We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
preiesoompletien time in a given duration is also caleut
considered as advancement over CPM.
In both these methods we have to draw network diagram to deter:
project completion time. A network is a diagrammatic FePresentation ont the
activities concerning a project arranged in a logical manner. Bach acy,
represented by a straight line with an arrow indicating the direction ar Livi, i
of the project. Each activity is connected by two events called activi "Petes
vent and activity finishing event. Events are represented by circles Batting
network are numbered 1, 2, 3 etc., activities are denoted by the even ms of
3, 2-4, ete. By representing an activity 1-2 we mean that is athe Stani. 2! 2.
and? is the finishing point of the activity. The duration of the activity is, itd Pri
by a number ( denoting the number of days required to perform the activiyy gt
above the line Tepresenting the activity. st
The following diagram is an example of a network diagram,
——_—_—___-—— eration, R,
inties are attached with these estimates, Probability op Tone
lated Pen te
bs
A path ofa network is the Sequence of activities Starting from the initial event
to the final event proceedin, the direction of arrows, The duration of a path i,
the sum of the activities Coming along the path.
The various paths and their durations in the above network diagram are given
below:
Paths Duration
1. 1-2-4-5 S+74+8 = 20
2. S+6+5+8 = 24
3. 5+6+4 15
4. 84548 a2
5 4 = 12
+ *
The Path that takes the longest duration is called the o tical path. The duita
OF this path is called the Project duration. The activities coming along this Pa!
are called bottleneck activities, ect
There is another method of determining the critical path and the projet
Qe seth
duration. For obtaining the project duration and the critical path by this me
We introduce the following definitions.vy
-atwork Analysis 143
e carliest start time (EST): =
w waity can be started assuming tha all the precediy time at which an
pe started at the earliest start times. anpractivies’s
arliest finish time (EFT): The earliest finish ti ag
fn varies start time plus the duration of the ie Dees bai
qatest finish time (LFT): The latest finish time for an acti ae
iutest possible time at which an activity can be finished ashing a ny
the subsequent activities can also be finished at the latest possible tine,
)) The latest start time (LST): The latest start time of an activity 1s equal
tore latest finish time minus the duration ofthe activity —,
Total float (F) This is the amount of time a path of activities could
be delayed without affecting the overall project duration.
(ig., Total Float (TF) = Head event L. ~ Tail event E ~ Duration
Total float is also defined as the difference between the two finishing
times or the difference between the starting times. .
(ie) TF = LFT - EFT = LST - EST
(6 Free Float (FF): This is the amount of time an activity can be delayed
without affecting the commencement of a subsequent activity at its earliest
start time, but may affect the float of a previous activity,
Free float = Head event L. - Tail event E - Duration
‘Also FF = TF - Head event Slack (1. - E)
Independent Float (IF): This is the amount of time an activity can
be delayed when all the preceding activities are completed as late as possible
and all subsequent activities are completed as early as possible.
Independent float therefore does not affect the float of either preceding
or subsequent activities:
IF = Head event L ~ Tail event -
= FF - Tail event slack (L ~ EF,
t of an activity is called the head event and the siarting
The finishing point
point is called tail event. L is the latest finish time of an activity and E is the
Liest start time of an activity. In the
earliest start time of an activity and E is the ear
network diagram we calculate the values of E and Lat each event. If there are
‘two or more values of E occurring at an event we take the largest as the value of
Eatthe event. Iftwo more values of L occur at an event We trike the lowest as the
value ofL at the event, Thus, we calculate E and L at cach event, Consider the
Nelwork diagram given earlier.
an,
(0
E — Duration