0% found this document useful (0 votes)
35 views1 page

Act1 Aon2

The document outlines a project management task involving a precedence diagram. It identifies the critical path as A-B-D-I-H and calculates the expected project duration to be 31 days. The diagram visually represents task dependencies and durations.

Uploaded by

osinsao.maryjoy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views1 page

Act1 Aon2

The document outlines a project management task involving a precedence diagram. It identifies the critical path as A-B-D-I-H and calculates the expected project duration to be 31 days. The diagram visually represents task dependencies and durations.

Uploaded by

osinsao.maryjoy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

2 A. Draw the precedence diagram.

B. Find the critical path. A-B-D-I-H


C. Determine the expected duration of the project. 31 days

PRECEDENCE DIAGRAM

B 16 D
16

A 4 21 I 22 H
4 21 22

E 3 F 12 J 15 K
2 13 16