Estimation and Costing Notes
Estimation and Costing Notes
TECHNICAL TERMS
Estimate
An estimate is the anticipated or probable cost of work and is usuallyprepared before the
construction is taken up. It is indeed calculations or computations of various items of an
engineering work.
Quantity survey
It is the schedule of all items of work in a building. Thesequantities are calculated from the
drawing of the building. Thus quantity survey gives quantities of work done in case of each
items, when priced gives the total cost. In short, quantity survey means calculations of quantities
of materials required to complete the work concerned.
Specifications
Detailed specifications gives the nature, quality and class of work,materials to be used in the
various parts of work , quality of the material, their proportions, method of preparation,
workmanship and description of execution of work are required.
Rates
The rates of various items of works, materials to be used in the construction andthe wages of
different categories of labor (skilled and unskilled) should be available for preparing an estimate.
The cost of transportation charges should also be known. As far as possible sanctioned
“Schedule of Rates” shall be followed or the rates may be worked out by the “Analysis of Rates”
method.
Site plan
It is the plan drawn for a particular construction showing its position withrespect to approaching
roads, main bazars, markets and other permanent features in a populated area. It shows the
location of the area under construction with respect to the other areas and on it generally the
names of the owners of areas or property holders adjoining to it are also denoted. North line is
also clearly marked on it.
Line plan
Line plan can be defined as the plan of a particular construction simplyshowing main features
with the help of the single lines of different portions of the constructions. Details of
constructions are not generally shown on this plan. This inside and outside dimensions shown on
this plan should necessarily be corresponding to actual dimensions.
2
Index plan
This is the plan of a particular colony showing the positions of differenthouses in single lines
their number if any position of roads, schools, market, hospitals and other features etc. this plan
is generally fixed on the entrance, or at exit or in the central place of the colony, for the guidance
of the inhabitants and outsiders.
Detailed plan
This plan indicates a plan of a construction drawn to a definite scale,showing all detailed
information required for its execution. Various sections and elevations are clearly drawn on this
plan.
Supplemantary estimate
When some additions are done in the original work, afresh detailed estimate is prepared to
supplement the original work. This estimate is called supplementary estimate. It is also
accompanied by all the papers as required in thru detailed estimate.
Administrative approval
For any project required by the department an approvalso sanction of the competent authority
with respect to the cost and work is necessary at the first instance. Thus administrative aooroval
denotes the formal acceptance by the administrative department concerned of the proposals for
incurring expenditure.
Technical sanction
It means the sanction and order by the competent authority ofthe department for the detailed
estimate design calculations quantities of work rates and cost of work..after the technical
sanction of the estimate is received the work is then taken up for construction.
Competent authority
An officer or any other authority in the department to whomrelevant powers are delegated by the
government (Financial Department).
3
Lumpsum items
Sometimes while preparing estimate for the certain small items like front architecture or
decoration work of a building it is not possible to workout detailed quantities so far such lump
sum items a lump sum rate is provided.
Plinth area
The built up covered area of a building measured at floor level of any storey is called plinth area.
Circulation area
The total cost of construction including all expenditures incurred plus the cost of external
servicesup to the end of the completion of the work is called capital cost. It also includes the cost
of preliminary works, miscellaneous items and supervisioncharges etc.
General
Estimating is the technique of calculating or computing the variousquantities and the expected
Expenditure to be incurred on a particular work orproject. In case the funds available are less
than the estimated cost the work isdone in part or by reducing it or specifications are altered, the
following requirementare necessary for preparing an estimate.
Units of measurements
The units of measurements are mainly categorized for their nature, shape and size and for
making payments to the contractor and also. The principle of units of measurements normally
consists the following:
a) Single units work like doors, windows, trusses etc., is expressed in numbers.
b) Works consists linear measurements involve length like cornice, fencing, hand rail,
bands of specified width etc., are expressed in running meters (RM)
c) Works consists areal surface measurements involve area like plastering, white
washing, partitions of specified thickness etc., and are expressed in square meters
(m2)
d) Works consists cubical contents which involve volume like earth work, cement
4
Rules for measurement
The rules for measurement of each item are invariably described in IS- 1200.
Same type of work under different conditions and nature shall be measured separatelyunder
separate items.
The bill of quantities shall fully describe the materials, proportions, workmanships and
accurately represent the work to be executed.
In case of masonry (stone or brick) or structural concrete, the categories shall be measured
separately and the heights shall be described:
b)Estimate gives an idea of time required for the completion of the work.
c)Estimate is required to invite the tenders and Quotations and to arrange contract.
d)Estimate is also required to control the expenditure during the execution of work.
e)Estimate decides whether the proposed plan matches the funds available or not.
5
Procedure of estimating or method of estimating.
Specifications.
Rates.
Drawings
If the drawings are not clear and without complete dimensions the preparation of estimation
become very difficult. So, it is very essential before preparing an estimate.
Specifications
General Specifications: This gives the nature, quality, class and work and materials in general
terms to be used in various parts of wok. It helps no form a general idea of building.
Detailed Specifications: These gives the detailed description of the various items of work
laying down the Quantities and qualities of materials, their proportions, the method of
preparation workmanship and execution of work.
Rates
For preparing the estimate the unit rates of each item of work are required.
6
Complete estimate
Most of people think that the estimate of a structure includes cost of land, cost of materials and
labor, but many other direct and indirect costs included and are shown below.
Architectural features.
In general, certain percentage on the cost of estimation is allotted for the above [Link] Even if
sub estimates prepared or at the end of execution of work, the actual cost should not exceed the
[Link] provided in the main estimate.
During the construction of a project considerable number of skilled supervisors, work assistance,
watch men etc., are employed on temporary basis. The salaries of these persons are drawn from
the L.S. amount allotted towards the work charged establishment. That is, establishment which
is charged directly to work. [Link] of 1½ to 2% of the estimated cost is provided
towards the work charged establishment.
The quantities like earth work, foundation concrete, brickwork in plinthand super structure
etc., can be workout by any of following two methods:
In this method, the wall along the length of room is considered to be longwall while the wall
perpendicular to long wall is said to be short wall. To get thelength of long wall or short wall,
calculate first the centre line lengths of individual walls. Then the length of long wall, (out to
7
out) may be calculated after adding half breadth at each end to its centre line length. Thus the
length of short wall.
Measured into in and may be found by deducting half breadth from its centre linelength at each
end. The length of long wall usually decreases from earth work tobrick work in super structure
while the short wall increases. These lengths aremultiplied by breadth and depth to
getquantities.
This method is suitable for walls of similar cross sections. Here the totalcentre line length is
multiplied by breadth and depth of respective item to get thetotal quantity at a time.
When cross walls or partitions or verandah walls joinwith main all, the centre line length gets
reduced by half of breadth for eachjunction. Such junction or joints are studied carefully while
calculating total centreline length. The estimates prepared by this method are most accurate and
quick.
Partly centre line and partly cross wall method
This method is adopted when external (i.e., around the building) wall isof one thickness and the
internal walls having different thicknesses. In such cases,centre line method is applied to
external walls and long wall-short wall method isused to internal walls. This method suits for
different thicknesses walls and differentlevel of foundations. Because of this reason, all
Engineering departments arepracticing this method.
Detailed estimate
The preparation of detailed estimate consists of working out quantities of various items of
work and then determines the cost of each item. This is prepared in two stages.
The complete work is divided into various items of work such as earth work concreting, brick
work, R.C.C. Plastering etc., The details of measurements are taken from drawings and entered
in respective columns of prescribed preformed. The quantities are calculated by multiplying the
values that are in numbers column to Depth column as shown below:
8
Details of measurements form
The cost of each item of work is worked out from the quantities that already computed in the
details measurement form at workable rate. But the total cost is worked out in the prescribed
form is known asabstract of estimated form. 4%of estimated Cost is allowed for Petty
Supervision, contingencies and Unforeseen items.
Types of Estimates
i) Report
ii) Specification
9
Factors to be consisdered while preparing detailedEstimate
For bigger project, the requirement of materials is more. such bulk volume of materials will be
purchased and transported definitely at cheaper rate.
The site of work is selected, such that it should reduce damage or in transit during loading,
unloading, stocking of materials.
The skill, suitability and wages of local labors are considered while preparing the detailed
estimate.
Data
The process of working out the cost or rate per unit of each item is called as Data. In
preparation of Data, the rates of materials and labor are obtained from current standard
scheduled of rates and while the quantities of materials and labor required for one unit of item
are taken from Standard Data Book.
Fixing of rate per unit of an item
The requirement of materials is taken strictly in accordance with standard data book(S.D.B).
The cost of these includes first cost, freight, insurance and transportation charges.
Cost of labour
The exact number of labourers required for unit of work and the multiplied by the wages/ day to
get of labour for unit item work.
Some works need special type of equipment, tools and plant. In such case, an amount of 1 to 2%
of estimated cost is provided.
10
Overhead charges:
To meet expenses of office rent, depreciation of equipment salaries of staff postage, lighting an
amount of 4% of estimate cost is allocated.
Methods of preparation of approximate estimate
Preliminary or approximate estimate is required for studies of various aspects of work of project
and for its administrative approval. It can decide, in case of commercial projects, whether the
net income earned justifies the amount invested or not. The approximate estimate is prepared
from the practical knowledge and cost of similar works. The estimate is accompanied by a
report duely explaining necessity and utility of the project and with a site or layout plan. A
percentage 5 to 10% is allowed for contingencies. The following are the methods used for
preparation of approximate estimates.
The cost of construction is determined by multiplying plinth area with plinth area rate. The area
is obtained by multiplying length and breadth (outer dimensions of building). In fixing the
plinth area rate, careful observation and necessary enquiries are made in respect of quality and
quantity aspect of materials and labour, type of foundation, height of building, roof, wood
work, fixtures, number of storey’s etc., As per IS 3861-1966, the following areasinclude while
calculating the plinth area of building.
Types of Estimates
Internal shafts of sanitary installations not exceeding 2.0m2, lifts, air-conditioning ducts
etc.,
Area of barsati at terrace level: Barsati means any covered space open on one side constructed
on one side constructed on terraced roof which is used as shelter during rainy season.
11
Area of lofts.
Unenclosed balconies.
This method is generally used for multistoreyed buildings. It is more accurate that the other two
methods viz., plinth area method and unit base method. The cost of a structure is calculated
approximately as the total cubical contents (Volume of buildings) multiplied by Local Cubic
Rate. The volume of building is obtained by Length x breadth x depth or height. The length and breadth
are measured out to out of walls excluding the plinth off set. The cost of string course, cornice, corbelling
etc., is neglected. The cost of building= volume of buildings x rate/ unit volume.
Problems
Estimation of different foundations, steps and boundary [Link] : 1 From the
Drawing given below determine (a) Earth work excavationCC ([Link]) Bed (c) [Link] in
C.M. (1:6) (d) Brick Work in C.M.(1:6).
C.M.(1:6). by
12
Technical Terms
Retaining wall
It is a structure designed and constructed to resist the lateral pressure of soil when there is a
desired change in ground elevation that exceeds the angle of repose of the soil.
Aqueduct
Arch
Pitched roof
It is a roof structure where the roof leans to one side of the house
Flat roof
It is a type of covering of a building. In contrast to the sloped form of a roof, a flat roof is
horizontal or nearly horizontal.
Culvert
It is device used to channel water. It may be used to allow water to pass underneath a road,
railway, or embankment
Formwork
It is the term given to either temporary or permanent moulds into which concrete or similar
materials are poured. In the context of concrete construction, the false work supports the
shuttering moulds.
Load bearing
It is one in which a wall of a structure bears the weight and force resting upon it, conducting the
vertical load from the upper structure to the foundation.
13
Handrail
Tread
Riser
This is the vertical portion of a step. It means the vertical distance between the horizontal
surfaces of two consecutive steps.
Landing
Nosing
Flight
Flatslab
A flat slab is reinforced concrete slab supported directly over the columns without beams.
Generally used when head room is limited. Such as in cellars and warehouses.
Panel
Panel is that the part of the slab bounded on each of its form sides by the centre line of columns
or center lines of adjacent spans.
Drop
The drop panel is formed by increasing the thickness of slab in vicinity of supporting column.
14
Column head
The column head or capital located by flaring of the column at the top is primarily intended
to increase the punching shear of the slab.
Brick masonry
Masonry wall
Mortar
15
UNIT-II
EARTH WORK
All the civil engineering structures such as buildings , roads, canals, railway lines, culverts
and dams earth work will there.
Cross-section of earth work of road in banking or in cutting is usually in the form of
trapezium.
Sectional area= Area of central rectangular portion+ Area of two side triangular portions. =
Bd+2(1/2sdxd) =Bd+sd2
16
Lead and Lift
Earth work is estimated for 30m lead for distance and 1.5m lift for height or depth and this
distance of 30m and height of 1.5m are known as normal lead and lift.
For greater lead or lift the rates will be different for every unit of 30m lead & for every unit
of 1.5m lift.
Longitudinal section is usually plotted with horizontal scale of 1cm=10m to 1cm = 30m lead
& a vertical scale of 1cm=1m to 1cm=5m.
Let d1 & d2 be the height of bank at two ends portion of embankment, L the length of the
section B
The area of sides which may require turfing or pitching , may be found by multiplying the
mean
sloping by length
Sectional area at other end A2 =Bd2 +sd22 , d1 and d2 are the heights or depths at the two
ends
17
Prismoidal formula method
at the two ends of a portion of embankment of a road of length L and A is the mid-
m
sectional area.
18
UNIT - III
RATE ANALYSIS
Scope
This specification covers the general requirements for concrete jobs, using on-site production
facilities including requirements in regard to the quantity, handling, storage of ingredients,
proportioning, batching, mixing and testing of concrete and also requirements in regard to the
quality. This also covers the transportation of concrete from the mixer to the place of final
deposit and the placing, consolidation, curing, protecting, repairing ad finishing of concrete.
After award of the work, if so desired by the contractor, he / they may be allowed by the
Engineer-in-charge till the designed mix is obtained, to carry out the reinforce concrete work In
foundation and plinth as per equivalent nominal mix against the specified design mix concrete as
per IS Codes. However, all other specification for design mix shall govern for nominal mix also
and nothing extra shall be paid for use of extra cement on this account whether the cement is
supplied by the Department or procured by the contractor.
The quality of materials and method and control of manufacture and transportation of all
concrete work in respect of mix, where reinforced or otherwise, shall conform to the applicable
portions of these specifications. The Engineer-in-charge shall have the right to inspect the
sources of materials, the layout and operation of procurement and storage of materials, the
concrete batching and mixing equipments and the quality control system. Such an inspection
shall be arranged by the contractor and the Engineer-in-charge's approval shall be obtained prior
to starting the concrete work.
19
Materials for Standard Concrete
The ingredients to be used in the manufacture of standard concrete shall consist solely of a
standard type Portland cement, clean sand, natural coarse aggregate, clean water, ice and
admixtures if specially called for as per drawings or schedule of quantities.
Cement
Unless otherwise specified or called for by the Engineer-in-charge, cement shall be ordinary
Portland cement in 50 kg bags. The use of bulk cement will be permitted only with the approval
of the Engineer-in-charge. Changing of brands or type of cement within thesame structure will
not be permitted. Ordinary Portland cement (OPC) 43 grade manufactured as per I.S.
specifications of reputed brands like ACC / Ultratech / Zuari / Coramendel or any other brands
as approved by the Engineer-in-charge from time to time shall be procured and used on the work.
Joint account of cement consumed at site for every day for items of work carried shall be
maintained by the Contractor for verification to ensure effective control on quality of cement
used in the work.
A certified report attesting to the conformity of the cement to IS specifications by the cement
manufactures chemist shall be furnished to the Engineer-in-charge, if demanded. Incase the
cement is required to be arranged by the Contractor, the Contractor will have to make his own
arrangement for the storage of adequate quantity of cement. Cement in bulk may be stored in
bins or silos which will provide complete protection from dampness, contamination and
minimize caking and false set. Cement bags shall be stored in a dry enclosed shed (storage under
tarpaulins will not be permitted), well away from the outer walls and insulated from the floor to
avoid contact with moisture from ground and so arranged as to provide ready access. Damaged
or reclaimed or partly set cement will not be permitted to be used and shall be removed from the
site. The storage bins and storage arrangements shall be such that there is no dead storage. Not
more than 12 bags shall be stacked in any tier. The storage arrangement shall be got approved by
the Engineer-in-charge. Consignments in cement shall be stored as received and shall be
consumed in the order of their delivery. Contractor shall establish cement/concrete/soil testing
laboratories at site of work with qualified person to handle the laboratory. Every consignment of
cement procured shall accompany test certificate from the company indicating lot No etc.
20
Sample shall betaken for each lot and sent to Standard Approved Material Testing Laboratory for
physical and chemical analysis. The cost of testing shall be borne by the Contractor.
Cement held in store for a period of 90 (ninety) days or longer shall be retested before use in
work. Should at any time the Engineer-in-charge have reasons to consider that any cement is
defective, then irrespective of its origin and / or manufacturers test certificate, such cement
shallbetested immediately at a National Test Laboratory / Departmental Laboratory or such
approved laboratory, and until the results of such tests are found satisfactory, it shall not be used
in any work.
Aggregates
"Aggregate" in general designates both fine and coarse inert materials used in the manufacture of
concrete."Fine Aggregate" is aggregate most of which passes through 4.75 mm I.S. sieve.
"Coarse Aggregate" is aggregate most of which is retained on 4.75 mm I.S. sieve. All fine and
coarse aggregates proposed for use in the work shall be subject to theEngineer-in-charge's
approval and after specific materials have been accepted, the source of supply of such materials
shall not be changed without prior approval of the Engineer-incharge. Aggregate shall, except as
noted above, consists of natural sand, crushed stone and gravel from a source known to produce
satisfactory aggregate for concrete and shall be chemically inert, strong, hard, curable against
weathering, of limited porosity and free from deleterious materials that may cause corrosion to
the reinforcement or may impair the strength and / or durability of concrete. The grading of
aggregates shall be such as to produce a dense concrete of and shall be based on the "mix design"
and preliminary test on concrete specified hereinafter.
Sampling of the aggregates for mix design and determination of suitability shall be taken under
the supervision of the Engineer-in-charge and delivered to the laboratory, well in advance of the
schedule placing of concrete. Record of tests which have been made on proposed aggregates and
on concrete made from this source of aggregates shall be furnished to the Engineer-in-charge in
advance of the work or use, in determining suitability of the proposed aggregate.
Storage of aggregates
All coarse and fine aggregates shall be stacked separately in stock pile in the materialyard near
the work site in bins properly constructed to avoid inter mixing of different aggregates.
Contamination with foreign materials and earth during storage and while heaping the materials
21
shall be avoided. The aggregate must be of specified quality not only at the time of receiving at
site but also at the time of loading into mixer. Rakers shall be used for lifting the coarse
aggregate from bins or stock piles. Coarse aggregate shall be piled in layers not exceeding 1.00
meters in height to preventconning or segregation. Each layer shall cover the entire area of the
stock pile before succeeding layers are started. Aggregates that have become segregated shall be
rejected. Rejected materials after remixing may be accepted, if subsequent tests demonstrate
conformity with required gradation.
Specific Gravity
Aggregates having a specific gravity below 2.6 (saturated surface dry basis) shall not be used
without special permission of the Engineer-in-charge.
Fine Aggregate
Fine aggregate except as noted above, and for other than light weight concrete shall consist of
natural or crushed sand conforming to IS 383. The sand shall be clean, sharp, hard, strong and
durable and shall be free from dust, vegetable substances, adherent coating, clay, loam, alkali,
organic matter mica, salt or other deleterious substances which can be injurious to the setting
qualities / strength / durability of concrete.
Sand shall be prepared for use by such screening or washing or both as necessary, to remove all
objectionable foreign matter while separating the sand grains to the required size fractions. Sand
with silt content more than 3 percent will not be permitted to be used unless same is washed and
silt content is brought within 3% by weight.
Gradation
Unless otherwise directed or approved, the grading of sand shall be within thelimit indicated here
under:-Where the grading falls outside the limits of any particular grading zone of sieves, other
than 600 micron (IS) sieve by not more than 5% it shall be regarded as falling within that grading
zone. This tolerance shall not be applied to percentage passing the 600 micron (IS)sieve or to
percentage passing any other sieve size on the coarser limit of grading zone I or the finer limit of
grading zone IV. Fine aggregates conforming to Grading zone IV shall not be used unless mix
designs and preliminary tests have shown its suitability for producing concrete of specified
strength and workability.
22
Fineness Modulus
The sand shall have a fineness modulus of not less than 2.2 or more than 3.2 the fineness
modulus is determined by adding the cumulative. Percentages retained on the following IS sieve
sizes (4.75 mm, 2.36 mm, 1.18mm, 600 micron, 300 micron and 150 micron) and dividing the
sum by 100.
Coarse Aggregate
Coarse aggregate for concrete except as noted above and for other than light weight concrete
shall conform to IS 383. This shall consist of natural or crushed stone and gravel, and shall be
clean and free from elongated, flaky or laminated pieces, adhering coatings, clay lumps, coal
residue, clinkers, sag, alkali, mica, organic matter or other deleterious matter. The coarse
aggregate and fine aggregate shall be tested from time to time as required by the Engineer-in-
charge to ascertain its suitability for use in construction and the charges for testing aggregate
shall be born by the contractor as specified herein after.
Crushed rock shall be screened and / or washed for the removal of dirt or dust coating, if so
demanded by Engineer-in-charge.
Grading
Coarse aggregates shall be either in single or graded in both the cases. The grading
shall be within the following limits:
Foreign Material Limitations
The percentages of deleterious substances in the coarse aggregate delivered to the mixer shall not
exceed the following.
23
Water
Water used for both mixing and curing shall be free from injurious amount of deleterious
materials; potable waters are generally satisfactory for mixing and curing concrete. In case of
doubt, the suitability of water for making concrete shall be ascertained by the compressive
strength and initial setting time test specified in IS 456. The sample of water taken for testing
shall be typical of the water proposed to be used for concreting, due account being paid to
seasonal variation. The samples shall not receive any treatment before testing other than that
envisaged in the regular supply of water proposed for use in concrete. The sample shall be stored
in a clean container previously rinsed out with similar water. Average 28 days compressive
strength of at least three 150mm concrete cubes prepared with water proposed to be used shall
not be less than 90% of the average strength of three similar concrete cubes prepared with
distilled water. The initial setting time of test block made with the appropriate test cement and
the water proposed to be used shall not be less than 30 minutes and shall not differ by more than
(+) 30 minutes form the initial setting time of control test block prepared with the appropriate
test cement and distilled water. The test blocks shall be prepared and tested in accordance it the
requirements of IS 4031. Where water can be shown to contain an excess of acid, alkali, sugar or
salt, Engineer-in-charge may refuse to permit its use. As a guide, the following concentrations
represent the maximum permissible values.
Limits of acidity
To neutralize 200ml sample of water, using phenolphthalein as an indicator, it should not require
more than 2ml of 0.1 normal NaOH. The details of test shall be as given in IS 3025. Limits of
alkalinity
24
To neutralize 200ml sample of water, using methyl orange as an indicator, it should not require
more than 10ml of 0.1 normal HCL. The details of test shall be as given in IS 3025.
All reinforced concrete in the works shall be "Design Mix Concrete" as defined in I.S.456-2000.
All "Design Mix Concrete" work to be carried out under these specifications shall be in grades
designated as per table below:
Grades of Concrete
Mix Design
This is to investigate the grading of aggregates, water cement ratio, workability and the quantity
of cement required to give works cubes of the characteristic strength specified. The proportion of
the mix shall be determined by weight. Adjustment of aggregate proportions due to moisture
present in the aggregate shall be made. Mix proportioning shall be carried out accordingto the
ACI standard designation ACI-613 or Design of concrete mixes –Road research Note No. 4,
Department of Scientific and Industrial Research U.K. or I.S.10262-1982.
Since different cements and aggregates of different maximum size, grading, surface texture,
shape and other characteristics may produce concretes of different compressive strength for the
same free water cement ratio, the relationship between strength and free water cement ratio
should preferably be established for the materials actually to be used. In the absence of such
data, the preliminary free water cement ration (by mass) corresponding to the target strength of
28 days may be selected from the relationship shown in Fig. 1 of IS. 10262- page 7.
Alternately, the preliminary freewater ratio (by mass) corresponding to the target average
strength may be selected from the relationship in Fig2-IS 10262-1982, Page 8 using the curve
25
corresponding to the 28 days cement strength to be used for the purpose. Other relevant items to
be used with design of mix should strictly conform to the relevant clauses and appendices of IS
10262 – 1982.
General
Concrete as actually done shall be measured for payment, subject to the following tolerances,
unless otherwise stated hereinafter. Any work done extra over the specified dimensions shall not
be measured for payment.
a. Linear dimensions shall be measured in full centimeters except for the thickness of
slab which shall be measured tot eh nearest half centimeter.
d. The concrete shall be measured for its length, breadth and height/depth limiting
dimensions to those specified on drawings or as directed by the Engineer-incharge.
Note: The sizes of RCC members as assumed in to estimate are based on preliminarydrawings
andare likely to be changed. The contractor is not entitled to any extra claim due to such
changes.
Deductions
26
R.C.C. in foundation and footings shall be measured for its length, breadth and depths limiting
dimensions to those specified in drawing or as ordered in writing by the Engineer-incharge. In
case of tapering portions of column footings, the quantities shall be calculated by Prismoidal
Formula.
Column
Column shall be measured from top footings to the plinth level and from plinth level to the
structural slab level ad to the subsequent structural slab levels. Measurements for higher grade
concrete in column at its junction with lower grade concrete beams shall be restricted total
column section supporting the beam in question.
Wall
All walls shall be measured from top of the wall footing to the plinth level ad from plinth level to
the top of structural first floor and to subsequent floors.
Beam shall be measured from face to face of the columns, walls, cross beams including haunches
if any. The depth of the beams shall be measured from the top of the slab tot eh bottom of the
beam except in the case of inverted beam where it shall be measured from top of slab to top
beams. The beams and lintels with narrow width even though acting as facia in elevation in some
cases will be measured as beams and lintels only.
Slab
The length and breadth of slab laid to correct thickness as shown in the detailed drawing for as
ordered by the Engineer-in-charge shall be measured between beams, walls ad columns.
Chajjas, Facias, Fins ad Mullions
a. Chajjas shall be measured net from supporting faces upto the edges of chajjas without
any facia.
27
other supporting structural members.
Staircase
The concrete in all members of staircase like waist slabs, steps, cantilever steps, stringer beams
etc. shall be measured for their length, breadth ad depth, limiting dimensions to those specified
on drawings. No deductions shall be made for embedded plugs, pockets.
Rates
The rate for PCC / RCC shall include the cost of all materials, labour, transport, tools ad plants
and all the operations mentioned hitherto, including or excluding the cost of form work and / or
reinforcement as mention din the schedule for quantities. The rates also shall include the cost of
testing material, mix design; cube test ad allied incidental expenses. The reinforcement steel used
in the works shall be measured and paid for separately under relevant item.
Form work
General
The form work shall consist of shores, bracings, sides of beams and columns, bottom of slabs
etc, including ties, anchors, hangers, inserts etc. complete which shall be properly designed and
planned for the work. The false work shall be so constructed that up and down vertical
adjustment can be made smoothly. Wedges may be used at the top or bottom of timber shores,
but not at both ends, to facilitate vertical adjustment and dismantling of form work.
The design and engineering of form work as well as its construction shall be the responsibility of
Contractor. The drawings and calculations for the design of the form work shall be submitted
well in advance to the Engineer-in-charge for approval before proceeding with work, at no extra
cost to the Department. Engineer-in-charge's approval shall not however, relieve Contractor of
the full responsibility for the design and construction for the form work. The design shall take
28
into account allhe loads vertical as well as lateral that the forms will be carrying including live
and vibration loadings.
Tolerances
Tolerances are specified permissible variation from lines, grade or dimensions given in
drawings. No tolerances specified for horizontal or vertical buildings lines or footings. Unless
otherwise specified, the following tolerances will be permitted.
Steel reinforcement
Steel reinforcement bars, if supplied or arranged by contractor, shall be either plain round mild
steel bars grade as per IS 432 (part-I) or medium tensile steel bars as per IS 452 (part-I) or hot
rolled mild steel ad medium tensile steel deformed bars as per IS 1139 or cold twisted steel bars
and hot weld strength deformed bars as per IS 1786, as shown and specified on the drawings.
Wire mesh or fabric shall be in accordance with IS 1566. Substitution of reinforcement will not
be permitted except upon written approval from Engineer-in-charge.
Storage
The reinforcement steel shall not be kept in direct contact with ground but stacked on top of
an arrangement of timber sleepers or the like. Reinforcement steel shall be with cement wash
before stacking to prevent scale and rust. Fabricated reinforcement shall be carefully stock to
prevent damage, distortion, corrosion ad deteriorations.
Quality
All steel shall be grade I quality unless specifically permitted by the Engineer-incharge. No
rolled material will e accepted. If demanded by the Engineer-in-charge. Contractor shall submit
the manufacturers test certificate for steel. Random tests on steel supplied by contractor may
beperformed by Department as per relevant Indian Standards. All costs incidental to such tests
shall be at contractors expense. Steel not conforming to specifications shall be rejected. All
reinforcement shall be clean, free from grease, oil, paint, dirt loose mill, scale dust, bituminous
materials or any other substances that will destroy or reduce the bond. All rods shall be
thoroughly cleaned before being fabricated. Pitted and defective rods shall not be used. All bars
shall be rigidly held in position before concreting. No welding of rods to obtain continuity shall
be allowed unless approved by the Engineer-incharge. If welding is approved, the work shall be
29
carried as per 2751, according to best modern practices ad as directed by the Engineer-in-charge
in all cases of important connections, tests shall be made to prove that the joints are of the full
strength of bars welded. Special specifications, as specified by the Engineer-in-charge, shall be
adhered to in the welding of cold worked reinforcing bars and bars other than mild steel.
Laps
Laps ad splices for reinforcement shall be shown in the drawings. Splices, in adjacent bars shall
be staggered ad the locations of all splices, except those pecified on the drawing shall be
approved by the Engineer-in-charge. The bars shall not be lapped unless the length required
exceeds the maximum available length of bars at site.
Bending
All bars shall be accurately bent according to the sizes ad shapes shown on the detailed working
drawings/ bar being schedules. They shall be bent gradually by machine or other approved
means. Reinforcing bars shall not be straightened and rebent in a manner that will injure the
materials. Bars containing cracks or splits shall be rejected. They shall be bent cold, except bars
of over 25mm in diameter which may be bent hot if specifically approved by the Engineer-
incharge. Bars bent hot shall not be heated beyond cherry red colour (not exceeding 645oC ) and
after bending shall be allowed to cool slowly without quenching. Bars incorrectly bent shall be
used only of ht means used for straightening and rebinding be such as shall not, in the opinion of
the Engineer-in-charge injure the material. NO reinforcement bar shall be bent when in position
in the work without approval, whether or not it is partially embedded in ardened concrete. Bars
having links or bends other than those required by design shall not be used.
Bending at Construction Joints
Where reinforcement bars are bent aide at construction joints and afterwards bent back into their
original position, care should be taken to ensure that no time the radius of the bend is less than 4
bar diameters for plain mild steel or 6 bar diameters for deformed bars. Care shall also be taken
when bending back bars to ensure that the concrete around the bar is not damaged.
Reinforcement shall be accurately fixed by ay approved means maintain din the correct position
as shown in the drawings by the use of blocks, spacer and chairs as per IS 2502 to prevent
30
displacement during placing ad compaction of concrete. Bar intended to be in contact at crossing
point shall be securely bound together at all such points with number16 gauge annealed soft iron
wire. The vertical distances required between successive layers of bars in beams or similar
members shall be maintained by the provision of mild steel spacer bars at such intervals that the
main bars do not perceptibly sag between adjacent spacer bars.
Unless otherwise specified by the Engineer-in-charge, reinforcement shall be placed within the
following tolerances:
Tolerance in spacing
Painting
31
UNIT-V
VALUATION
Definitions
Expenditure
The whole amount can be spent during the financial year or not.
Capital cost
Total cost including all the expenditure incurred from beginning to the completion of a
work.
Provisional sum
Estimate of bill quantities for some special work to be done by a specialist firm whose details
are known at the time of preparation of estimate.
Rate of cost
The cost per unit of subhead which is arrived at by dividing the up-todate final charges on a
sub-head by its up-to-date progress.
Premium
REBATE
PLINTH AREA
RATES
32
Contingencies
Valuation
Valuation is the technique of estimating or determining the fair price or value of a property
such as building, a factory, other engineering structure of various types, land…etc.
Salvage value
Sinking fund
The fund is gradually accumulated by way of periodic on annual deposit for the replacement
of the building or structure at the end of its useful life.
Depreciation
Depreciation is the gradual exhaustion of a usefulness of a property. Decrease or loss in the
value of a property due to its structural deterioration use, life wear and tear, decay and
obsolescence.
Scrap value
Scrap value is the value of dismantled materials. For a building when the life is over the end
of utility period of dismantled materials as steel, bricks, timber. Etc. will fetch certain amount
which is scrap value of a building.
Objects of valuation
It is the technique of estimating and determining the fair price or value of a property such as a
building, a factory or other engineering structures of various types, land etc.
33
When it is required to buy or sell a property, its valuation is required.
Taxation
To assess the tax of a property, its valuation is required. Taxes may be municipal tax, wealth
tax, Property tax etc, and all the taxes are fixed on the valuation of the property.
Rent Function
In order to determine the rent of a property, valuation is required. Rent is usually fixed on the
certain percentage of the amount of valuation which is 6% to 10% of valuation.
When loans are taken against the security of the property, its valuation is required.
Compulsory acquisition
Whenever a property is acquired by law; compensation is paid to the owner. To determine the
amount of compensation, valuation of the property is required.
Valuation of a property is also required for Insurance, Betterment charges, speculations etc.
Valuation of Building
Valuation of a building depends on the type of the building, its structure and durability, on the
situation, size, shape, frontage, width of roadways, the quality of materials used in the
construction and present day prices of materials. Valuation also depends on the height of the
building, height of the plinth, thickness of the wall, nature of the floor, roof, doors, windows
etc.
The valuation of a building is determined on working out its cost of construction at present
day rate and allowing a suitable depreciation.
34
6. Depreciation method of Valuation
Definitions
Market Value
The market value of a property is the amount which can be obtained at any particular time
from the open market if the property is put for sale. The market value will differ from time to
time according to demand and supply.
The market value also changes from time to time for various miscellaneous reasons such as
changes in industry, changes in fashions, means of transport, cost of materials and labour etc.
Book Value
Book value is the amount shown in the account book after allowing necessary depreciations.
The book value of a property at a particular year is the original cost minus the amount of
depreciation allowed per year and will be gradually reduced year to year and at the end of the
utility period of the property, the book value will be only scrap value.
Capital cost
Capital cost is the total cost of construction including land, or the original total amount
required to possess a property. It is the original cost and does not change while the value of
the property is the present cost which may be calculated by methods of Valuation.
Capitalized Value of a Property
The capitalized value of a property is the amount of money whose annual interest at the
highest prevailing rate of interest will be equal to the net income from the property. To
determine the capitalized value of a property, it is required to know the net income from the
property and the highest prevailing rate of interest.
Therefore, Capitalized Value = Net income x year’s purchase
Year’s Purchase
Year’s purchase is defined as the capital sum required to be invested in order to receive a net
receive a net annual income as an annuity of rupee one at a fixed rate of interest.
35
The multiplier of the net annual income to determine the capital value is known as the
Year’s Purchase (YP) and it is useful to obtain the capitalized value of the property.
In this method, the depreciation of a property is assumed to be equal to the annual sinking
fund plus the interest on the fund for that year, which is supposed to be invested on interest
bearing investment.
In this method, the net income by way of rent is found out by deducting all outgoing from the
gross rent. A suitable rate of interest as prevailing in the market is assumed andYear’s
purchase is calculated. This net income multiplied by Year’s Purchase gives the capitalized
value or valuation of the property. This method is applicable only when the rent is known or
probable rent is determined by enquiries.
This method may be adopted when the rental value is not available from the property
concerned, but there are evidences of sale price of properties as a whole. In such cases, the
capitalized value of the property is fixed by direct comparison with capitalized value of
similar property in the locality.
This method of Valuation is suitable for buildings like hotels, cinemas, theatres etc for which
the capitalized value depends on the profit. In such cases, the net income is worked out after
deducting gross income; all possible working expense, outgoings, interest on the capital
invested etc. The netprofit is multiplied by Year’s Purchase to get the capitalized value. In
such cases, the valuation may work out to be high in comparison with the cost of
construction.
In this method, the actual cost incurred in constructing the building or in possessing the
property is taken as basis to determine the value of property. In such cases, necessary
depreciation should be allowed and the points of obsolescence should also be considered.
36
Development Method of Valuation
This method of Valuation is used for the properties which are in the underdeveloped stage or
partly developed and partly underdeveloped stage. If a large place of land is required to be
divided into plots after providing for roads, parks etc, this method of valuation is to be
adopted. In such cases, the probable selling price of the divided plots, the area required for
roads, parks etc and other expenditures for development should be known.
If a building is required to be renovated by making additional changes, alterations or
improvements, the development method of Valuation may be used.
According to this method of Valuation, the building should be divided into four parts:
1. Walls
2. Roofs
3. Floors
And the cost of each part should first be worked out on the present day rates by detailed
measurements.
The present value of land and water supply, electric and sanitary fittings etc should be added
to the valuation of the building to arrive at total valuation of the property.
Depreciation is the gradual exhaustion of the usefulness of a property. This may be defined as
the decrease or loss in the value of a property due to structural deterioration, life wear and
tear, decay and obsolescence.
37
Straight Line Method
In this method, it is assumed that the property losses its value by the same amount every year.
A fixed amount of the original cost is deducted every year, so that at the end of the utility
period, only the scrap value is left.
For example, a vehicle that depreciates over 5 years, is purchased at a cost ofUS$17,000,
and will have a salvage value ofUS$2000, will depreciate at US$3,000 per year.
In this method, it is assumed that the property will lose its value by a constant percentage of
its value at the beginning of every year.
FIXATION OF RENT
Capitalized value of the property can be known by any of the methods discussed earlier and
suitable value of year’s purchase is adopted according to the admissible rate of interest (8%
or any other fair rate).
All possible outgoings are added to this net income which will give gross income from the
property. Gross income or gross rent = Net rent + outgoings.
38
General or brief specification
This gives the nature and class of the work and materials in general terms, to be used in the
various parts of work, from the foundation to the superstructure. It is a short description of
different parts of work specifying materials, proportions, qualities, etc., General
specifications give general idea of the whole work or structure and are useful for preparing
for estimate.
Detailed specifications
Scope of Work
The scope for work covered under this specifications pertain to excavation of foundations,
trenches, pits and over areas, in all sorts of soil, soft and hard rock, correct to dimensions
given in the drawing including shoring, protections of existing underground utilities of any,
such as water lines, electric cables etc. dewatering and shoring if necessary, stacking the
useful materials as directed within the lead specified, refilling around the foundation and into
the plinth with selected useful excavated earth and disposing off the surplus earth / materials
within specified lead and finishing the surface to proper levels, slopes and camber etc. all
complete.
Site Clearance
Before the earth work is started the area coming under cutting and filling shall be cleared of
all obstruction, loose stones, shrubs, rank vegetation, grass, bushes and rubbish removed up
to a distance of 150 metres outside the periphery of the area under clearance. This work is
deemed to be included in the earthwork item rate and no separate payment will be admissible.
Roots and Vegetation clearance
The roots of trees if any shall be removed to a minimumdepth of 60 cm below ground level
or a minimum of 30 cm below formation level whichever is lower and the hollows filled up
with earth leveled and rammed. This work is deemed to be included in the earthwork items
and no separate payment will be admissible for the work. Any material obtained from the site
will be the property of the Government of India and the useful materials as decided by the
Engineer-in-charge will be conveyed and properly stacked as directed within the lead
specified.
39
or any other permanent benchmark approved by the Engineer-in-charge. Necessary profiles
with pegs, bamboos and strings or Burjis shall be made to show the correct formation levels
before the work is started. The contractor shall supply labour and materials for setting out and
making profiles and Burjis for the work at his own cost and the same shall be maintained
during the excavation work. The Department will show grid co-ordinate or other reference
points. It shall bethe responsibility of the contractor to set out center lines correctly with
reference to the drawings and install substantial reference marks. Checking of such alignment
by the Department will not absolve the contractor from his responsibility to execute the work
strictly in accordance with the drawings.
Excavation
The contractor shall notify the Engineer-in-charge before starting excavation and before the
ground is disturbed, to enable him to take existing level for the purpose of measurements.
The ground levels shall be taken at 5 to 15 metres intervals in uniformly sloping ground and
at closer distance where local mounds, pits, or undulations are met with, as directed by the
Engineer-in-charge. The ground levels shall be recorded in field books and plotted on plans,
which shall be signed by the Contractor and the Engineer-in-charge, before the earthwork is
actually started. The labour required for taking levels, shall be supplied by the Contractor at
his own cost. The Contractor shall perform excavation in all types of soils, murrum, soft and
hard rock, boulders etc. in foundation, over areas and in trenches to widths, lines, levels,
grades and curves as shown in the drawing or lesser widths, lines, levels, grades and levels as
directed by the Engineer-in-charge and per items in the schedule of quantities.
The item in the schedule of quantities shall specify the excavation in trenches or over areas.
For this purpose, the excavation for any depth in trenches for foundation not exceeding 1.5m
in width or 10sqm. on plan shall be described as excavation in foundation trenches.
Excavation exceeding 1.5m in width as well as [Link] plan (excluding trenches for pipes,
cables etc.) and exceeding 30cm in depth shall be described as excavation over areas.
Excavation exceeding 1.5m in width as well as [Link] plan but not exceeding 30cm. in
depth shall be described as surface Excavation.
Classification of Earth work
The earthwork shall be classified under the following main categories and measured
separately for each category. All types of soil, murrum, boulders, Soft rock, Hard rock.
This includes earth, murrum, top deposits of agricultural soil, reclaimed soil, clay, sand or
any combination thereof ad soft and hard murrum, shingle etc. which is loose enough to be
40
removed with spadies, shovel and pick axes. Boulders not more than 0.03 cum. in volume
found during the course of excavation shall also fall under this classification.
This shall include all materials which are rock or hard conglomerate, all decomposed
weathered rock, highly fissured rock, old masonry, boulders bigger than 0.03 cum, in volume
but not bigger than 0.5 cum. and other varieties of soft rock which can be removed only with
pick axes, crow bars, wedges and hammers with some difficulty. The mere fact that the
contractor resorts to blasting and / or wedging and chiseling of reasons of his own, shall not
mean the rock is classifiable as hard rock.
This includes all rock other than soft rock mentioned in para above 1.5.1 (b) viz. soft rock,
occurring in masses, boulders having approximate volume more than 0.5 cum. plain or
reinforced cement concrete, which can best be removed by chiseling and wedging where
blasting cannot be permitted owing to any restriction at site.
Where blasting is not permitted and if the Engineer-in-charge so desires, the excavation shall
be done by chiseling and wedging or any other agreed method.
Note: All the excavated hard rock obtained shall be stacked properly and neatly within
thespecified leadby the contractor as directed by the Engineer-in-charge.
Excavation
The excavation under all classifications in areas in trenches or in pits shall be carried out
systematically. Cutting shall be done from top to bottom and not under pining or under
cutting will be allowed. The bottom and sides of excavation shall be dressed to proper level,
slopes, steps, camber etc. by removing high spots and ramming thoroughly as directed by the
Engineerin-charge. All the excavation shall be carried out strictly to the dimensions given in
the drawing. The width shall generally be of the width of mudmat concrete and depth as
shown in drawing or as directed by the Engineer-in-charge, according to availability of the
desired bearing capacity of soil below. Any excavation if taken below the specified depths
and levels, the contractor shall at his own cost fill up such over cut to the specified level with
cement concrete [Link] in case of excavation in all types of soils an with cement concrete
[Link] in case of excavation soft and hard rock. After the excavation is completed, the
contractor shall notify the Engineer-in-charge to that effect and no further work shall be taken
up until the Engineer-in-charge has approved the depth and dimensions an also the nature of
41
foundation materials, levels and measurements shall also be recorded prior to taking up any
further work.
Shoring:
Unless separately provided for in the schedule of quantities, the quoted rate for excavation
shall include excavation of slopes to prevent falling in soil by providing and / or fixing,
maintaining and removing of shorting, bracing etc. The contractor would be responsible for
the design of shoring for proper retaining of sides of trenches, pits etc. with due consideration
to the traffic, superimposed loads etc. shoring shall be of sufficient strength to resist the
pressure and ensure safety from slips and to prevent damage to work and property and injury
to persons. It shall be removed as directed after items for which It is required are completed
should the slips occur, the slipped materials shall be removed and slope dressed to a modified
stable slope. Removal of the slipped earth will not be measured for payment.
Dewatering:
Unless specifically provided for as a separate item in the schedule of quantities, rate shall
also include bailing or pumping out all water which may accumulate in the excavation during
the progress of further works such as mud mat concrete, R.C. footings, shuttering etc. either
due to seepage, springs, rain or any other cause and diverting surface flow by bunds or other
means. Care shall be taken to ensure that the water discharged sufficiently away from the
foundations keep it free from nuisance to other works in the neighborhood.
Antiquities
Any finds of archeological interest such as relics of antiquity, coins, fossils or other articles
of value shall be delivered to the Engineer-in-charge and shall be the property of the
Government.
Useful Materials:
Any material obtained from the excavation which in the opinion of the Engineerncharge is
useful, shall be stacked separately in regular stacks as directed by the Engineerincharge and
shall be the property of the Government. No material excavated from foundation trenches of
whatever kind they may be are to be placed even temporarily nearer than about 3m from the
outer edge of excavation. Discretion of the Engineer-in-charge in such cases is final. All
materials excavated will remain the property of the Department. Rate for excavation includes
sorting out of the useful materials and stacking them separately as directed within the specific
42
lead. Material suitable and useful for backfilling or there use shall be stacked in convenient
place but not in such a way as to obstruct free movement of materials, workers and vehicles
or encroach on the area required for constructional purposes. It shall be used to the extent
required to completely backfill the structure to original ground level or other elevation shown
on the plan or as directed by the Engineer-in-charge. Materials not useful in anyway shall be
disposed off, leveled and compacted as directed by the Engineer -in-charge within a specified
lead. The site shall be left clan of all debris and leveled on completion.
Backfilling in sides of Foundations, Plinth, Under Floor etc
The backfilling shall be done after the concrete or masonry has fully set and shall be done in
such a way as not to cause under-thrust on any part of the structure. Where suitable excavated
material is to be used for backfilling, it shall be brought from the place where it was
temporarily deposited and shall be used in backfilling. The scope of work for backfilling/
filling in foundation, plinth, under floors etc. shall include filling for all the buildings covered
under the contract. Surplus earth available from one building, if required, shall be used for
backfilling filling for other buildings also within the specified lead mentioned in the item. All
timber shoring and form work left in the trenches, pits, floors etc. shall be removed after
their necessity ceases and trash of any sort shall be cleared out from the excavation. All the
space between foundation masonry or concrete and the sides of excavation shall be backfilled
to the original surface with approved materials in layers not exceeding 150mm, in thickness,
watered and well consolidated by means of rammers to at least 90% of the consolidation.
Areas inaccessible to mechanical equipment such as areas adjacent to walls and columns etc.
shall be tamped by hand.
rammer or by hand held power rammers to the required density. The backfill shall be
uniform in character and free from large lumps, stones. shingle or boulder not larger than
75mm. in any direction, salt, clods, organic or other foreign materials which might rot. The
backfilling in plinth and under floor shall be well consolidated by means of mechanical or
hand operated rammers as specified to achieve the required density. Test to establish proper
consolidation as required will be carried out by the Department at rates specified. Two tests
per 50 sqm. will be taken to ascertain the proper consolidation. The cost of tests carried out
will be recovered from the contractor’s bill.
After the available suitable excavated materials are exhausted as backfilling, the contractor
shall notify the Engineer-in-charge of the fact and levels taken jointly with Engineerin-
charge. The earth, murrum, sand, gravel etc. or such materials suitable for filling proposed to
43
be filled under floors and so mentioned in t he item of schedule of quantities shall then be
brought to site from approved locations and sources.
Earth Filling
The earth, soft murrum etc. so brought shall be filled up in layers of 15 cm depth, each layer
being well watered and consolidated by approved hand or mechanical tampers or other
suitable means to achieve the required density.
Gravel if required to be filled under floors, shall be single washed gravel of approved quality
and of size varying from 12mm t0 20mm. it shall be uniformly blind with approved type of
soil and / or sand to obtain full compaction. Gravel shall be filled in specified thickness and
shall be well watered and rammed entirely to the satisfaction of the [Link]
sand is required to be filled under floors, it shall be clean, medium grained and free from
impurities. The filled in sand shall be kept flooded with water for 24hrs. to ensure maximum
consolidation shall be done by the contractor at his own cost. The surface shall then be well
dressed and got approved from Engineer - in-charge before any other work is taken over the
fill.
Lead and Lift
Lead
The lead for disposal / deposition of excavated materials shall be as specified in
therespectiveitem of work. For the purpose of measurements of lead, the area to be excavated
or filled or area onwhich excavated material is to be deposited/ disposed off shall be divided
in suitable blocks and for each of the block, the distance between center lines shall be taken
as the leads which shall be measured by the shortest straight line route on the plan and not the
actual route adopted.
Lift: Lift shall be measured from ground level. Excavation up to 1.5m depth below
groundlevel anddepositing excavated material on the ground shall be included in the item of
earthwork for various kinds of soil. Extra lift shall be measured in unit of 1.5m or part
thereof. Obvious lift shall only be measured that is lifts inherent in the lead due to ground
slope shall not be measured, except for lead up to 250m. All excavation shall be measured in
successive stages of 1.5m stating the commencing level. This shall not apply to cases where
no lift is involved as in hill side cutting.
44
Mode of Measurements:
All excavation in areas having depth more than 30cm. pits, trenches etc. shall be measured
net. The dimensions for the purpose of payment shall be reckoned on the horizontal area of
the excavations for the purpose of payment shall be reckoned on the horizontal area of the
excavation at the base for foundations of the walls, columns, footings, rafts or other
foundations, multiplied by the mean depth from the surface of ground determined by levels.
Excavation for side slopes will not be paid for. Excavation in areas having depths less than
30 [Link] be measured as surface excavation on square meter basis, mentioning the
average depth of excavation.
Reasonable working space beyond concrete dimension required for waterproofing and
shuttering where considered necessary in the opinion of Engineer-in-charge will be allowed
in execution and considered for payment for underground water tank, sump septic tank etc.
Where direct measurements of rock excavation are not possible, volume of rock can be
calculated on the basis of length, breadth, and depth of stacks made at site as mentioned in
para 1.5.1 (c). The net volume shall be worked out by reducing it by 40% taking the voids
into consideration as 40%. Similarly to arrive at net quantity to be paid in the case of soil,
reduction at 20% of corresponding stack / truck measurements shall be made. The rate for
excavation shall include carting and disposing and leveling the excavated materials within
the specified lead. The rate shall also be inclusive of cost of all tools, plants, explosives,
shoring, dewatering at various stages, labour, materials etc. to complete all the operations
specified.
The backfilling and consolidation in sides of foundation and in plinth with excavated material
will not be paid for separately. The rate quoted for excavation shall be deemed to have been
included the cost of stacking of excavated materials, conveying within the specified lead,
picking of selectedstacked materials, conveying it to the place of final backfill, compaction to
the required proctor density etc. Payment for filling and consolidation inside the trenches,
sides of foundations, plinth etc. with selected materials brought by the contractor other than
the excavated material, shall be paid for separately as per the rates in schedule of quantities
which includes cost of such materials/ excavation, royalty, its conveyance within the
specified lead, watering, consolidating, dressing etc. Actual quantity of consolidated filling
shall be measured and paid in cubic meters up to two places of decimal. The rate quoted in
cum. for items of excavation is deemed to include the necessary additional quantity of
excavation involved beyond the plan dimensions of the work which may be necessary to be
carried out for carrying out the work in an engineering made, decided upon by the contractor.
Therefore no extra payment will be made for any excavation done other than the required
quantity as per the plan dimension indicated in the drawings. Measurements for excavation
over areas shall be determined by levels or by "Dead men" or both at the discretion of the
45
Engineer-in-charge. If however the Engineer-in-charge decided on measurement by levels,
levels of site shall be jointly taken and recorded by the Engineerincharge or his
representatives and the contractor, before commencement of the work and after completion
of the work and the quantity of work done shall be computed based on these levels. The
volume of earth work shall be computed based on "Simpson's formula ' or any other
approved method at the discretion of the Engineer-in-charge.
Antitermite treatment
General
Scope
The scope of pre constructional anti-termite treatment covers the soil treatment with approved
chemicals in water emulsion in foundation trenches for columns, plinth beams, plinth filling,
at junction of walls and floor, in expansion joints etc. in stages as detailed in this
specifications and drawings. Unless otherwise stipulated, the anti-termite treatment will be
carried out as per IS 6313 (part II) 1981 and / or as per direction of the Engineer-incharge.
Site preparation
In order to ensure uniform distribution of the chemical emulsion and to assist penetration, the
following site preparation shall be carried out:
a) Remove all trees, stumps, logs or roots from the building site.
b) Remove all concrete form work if left anywhere, leveling pegs, timber
offcuts and other building debris from the area to be treated.
46
c) If the soil to be treated is sandy or porous, preliminary moistening will
be required to fill capillary spaces in soil in order to prevent the loss of
emulsion through piping or excessive percolations.
All sub-floor leveling and grading should be completed. All cutting trenches and excavations
should be completed with backfilling in place, borrowed fill must be free from organic debris
and shall be well compacted. If this is not done supplementary treatments should be made to
complete the barrier.
Chemical to be used
The effectiveness of chemical depends upon the choice of the chemical, the dosage adopted
and the thoroughness of application. The chemical solutions or emulsions are required to be
dispersed uniformly in the soil and to the required strength so as to form an effective chemical
barrier which is lethal and repellent to termites.
Soil treatment
One of the following chemicals in water emulsion, after approval from the Engineerincharge
shall be used uniformly over the area to be treated.
The chemical emulsion as stated above will be applied uniformly by sprayers at the
prescribed rates as detailed below in all the sages of the treatment.
In case of normal wall load bearing structures, columns pits, wall trenches and basement, the
treatment shall be at 5 litres/sqm. or surface area of the bottom and sides to a height of at least
300mm. After the foundation work, the sides shall be treated at 7.5 litres/sqm. of vertical
surface of substructure on each side. After the earth filling is done, treatment shall be done by
rodding the earth at 150mm centers close to wall surface and spraying the chemical with the
above dose i.e. 7.5 litres/sqm. In case of framed structure, the treatment shall start at adepth of
47
500mm below ground level. From this depth the backfill around the columns, beams and
R.C.C. basement walls shall be treated at 7.5 litres / sqm. of the vertical and at 5 litres / sqm.
for the horizontal surface at the bottom in the trenches / pits.
The top surface of the filled earth within plinth walls shall be treated with chemicalemulsion
at the rate of 5 litres/sqm. of the surface area before sub-base to floor is laid. If filled earth has
been well rammed and the surface does not allow the emulsion to seep through, holes up to
50 to 75mm deep at 150 mm centers both ways shall be made with crow bars on the surface
to facilitate saturation of the soil with the emulsion.
Special care shall be taken to establish continuity of the vertical chemical barrier on the inner
wall surfaces from the finished ground level (or from level where the treatment had stopped)
up to the level of the filled earth surface. To achieve this a small channel 30 X 30 mm. shall
be made at all the junctions of wall / column with floor (before laying subgrade) and rod
holes made in the channel up to the finished ground level at 150mm apart and the iron rod
moved backward and forward to break the earth and chemical emulsion poured along the
channel at 7.5 litres (or at recommended quantity per sqm. of the vertical wall / column
surfaces so as to soak the soil right up to the bottom. The soil shall be tamped back into place
after this operation.
The soil beneath the expansion joins shall receive special attention when the treatment under
2.5.1 above is in progress. This treatment shall be supplemented by treating through the
expansion joint after sub-grade has been laid at the rate of 2 litres per metre length of
expansion joint.
Utmost care shall be taken to see that the chemical barrier is complete and continuous. Each part of
the area shall receive the prescribed dosage of chemical emulsion.
The treatment should not be carried out when it is raining or when the soil is wet with rain or sub-soil
water.
Once formed, the treated soil barrier shall not be disturbed. If by chance, treated soil barriers are
disturbed, immediate steps shall be taken to restore the continuity and completeness of the barrier
system.
48
Precautions for Health Hazards and Safety Measures
All the chemicals mentioned above are poisonous and hazardous to health. These chemicals
can have an adverse effect upon health when absorbed through the skin, inhaled asvapours or
spray mist or swallowed. Persons handling or using these chemicals should be warned of
these dangers and advised that absorption through the skin is the most likely source of
accidental poisoning. They should be cautioned to observe carefully all the safety precautions
particularly when handling these chemicals in the form of concentrates. These chemicals are
usually brought to the site in the form of emulsifable concentrates.
The containers should be clearly labeled and should be storedcarefully out of the reach of
children and pets animal. They should be kept securely locked. Particular care should be
taken to prevent skin contact with concentrates. Prolonged exposure to dilute emulsions
should also be avoided. Workers should wear clean clothing and should wash thoroughly
with soap and water especially before eating. In the event of severe contamination, clothing
should be removed at once and the skin washed with soap and water. If chemicals splash into
the eyes they shall be flushed with plenty of water and immediate medical attention should be
sought.
The concentrates are oil solutions and present a fire hazard owing to the use of petroleum
solvents. Flames should not be allowed during mixing. Care should be taken in the
application of chemicals / soil toxicants to see that they are not allowed to contaminate wells
or springs and other sources of drinking water.
Guarantee
The contractor has to furnish the guarantee for 10 (ten) years from the date of completion of
work, starting that in case of reappearance of termites within the building area due to
defective materials or workmanship or due to any other reasons, the contractor will arry out
the necessary post constructional treatment to keep the entire area free from termite, once
again, without any extra cost to the Department during the guarantee period.
Mode of measurement
The payment will be made on the basis of plinth area measurements at ground floor only for
all the stages of treatment in sqm. correct to two places of decimals. Rate includes the cost of
materials, labour and all tools, plants, sprayers required for complete operation.
49
HARD CORE / SOLING UNDER FLOORS / FOUNDATIONS
Scope of work
The work covered under this specification includes all type of soling work either by bricks or
by rubble stones laid under floors / foundations, hand packed, complete as per specification
mentioned below and applicable drawings.
The rubble stone shall be of best variety of black trap / granite / basalt or other approved-
variety of stone available locally. The stone shall be hard, durable free from defects and of
required size and shall be approved by the Engineer-in-charge.
Preparation of Surface
The bed on which rubble soling is to be laid shall be cleared of all loose materials, leveled,
watered ad compacted and got approved by the Engineer-in-charge before laying rubble
soling. Cable or pipe trenches if shown in the drawing and as required by the Engineer-in-
charge shall be got done before the soling is started.
Workmanship
Over the prepared surface, the stone shall be set as closely as possible and well packed and
firmly set. The stones shall be of full height and shall be laid so as to have their bases of the
largest area resting on the sub-grade. Soling shall be laid in one layer of 230mm or 150mm
depth or specified thickness of soling with a tolerance of 25mm. After packing the stones
properly in position, the interstices between them shall be carefully filled with quarry spoils
or stone chips of larger size possible to obtain a bard, compact surface. Spreading of loose
spoils or stone chips is prohibited. The entire surface shall be examined for any protrusions
and the same shall be knocked off by a hammer and all interstices shall be filled with
approved murrum. Excess murrum if any over the surfaces shall be removed. Unless other
wise specified, the murrum shall be supplied by the contractor at his own cost from the
selected area. The surfaces shall then be watered and consolidated with mechanical or
sufficiently heavy wooden tampers and log-rammers as approved by the Engineer. After
compaction, the Engineer-in-charge to give the required slope or level and dense sub-base
and the surface shall present clean look. Adequate care shall be taken by the contractor while
laying and compacting the rubble soling to see that concrete surfaces in contact with soling
are not damaged.
50
Mode of Measurement
The quoted rate shall be per square metre of the soling of specified thickness. The linear
dimension shall be measured up to two places of decimals of a metre and are worked out
correct to the two places of decimals of a square metre. Plan areas of soling work actually
done limiting to the dimensions as per drawings shall be measured for payment. The rate
shall include all the materialslabour, transport etc. and no extra payment shall be made for
work done at different levels. The rate shall also include the cost of preparation of surface, all
materials and labour, watering, consolidation etc. all complete.
51