.5 nos 1200.00 600.00
Semi skilled 0.5 nos 900.00 450.00
Un Skilled 0.5 nos 900.00 450.00
1500.00
materials a. poe 1 nos 9200.00 9200.00 cctv system l
b. Minor Materials 1 LS 500.00 500.00
c. Testing and Comissioning 1 LS 1000.00 1000.00
10700.00
Actual rate 12200.00
15% conctractor overhead 1830.00
Total (Rs.) 14030.00
Rate per set Rs. 14030.00
5 CCTV point wiring
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.1 nos 1200.00 120.00
Semi skilled 0.2 nos 900.00 180.00
Un Skilled 0.2 nos 900.00 180.00
480.00 Other
necessary
materials a. cat 6 cable 20 Rm 36.27 725.37 activites
b. pvc Conduit 20 Rm 69.00 1380.00 pvc conduti 3
7/30/2024 25 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
c. Minor Materials 1 LS 200.00 200.00
2305.37
Actual rate 2785.37
15% conctractor overhead 417.81
Total (Rs.) 3203.18
Rate per set Rs. 3203.18
K COMPUTER NETWORK SYSTEM
1 Cat 6 cable
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.01 nos 1200.00 12.00
Semi skilled 0.015 nos 900.00 13.50
Un Skilled 0.015 nos 900.00 13.50
39.00 Other
necessary
materials a. cat 6 cable 1 Rm 36.27 36.27 activites
b. pvc Conduit 1 Rm 69.00 69.00 pvc conduti 3
c. Minor Materials 1 LS 20.00 20.00
125.27
Actual rate 164.27
15% conctractor overhead 24.64
Total (Rs.) 188.91
Rate per set Rs. 188.91
3 network point wiring
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.1 nos 1200.00 120.00
Semi skilled 0.15 nos 900.00 135.00
Un Skilled 0.15 nos 900.00 135.00
390.00 Other
necessary
materials a. cat 6 cable 20 Rm 36.27 725.37 activites
b. pvc Conduit 20 Rm 69.00 1380.00 pvc conduti 3
c. Minor Materials 1 LS 200.00 200.00
2305.37
Actual rate 2695.37
15% conctractor overhead 404.31
Total (Rs.) 3099.68
Rate per set Rs. 3099.68
4 network socket
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0 nos 1200.00 0.00
7/30/2024 26 of 26
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Semi skilled 0.015 nos 900.00 13.50
Un Skilled 0.015 nos 900.00 13.50
27.00
Modular type
materials a. network socket 1 nos 574.00 574.00 switch 19
Modular type
b. 1 module plate 1 nos 74.00 74.00 switch 25
c. metal box 1 nos 54.00 54.00 Metal box 1
d. Minor Materials 1 LS 5.00 5.00
707.00
Actual rate 734.00
15% conctractor overhead 110.10
Total (Rs.) 844.10
Rate per set Rs. 844.10
5 router point wiring
sources Level Qty Unit Rate/unit cost Total Cost Remarks
labour Skilled 0.1 nos 1200.00 120.00
Semi skilled 0.2 nos 900.00 180.00
Un Skilled 0.2 nos 900.00 180.00
480.00 Other
necessary
materials a. cat 6 cable 25 Rm 36.27 906.71 activites
b. pvc Conduit 25 Rm 69.00 1725.00 pvc conduti 3
c. Minor Materials 1 LS 200.00 200.00
2831.71
Actual rate 3311.71
15% conctractor overhead 496.76
Total (Rs.) 3808.47
Rate per set Rs. 3808.47
7/30/2024 1 of 11
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
1154
CPVC Pipe SDR 13.5, 15mm (1/2") CTS
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.1 nos 1200.00 120.00
un skilled 0.1 nos 900.00 90.00 210.00
materials a. 15 mm CPVC Pipe SDR 13.5 CTS, 22.5 kg/cm2 1 Rm 133.00 133.00
b. Cpvc fittings Ls 99.75
c. Jointing materials (flow guard adesive soln) Ls 33.25 266.00
Actual rate 476.00
15% contractor overhead 71.4
Rate per RFt Rs. 166.89 Total (Rs.) 547.40
1155
CPVC Pipe SDR 13.5, 20mm (3/4") CTS
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.1 nos 1200.00 120.00
un skilled 0.1 nos 900.00 90.00 210.00
materials a. 20 mm CPVC Pipe SDR 13.5 CTS, 22.5 kg/cm2 1 Rm 178.00 178.00
b. Cpvc fittings Ls 133.50
c. Jointing materials (flow guard adesive soln) Ls 44.50 356.00
Actual rate 566.00
15% contractor overhead 84.9
Rate per RFt Rs. 198.45 Total (Rs.) 650.90
1156
CPVC Pipe SDR 13.5, 25mm (1") CTS
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 1200.00 132.00
un skilled 0.19 nos 900.00 171.00 303.00
materials a. 25 mm CPVC Pipe SDR 13.5 CTS, 22.5 kg/cm2 1 Rm 248.00 248.00
b. Cpvc fittings Ls 186.00
c. Jointing materials (flow guard adesive soln) Ls 62.00 496.00
Actual rate 799.00
15% contractor overhead 119.85
Rate per RFt Rs. 280.14 Total (Rs.) 918.85
1157
CPVC Pipe SDR 13.5, 32mm (1 1/4") CTS
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 1200.00 132.00
un skilled 0.19 nos 900.00 171.00 303.00
materials a. 32 mm CPVC Pipe SDR 13.5 CTS, 22.5 kg/cm2 1 Rm 300.00 300.00
b. Cpvc fittings Ls 225.00
c. Jointing materials (flow guard adesive soln) Ls 75.00 600.00
Actual rate 903.00
15% contractor overhead 135.45
Rate per RFt Rs. 316.60 Total (Rs.) 1038.45
7/30/2024 2 of 11
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
1158
CPVC Pipe SDR 13.5, 40mm (1 ½") CTS
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 1200.00 132.00
un skilled 0.19 nos 900.00 171.00 303.00
materials a. 32 mm CPVC Pipe SDR 13.5 CTS, 22.5 kg/cm2 1 Rm 347.00 347.00
b. Cpvc fittings Ls 260.25
c. Jointing materials (flow guard adesive soln) Ls 86.75 694.00
Actual rate 997.00
15% contractor overhead 149.55
Rate per RFt Rs. 349.56 Total (Rs.) 1146.55
1112
50 mm dia PVC PIPE 4 KG/CM. SQ.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled(1/18) 0.06 nos 1200.00 72.00
un skilled(1/10) 0.10 nos 900.00 90.00 162.00
materials a.50 mm dia. Pvc pipe 1 RM 107.00 107.00
b. Jointing materialsetc. Ls 80.25 187.25
Actual rate 349.25
15% contractor overhead 52.3875
Rate per RFt Rs. 122.45 Total (Rs.) 401.64
1113
75 mm dia PVC PIPE 4 KG/CM. SQ
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 1200.00 132.00
un skilled 0.11 nos 900.00 99.00 231.00
materials a.75 mm dia. Pvc pipe 1 Rm 240.00 240.00
b. Jointing materialsetc./metal clamp Ls 180.00 420.00
Actual rate 651.00
15% contractor overhead 97.65
Rate per RFTt Rs. 228.25 Total (Rs.) 748.65
1114
110 mm dia PVC PIPE 4 KG/CM. SQ
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.17 nos 1200.00 204.00
un skilled 0.20 nos 900.00 180.00 384.00
materials a.110 m m dia. Pvc pipe 1 Rm 499.00 499.00
b. Jointing material setc./metal clamp Ls 374.25 873.25
Actual rate 1257.25
15% contractor overhead 188.5875
Rate per RFt nos Rs. 440.80 Total (Rs.) 1445.84
1114
160 mm dia PVC PIPE 6 KG/CM. SQ
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.17 nos 1200.00 204.00
un skilled 0.20 nos 900.00 180.00 384.00
7/30/2024 3 of 11
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
materials a.160 m m dia. Pvc pipe 1 Rm 1059.00 1059.00
b. Jointing material setc./metal clamp Ls 794.25 1853.25
Actual rate 2237.25
15% contractor overhead 335.5875
Rate per RFt nos Rs. 784.40 Total (Rs.) 2572.84
1093
PVC FLOOR TRAP 11x7.5cm (4" X 2½")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.22 nos 1200.00 264.00
un skilled 0.22 275.00 60.50 324.50
materials Floor Trap 11x7.5cm (4" X 2½") 1 nos 360.00 360.00 360.00
Actual rate 684.50
15% contractor overhead 102.675
Rate per nos Rs. 787.18 Total (Rs.) 787.18
1096
C P GRATING 110mm (4") dia
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.06 nos 1200.00 72.00 72.00
materials C P GRATTING 110 mm (4") DIA SIZE 1 nos 300.00 95.00 95.00
Actual rate 167.00
15% contractor overhead 25.05
Rate per nos. Rs. 192.05 Total (Rs.) 192.05
1160
1161
CPVC CTS. 20 mm ball Valve( 3/4")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 1200.00 132.00
materials a. 20 mm CPVC ball valve, CTS sockets, 1 nos 366.00 366.00 498.00
Actual rate 498.00
15% contractor overhead 74.7
Rate per Rm Rs. 572.70 Total (Rs.) 572.70
1162
CPVC CTS. 25 mm ball Valve (1")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 1200.00 132.00
materials a. 25 mm CPVC ball valve, CTS sockets, 1 nos 618.00 618.00 750.00
7/30/2024 4 of 11
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Actual rate 750.00
15% contractor overhead 112.5
Rate per Rm Rs. 862.50 Total (Rs.) 862.50
1163
CPVC CTS. 32 mm ball Valve (1 1/4")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 1200.00 132.00
materials a. 32 mm CPVC ball valve, CTS sockets, 1 nos 1052.00 1052.00 1184.00
Actual rate 1184.00
15% contractor overhead 177.6
Rate per Rm Rs. 1361.60 Total (Rs.) 1361.60
1164
CPVC CTS. 40 mm ball Valve (1½")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 1200.00 132.00
materials a. 32 mm CPVC ball valve, CTS sockets, 1 nos 1052.00 2271.00 2403.00
Actual rate 2403.00
15% contractor overhead 360.45
Rate per Rm Rs. 2763.45 Total (Rs.) 2763.45
1009
ONE PIECE COMODE
1009
ONE PIECE COMODE
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 1 nos 1200.00 1200.00
un skilled 1 nos 900.00 900.00 2100.00
a. Porcelain clay white glaze Indian Pattern comode all
complete set(Parryware, Classica or equivalent ) 61.5 X 37 8223.00 8223.00
X 70 cm 1 nos
f. screw, etc. 1 50.00 50.00 8273.00
Actual rate 10373.00
7/30/2024 5 of 11
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
15% contractor overhead 1555.95
Rate per set Rs. 11928.95 Total (Rs.) 11928.95
Floor Pan
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 1 nos 1200.00 1200.00
un skilled 1 nos 900.00 900.00 2100.00
a. Porcelain clay white glaze Indian Pattern Floor Pan all
complete set(Parryware, Classica or equivalent ) 61.5 X 37 3400.00 3400.00
X 70 cm with 10 Lit plastic water tank 1 nos
b. 15 mm angle valve parryware, ark or equivqlent 1 nos 1157.00 1157.00
c.1.5x45 cm(½" x18") PVC pipe connector 1 nos 150.00 150.00
d. screw, etc. 1 50.00 50.00 4757.00
Actual rate 6857.00
15% contractor overhead 1028.55
Rate per set Rs. 7885.55 Total (Rs.) 7885.55
1012
BASIN with single tap COMPLETE SET 53 X 41 X 20.5 cm
h. screw etc
1 500.00 19814.00
Actual rate 22814
15% contractor overhead 3422.1
Total (Rs.) 26236.10
Rate per set Rs. 26236.10
1051
Urinal
7/30/2024 6 of 11
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
sources Level Qty Unit Rate/unit cost Total Cost
skilled 1.00 nos 1200 1200.00 1200.00
labour
un skilled 1.00 nos 900.00 900.00 900.00
materials a.Urinal white glaze poreaselin clay large size 1 nos 1382.00 1382.00
b.Urinal spreader 1 nos 869.00 869.00
c. Urinal trap 1 nos 450.00 450.00
b.Zink oxide screw etc. Ls 200.00 200.00 2901.00
Actual rate 3801.00
15% contractor overhead 570.15
Rate per nos Rs. 4371.15 Total (Rs.) 4371.15
1052
Partition
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 1.00 nos 1200.00 1200.00 1200.00
a.Urinal division plate white glaze poreaselin clay 68 X 30
materials cm 1 nos 1605.00 1605.00
b.Zink oxide screw etc. Ls 200.00 200.00 1805.00
Actual rate 3005.00
15% contractor overhead 450.75
Rate per nos Rs. 3455.75 Total (Rs.) 3455.75
1053
Flush valve
sources Level Qty Unit Rate/unit cost Total Cost
skilled 1.00 nos 1200 1200.00 1200.00
labour
un skilled 1.00 nos 900.00 900.00 900.00
materials a.Flush valve 1 nos 5133.00 5133.00
b. Steel flush pipe 1 nos 1000.00 1000.00
b.Zink oxide screw etc. Ls 200.00 200.00 6333.00
Actual rate 7233.00
15% contractor overhead 1084.95
Rate per nos Rs. 8317.95 Total (Rs.) 8317.95
1054
TOWEL RING
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.222 nos 1200.00 266.40 266.40
materials a . Towel ring 1 nos 510.00 510.00
b. Screws etc. Ls 25.00 535.00
7/30/2024 7 of 11
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Actual rate 801.40
15% contractor overhead 120.21
Rate per nos Rs. 921.61 Total (Rs.) 921.61
TOWEL RAIL
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.222 nos 1200.00 266.40 266.40
materials a . Towel rail 1 nos 510.00 510.00
b. Screws etc. Ls 25.00 535.00
Actual rate 801.40
15% contractor overhead 120.21
Rate per nos Rs. 921.61 Total (Rs.) 921.61
PAPRE HOLDER
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.222 nos 1200.00 266.40 266.40
materials a . Paper holde 1 nos 929.00 929.00
b. Screws etc. Ls 25.00 954.00
Actual rate 1220.40
15% contractor overhead 183.06
Rate per nos Rs. 1403.46 Total (Rs.) 1403.46
1054
TUMBLER HOLDER
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.222 nos 1200.00 266.40 266.40
materials a . Tumbler holder 1 nos 1090.00 1090.00
b. Screws etc. Ls 100.00 1190.00
Actual rate 1456.40
15% contractor overhead 218.46
Rate per nos Rs. 1674.86 Total (Rs.) 1674.86
1057
LOOKING MIRROR 55x40 cm (22"x 16")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled(1/3) 0.33 nos 1200.00 396.00 396.00
materials a.Bevelled edge looking mirror 1 nos 1225.00 1225.00
b . Screws Ls 200.00 1425.00
Actual rate 1821.00
15% contractor overhead 273.15
Rate per nos Rs. 2094.15 Total (Rs.) 2094.15
1067
CP BIB COCK
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 1200.00 133.33 133.33
materials a. 15mm fancy type bib cock 1 nos 859.05 859.05 859.05
7/30/2024 8 of 11
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
Actual rate 992.38
15% contractor overhead 148.8575
Rate per nos Rs. 1141.24 Total (Rs.) 1141.24
1072
ANGLE VALVE
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 1200.00 132.00 132.00
materials a. 15mm Angle valve 1 nos 1157.00 1157.00 1157.00
Actual rate 1289.00
15% contractor overhead 193.35
Rate per nos Rs. 1482.35 Total (Rs.) 1482.35
1073
15mm Two way angle valve
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.25 nos 1200.00 300.00 300.00
materials a. 15mm two way angle valve, jaquar, essco, or equivalent 1 nos 1244.00 1244.00 1244.00
Actual rate 1544.00
15% contractor overhead 231.6
Rate per nos Rs. 1775.60 Total (Rs.) 1775.60
1140
HEALTH FAUCETS (Toilet spray)
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 0.25 nos 1200.00 300.00
un skilled 0.17 nos 900.00 153.00 453.00
a.Water spray (Health faucet) with 1.2 m. long flexible pipe.
materials
1 sets 1200.00 1200.00
1200.00
Actual rate 1653.00
15% contractor overhead 247.95
1900.95 Total (Rs.) 1900.95
Shower
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 1 nos 1200.00 1200.00
7/30/2024 9 of 11
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
un skilled 2 nos 900.00 1800.00 3000.00
a. 15 mm Devoter valve dia. ½" 1 nos 15400.00 15400.00
b. Overhead shower and fouset 1 nos 4627.00 4627.00
c. screw etc 1 500.00 20527.00
Actual rate 23527
15% contractor overhead 3529.05
Total (Rs.) 27056.05
Rate per set Rs. 27056.05
1043
2 H.P. Electrical motor water pump Multi stage, coupled pump (Crompton)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 4 nos 1200.00 4800.00
un skilled 3 nos 900.00 2700.00 7500.00
a.2 H P Electricmotor pump with base plate nuts, bolts
materials etc.set crompton 1 nos 22587.00 22587.00
b.Zink oxide screws etc. Ls 40.00 22627.00
Actual rate 30127.00
15% contractor overhead 4519.05
Rate per nos Rs. 34646.05 Total (Rs.) 34646.05
1082
G.M.65 mm GATE VALVE
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.44 nos 1200.00 528.00 528.00
materials a.65 mm gate valve 1 nos 11411.00 11411.00 11411.00
Actual rate 11939.00
7/30/2024 10 of 11
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
15% contractor overhead 1790.85
Rate per nos Rs. 13729.85 Total (Rs.) 13729.85
1125
C I Cover 45x45cm (18"X18") (Medium)
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 0.33 nos 1200.00 396.00 396.00
materials CI Cover 45x45cm (18" X 18") 1 nos 9043.00
9043.00
Actual rate 9439.00
15% contractor overhead
Rate per set Rs. 9439.00 Total (Rs.) 9439.00
1126
C I Cover 55x55cm (22"X 22") (Medium)
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 0.33 nos 1200.00 396.00 396.00
materials CI Cover 22" X 22" 1 nos 2484.00 2484.00
2484.00
Actual rate 2880.00
15% contractor overhead
Rate per set Rs. 2880.00 Total (Rs.) 2880.00
1149
5 kg Fire extingusher
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 1.0 nos 1200.00 1200.00
un skilled 1200.00
materials a.5 kg Fire extingusher ABC type minimax 1.0 nos 5216.40 5216.40
5216.40
Actual rate 6416.4
15% contractor overhead 962.46
Rate per set Rs. 7378.86 Total (Rs.) 7378.86
Project: Preparation of Master Plan and DPR of Proposed ward administrative office building of ward-2
Project Location: Madhyapur Thimi, Bhaktapur
Project duration: ………………………..
15% contractor overhead 1983.75
Total (Rs.) 15208.75
Rate per set Rs. 15208.75