Chemical Engineering Design Course Outline
Chemical Engineering Design Course Outline
Course Outline
• Unit 1: Methodology of the Design Process
• Unit 2: Codes and Standards, Design Factors, Variable
&Mathematical Representation of
• Design Problems
• Unit 3: Optimization and Batch Production Process
• Unit 4: Process Synthesis
• Unit 5: Process Simulation
• Unit 6: Flow Sheeting, Piping and Instrumentation
• Unit 7: Process Economics: Cost Estimation
• Unit 8: Process Economics: Depreciation and
Profitability Analysis
2
Required Text & Student
Responsibilities
• Required Text
– Plant Design and Economics for Chemical
Engineers: By Peters and Timmerhaus
– Coulson & Richardson’s Chemical Engineering
Design: By Sinnot, Volume 6
• Student Responsibility:
– Attendance and Participation
– Students miss class at their own risk.
3
Exams
• There are two exams:
– Mid-semester and
– Final exams.
4
Grades
• Grades will be assigned according to the
following distribution:
– Midterm 20%
– Final 70%
– Question of the day(attendance) or homework
problems 10%
5
UNIT ONE
Methodology of the Design Process
1.1 Design: it is the synthesis of ideas to achieve
a desired goal.
• Designer starts with specific objective, develops and
evaluates new designs & arrives at what he considers
the best design.
6
1-1.2 Design Contraints
7
1-1.3 The Design Process
8
1-1.3.1 Design Objective
• For a Chemical Process Plant or in designing a
manufacturing process, Objective is:
– Satisfy public need for product
9
1-1.3.2 Data Collection
• Designer must assemble all relevant facts and
data required.
• For process Design;
– Process alternatives
– Equipment performances
– Physical property data
10
Data Collection (cont.)
• Many design organisations will prepare a basic data
manual, containing all the process "know-how" on which
the design is to be based.
11
1-1.3.3 Generation of Possible
Designs
• Designer must come up with possible solutions
for;
– Analysis
– Evaluation
– Selection
• Chemical Engineering Projects are divided into 3
types
– Modification
– New production capacity to meet growing sales
– New processes, developed from lab research, pilot
plant
12
1-1.3.4 Selection
• The selection process can go through the ff
stages:
– Possible designs (credible) within the external
-
constraints.
– Plausible designs (feasible) within the internal
-
constraints.
– Probable designs - likely candidates.
– Best design (optimum) -judged the best solution
to the problem.
13
1-1.4 Chemical Manufacturing
Process
14
1-1.5 Continuous & Batch Processes
• Continuous processes are designed to operate 24 hours a
day, 7 days a week, throughout the year. Some down time
will be allowed for maintenance and, for some processes,
catalyst regeneration.
16
1-1.5.2 The Organisation of a
Chemical Engineering Project
• The design work required in the engineering
of a chemical manufacturing process plant
can be divided into two broad phases:
• Phase 1
– Process Design: Covers the steps from the initial
selection of the process to be used, through to
the issuing of the process flow-sheets; and
includes the selection specification and chemical
engineering design of equipment
17
The Organisation of a Chemical
Engineering Project(contd.)
• Phase 2
– The detailed mechanical design of equipment; the
structural, civil and electrical design, and the
specification and design of the ancillary services.
18
Project Organisation
19
PROJECT DOCUMENTATION
The Project documentation will include:
1. General correspondence within the design group and with:
– government departments
– equipment vendors
– site personnel
– the client
2. Calculation sheets
– design calculations
– costing
– computer print-out
3. Drawings flow-sheets
– piping and instrumentation diagrams
– layout diagrams 20
PROJECT DOCUMENTATION(contd.)
– plot/site plans
– equipment details
– piping diagrams
– architectural drawings
– design sketches
4. Specification sheets for equipment, such as:
– heat exchangers
– pumps
5. Purchase orders quotations
– Invoices
– quotations
21
UNIT 2:
2-1.1 Codes and Standards
• Code of practice: recommended design or
operating procedure
• Standard:refers to preferred sizes, eg. pipes,
composition etc.
• Standards and codes cover various functions:
– Materials, properties and composition
– Testing procedures for performance, composition and
quality.
– Preferred sizes, e.g. tubes, plates, sections
– Design methods, inspection, fabrication
– Codes of practice; for plant operation and safety
procedures.
22
Codes and Standards (Contd.)
• Standards
– A prescribed set of rules
– Not optional, must be followed
• Codes
– A rule or set of rules governing applied use of
standards
– May be made into law
• Other
– Guidelines
• For guidance only and therefore optional
• May be company specific
– Recommended Practices
• Generally regarded as a valid approach to an issue
23
Codes and Standards (contd)
• All developed countries have national
organizations responsible for the issue and
maintenance of standards for the
manufacturing industries and for the
protection of consumers:
– U.K; British Standards Institution
– U.S; National Bureau of Standards
24
Codes and Standards (contd)
• Principal ones of interest to chemical
engineers are:
– American National Standards Institute (ANSI)
– American Petroleum Institute (API)
– American Society for Testing Materials (ASTM)
– American Society of Mechanical Engineers (ASME)
(pressure vessels)
25
Codes & Standards, Contd.
• ASME Code Case 2211
– Pressure vessels with overpressure protection
system design
• ASME Code Case 2290
– In 1999 new maximum allowable stresses in ASME
VIII are based on safety factor of 3.5 ( safety factor
previously was 4)
• ASME B16.34
– Valves and flanges
26
Codes and Standards (contd)
• In Ghana,
– No national standard organization to
coordinate local standards for industries.
– However there are national standard
organizations with standards for the
protection of consumers:
• Ghana Standards Authority,
• Food and Drug Administration (FDA),
• Environmental Protection Agency (EPA).
27
2-1.2 Factors of Safety (Design
Factors)
• Design factors:
– give a margin of safety in design to prevent
equipment failure and operate safely.
28
2-1.3 System of Units
30
The Design Unit
31
The mathematical representation of the design problem:
Degrees of freedom and design variables (contd)
32
The mathematical representation of the design problem:
Degrees of freedom and design variables (contd)
33
The mathematical representation of the design problem:
Degrees of freedom and design variables (contd.)
36
Degrees of freedom and design
variables(contd.)
1. If Nv Nr , Nd 0 and there is only one unique solution to the problem.
The problem is not a true design problem,
no optimisation is possible.
38
Process Stream( contd)
39
2-1.5 Selection of Design Variables
• To solve a design problem, the designer has to
decide which variables to choose as design
variables, i.e the ones he can manipulate to
produce the best design.
40
Selection of Design Variables( contd)
41
Selection of Design Variables(contd)
42
UNIT 3: Optimization and Batch Production Process
3-1 Optimization
– Step1: clearly define the objective. i.e. the criteria to be used for
measuring the performance of the system. For a chemical
process plant, the overall objective is to maximize profit.
• minimize operating cost, reduce labour requirements, reduce
maintenance, operate safely.
– Step 3: find values of the variables that give the optimum value
of objective function i.e maximum or minimum.
44
3-1.2 Simple Models (contd)
A DL 2 D 2 DL D 2
4 2
D2
the objective function is f D, L D L (1)
2
for a given volume (V) we have,
D2 4V
V L L (2)
4 D2
exp res sin g the objective function in terms of one variable D, we have
4V D 2
f(D)
D 2
4V
differentiating; f ' (D) D (3)
D 2
2 1
4V 4V 3
4V 3
substituting D in (2) above L
45
3-1.2 Simple Models (contd)
• For a cylindrical container, the minimum
surface area to enclose a given volume is
obtained when the length (height) is made
equal to the diameter.
46
3-1.3 Multiple Variable Problem
• The general optimization problem can be
represented mathematically as:
47
3-1.4 Methods of Analysis
• Analytical Method:
– The method of Lagrange's undetermined multipliers is a useful
analytical technique for dealing with problems that have equality
constraints (fixed design values).
– For the general, unconstrained, objective function, the derivatives will
give the critical points; which may be maximum or minimum, or
ridges or valleys
48
Methods of Analysis (contd.)
• Search Method:
– requires that the objective function be
computed from arbitrary values of the
independent values.
49
Methods of Analysis (contd.):
Search Method
50
3-1.5 Other Optimization Methods
• Linear Programming
– A technique used when the objective function and
constraints can be expressed as a linear function
of the variables
• Dynamic Programming
– Used for optimization of large systems
51
3-2 Batch Production Process
• Productive period: this is the period when product is
being produced
52
Batch Production Process(contd.)
• Batches per year = 8760 x Plant attainment
batch cycle time
53
Batch Production Process(contd.)
• With many batch processes, the production
rate will decrease during the production
period;
– Eg. For batch reactors , there will be an optimum
batch size, or optimum cycle time, that will give
the minimum cost per unit of production.
54
Batch Production Process (contd.)
• For some processes, the period of continuous
production will be limited by gradual changes in
process conditions;
55
Batch Production Process(contd.)
• With batch processes, the period between shut-
downs will usually be a function of equipment
size. Increasing the size of equipment will extend
the production period, but at the expense of
increased capital cost.
58
Process Synthesis: introduction
(contd)
• Approach 2. Heuristic rules based on
experiences that are used for the selection
and positioning of processing operations as
flow sheets are assembled.
59
4-1.2 Raw Materials and Chemical
Reactions
• Heuristic 1: Select raw materials and chemical
reactions to avoid or reduce the handling and
storage of hazardous and toxic chemicals.
E.g. Manufacture of ethylene glycol
60
61
Raw Materials and Chemical
Reactions(contd.)
• Heuristic 2: Distribution of Chemicals
– Use an excess of one chemical reactant in a reaction to
completely consume a second valuable, toxic or hazardous
reactant.
– E.g. use an excess of ethylene in the production of
Dichloroethane.
62
Raw Materials and Chemical
Reactions(contd.)
• Heuristic 3: when nearly pure products are
required, eliminate the inert species before the
reaction operations, when the separations are easily
accomplished, or when the catalyst is adversely
affected by the inert.
63
Raw Materials and Chemical
Reactions(contd.)
• Heuristic 4: Introduce liquid or vapor purge
streams to provide exit for species that;
– Enter the process as impurities in the feed.
– Produced by irreversible side reactions
• E.g. Ammonia, NH3 synthesis loop
64
Raw Materials and Chemical
Reactions(contd.)
• Heuristic 5: Do not purge valuable species or
species that are toxic and hazardous, even in small
concentrations
– Add separators to recover valuable species
– Add reactors to eliminate toxic and hazardous species
e.g. catalytic converter in car exhaust
65
Raw Materials and Chemical
Reactions(contd.)
• Heuristic 6: For competing series or parallel reactions, adjust
temperature, pressure, and catalyst to obtain high yields of desired
products. In the initial distribution of chemicals, assume that these
conditions can be satisfied; obtain kinetic data, and check this assumption
before developing a base-case design.
– E.g. Manufacture of alkyl-chloride
66
Raw Materials and Chemical
Reactions(contd.)
• Heuristic 7: For reversible reactions, consider conducting
them in a separation device capable of removing products,
and hence driving the reaction to the right.
e.g. manufacture of ethyl-acetate using reactive distillation
67
Raw Materials and Chemical
Reactions(contd.)
• Heuristic 8: Separations : separate liquid
mixtures using distillation, stripping towers
and liquid-liquid extractors.
68
Raw Materials and Chemical
Reactions(contd.)
• Heuristic 9: attempt to condense vapour mixtures with
cooling water, then use heuristic 8.
69
Raw Materials and Chemical
Reactions(contd.)
• Heuristic 10: Heat Transfer in reactors: to
remove highly exothermic heat of reaction, consider
the use of excess reactant, an inert diluents.
70
Raw Materials and Chemical
Reactions(contd.)
• Heuristic 11: For less exothermic heat of reaction,
circulate reactor fluid to an external cooler, or use a jacketed
vessel or cooling coils
71
Raw Materials and Chemical
Reactions(contd.)
• Heuristic 12: Pumping and Compression: To increase the
pressure of a stream, pump a liquid rather than compress a gas: i.e
condense a vapor as long as refrigeration ( and compression) is not
needed before pumping.
72
UNIT 5: Process Simulation:
5-1.1 Introduction
• Process simulation is the act of representing some aspects of the real
world by numbers or symbols that may be easily manipulated to facilitate
their study.
73
5-1.2 Process Simulator
• Computational package that enables predictions
of the process behavior
76
5-1.5. Uncertainty and Sensitivity
Issues
• It is important to be able to quantify the uncertainty of results:
• Determine the probability of accuracy of results
• Determine what part of results obtained is most likely to be incorrect, and
estimate error range
77
UNIT 6: Flow Sheeting, Piping and
Instrumentation
• The flow sheet is the key document in process design.
It shows the arrangement of the equipment selected
to carry out the process.
78
6-1.2 Piping and Instrumentation
• The Piping and Instrument diagram (P and I diagram) shows the
arrangement of the process equipment, piping, pumps,
instruments, valves and other fittings.
79
6-1.3 Valve Selection
• The valves used for chemical process plant can
be divided into two broad classes, depending
on their primary function:
• Shut-off valves (block valves), whose purpose
is to close off the flow.
• Control valves, both manual and automatic,
used to regulate flow.
80
Valve Selection (Contd.)
81
Valve Selection (Contd.)
• The main types of valves used are:
– Gate: used when flow is straight, often used –(a)
– Plug: for flow shut off –(b)
– Ball: for flow shut off –(c)
– Globe: used when flow control is rqd. due to
change in flow dxn., are automatic valves-(d)
– Diaphragm: -e
– Butterfly: Figure –f – normally for gas & vapor
control
82
6-2.1 Introduction of Pumps
• They are mechanical devices used to increase
the energy of a liquid stream flowing in a
closed conduit or pipe.
83
6-2.2 Classification of Pumps
• Pumps are generally classified into two main
categories namely:
– Centrifugal pumps( dynamic pumps)
– Positive displacement pumps
Category Types Structure
Reciprocating Piston
Diaphragm
Plunger
84
6-2.3 Factors to Consider in Pump
Selection
• Capacity (flow rate in m3/h)
• The pressure head that is generated by the pump
• The type of liquid pumped (its viscosity and
vapour pressure under inlet conditions)
86
6-2.4 Centrifugal Pumps
• Basically consists of an impeller equipped
with radial vanes rotating inside a shell called
the pump casing.
• It works by the transfer of centrifugal force of
the rotating impeller into kinetic energy of
the liquid.
• This energy is then converted into pressure
when the fluid velocity decreases.
87
6-2.4.1 Effective characteristic curves
• A centrifugal pump is characterized by 4 basic
curves, all of which are expressed versus the
flow rate:
– The head generated
– The mechanical/hydraulic conversion efficiency
– The mechanical power input consumed at the
shaft
– The pump suction capacity or NPSH.
88
Basic Curves Characterizing a
Centrifugal Pump
89
6-2.4.2 Design parameters of
centrifugal pumps
• The rotation speed
• The number of impellers
• The impeller diameter
• The impeller design
90
6-2.4.3 Operating point
• The pressure head HA required by the installation is
represented by the system curve versus flow rate, Q.
92
• A centrifugal pump adjusts itself on an
operating point B, corresponding to the
intersection between the Q/H curve of the
pump and the HA curve of the system (Figure
6-2.4).
93
Effect of impeller diameter on pump
characteristic curve
94
Figure 6-2.4: Variation of Operating
Point by means of a Valve.
95
96
6-2.4.4 Q/H Curve versus Technical
Choices
• Basic choices; concept of specific speed
• The number Nq, called the “specific speed”, allows all
centrifugal pumps to be compared with one another.
• It is calculated from the following expression:
N Q
Nq 3
4
60H
Where
• N = rotational speed in rpm
• Q= flow rate for the best efficiency in m3/h (through one eye
if double-suction impeller)
• H= head in m generated at the best efficiency (for one stage)
97
Pressure Drop in Pipelines
• The pressure drop in a pipe, due to friction, is a
function of:
– the fluid flow-rate,
– fluid density and viscosity,
– pipe diameter,
– pipe surface roughness and
– the length of the pipe.
98
Pressure Drop in Pipelines
• It is represented by:
99
Pressure Drop in Pipelines
• The friction factor is dependent on the
Reynolds number and pipe roughness.
100
EXAMPLE 6-1.1
• A pipeline connecting two tanks contains four
standard radius elbows, a globe valve that is
fully open and a gate valve that is half open.
The line is commercial steel pipe, 25 mm
internal diameter, length 120 m. The
properties of the fluid are: viscosity 0.99
mNM-2 s, density 998 kg/m3. Calculate the
total pressure drop due to friction when the
flow rate is 3500 kg/h.
101
102
103
104
6-2.4.6 Suction Conditions:
Net positive suction Head (NPSH)
• The pressure at the inlet to a pump must be
high enough to prevent cavitation occurring in
the pump.
105
Net positive suction Head (NPSH)
• The net positive suction head available
(NPSHavail.) is the pressure at the pump suction,
above the vapor pressure of the liquid, expressed
as head of liquid.
115
UNIT 7: PROCESS ECONOMICS:
7.1 Cost Estimation
• Capital must be allocated for direct plant
expenses, such as those for equipment,
materials, labor.
117
7-1.3 Factors affecting Investment and
Production Costs
• Sources of equipment
• Price fluctuations
• Company policies
• Operating time and rate of
production
• Governmental policies
118
7-1.4 Capital Investment
• Capital Investment :
– Money to purchase and install the necessary
machinery and equipment.
– Land and service facilities must be obtained, and
the plant must be erected complete with all
piping, controls, and services.
– In addition it is necessary to have money available
for the payment of expenses involved in the plant
operation.
119
Capital Investment(contd.)
120
Fixed Capital Investment
• Fixed Capital Investment:
– The capital needed to supply the needed
manufacturing and plant facilities.
– Or the total cost of the plant ready for
start-up.
–Manufacturing fixed capital
investment + Non-manufacturing
fixed investment
121
Fixed Capital Investment(cntd.)
• It includes the cost of:
– Design, and other engineering and construction
supervision.
– All items of equipment and their installation.
– All piping, instrumentation and control systems.
– Buildings and structures.
– Auxiliary facilities, such as utilities, land and civil
engineering work.
• It is a once-only cost that is not recovered at the
end of the project life, other than the scrap value.
122
Working Capital
• Working Capital:
– the additional investment needed, over and above
the fixed capital, to start the plant up and operate
it to the point when income is earned.
123
Working capital
• The working capital for an industrial plant consist
of the total amount of money invested in:
– Start-up
– Raw materials and supplies carried in stock
– Initial catalyst charges
– Finished products in stock and semi-finished products
in process of being manufactured
– Accounts receivable
– Cash kept on hand for monthly payment of operating
expenses , such as salaries, wages, and raw materials
purchases
– Accounts payables
– Taxes payables
124
Working Capital
• Most of the working capital is recovered at the end of
the project.
126
Non- manufacturing fixed capital
investment
• The fixed capital required for construction
overhead and for all plant components that
are not directly related to the process
operation.
– Plant Comp. not directly rel. to process operation
the land, processing buildings, administrative and
other offices, warehouses, laboratories,
transportation, shipping and receiving facilities,
utilities and waste disposal facilities, shops and
other permanent parts of the plant.
127
Non-manufacturing Fixed capital Investment
128
7-1.5 Estimation of Capital
Investment
• A check list of items covering a new facility is
an invaluable aid in making a complete
estimation of the fixed capital investment. A
typical list of items is:
129
Estimation of Capital Investment(contd.)
• Direct cost
– Purchased equipment; all equipments listed on a flow
sheet
– Purchased-equipment installation
– Instrumentation and controls
– Piping
– Electrical equipment and materials
– Buildings(including services)
– Yard improvements
– Service facilities
– land
130
Estimation of Capital Investment(contd)
• Indirect cost
– Engineering and supervision
– Construction expenses
– Contractor’s fees
– Contingencies
131
7-1.5.2 Types of capital cost estimates
• The following five categories represent the
accuracy range and designation normally used for
design purposes:
– Order-of-magnitude estimate based on similar
previous cost data
– Study estimate based on knowledge of major items of
equipment
– Preliminary estimate based on sufficient data to
permit the estimate to be budgeted
– Definitive estimate based on almost complete data
but before completion of drawings and specifications
– Detailed estimate based on complete engineering
drawings, specifications and site surveys
132
7-1.5.3 Cost Indexes(contd.)
• Cost index: is an index value for a given point
in time showing the cost at that time relative
to a certain base time.
133
Cost Indexes(contd.)
• The common indexes permit fairly accurate estimates if
the time period involved is less than 10 years.
135
7-1.5.4 Methods for Estimating Capital
Investment
• Power factor applied to plant capacity ratio
• Percent of delivered equipment cost
• Lang factors for approximation of capital
investment
• Detailed factorial Estimate
• Unit cost estimate
136
(a) Power factor applied to plant capacity
ratio
Cn CFE R
n
Cn , C Equipment cost
R capacity of new facility divided by the capacity of old facility
FE Ratio of M & S equipment cost index of new year to old year
n power, averaged between 0.6 to 0.7 for many process facilities
(or equipment size or capacity exponent)
137
Table 7-1.2 Typical Exponents for Equipment Cost vs. Capacity
138
EXAMPLE 7-1.1
• If a process plant was erected in Kumasi at a
fixed capital investment of $436,000 in 1970,
determine what the capital investment will be
in 1975 for a similar process plant located
near Dansoman in Accra with twice the
process capacity but with an equal number of
process equipment. Assume capacity
exponent is 0.7.
139
(b) Percentage of Delivered Equipment
Cost
• This method for estimation of the fixed or total-
capital investment requires determination of the
delivered equipment cost.
142
(d) The factorial methods of capital cost estimation:
Detailed factorial (or item) estimates
143
EXAMPLE 7-1.2
• Initial design work was done for a chemical
plant to revamp the process in order to
recover valuable product from an effluent gas
stream. The gas will be scrubbed with a
solvent in a packed column and the recovered
product and solvent separated by distillation.
The solvent will then be cooled and recycled.
The major items of equipment required and
their purchased costs in cedis are:
144
• Absorption column
– Column purchased cost = 19,800
– Cost of column packing = 6,786
• Recovery column
– Column purchased cost = 45,000
– Cost of 30 sieve trays = 8,670
• Reboiler
– Cost of reboiler = 7,600
• Condenser
– Purchased cost = 4,800
• Recycle solvent cooler
– Cost of cooler = 2,550
• Storage tank
– Cost of tank = 7,790
145
• The relevant component factors for this
processing plant are;
– f1: equipment erection = 0.40
– f2: piping = 0.70
– f3: Instrumentation = 0.2
– f4: electrical = 0.10
– f10: design and engineering = 0.30
– f12: contingencies = 0.20
• Estimate the total capital investment for the
project, if the working capital can be taken as
10 % of the fixed capital cost.
146
Quest. 2
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
Turnover Ratio
• Turnover ratio: is the ratio of gross annual
sales to the fixed capital investment.
gross annual sales
Turnoverratio
fixed capital investiment
1
Capital ratio or investment ratio
Turnover ratio
167
Break-even Point(Contd.)
168
Break-even Point(Contd.)
169
• A-B The investment required to design the plant.
• B-C The heavy flow of capital to build the plant, and provide funds
for start-up.
• C-D The cash-flow curve turns up at C, as the process comes on
stream and income is generated from sales. The net cash flow is
now positive but the cumulative amount remains negative until the
investment is paid off, at point D.
• Point D is known as the break-even point and the time to reach the
break-even point is called the pay-back time. In a different context,
the term "break-even point" is used for the percentage of plant
capacity at which the income equals the cost for production.
• D-E In this region the cumulative cash flow is positive. The project is
earning a return on the investment.
• E-F Toward the end of project life the rate of cash flow may tend to
fall off, due to increased operating costs and falling sale volume and
price, and the slope of the curve changes.
• The point F gives the final cumulative net cash flow at the end of
the project life. 170
EXAMPLE 7-2.1
• The annual direct production costs for a plant
operating at 70 % capacity is $ 280,000 while the sum
of the annual fixed charges, overhead costs and
general expenses is $ 200,000. What is the break-even
point in units of production per year if the total annual
sales are $ 560,000 and the product sells at $ 40 per
unit?
• (ii) What are the annual gross earnings and net profits
for this plant at 100 % capacity in the year 1974 when
corporate income taxes required 22 %, normal tax on
the total gross earnings plus 26 % surtax on gross
earnings above $ 25,000?
171
UNIT 8:PROCESS ECONOMICS:
Depreciation and Profitability Analysis
• 8-1.1 Depreciation: Two types exist:
– Physical depreciation: is the measure of the decrease
in value due to changes in the physical aspect of the
property. Wear and tear, corrosion, accidents and
deterioration due to age.
172
Depreciation(Contd.)
• Service life: The period during which the use
of a property is economically feasible.
– Synonymous with economic or useful life
173
Depreciation(Contd.)
• Scrap or junk value: If the property cannot be
disposed of as a useful unit, it can often be
dismantled and sold as junk to be used again
as a manufacturing raw material. The profit
obtainable from this type of disposal is scrap
or junk value
174
• Present Value: It is the value of an asset in its
condition at the time of valuation.
Va V ad
177
8-1.5.2 Textbook Declining – Balance ( or Fixed
Percentage) Method: here, the annual depreciation
cost is a fixed percentage of the property value at the
beginning of the particular year.
183
EXAMPLE 8-1.3
• Consider an equipment costing $20,000 and
with a service life estimated at 5 years. If the
salvage value is $2,000, find the depreciation
cost for the 1st , 2nd and 3rd years using the
sum-of-the-years-digits method.
184
5. Sinking-Fund Method: here the use of compound
interest is involved.
– At the end of each year the sum of all the deposits plus
accrued interest must equal the total amount of
depreciation.
185
da depreciation for year a
n a 1
V V
n s
a
1
2n a 1
da V Vs
nn a
but from previous eqn. for an ordinary annuity
R V Vs
i
1 i 1
n
186
• The amount accumulated in the fund
after a years of useful life must be equal
to the total amount of depreciation up
to that time.
V Va R
1 i
a
1
i
Combining last 2 equations :
V Va V Vs
1 i 1
a
1 i 1
n
Va V V Vs
1 i 1
a
1 i 1
n
188
Evaluation of Depreciation Methods
• Declining –balance and Sum-of-the years digits
methods gave similar results.
– Depreciation costs in both cases are greater in
the early-life years of the property than in the
latter years.
191
8-2.3 Basis for Evaluating Project
Profitability
• Total profit alone cannot be used as the deciding
profitability factor in determining if an investment
should be made.
• Investment B gives a greater yearly profit than A but annual rate of return
on the second investment is only
• ($25,000/$1,000, 000) x100=2.5%
• While annual rate of return on $100,000 is 10%.
• Therefore, the rate of return rather than the total amount of profit is the
important profitability factor in determining if the investment should be
made.
193
8-2.4Mathematical Methods for
Profitability Evaluation
• The most commonly used methods for profitability
evaluation are:
– Rate of return on investment
– Discounted cash flow based on full-life performance
– Net present worth
– Capitalized cost
– Payout period
Profit
ROR 100%
Total initial investment Years
195
Rate of Return on Investment(Contd.)
197
8-2.4.2 Discounted Cash Flow
• Discounted Cash Flow : takes into account the time value of money
and it is based on the amount of the investment that is unreturned
at the end of each year during the estimated life of the project.
where
NPW net present worth
NPV net present value
NFW net future worth
r discounted rate (interest rate)
t life of project
n nth year
199
EXAMPLE 8-2.3
• Initial fixed capital investment = $100,000
• Working capital investment = $10,000
• Salvage value at end of service-life = $10,000
• The predicted after-tax cash flow to project based on total income minus
all costs except depreciation in dollars is shown in the table below.
Estimate the discounted cash flow rate of return (DCFRR).
Year Cash flow into the project,$
0 -110,000
1 30,000
2 31,000
3 36,000
4 40,000
5 43,000
200
8-2.4.3 Capitalized cost
• The capitalized cost profitability concept is used for comparing
alternatives which exists as possible investment choices
within a simple overall project.
• Basic equation for capitalized cost:
CR C R (1 i ) n
K Cv Vs
(1 i ) n 1 (1 i ) n 1
where
K Capitalized cost
C R Re placement cost
C v Original cost of equipment
Vs Salvage value at end of estimated useful life
n Estimated useful life of equipment
i int erest rate
(1 i ) n
capitalised cost factor
(1 i ) 1
n
201
EXAMPLE 8-2.4
• A reactor, which will contain corrosive liquids, has been
designed. If the reactor is made of mild-steel, the initial
installed cost will be $5000 and the useful life period
will be 3 years. Since stainless- steel is highly resistant
to the corrosive action of the liquids, stainless- steel as
the material of construction has been proposed as an
alternative to mild-steel. The stainless-steel reactor will
have an initial installed cost of $15,000. The scrap value
at the end of the useful life would be zero for either
type of reactor, and both could be replaced at the cost
equal to the original price. On the basis of equal
capitalized cost for both types of reactors, what should
be the useful life period for the stainless-steel reactor if
money is worth 4% compounded annually?
202
8-2.4.4 Payout period (or Pay-back time)
• Payout period or pay-back time is the minimum
length of time theoretically necessary to recover the
original capital investment in the form of cash flow to
the project based on total income minus all costs
except depreciation.
203
Payout period (Contd.)
• Pay-back time (or payout period), is a useful
criterion for judging projects that have a short
life, or when the capital is only available for a
short time.