SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
QN Prepare the detailed estimate of various item of work of aquaduct from given drawing
a) Foundation concrete shall be of [Link] cement concrete
b)All brick shall be of 1:4 cement sand mortar
c)The trough shall be ofRCC [Link] with 1% reinforcement finishes with plastering
d)all exposed surface of brick work shall be pointed with 1:2 cement mortar
e) Brick pitching shsll be of dry straight over burnt brick .
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
SN Description of work Unit No L(m) B(m) H(m) Quantity Remarks
Earthwork in excavation in
1 cum
foundation
a)Central pillar
straight portion 1 1.8 0.5 0.5 0.45
Area=1/2*base*height
Triangular portion 2 1/2*0.5 *0.5/2*tan60 0.5 0.11
Height=0.5/2*tan60
b)End pillar at bed 2 2.1 0.5 0.5 1.05 L=0.15*2+1.5+0.15*2
c) End Pillar at bank including
2 6.3 0.5 0.3 1.89
wing wall
L=(6+8.8)/2
d) slope of stream for pitching 2 7.4 1.84 0.2 5.46
B=sqrt(1.2^2+1.4^2)
d)Bed of minor for pitching 2 3 1.8 0.1 1.08
d) slope of minor for pitching 4 3 1.80 0.1 2.16 B=sqrt(1^2+1.5^2)
e) toe wall 2 8.8 0.2 0.3 1.06
Total 13.26 cum
Cement concrete [Link] in
2 cum
foundation
a)Central pillar
straight portion 1 1.8 0.5 0.2 0.18
Triangular portion 2 1/2*0.5 *0.5/2*tan60 0.2 0.04
b)End pillar at bed 2 2.1 0.5 0.2 0.42
c) End Pillar at bank including
2 6.3 0.5 0.2 1.26
wing wall
Total 1.90 cum
First class brick work in 1:4
3 cum
Cement sand mortar
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
a)Central pillar
straight portion 1 1.8 0.3 2.1 1.13 L=1.5+0.3 H=0.3+1.2+0.6
Triangular portion 2 1/2*0.3 *0.3/2*tan(60) 2.1 0.16
b)End pillar at bed 2 1.8 0.3 2.1 2.27
c) End Pillar at bank 2 1.8 0.3 0.7 0.76
d)wing wall 4 2.1 0.3 2.15 5.42
Total 9.74 cm
RCC [Link] in trough excluding
4 cum
steel
Bottom s;ab 1 8.3 1.8 0.15 2.24
Vertical slab 2 8.3 1.3 0.15 3.24
Total 5.48 cum
Steel reinforcement including
5
bending
Rebar @1% of Concrete 5.48 0.01 7850 430.02 Density of steel =7850kg/cum
TOTAL 430.02 Kg