Time & Work, Pipes & Cistern
Time & Work, Pipes & Cistern
1
x = 15
60
So A & B can do the work in 15 & 45 days respectively. B’s per day work = = 4 units/dayy
Let the total work is 45 units [LCM of (15, 45)] 15
(A + B)’s per day work = 5 + 4 = 9 units/day.
45
A will do = = 3 units/day Let the number of day A alone worked be x days.
15 According to the question,
45 9 × 5 + 5 × x = 60
B will do = = 1 unit/day
45 5x = 15
x = 3 days.
45
A & B together can finish the work in i.e. 11.25
4 11. (a)
days. Let total work = 24 units (LCM if 8 & 12)
24
8. (a) Per day work of A & B 3
Let total work is 18 units [LCM of (3, 6, 18)] 8
18 24
M, W & B will do = = 6 units/day Per day work of B 2
3 12
So, Per day work of A = 3 – 2 = 1
18 In the first four days B will do 4 × 2 i.e. 8 units
M will do = = 3 units/day
6 Remaining units = 24 – 8 = 16
18 16
B will do = = 1 unit/day Now A will finish the remaining 16 units in i.e.
18 1
W = 6 – (3 + 1) = 2 16 days
18 12. (d)
Women can finish the work alone in i.e. 9 days.
2 Let the total unit of work be 30 units (LCM of 15
& 10)
9. (d)
Ratio of time taken by A, B & C = 2 : 1 : 3 30
A’s per day work = = 2 units/dayy
Let the time taken by 2x, x & 3x 15
Let Total work = 6x (LCM of 2x, x & 3x)
30
6x B’s per day work = = 3 units/dayy
Work done by A per day 3 units 10
2x Money is distributed in the ratio of per day work
6x A:B=2:3
Work done by B per day 6 units
x 2
Share of A = 30000 12000
5
Work done by C per day 6x 2 units
3x
Now together they can complete the work in 12 days 13. (b)
Let the total work is 24 units [LCM of (8, 12, 4)]
6x
So 12 24
36 2 A will do = = 3 units/day
x = 22 8
Time taken by A alone = 2x 24
= 2 × 22 B will do = = 2 units/day
12
= 44 days
24
A, B and C will do = = 6 units/day
10.(a) 4
Let the total unit of work be 60 units (LCM of 12 & 15)
C = 6 – (3 + 2) = 1
60 So, Ratio of efficiency = 3 : 2 : 1
A’s per day work = = 5 units/dayy
12 1
C’s share of money = 4500 = 750
50
6
2
120
14.(a) A will fill = = 4 units/min.
30
A B C
120
Number of Days 6 4 9 B will fill = = 3 units/min.
Daily Wages 5 6 4 40
6 5 4 6 9 4 C = 12 – (4 + 3) = 5 units/min
Final Ratio
(30) (24) (36) 120
So, Tap C alone can fill the tank in = 24 minutess
5
So the total money of Rs. 1800 will be divided among
A, B & C in the ratio of 5 : 4 : 6 [30 : 24 : 36] 20.(d)
Let total capacity = x gallons
5
Amount received by A = 1800 = 600 15
15 A will fill x
20
15.(c) 15
B will fill x
Men Toys Days Hrs/day 24
10 16 6 3 C will remove = 15 × 6 = 90
12 40 x 8
15 15
x x 90 x
20 24
3 40 10
x 6 x = 240 gallons
8 16 12
75 11 21.(c)
4 Let Capacity of the tank is N litres
16 16
After 30 minutes the tank contains N litres
16.(a) N
After 25 minutes the tank contains litres
6M = 10W 2
Now,
N
12M & 10W After 20 minutes the tank contains litres
= 12M + 10W 4
= 2 × 10W + 10W 1
th
18.(b) TYPE - 1:
Let 15 Men leave the work after A days. 1.1(c)
So, 25 20 = (25 × A) + (10 × 40) Let the total work is 360 [LCM of (72, 120, 90)]
x=4
360
A and B will do = = 5 units/day
19.(b) 72
Let total capacity be is 120 units [LCM of (10, 30, 40)]
360
120 B and C will do = = 3 units/day
A, B and C will fill = = 12 units/min. 120
10
360
C and A will do = 4 units/day
90
3
2(A + B + C) = 12 units/day the total work.
A + B + C = 6 units/day 2
Also A = (A + B + C) – (B + C) = 6 – 3 = 3 Remaining work is done by P is 20 days
3
360 So, P alone will finish the whole work in
So, A alone would complete the work in = 120 days
3 3
20 i.e. 30 days
2
1.2(a)
Let the total work is 24 [LCM of (8, 12, 16)] 2.3(a)
24 Let total work = 180 units (LCM of 60 & 90)
A and B will do = = 3 units/day
8 180
Per day work of A 3 units
24 60
B and C will do = = 2 units/day
12 180
Per day work of B 2 units
90
24
A, B and C will do = = 4 units/day Let the work lasts for x days.
6 Now, A has worked for x days
A + 2B + C = 5 and B has worked for (x – 15) days
and A + B + C = 4 So, 3x + 2(x – 15) = 180
So, B = 1 and A + C = 3 5x = 210
x = 42
24
So, A & C together can complete the work in i.e. 8
3
days TYPE - 3:
3.1(d)
TYPE - 2: Let total work is 36 [LCM (12, 18)]
2.1(b)
36
2 A will do i.e. 3 units/day
In the first two days they must have done of the 12
3
work 36
B will do i.e. 2 units/day
18
2 1
Remaining work 1
3 3 A B A B A B
3 2 3 2 3 2
1
Now A can finish work in 2 days
3 5 units of work is completed in 2 days.
So, A will do the whole work alone in 3 × 2 i.e. 6 days
35
A&B 3 So, 35 units of work will be completed in 2 × = 14
5
A 6
Let total work = 6 units days.
1
Units done by A & B per day 6 2 The remaining 1 unit of work will be done by A in rd
3 3
of the day
Units done by A per day 6 1 1
6 So total days = 14
3
Units done by B per day = 2 – 1 = 1
Time taken by B to finish the whole work alone
3.2(c)
6 Let total work = 72 units (LCM of (18, 27 & 36))
6 days
1
72
Per day work of A 4 units
2.2(a) 18
10 1 72
In the first 10 days, they must have done i.e. of Per day work of B 3 units
30 3 24
4
TYPE - 5:
72
Per day work of C 2 units 5.1(d)
36
8 48
C B A C B A 10 men can do the work in 12 × = days.
2 3 4 2 3 4 --------
10 5
9 units 9 units 4 women can do the work in 48 days.
10 children can do the work in 24 days.
9 units has been done in 3 days Let the total work = 48 units
So, 72 units will be done in 3 8 = 24 days
48
10 men’s 1 day work = = 5 unitss
TYPE - 4: 48
4.1(b) 5
Ratio of days = 12 : 16 : 24 or 3 : 4 : 6
48
1 1 1 4 women’s 1 day work = = 1 unit
Ratio of efficiency/wages : : 48
3 4 6
Ratio of wages = 4 : 3 : 2 48
10 children 1 day work = = 2 units
24
3
Share of B 2700 900 48
9 Together they can finish the work in =6
5+1+2
4.2(a) days.
Let the wages be M, W & B
3M = 4W 5.2(d)
M 4 10W 8 days
W 3 8 × 10 40
6W = days
& 2W = 3B 6 3
W 3 10C 12
B 2 12 × 10
3C = 40 days
So M : W :B = 4 : 3 : 2 3
Now 3M + 2W + 4B = 26
3 × 4x + 2 × 3x + 4 × 2x = 26 40
Let total work = 40 units LCM , 40
26x = 26 3
x=1
So, wages of 4 men, 3 women and 2 boys = 4 × 4x + 3 × 40
1 day work of 6W = = 3 units
3x + 2 × 2x = 29 x = 29 × 1 = 29 40
3
4.3(b)
Let each man get Rs. m per day 40
1 day work of 3C = = 1 unit
Let each women get Rs. w per day 40
So,
40
(4 × 5)m + (6 × 5)w = 1600 ..... (1) Together they can finish the work in i.e. 10 days.
4
(3 × 6)m + (7 × 6)w = 1740 ..... (2)
5.3(c)
20m + 30w = 1600 ..... (3) 1M = 2W = 3B
18m + 42w = 1740 ..... (4) So, 1M + 1W + 1B =
Solving (3) and (4)
m = 50, w = 20 1 1
1M M M
Let the no. of day be ‘d’ 2 3
So, (7 × 50)d + (6 × 20)d = 3760 6 3 2 11
350d + 120d = 3760 M
6 6
470d = 3760 1M can complete a job in 88 days
3760 11 6
d 8 So M will do the same job in 88 48 days
470 6 11
5
TYPE - 6: 7.2(c)
6.1(d) Let capacity = 40 units
40
Men Hr/Day Days Inlet pipe work/min = =5
8
9 7 15
6 9 x 40
Outlet pipe work/min = =8
5
7 9 Half fill means 20 units is there
x = 15 × × = 17.5 days Net work/min = 8 – 5 = 3
9 6
20 2
6.2(a) Required time = = 6 or 6 hrs 40 minutes.
3 3
Men Hr./day Volume Days
16 18 3456 (36 × 4 × 24) 20 7.3(d)
x 12 6912 (64 × 6 × 18) 16 Let tank Capacity = 60 units
60
18 6912 20 A’s work done/min = =4
x 16 15
12 3456 16
= 60 60
B’s work done/min = =3
20
6.3(b) Work done in 4 mins = 7 4 = 28 unitss
Remaining = 60 – 28 = 32 units
Men Work Days
20
1
20 32 2
3 B will do remaining work in = 10 mins i.e. 10
2 3 3
X 3 25
min 40 seconds
Total time = 14 min 40 sec.
2
3 20 7.4(b)
x = 20 × × = 32 Let Capacity = 12 units
1 25
3 12
Per hour Capacity of A 4
Extra person required = 32 – 20 = 12 3
6.4(d) 12
Per hour Capacity of B 3
Let the number of days for which they are able to 4
carry = D 12
So, 1000 × 30 Per hour Capacity of C 12
= 1000 × 10 + 2000 × D 1
D = 10 days. Till 5 PM
Tank filled = 4 × 2 + 3 × 1
TYPE - 7: = 11
7.1(d) Work done from 5 to 6 = 4 + 3 – 12 = –5
Let Capacity = 60 units Work done form 6 to 7 = –5
60 1
First Inlet pipe units/min = =3 Remaining 1 unit will be emptied in hrs.
20 5
60 So exact time is 7:12 PM
Second Inlet pipe units/min = =1
60
Units done in 1 min = 3 + 1 = 4
In First 10 minutes, units completed = 4 10 = 40
Remaining units = 60 – 40 = 20
20
Second pipe will fill remaining in = = 20 mins
1