Project Integration Management
3
CTEC210
Fundamentals of
Project Management
Agenda
Review Project Management Concepts
Team Development
Conflict Management
The Role of Project Manager
Organizational Types
Project Integration Management
2
Project Integration Management
Bringing it all together
Processes to ensure that various project elements are
properly coordinated
PM determines level of implementation for each process
PM processes are identified as discrete
but processes overlap and interact with each other
Integration must occur in other areas as well
Projects with ongoing operations
Product scope and project scope
PM software may span all process groups
3
Project Integration Processes
4.2 Develop Project
4.1 Develop Project Charter Management Plan
INITIATING PLANNING 4.3 Direct and Manage
PROCESSES PROCESSES Project Work
4.4 Manage Project
Knowledge
MONITORING
EXECUTING
& CONTROLLING
PROCESSES
PROCESSES
4.5 Monitor and Control Project Work
4.6 Perform Integrated Change
CLOSING 4.7 Close Project
Control
PROCESSES or Phase
4
Project Charter
After deciding what project to work on, it is important to formalize
projects
A project charter is a document that formally recognizes the
existence of a project and provides direction on the project’s
objectives and management
Establishes authorization for the project by someone external to the
project such as a sponsor, PMO, or portfolio steering committee – at
a level appropriate to fund the project
Key project stakeholders should sign a project charter to
acknowledge agreement on the need and intent of the project
Establishes a partnership between the performing organization and
the requesting organization
May delegate the creation of the project charter to the PM
Links the project to the strategy and ongoing work of the
organization.
5
4.1 Develop Project Charter
Inputs Tools and Outputs
Techniques
• Business • Expert judgment • Project charter
documents • Data gathering • Assumption log
• Agreements • Interpersonal
• Enterprise and team skills
environmental • Meetings
factors
• Organizational
process assets
Adapted from Figure 4-2, A Guide to the Project Management Body of Knowledge (PMBOK®
Guide) - Sixth Edition, Project Management Institute, Inc., 2017. Copyright and all rights reserved.
Material from this publication has been reproduced with the permission of PMI. 6
Develop Project Charter: Inputs
Business case Enterprise environmental
documents factors
Business case – review the Government or industry
cost-benefit analysis and standards, legal and
consider the market regulatory requirements,
demand, organizational marketplace conditions,
need, customer request, organizational culture and
etc. political climate, etc.
Benefits management plan Organizational process
Agreements assets
For example, Organizational standard
memorandums of policies, process, and
understanding (MOU), procedures; governance
service level agreement framework; monitoring and
(SLA), etc. reporting methods; and
templates
7
Develop Project Charter:
Tools and Techniques
Expert judgment Interpersonal and
Include individuals or team skills
groups with specialized Conflict management
knowledge or training Facilitation
Data gathering Meeting management
Brainstorming Meetings
Focus groups Work with stakeholders
Interviews to identify the project
objectives, success
criteria, etc.
8
Develop Project Charter: Outputs
Project charter
Document that formally authorizes a project or
phase
What is the organizational strategic objective the
project is meant to achieve?
Assumption log
High-level strategic and operational assumptions
and constraints
9
Project Charter Questions
What is the organizational strategic
objective the project is meant to achieve?
What are the objectives for the project?
What is the purpose or justification?
What are the high-level requirements?
What are the high-level project description and
boundaries?
Who is involved in the project?
What are the assumptions and constraints?
10
Project Charter Questions
(continued)
What are the objectives for the project?
What are the measureable project objectives and
related success criteria
What are the project approval requirements (i.e.
what constitutes project success, who decides the
project is successful, and who signs off on the
project)?
What are the key milestones?
What is the summary budget?
What are the high-level risks?
11
Project Charter Questions
(continued)
What are the assumptions and constraints?
Organizational: formal and informal policies, procedures,
guidelines, plans, standards, knowledge base from
previous projects
Environmental: company culture, structure company
infrastructure, equipment, facilities, current human
resources and their skills and competencies, project
management information systems, software, web
interfaces, etc.
External: consultants, industry groups, professional
associations, departments within performing organization,
etc., market place conditions, stakeholder risk tolerances,
governmental or industry standards.
12
Project Charter Questions
(continued)
Who is involved in the project?
Who are the key stakeholders for the project?
Who is the assigned project manager,
responsibility, and authority level
Who are the project sponsor and other persons
involved in authorizing the project charter?
13
4.2 Develop Project Management
Plan
Defines, prepares and coordinates all plan
components and consolidates them into an
integrated project management plan
Defines how the project is executed,
monitored and controlled, and closed
Either a summary level or detailed depending
on the size and complexity of the project
The project management plan is not just the
Microsoft Project file or a project schedule!
14
4.2 Develop Project Management
Plan
Inputs Tools and Outputs
• Project charter
Techniques • Project
• Expert judgment
• Outputs from management
• Data gathering
planning plan
• Interpersonal and
processes
team skills
• Enterprise
• Meetings
environmental
factors
• Organizational
process assets
Adapted from Figure 4-4, A Guide to the Project Management Body of Knowledge (PMBOK®
Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Copyright and all rights reserved. 15
Material from this publication has been reproduced with the permission of PMI.
Develop Project Management Plan:
Inputs
Project charter
Documents the business needs, current understanding of the customer’s needs, and
the new product, service or result that it is intended to satisfy
Outputs from planning across all knowledge areas
Information from the subsidiary plans is used to fully development this plan
Enterprise environmental factors
Governmental or industry standards
Project management information systems
Organization structure and culture
Infrastructure
Personnel administration
Organizational process assets
Standardized guidelines, work instructions, proposal evaluation criteria, and
performance measurement criteria
Project management plan template
Change control procedures
Project files from past projects
16
Develop Project Management Plan:
Tools and Techniques
Expert judgment
Tailor the process to meet the needs of the project
Develop technical and management details to be included in the project
management plan
Determine resources and skill levels needed to perform project work
Define the level of configuration management to apply on the project
Determine which project documents will be subject to the formal change
control process
Data gathering
Brainstorming, checklists, focus groups and interviews
Interpersonal and team skills
Conflict management, facilitation and meeting management
Meetings
Schedule a kick-off meeting, either at the beginning of the project, or
between the end of project planning and the start of project execution
17
Develop Project Management Plan:
Outputs
Project management plan
Integrates and consolidates all of the subsidiary management plans and
baselines from the planning processes and includes but is not limited to:
The life cycle selected for the project and the processes that will be
applied to each phase
Results of the tailoring by the project management team
How work will be executed to accomplish the project objectives
A change management plan that documents how changes will be
monitored and controlled
A configuration management plan that documents how configuration
management will be performed
How integrity of the performance measurement baselines will be
maintained
Need and techniques for the communication among stakeholders
Key management reviews for content, extent, and timing to facilitate
addressing open issues and pending decisions
18
Develop Project Management Plan:
Outputs
Project management plan Subsidiary management
Project baselines plans
Scope Scope
Schedule Requirements
Cost
Schedule
Additional components
Cost
Change management plan
Configuration management Quality
plan Resource
Performance measurement Communications
baseline
Risk
Project life cycle
Development approach Procurement
Management reviews Stakeholder
Subsidiary Management
Plans
19
Project Management Plan and
Project Documents
20
4.3 Direct and Manage Project Work
Leading and performing the work defined in the
project management plan
Implementing approved changes to achieve the
project’s objectives
21
4.3 Direct and Manage Project Work
Inputs Tools and Outputs
Techniques
• Project management • Expert judgment • Deliverables
plan • Project management • Work performance data
• Project documents information system • Issue log
• Approved change • Meetings • Change requests
requests • Project management
• Enterprise plan updates
environmental factors • Project documents
• Organizational updates
process assets • Organizational process
assets updates
Adapted from Figure 4-6 A Guide to the Project Management Body of Knowledge (PMBOK® 22
Guide) - Sixth Edition, Project Management Institute, Inc., 2017. Copyright and all rights reserved.
Material from this publication has been reproduced with the permission of PMI.
Direct and Manage Project Work:
Outputs
Deliverables Project management
Completed and approved plan updates
Work performance data Update as needed as per
Raw observations and the change control
measurements identified process
during activities
Project document
Issue log updates
Type, description,
priority, status, etc. Activity list, assumption
log, lessons learned
Change requests register, etc.
Corrective, preventive,
defect repair and Organizational process
updates assets updates
23
4.4 Manage Project Knowledge
Uses existing knowledge and create new
knowledge to achieve the project’s objectives
Contributes to organizational learning
Helps produce or improve project outcomes
Supports organizational operations and fuure
projects or phases
24
4.4 Manage Project Knowledge
Inputs Tools and Outputs
Techniques
• Project management • Expert judgment • Lessons learned
plan • Knowledge register
• Project documents management • Project management
• Deliverables • Information plan updates
• Enterprise management • Organizational process
environmental factors • Interpersonal and assets updates
• Organizational team skills
process assets
Adapted from Figure 4-8, A Guide to the Project Management Body of Knowledge (PMBOK® 25
Guide) - Sixth Edition, Project Management Institute, Inc., 2017. Copyright and all rights reserved.
Material from this publication has been reproduced with the permission of PMI.
Manage Project Knowledge: Outputs
Lessons learned register
Includes impacts, recommendations and actions
Records challenges, problems, realized risks and
opportunities, or other content as appropriate
Project management plan updates
Update as needed as per the change control
process
Organizational process assets update
Codify or embed new knowledge as needed
26
4.5 Monitor and Control Project
Work
With the proper project plan in place, the project
manager is equipped with the necessary baselines
against which to measure performance and
Determine any necessary corrective or preventive action
Analyze, track and report on the status of project risks and
the implementation of their respective response plans
Identify any emerging trends affecting performance
Report on progress and forecast project completion data
Monitor implementation of approved changes
27
4.4 Monitor and Control Project
Work
Inputs Tools and Outputs
Techniques
• Project management • Expert judgment • Work performance
plan • Data analysis reports
• Project documents • Decision making • Change requests
• Work performance • Meetings • Project management
information plan updates
• Agreements • Project documents
• Enterprise updates
environmental factors
• Organizational
process assets
Adapted from Figure 4-10, A Guide to the Project Management Body of Knowledge (PMBOK® 28
Guide) - Sixth Edition, Project Management Institute, Inc., 2017. Copyright and all rights reserved.
Material from this publication has been reproduced with the permission of PMI.
Monitor and Control Project Work:
Outputs
Work performance Project management
reports plan updates
Combined, recorded Any component
and distributed
Project documents
Change requests
Expand, adjust or
updates
reduce the project or Costs forecasts, issue
product scope, quality log, lessons learned
requirements, and register, risk register
schedule or cost and schedule forecasts
baselines
29
4.6 Perform Integrated Change
Control
Performed throughout the project
Capture changes that occur, analyze, reject or accept them and then
integrate the approved changes into the project plan and its baselines
Changes must be managed
Identify changes that need to occur
Influence factors which create change to ensure only approved changes
are implemented
Maintain integrity of baseline by releasing only approved changes and
maintaining their documentation
Review, approve or deny all recommended corrective and preventive
actions
Coordinate change across the project and updating project
documentation (schedule changes, cost, risk, quality, staffing)
Document the impact of change requests
Align quality of work performance to required quality standards
30
Perform Integrated Change Control
(continued)
Changes may be requested by any stakeholder on the project
All changes should be recorded in the change management
and/or configuration management systems
Effective way to centrally manage changes and baselines
Configuration control is focused on specification of deliverables and
processes
Change control is focused on identifying, documenting and controlling
changes to the project and baselines
Applying the configuration management system with integrated
change control processes provides:
A method to identify and request changes to project baselines
Opportunity to continuously validate and improve the impact of each
change on the project
Consistent communication of both approved and rejected changes
31
4.6 Perform Integrated Change
Control
Inputs Tools and Outputs
Techniques
• Project management • Expert judgment • Approved change
plan • Change control tools requests
• Project documents • Data analysis • Project management
• Work performance • Decision making plan updates
reports • Meetings • Project documents
• Change requests updates
• Enterprise
environmental factors
• Organizational
process assets
Adapted from Figure 4-12, A Guide to the Project Management Body of Knowledge (PMBOK® 32
Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Copyright and all rights reserved.
Material from this publication has been reproduced with the permission of PMI.
Perform Integrated Change Control:
Inputs
Project management plan Change requests
Change management plan, Corrective and preventive
configuration management plan, actions affect performance
scope baseline, schedule against the baselines, not
baseline and cost baseline the actual baselines
Project documents Enterprise environmental
Basis of estimates, requirements factors
traceability matrix and risk report
Work performance reports Organizational process
Resource availability, schedule
assets
and cost data, earned value Change control procedures,
management (EVM) reports, and authorizations for approving
burnup or burndown charts and issuing changes,
databases, project files,
configuration management
knowledge base
33
Perform Integrated Change Control:
Outputs
If a change request can be performed but is outside
of the project scope, a baseline change is required
if approved
Approved change requests
Changes, regardless of whether it is approved or rejected,
are updated in the change log
Project management plan updates
Any component
Project documents updates
Change log
34
Change Opportunity and
Change Costs
Relative impact
Costs of
Opportunity
Implementing
for Making
Changes
Changes
Progress of the project
35
Change Avoidance
1 Proactive Approach
Complete user requirements
Detailed document
Scope Statement approval
Departmental signoff
Focus groups
Visible and cross-departmental
Client communications
Presentations, newsletters
Other means of ensuring stakeholders are aware
36
Change Avoidance
2 Freeze Approach
Force the client and users to deal with issue
A freeze date is established at the outset
Date cannot be postponed
Freeze project before the end of design
Ensure executive support
No exceptions
37
Change Avoidance
3 Postponement Approach
Linked to freeze approach
Collection of all requests, without action
Sub-project to implement some, not all
Main project schedule is unaffected
Resolve conflicting changes
Economies of scale are possible
Decide once the total cost is known
38
Change Avoidance
4 Procedural Approach
Escalation of approval
Changes are reviewed at executive level
Ensure changes meet project objectives
Do all user groups agree with the change?
Enable access to project reserve funds
Increase total budget
39
Project Change Request - Internal
PM must implement a formal change process
Requests for change come from Owner or Client
Users may also request changes
Statement of change - what is really required?
Reason for change vs. original purpose
Estimate of change impact
Effect on activities already completed
Potential rework requirements
Effect on future activities - possible to identify
Effect on schedule - what will be delayed?
Effect on costs - what are the added expenditures?
40
Change Request Process - External
PM must assess the impact on work in progress
Especially that under contract to consultants, suppliers
A consultant/supplier can only suggest changes
Owner is not obligated to consider/approve any suggestions
Change Notice
Requests a contractor/supplier to quote the cost/time impact of
a proposed change in the work
Change Order
instructs the contractor/supplier to implement a specific
change immediately
41
4.7 Close Project or Phase
Once confirmed, the project or phase can be
closed, all information will be reviewed by the
project manager to ensure all work has been
completed and the project objectives met
If a project is terminated before completion, the
procedures to determine the reasons will be
established at this time
Administrative closure will also be performed to
complete the project or phase
42
4.6 Close Project or Phase
Inputs Tools and Outputs
• Project charter
Techniques • Project documents
• Expert judgment
• Project updates
• Data analysis
management plan • Final product,
• Meetings
• Project documents service, or result
• Accepted transition
deliverables • Final report
• Business • Organizational
documents process assets
• Agreements updates
• Procurement
documentation
• Organizational
process assets
Adapted from Figure 4-14, A Guide to the Project Management Body of Knowledge (PMBOK® 43
Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Copyright and all rights reserved.
Material from this publication has been reproduced with the permission of PMI.
Close Project or Phase: Inputs
Project charter Project documents
Project management plan Assumption log
Basis of estimates
All components
Change log
Accepted deliverables Issue log
Business documents Lessons learned register
Business case Milestone list
Benefits management plan Project communications
Agreements Quality control
measurements
Procurement Quality reports
documentation Requirements
Organizational process documentation
assets Risk register
Risk report
44
Close Project or Phase
Tools and Techniques Outputs
Expert judgment Project documents
updates
Data analysis
Lessons learned register
Document analysis
Final product, service,
Regression analysis
or result transition
Trend analysis
Final report
Variance analysis
Organizational process
Meetings assets updates
45
Close Project or Phase:
Closure Procedures
Activities, roles and responsibilities of all team
members and other stakeholders involved in
closing the project or phase
Activities include:
Collection of project records
Analysis of project success and effectiveness
Documentation of lessons learned
Archiving project information for future use
Develop procedures to transfer project products/services to
production and/or operations
Procedures to confirm that project has met all client
requirements
Verification that all deliverables have been delivered and
accepted
Validation that all exit criteria have been met
46
Close Project or Phase:
Transition and Updates
Transition of final product, services or result to the
customer
Receipt of a formal statement confirming that the
terms of the contract have been met and that the
customer has officially accepted the deliverables
Project files completed with project documentation
such as: plans, baselines, risk registers, planned
risk response plans and risk impact
Lessons learned documented and archived
47
Closing the Project
The purpose of properly terminating a project is to
learn from the experience in order to improve
performance on future projects.
Termination activities should be identified in the
baseline plan
Assure that all payments have been collected from
the customer
Assure that all payments for materials and
subcontractors have been paid
48
Closing the Project (continued)
Prepare a written performance evaluation of
each member of the project team
Hold post-project evaluation meetings
Celebrate
49
Early Project Termination
If research shows costs will be much more
than originally anticipated
If there is a change in a company’s financial
situation
Because of dissatisfaction of the customer
Avoid early termination due to customer
dissatisfaction by monitoring customer satisfaction
continually and taking corrective action
50
Internal Post-Project Evaluation
Have individual meetings with team members
and a group meeting with the project team
Hold soon after the completion
Announce meeting in advance so people can
be prepared
Individual meetings allow team members to
give their personal impressions
51
Internal Post-Project Evaluation
(continued)
Develop an agenda for a group meeting
Group meeting should discuss performance and
recommendations for improvement
Issue a brief written report to management with
a summary and recommendations
52
Internal Post-Project Evaluation
(continued)
Some topics that might be discussed:
Technical performance
Cost performance
Schedule performance
Project planning and control
Customer relationships
Team relationships
Communications
Problem identification and resolution/recommendations
53
Customer Feedback
Meet to discuss whether the project provided the
customer with the anticipated benefits, assess
the level of customer satisfaction, and obtain any
feedback
Participants include the project manager, key
project team members, and key representatives
of the customer
Ask open-ended questions
Customers can express their level of satisfaction
and provide detailed comments
54
Customer Feedback (continued)
If the customer is satisfied with the project:
Ask about other projects you could do—perhaps
without going through a competitive RFP process
Ask permission to use the customer as a
reference
Get feedback regarding satisfaction through a
post-project customer evaluation survey
55
Ethical Behavior
Unethical behavior is rationalized:
It’s not hurting anyone
Everybody does it
Ethical behavior is built on trust, which is
crucial for business relations development
between
Customers
Suppliers
Subcontractors
56
Ethical Behavior
Examples of unethical behavior
Knowingly use marginal or unsafe materials or
design
Putting pressure on the project team to charge
more or less hours than they actually worked to
mislead management or customers that project is
on budget
Knowingly approving test results that are
inaccurate
Paying off inspectors to approve work that
otherwise will not pass inspection
57
Ethical Behavior
Examples of unethical behavior
Intentionally submitting a low bid on a proposal with
the intention that you will make up the price by
charging the customer for high priced changes after
getting the contract
Purchasing material from suppliers who give you
“kickbacks”
Dishonesty in time card reporting of hours worked
resulting in overcharges to the customer
Padding or falsifying travel expenses
Plagiarizing the work of others and taking credit for
them
58
Ethical Behavior
Key principles of ethical behavior
Treat others the way you would like to be treated
(project managers set the example)
Don’t do anything that you wouldn’t want your
family, friends, neighbors or coworkers to read
about it in the newspaper or hear on the news
59