Weekly Progress Report

The weekly progress report for the construction of the Bamboo Link Road from Lengpui to Saiphal Bamboo Plantation indicates that significant milestones have been achieved, including the completion of earthwork, culverts, retaining walls, and drainage systems. However, construction of minor bridges and road furniture has not yet started, while cement concrete pavement and masonry lined drains are still in progress. The overall physical progress of the project is at 10.24% for the week ending January 5, 2025.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
58 views6 pages

Weekly Progress Report

The weekly progress report for the construction of the Bamboo Link Road from Lengpui to Saiphal Bamboo Plantation indicates that significant milestones have been achieved, including the completion of earthwork, culverts, retaining walls, and drainage systems. However, construction of minor bridges and road furniture has not yet started, while cement concrete pavement and masonry lined drains are still in progress. The overall physical progress of the project is at 10.24% for the week ending January 5, 2025.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Construction of Bamboo Link Road from Lengpui to Saiphal Bamboo Plantation (41 Km) under PM-DevINE

Weekly Progress Report for the week 30 Dec 24 to 05 Jan 25


Achevemnet upto Achievement
Qty as per previous week upto this week Cumulative
Sl/No Item Discreptions
Agreement Achievment
Physical Progress Bar Chart Remark's
Dt: 30/12/24 Dt: 05/01/25
Km/Nos/Rm Km/Nos/Rm Work Done Target

Earthwork for widening and 100.00%


1.00 41.00 Km 41 Km 0.00 Km 41 Km Completed
Curve Improvement. 100.00%

100.00%
2.00 Construction of culverts 76.00 No's 76.00 No's 0.00 No's 76.00 No's Completed
100.00%

100.00%
3.00 Construction of retaining walls 343 Rm 343 Rm 0 Rm 343 Rm Completed
100.00%

4.00 Construction of Minor Bridges 2.00 No's 0.00 No's 0.00 No's 0.00 No's 0.00% Not Yet Started
100.00%

Gravel Soil Aggregate base


5.00 (For Profile Correction 7.145 Km 7.145 Km 0.00 Km 7.145 Km 100.00%
Completed
Between 14.00 - 41.00) 100.00%

Water Bond Macadam for


6.00 (Pavement Portion Betwwen 27.00 Km 27.00 Km 0.00 Km 27.00 Km Completed
100.00%
14.00 - 41.00) 100.00%

Water Bond Macadam (For


7.00 41.00 Km 0.000 Km 0.000 Km 0.000 Km 0.00% Not Yet Started
hard shoulder)
100.00%

8.00 Cement Concrete Pavement 41.00 Km 4.00 Km 0.20 Km 4.20 Km 10.24% Under Progress
100.00%

9.00 Unlined Drain 22.886 Km 22.886 Km 0.000 Km 22.89 Km Completed


100.00%
100.00%

10.00 Masonary Lined Drain 11.820 Km 5.000 Km 0.665 Km 5.67 Km Under Progress
47.93%
100.00%

11.00 Road furniture 41.00 Km 0.00 Km 0.00 Km 0.00 Km Not Yet Started
0.00%
100.00%

Sr. Sub-Divisionasl Officier, PWD., Sr. Executive Engineer, PWD.,


National Highway Division-I, Aizawl. National Highway Division-I, Aizawl.

Page 1 of 6
Construction of Bamboo Link Road from Lengpui to Saiphal Bamboo Plantation (41 Km) under PM-DevINE
Weekly Progress Report for the week
Achevemnet
This week
upto previous
Qty as per Cumulative progress
Sl/No Item Discreptions week Progress Chart Remark's
Agreement Achievment
Dt: 30/12/24 Dt: 05/01/25
Km/Nos/Rm Km/Nos/Rm Work Done CA Scope
100.00%
100.00%
1.00 Earthwork upto top of the Subgrade 41 Km 41 Km 41 Km 0 Km Completed
100.00%
2.00 Gravel Soil Agg. Base 7.145 Km 7.145 Km 7.145 Km 0 Km 100.00%
Completed
100.00%
3.00 WBM For Pavement 27 Km 27 Km 27 Km 0 Km 100.00%
Completed
0.00%
4.00 WBM For Shoulder 41 Km 0.00 Km 0.00 Km 0 Km Under Progress
100.00%

10.24%
5.00 Cement Concrete Pavement 41.00 Km 4.20 Km 4.00 Km 0.20 Km Under Progress
100.00%

100.00%
6.00 Hume Pipe Culvert Type-I 40 No's 40 Km 40 No's 0 No's Completed
100.00%

100.00%
7.00 Hume Pipe Culvert Type-II 17 No's 17 Km 17 No's 0 No's Completed
100.00%

8.00 RCC Slab Culvert Type-I 12 No's 12 Km 12 No's 0 No's 100.00%


Completed
100.00%

9.00 RCC Slab Culvert Type-II 7 No's 7 Km 7 No's 0 No's 100.00%


Completed
100.00%

10.00 Minor Bridge 2 No's 0 Km 0 No's 0 No's 0.00% Not Yet Started
100.00%

11.00 [Link] Type-I 209 Rm 209 Km 209 Rm 0 Rm Completed


100.00%
100.00%

12.00 [Link] Type-II 94 Rm 94 Km 94 Rm 0 Rm Completed


100.00%
100.00%

13.00 [Link] Type-III 40 Rm 40 Km 40 Rm 0 Rm Completed


100.00%
100.00%
14.00 Road Signage 356 Each 0 Km 0 Each 0 Each 0.00% Not Yet Started
100.00%
15.00 KM Stones 41 No's 0 Km 0 No's 0 Each 0.00%
Not Yet Started
100.00%
16.00 Boundary Pillar 410 Each 0 Km 0 Each 0 Each Not Yet Started
0.00%
100.00%
17.00 PCC Crash Barrier 2000 Each 0 Km 0 Each 0 Each Not Yet Started
0.00%
100.00%
18.00 Masonry Lined Side Drain 11820 Rm 5665 Km 4000 Rm 1665.000 Rm Under Progress
47.93%
100.00%
19.00 Unlined Side Drain 28886 Rm 28886 Km 28886 Rm 0 Rm Completed
100.00%
100.00%

Page 2 of 6
Work Done CA Scope Item Description

41 Km 41 Km

7.145 Km 7.145 Km

27 Km 27 Km

0 Km 41 Km

4.20 Km 41 Km

40 No's 40 No's
₹ 60,000,000.00
₹ 0.00
₹ 120,000,000.00
₹ 180,000,000.00
₹ 240,000,000.00

Earthwork for widening and Curve


Improvement.
17 No's 17 No's
Construction of culverts

12 No's 12 No's Construction of retaining walls

Construction of Minor Bridges


7 No's 7 No's
Column EO

Gravel Soil Aggregate base (For Profile Cor-


rection Between 14.00 - 41.00)

Water Bond Macadam for (Pavement Por-


Chart Title

0 No's 2 No's

Page 3 of 6
tion Betwwen 14.00 - 41.00)
Column EQ

Water Bond Macadam (For hard shoulder)


209 Rm 209 Rm
Cement Concrete Pavement

94 Rm 94 Rm Masonary lined Drain

Unlined Drain

40 Rm 40 Rm
Nidhi Creative Infrastructure Private Limited

Road furniture

0 Each 356 Each

0 No's 41 No's

0 Each 410 Each

0 Each 2000 Each

5665 Rm 11820 Rm
Construction of Bamboo Link Road from Lengpui to Saiphal Bamboo Plantation (41 Km) under PM-DevINE

28886 Rm 28886 Rm
Up to Date: 05/01/25
Qty As Per
Work Done Agreement Item Description

0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

41 Km 41 Km Emb & Subgrade

7.145 Km 7.145 Km G/S Agg. Base

27 Km 27 Km WBM Pavement

Sr. Sub-Divisionasl Officier, PWD.,


National Highway Division-I, Aizawl.
0 Km 41 Km WBM Shoulder

4.20 Km 41 Km C.C Pavement

40 No's 40 No's HPC Ty-I

17 No's 17 No's HPC Ty-II

12 No's 12 No's RCC S.C Ty-I

33.59%
7 No's 7 No's RCC S.C Ty-II

Balance Work
MNB

Page 4 of 6
0 No's 2 No's

R/w Ty-I
209 Rm 209 Rm

66.41%

Work Done
Cumulative Physical Progress%

R/w Ty-II
94 Rm 94 Rm
Detailed Physical Progress Bar Chart

R/w Ty-III
40 Rm 40 Rm
Nidhi Creative Infrastructure Private Limited

Road Sianage
0 Each 356 Each

KM Stone
0 No's 41 No's

Boundary Pillar
0 Each 410 Each

PCC Crash Barrier


0 Each 2000 Each

M. linede Drain
5665 Rm 11820 Rm
Sr. Executive Engineer, PWD.,

M. Unlinede Drain
28886 Rm 28886 Rm
National Highway Division-I, Aizawl.
Construction of Bamboo Link Road from Lengpui to Saiphal Bamboo Plantation (41 Km) under PM-DevINE

Up to Date: 05/01/25
Sr. Sub-Divisionasl Officier, PWD.,
National Highway Division-I, Aizawl.

Page 5 of 6
Construction of Bamboo Link Road from Lengpui to Saiphal Bamboo Plantation (41 Km) under PM-DevINE
Detailed Scope of Work, Physical Progress by Component & Work Done

Value of
Weightage in Weightage
Planned in scope % Physical physical
Component percent to Item Description by Work Done upto
(as per work scope) progress progress
the contract component
(7*4)

Quantity
% Quantity Unit Unit
1 2 3 4 5 6 7 8
A-Widening and strengthening of
Road works including culverts, widening and repair of

existing road
1. Earthwork up to top of sub-grade 6.42 41.00 Km 41.00 Km 100.00 6.42

2. Gravel/Soil Aggregate Base (for profile


correction between Km 14.00 to Km 2.97 7.15 Km 7.15 Km 100.00 2.97
41.00)

3. Water Bound Macadam (Pavement 7.46 27.00 Km 27.00 Km 100.00 7.46


portion between Km 14.00 to Km 41.00)
culverts.

89.41%

4. Water Bound Macadam (for hard 11.69 41.00 Km - Km - -


shoulder)
5. Cement Concrete Pavement 62.03 41.00 Km 4.20 Km 10.24 6.35

D-Reconstruction and New culverts on


existing road, realignment, bypass:
1. Hume Pipe Culvert Type-I 3.84 40.00 Nos 40.00 Nos 100.00 3.84
2. Hume Pipe Culvert Type-II 2.07 17.00 Nos 17.00 Nos 100.00 2.07
3. RCC Slab Culvert Type-I 2.04 12.00 Nos 12.00 Nos 100.00 2.04
4. RCC Slab Culvert Type-II 1.48 7.00 Nos 7.00 Nos 100.00 1.48
32.63
Avg. (A) = 29.18
A-2. New Minor Bridges
1. New Minor Bridge @ Km 16.400
(1) Foundation + Sub-structure (including
Minor Bridges

28.58 - -
Wing wall and return wall) 1.00 No
2.29%

(2) Super Structure 21.42 - -


2. New Minor Bridge @ Km 34.315
(1) Foundation + Sub-structure (including
28.58 - -
Wing wall and return wall) 1.00 No
(2) Super Structure 21.42 - -
-
Avg. (B) = -
1. Retaining wall type-I 14.89 209.00 Rm 209.00 Rm 100.00 14.89
2. Retaining wall type-II 9.40 94.00 Rm 94.00 Rm 100.00 9.40
3. Retaining wall type-III 5.42 40.00 Rm 40.00 Rm 100.00 5.42
Other works

4. Road Signage 13.67 356.00 Each - - -


8.31%

5. KM Stones 0.61 41.00 Nos - - -


6. Boundary Pillar 0.66 410.00 Each - - -
7. PCC Crash Barrier 12.53 2000.00 Each - - -
8. Masonry Lined Side Drain 37.25 11820.00 Rm 5665.00 47.93 17.85
9. Unlined Side Drain 5.57 28886.00 Rm 28886.00 Rm 100.00 5.57
53.13
Avg. (C) = 4.42
Grand Total (A+B+C) = 33.59

Sr. Executive Engineer, PWD.,


Sr. Sub-Divisionasl Officier, PWD.,
National Highway Division-I, Aizawl.
National Highway Division-I, Aizawl.