September 16, 2019 4 min read time
AEP calculations uncertainties
Many users needed to have implemented uncertainty calculations to their
scenarios so we went right ahead and added that to the YOUWINd scenario
comparisons.
Our calculated figure for electricity production is the P50 AEP. This figure is the
level of production that is estimated to be exceeded 50% of the time in a year or
the average in a year. A P90 figure is therefore an estimate of production that is
forecasted to exceed 90% of the time in a year. The P stands for percentile. The
YOUWINd model P50 value is the mean value that represents the AEP with the
highest probability.
The AEP estimate varies from year to year as we don‘t know the future wind
speeds and therefore we always include uncertainties in our calculations. These
include uncertainties in our own modeling and the data itself. No developer can
promise that the wind farm site will not have years that will underperform. Like
in Youwind Model as in other calculation models, the distribution of uncertainty
does not perfectly follow normal (Gaussian) distribution but for the sake of
simplifying calculation, we use this distribution. We do this because we use the
mean wind speed with 10-minute intervals at 100m hub height and statistically
representative data is not always available.
Therefore we have also the P90 figure shown for the AEP which is more used by
investors that want a more viable estimate of the production over the lifetime of
the wind farm. In the graph below we show the AEP with P50 and P90 for a
typical wind farm production estimate.
The turbine’s power output is entered for each wind speed. The result of this
calculation is the AEP or annual energy production.
Depending on the reliability of the original data, turbine height, turbine design,
the variability in the weather, and maintenance or breakdown history, you will
have a likelihood or probability that the actual energy output will be less than
the calculated AEP.
Causes of uncertainty:
The calculation of the scenarios from the best estimate of the P50 takes the
total uncertainty into account that has been involved in the AEP modeling in the
YOUWINd model.
These are the following:
Data uncertainties – Weather data from our data source = Xdata = 5%
Interannual variability – Weather changes year to year = Xweather = 5%
AEP calculation model – calculation uncertainty = Xmodel = 4%
When you combine the uncertainty with the factors we can calculate the P90
using the normal distribution model. When combining the uncertainty models
we calculate them as independent from each other and then we can calculate
the overall uncertainty in the modal as:
Our overall uncertainty is
valued at 8,1% in our probability calculations. There are many ways of lowering
this uncertainty but this implies more accurate datasets.
With this uncertainty, we can evaluate our probability normal distribution. Let‘s
have a look at an example with the Borssele 1+2 Example scenario that is the
first on the list in the free version of Youwind Model (app.youwindmodel.eu). The
distribution level can be seen in the figure below:
The result of the P90 and the P50 can be seen on the scenario overview page
but the overall calculation is based on the P50 calculations.
Try it for yourself using your own data and make your own scenarios using the
YOUWINd model. Try it out here: app.youwindmodel.eu
Stay Up-To-Date with all things Youwind
Name
Michael Harper
Company
Wind Power Group
Email
[email protected]
protected by reCAPTCHA
Privacy - Terms
Send
You may also like this
Similar Articles
April 3, 2024 7 min read time
Youwind new tools and features, April 2024
In this article, we give an overview of the latest additions to the Youwind
web-based solution:...
Youwind Renewables Product Updates
January 17, 2024 11 min read time
Youwind new tools and features, January 2024
In this article, we give an overview of the latest additions to the Youwind
web-based solution:...
Youwind Renewables Product Updates
March 1, 2020 4 min read time
Offshore wind turbine swept area and rated power
The development of offshore wind turbine size has been astonishing over
the last two decades. The...
Youwind Renewables Youwind Academy
Youwind Renewables
Discover Youwind First-Hand
Request a Demo
Company
Home
About us
Blog
Log In
Services
Youwind Model
Pixel+
Optiwindow
Terms and Services
Privacy Policy
© 2025 Youwind Renewables