0% found this document useful (0 votes)
1K views3 pages

01 SPPCC

The document outlines the probable project construction costs for a proposed 2-unit, 2-storey commercial/residential building in Binangonan, Rizal, detailing both direct and indirect costs. Direct costs include site development, civil, structural, electrical, plumbing, and architectural works, while indirect costs cover architect and professional fees. The total estimated construction cost is PHP 6,005,000, with a note that final costs may vary by ±5-10%.

Uploaded by

JunJun SaS
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views3 pages

01 SPPCC

The document outlines the probable project construction costs for a proposed 2-unit, 2-storey commercial/residential building in Binangonan, Rizal, detailing both direct and indirect costs. Direct costs include site development, civil, structural, electrical, plumbing, and architectural works, while indirect costs cover architect and professional fees. The total estimated construction cost is PHP 6,005,000, with a note that final costs may vary by ±5-10%.

Uploaded by

JunJun SaS
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

STATEMENT OF PROBABLE PROJECT CONSTRUCTION COST

A. PROBABLE DIRECT PROJECT CONSTRUCTION COST


Scope of Works
 Site Development of the Building Grounds  Electrical Works
 Civil & Structural Works  Plumbing & Sanitary Works
 Architectural Works  Architectural Interior (AI) Works

Note:
*Price per sqm : The Statement of Probable Construction Cost (SPCC) is for budget purposes only and solely based on current
market cost of labor & materials at the time of writing. Project Construction Cost (PCC) will be defined once Building plans and
specifications are finalized.
PHP 25,000 PHP 35,000 PHP 40,000 PHP 50,000
FLOOR Smooth Concrete Finish Tiles Finish Tiles to Natural Stones Natural Stones

WALL Bare Concrete Finish Painted Finish w/ PVC Imported wall tiles or cladding Cladding to Natural Stones
cladding accents

WINDOWS Minimal to Standard Size Standard Size Windows Full Size Windows Full Size to Double Glaze

CEILING None / Exposed soffit Gypsum / Fibecement board uPVC Ceiling Wood Panels

B. PROBABLE INDIRECT PROJECT CONSTRUCTION COST

**Architect’s Fee + Allied Professionals Fee:


RESIDENTIAL
(Bungalow,Single Detached, Duplexes, Townhomes etc.)

STARTER BASIC ESSENTIAL PREMIUM ELITE ELITE PRO

PHP 220 PHP 700 PHP 1,800 PHP 2,400 PHP 2,600 PHP 3,000
PER SQM OF ESTIMATED PER SQM OF ESTIMATED PER SQM OF ESTIMATED PER SQM OF ESTIMATED PER SQM OF ESTIMATED PER SQM OF ESTIMATED
TGFA TGFA TGFA TGFA TGFA TGFA

Basic Plan Architectural Design Arch'l & Basic Eng'g A & E + Mechanical + Premium Package + Elite Package +
Design Fire Pro Design Electronics Plan Architectural Interiors

INCLUSIONS: INCLUSIONS: INCLUSIONS: INCLUSIONS: INCLUSIONS: INCLUSIONS:


- Initial Schematic Design - Initial Schematic Design - Initial Schematic Design - Initial Schematic Design - Initial Schematic Design - Initial Schematic Design
- Final Schematic Design - Final Schematic Design - Final Schematic Design - Final Schematic Design - Final Schematic Design
- Architectural Blueprints - Architectural Blueprints - Architectural Blueprints - Architectural Blueprints - Architectural Blueprints
- Estimates - Architectural - Structural Eng'g Blueprints - Structural Eng'g Blueprints - Structural Eng'g Blueprints - Structural Eng'g Blueprints
- Elec'l Eng'g Bluepriint - Elec'l Eng'g Bluepriint - Elec'l Eng'g Bluepriint - Elec'l Eng'g Bluepriint
- Sanitary/ Plumbing Blueprints - Sanitary/ Plumbing Blueprints - Sanitary/ Plumbing Blueprints - Sanitary/ Plumbing Blueprints
- Estimates - Architectural - Mechanical Blueprints - Mechanical Blueprints - Mechanical Blueprints
- Estimates - Structural - Fire Pro Blueprints - Fire Pro Blueprints - Fire Pro Blueprints
- Estimates - Electrical - Estimates - Architectural - Electronics Blueprints - Electronics Blueprints
- Estimates - Plumbing - Estimates - Structural - Estimates - Architectural - Arch'l Interiors Details
- Estimates - Electrical - Estimates - Structural - Estimates - Architectural
- Estimates - Plumbing - Estimates - Electrical - Estimates - Structural
- Estimates - Mechanical - Estimates - Plumbing - Estimates - Electrical
- Estimates - Fire Pro - Estimates - Mechanical - Estimates - Plumbing
- Estimates - Fire Pro - Estimates - Mechanical
- Estimates - Electronics - Estimates - Fire Pro
- Estimates - Electronics

***Permit Fees: Varies per municipality and scope of the project.

****Other Services: Site Survey services, Soil Exploration, Structural Analysis, Seismic Analysis, Electrical Design Analysis.

Statement of Probable Project Construction Cost


INITIAL STATEMENT OF PROBABLE PROJECT CONSTRUCTION COST

DATE : April 21, 2023


CLIENT : _______
PROJECT : Proposed 2 unit 2-storey Commercial/Residential Building with Roof Deck
LOCATION : San Carlos Subd., Brgy. Tayuman, Binangonan, Rizal
AREA / LM PRICE PER SQM

Ground Floor 60 sqm x PHP 35,000 /sqm = PHP 2,100,000


2nd Floor 90 sqm x PHP 35,000 /sqm = PHP 3,150,000
Roof Deck 0 sqm x PHP 25,000 /sqm = PHP 0
Carport 30 sqm x PHP 10,000 /sqm = PHP 300,000
Perimeter Fence 0 Lm x PHP 8,000 /Lm = PHP 0
Soil Backfill & Compacting =
Total Gross Floor Area 180 sqm Direct Cost PHP 5,550,000

B. Probable Indirect Project Construction Costs


Contractor's Profit PHP 0.00
**Architect's Fee + Allied Professional Fees 1900 PHP 555,000.00
Less Discount from Professional Fees PHP 100,000.00
***Permit Fees Varies
****Other Services Varies
Indirect Cost PHP 455,000
Statement of Probable Project Construction Cost PHP 6,005,000

Note:
Estimates: Estimated value subject to change, allow at least ±5-10% discrepancy from Probable Project Construction Cost to Final
Construction Cost.
Floor Area: Floor Area are based on Allowable Maximum Building Footprint for the lot considering the site restrictions and as prescribed from
the National Building Code.
* Renovation Cost: Rought estimate of cost per square meter depending on the complexity and quality of materials used
** Architect’s Fee + Allied Professional Fees: based on the UAP Doc. 208-A: Architect’s Guidelines on Standards of Professional
Practice, Method of Compensation and Schedule of Fees
***Permit Fees: based on Local Government Unit computation on permit fees (includes, Building permit, Zoning clearance, Fire Safety
Clearance etc.)
****Other Services: may include other technical requirements needed for the project (Surveying services, Soil Boring Test, etc.)

If you have any questions, comments, wish to discuss the conditions stated in this proposal, or if you would
like us to send a detailed quotation of your preferred services, please let us know and we will be glad to discuss the
matter with you.

Prepared by:

AR. JOHN MARI B. SAUSA


Registered & Licensed Architect | Registered Master Plumber
PRC No.: 0038512 PRC No.: 0007901

STATEMENT OF PROBABLE PROJECT CONSTRUCTION COST


Statement of Probable Project Construction Cost
A. Probable Direct Project Construction Costs
1. Site Development of the Building Grounds (to be planned/ designed only by
a Registered and Licensed Architect/ RLA as provided by law) PhP 0,000,000.00
2. Civil Works (to be planned/ designed by a Civil Engineer)
3. Architectural Works (Building and Exterior) - (to be planned/ designed only by a Registered and
Licensed Architect/ RLA as provided by law)
4. Structural Works (to be planned/ designed by a Civil or Structural Engineer)
5. Electrical Works (to be planned/ designed by a Professional Electrical Engineer/ PEE)
6. Mechanical Works (to be planned/ designed by a Professional Electrical Engineer/ PEE)
7. Plumbing and Sanitary Works (to be planned/ designed by a Plumbing Engineer and/or a Sanitary
Engineer as provided under law)
8. Electronics Works (to be planned/ designed by an Electronics Engineer)
9. Architectural Interior (AI) Works (to be planned/ designed only by a Registered and Licensed
Architect/ RLA as provided by law)
10. Others ___
Subtotal A* PhP 0,000,000.00
*Note: Subtotal A excludes Interior Design, Movable and Furniture Works, which are not attached to the
building (to be planned/ designed only by a Interior Designer as provided by law)

B. Probable Indirect Project Construction Costs


1. Contractor’s Profit PhP 0,000,000.00
2. Permits (all classes)
3. Others_________________________________________________________________________
Subtotal B PhP 0,000,000.00

C. Probable Project Construction Cost (Sum of A and B) PhP 0,000,000.00

Statement of Probable Project Construction Cost