Aquaduct Estimate

The document provides a detailed estimate for the construction of an aqueduct, specifying materials and methods for various components including foundation concrete, brick work, and RCC troughs. It includes calculations for earthwork excavation, cement concrete, brick work, and steel reinforcement. The estimates are organized by item, with specific dimensions and quantities outlined for each part of the project.

Uploaded by

Umesh Kumar pant
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
88 views10 pages

Aquaduct Estimate

The document provides a detailed estimate for the construction of an aqueduct, specifying materials and methods for various components including foundation concrete, brick work, and RCC troughs. It includes calculations for earthwork excavation, cement concrete, brick work, and steel reinforcement. The estimates are organized by item, with specific dimensions and quantities outlined for each part of the project.

Uploaded by

Umesh Kumar pant
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant

Dipayal, Doti
QN Prepare the detailed estimate of various item of work of aquaduct from given drawing
a) Foundation concrete shall be of [Link] cement concrete
b)All brick shall be of 1:4 cement sand mortar
c)The trough shall be ofRCC [Link] with 1% reinforcement finishes with plastering
d)all exposed surface of brick work shall be pointed with 1:2 cement mortar
e) Brick pitching shsll be of dry straight over burnt brick .
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
SN Description of work Unit No L(m) B(m) H(m) Quantity Remarks
Earthwork in excavation in
1 cum
foundation
a)Central pillar
straight portion 1 1.8 0.5 0.5 0.45
Area=1/2*base*height
Triangular portion 2 1/2*0.5 *0.5/2*tan60 0.5 0.11
Height=0.5/2*tan60
b)End pillar at bed 2 2.1 0.5 0.5 1.05 L=0.15*2+1.5+0.15*2
c) End Pillar at bank including
2 6.3 0.5 0.3 1.89
wing wall
L=(6+8.8)/2
d) slope of stream for pitching 2 7.4 1.84 0.2 5.46
B=sqrt(1.2^2+1.4^2)
d)Bed of minor for pitching 2 3 1.8 0.1 1.08

d) slope of minor for pitching 4 3 1.80 0.1 2.16 B=sqrt(1^2+1.5^2)

e) toe wall 2 8.8 0.2 0.3 1.06


Total 13.26 cum
Cement concrete [Link] in
2 cum
foundation
a)Central pillar
straight portion 1 1.8 0.5 0.2 0.18
Triangular portion 2 1/2*0.5 *0.5/2*tan60 0.2 0.04
b)End pillar at bed 2 2.1 0.5 0.2 0.42
c) End Pillar at bank including
2 6.3 0.5 0.2 1.26
wing wall
Total 1.90 cum
First class brick work in 1:4
3 cum
Cement sand mortar
SETI TECHNICAL SCHOOL Prapared By : Er Umesh Kumar Pant
Dipayal, Doti
a)Central pillar
straight portion 1 1.8 0.3 2.1 1.13 L=1.5+0.3 H=0.3+1.2+0.6
Triangular portion 2 1/2*0.3 *0.3/2*tan(60) 2.1 0.16
b)End pillar at bed 2 1.8 0.3 2.1 2.27
c) End Pillar at bank 2 1.8 0.3 0.7 0.76
d)wing wall 4 2.1 0.3 2.15 5.42
Total 9.74 cm
RCC [Link] in trough excluding
4 cum
steel
Bottom s;ab 1 8.3 1.8 0.15 2.24
Vertical slab 2 8.3 1.3 0.15 3.24
Total 5.48 cum
Steel reinforcement including
5
bending
Rebar @1% of Concrete 5.48 0.01 7850 430.02 Density of steel =7850kg/cum
TOTAL 430.02 Kg