0% found this document useful (0 votes)
148 views1 page

General Plumbing Notes & Specs

Uploaded by

bocove2670
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
148 views1 page

General Plumbing Notes & Specs

Uploaded by

bocove2670
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

HB

1 GENERAL PLUMBING NOTES & SPECIFICATION 150mmØ PVC DP


AV

P1 CB1 CB1
150mmØ PVC DP
CB1
150mmØ PVC DP
CB1
GT
DS AV
DS DS DS
1. ALL PLUMBING WORKS SHALL BE IN ACCORDANCE WITH THE LATEST EDITION
OF THE NATIONAL PLUMBING CODE OF THE PHILIPPINES, NATIONAL FIRE
50mmØ PVC WP
PROTECTION ASSOCIATION, THE FIRE CODE OF THE PHILIPPINES, NATIONAL KS
BUILDING CODE OF THE PHILIPPINES AND LOCAL REGULATION AND ORDINANCES.
KS
2. THE PLUMBING CONTRACTOR SHALL LOCATE AND DETERMINE THE ACTUAL
LOCATIONS OF EXISTING SANITARY FACILITIES TO COMFORM WITH THE
PROPOSED DESIGN. SV

150mmØ PVC DP
3. ALL PIPES SHALL BE INSTALLED AS INDICATED IN THE WORKING DRAWINGS.
ANY RELOCATION REQUIRED FOR PROPER EXECUTION OF OTHER TRADES
SHALL BE UPON THE APPROVAL OF THE SANITARY ENGINEER.

4. ALL PIPES PASSING THROUGH WALLS SHALL BE PROVIDED WITH SLEEVES.

100mmØ PVC SP
ANGULAR SPACE BETWEEN PIPE AND SLEEVE SHALL BE FIILIED WITH COAL TAR,
ASPHALT COMPOUND OR ANY OTHER MATERIALS FOUND EQUALLY APPROVED.

5. WRITTEN DIMENSIONS SHALL TAKE PRECEDENCE OVER SCALED DIMENSIONS. 75mmØ PVC WP WC
LAV
WC

150mm x 145 CHANNEL DRAIN


6. PROVIDE CONTROL VALVE FOR EACH GROUP OF FIXTURES. LAV AV BDT
AV SHV
CO FD SD
AV AV SHV
7. UNLESS OTHERWISE SPECIFIED, ALL PLUMBING FIXTURES SHALL BE PROPERLY
BDT
VENTED. MAXIMUM DISTANCE OF VENTILATION FROM FIXTURE SHALL BE 1.50m 75mmØ PVC WP
MEASURED ALONG THE LENGTH OF PIPE. FD SD LAV
WC
LAV
8. THE CONTRACTOR SHALL COORDINATE WITH OTHER RELATED TRADE PRIOR TO WC
TO INSTALLATION

150mmØ PVC DP
9. ALL B.I. PIPES FOR BRANCH LINES W/ ADEQUATE HANGERS SHALL BE
HYDROSTATICALLY TESTED AT 150 psi FOR A DURATION OF TWO (2) HOURS, AND HB
SHOULD BE WITNESSED AND CERTIFIED BY ENGINEERING REPRESENTATIVE.
AV
10. PIPE MATERIALS AND SPRINKLER HEAD SPECIFICATION SHALL CONFORM TO

150mmØ PVC DP
THE EXISTING BRAND AND REQUIREMENTS.

11. ALL SPRINKLER HEADS SHALL BE RATED AT 165F EXCEPT FOR KITCHEN AT 212F.

12. ALL SPRNKLER WORKS SHALL BE DONE ONLY BY A CONTRACTOR WITH


TECHNICAL EXPERTISE IN SPRINKLER SYSTEM INSTALLATION. M
CV CV
13. INSTALL ISOLATION VALVES (BALL VALVE) IN EXISTING BRANCH LINES IF THE
AFFECTED INSTALLATION COULD NOT BE COMPLETED WITHIN A DAYTIME PERIOD.
DS
14. SHUT-OFF OF FLOW CONTROL VALVE OF CERTAIN LOOP W/C SUPPLIES THE CB1
150mmØ PVC DP
SPRINKLER SYSTEM OF THE AREA. COORDINATE W/ THE IN-HOUSE ENGINEER. FROM THE NEAREST
3 WATERLINE LAYOUT WATERLINE SOURCE
15. ANY RELOCATION, MODIFICATION, DISMANTLING AND ADDITIONAL SPRINKLER/S P1 SCALE: 1:100M.
HEADS AND LINES ON THE EXISTING SHALL BE PROPERLY COORDINATED TO
EXISTING PROJECT CONTRACTOR ON FIRE PROTECTION.

16. ALL HORIZONTAL WASTE PIPING 75mm Ø AND SMALLER SHALL BE LAID WITH CB2
A MINIMUM SLOPE OF TWO (2%) PERCENT AND 100mmØ AND LARGER PIPES 150mm x 145mm CHANNEL DRAIN
SHALL HAVE ONE (1%) PERCENT SLOPE.
50mm THK REINF. CONC.
50mmØ PVC WP DETACHABLE COVER 50mm THK
17. ALL CHANGES IN DIRECTION SHALL BE MADE BY THE APPROPRIATE USE OF
FROM KS CONC. PRECAST
FORTY FIVE (45) WYELONG SWEEP QUARTER BEND. ONE EIGHT (1/8) BEND WHEN
THE CHANGE OF FLOW IS FROM HORIZONTAL TO VERTICAL. A SINGLE ONE EIGHT
SANITARY SEWER AND 50mmØ PVC WP
(1/8) BEND COMBINATION MAYBE USE ONLY ON VENT PIPE. 2 STORM DRAINAGE LAYOUT
4" THK CHB
18. NO DOUBLE HUB OR DOUBLE TEE BRANCH SHALL BE USED ON HORIZONTAL
P1 SCALE: 1:100M.
IN
SOIL OR WASTE LINES. OUT
TO THE NEAREST
PUBLIC CANAL 50mmØ PVC WP
19. PROVIDE PIPE SLEEVES AT WALL OR SLAB ONE SIZE BIGGER THAN THE ACTUAL 50mmØ PVC WP
FROM KS
LINES PASSING THROUGH WALLS OR SLAB TO PROTECT FROM BREAKAGE.

20. CLEANOUT ARE REQUIRED UNDER THE FOLLOWING CONDITIONS:


A. EVERY CHANGES IN HORIZONTAL DIRECTIONS
7 CHANNEL DRAIN DETAIL 10mm Ø VERT. BAR SPCD, @ .60 O.C. W/
B. EVERY 15.00 m IN HORIZONTAL LINE OF PIPE P1 SCALE: 1:25M.
10mm Ø HOR. BAR SPCD. @ EVERY LAYER
C. AT THE END OF ANY HORIZONTAL PIPE LINE. 600mm x 270mm CHANNEL
DRAIN GATE @ EVERY 3m.
21. CONTRACTOR TO VERIFY ACTUAL LOCATION AND ELEVATION OF STREET SECTION
DRAINAGE, STREET SEWER AND STREET WATER MAINS FOR CONNECTION
BEFORE CONSTRUCTION. 30mm THK
PLAN
CONC. PRECAST
6 GREASE TRAP DETAIL
P1 SCALE: 1:25M.
AV ANGLE VALVE KS KITCHEN SINK 150mm Ø PVC DRAINAGE PIPE
BDT BIDET LAV LAVATORY 100mm Ø PVC SOIL PIPE
SECTION
CB CATCH BASIN RD ROOF DRAIN 75mm Ø PVC WASTE PIPE
CHANNEL GATE
5 STANDARD SOIL PIPE CONNECTIONS
CO CLEAN OUT SD SHOWER DRAIN 50mm Ø PVC WASTE PIPE P1 SCALE: 1:40M.

CV CHECK VALVE SH SHOWER HEAD 50mm" Ø PVC VENT PIPE


REMOVABLE COUNTER SUNK SCREW PLUG
BRASS STRAINER BODY
DP DRAIN PIPE SHV SHOWER VALVE WATER SUPPLY LINE 100mmØ SOIL STACK STRAINER
CLEAN-OUT PLUG 100mmØ PVC CLEANOUT
FINISHED FLOOR LINE BRASS NICKEL FINISHED FLOOR LINE
COVER SEAL
DS DOWN SPOUT SP SOIL PIPE M WATER METER COUNTER SUNK
SCREW PLUG
100mmØ PVC 1/8 BEND
FD FLOOR DRAIN SV SEPTIC VAULT 100mmØ CLEAN-OUT
TO MAIN LINE
100mmØ WYE PVC CONNECTOR (SIZE AS INDICATED IN PLAN) 100mmØ PVC PIPE
2% SLOPE CONNECTION SUITE DRAIN &
GT GREASE TRAP WC WATER CLOSET P-TRAP SIZE 90° ELBOW 100mmØ PVC 1/8 BEND
4 LEGENDS & SYMBOLS 100mmØ 1/8 BEND PVC DEEP SEAL P-TRAP
GV GATE VALVE WP WASTE PIPE P1 SCALE: N.T.S. CLEANING EYE FLUSH TYPE STANDARD CONNECTION
VERTICAL TO HORIZONTAL CLEAN-OUT DETAIL CLEAN-OUT DETAIL
HB HOSE BIBB FLOOR DRAIN DETAIL
SOIL PIPE CONNECTION

PREPARED BY: ID NO.: PROJECT TITLE: CHECKED BY: SHEET CONTENTS: SHEET NO.

SUBJECT: CET-172 GENERAL PLUMBING NOTES & SPECIFICATION GREASE TRAP DETAIL

SECTION: M23 PROPOSED ONE-STOREY RESIDENTIAL BUILDING


SANITARY SEWER AND STORM DRAINAGE LAYOUT
STANDARD SOIL PIPE CONNECTIONS
CHANNEL DRAIN DETAIL
WATERLINE LAYOUT