CASE Drawing Review Checklist
CASE Drawing Review Checklist
B-1
CASE
DRAWING REVIEW CHECKLIST
√ √ √
ITEM Yes No N/A COMMENT
A. Is there a Project cover sheet including:
1. Name of Project?
2. Address of Project?
3. Design team and Contact person?
4. Scope of Work?
5. Location and Project Site Plan?
6. Deferred Item List?
7. List of Governing Codes?
8. Drawing List?
B. Do the sheet titles in the Drawing Index match the
individual drawing titles?
C. Are the dates, commission members, revision
descriptions, and initials consistent from sheet to
sheet?
D. Do title blocks appear consistent between
structural and architectural drawings (project
name, fonts, text size, drawing numbering
convention, etc.)?
B-2
II. ARCHITECTURAL/STRUCTURAL COORDINATION
√ √ √
ITEM Yes No N/A COMMENT
A. Do structural drawings address items shown on
demolition drawings?
B. Has the SER provided special direction on
demolition plans, particularly if phased or partial
demolition involves specific planned procedures,
including shoring?
B-3
√ √ √
ITEM Yes No N/A COMMENT
P. Are governing regulations and code references
coordinated between architectural and structural
drawings?
Q. Elevator Coordination
1. Do design loads include allowance for impact?
(typ. double static)
2. Are supports designed per ANSI/ASME allowable
stresses and deflections?
3. Are loads designed for points of application
indicated on drawings?
4. Does elevator up-pull reaction at pit included for
high speed elevators? Similarly for underslung
elevators?
5. Are intermediate elevator rail supports provided
where required?
6. Are Separator beams and intermediate rail bracing
designed for specified reactions including
horizontal?
7. Is elevator hoist beam provided over center of
shaft?
8. Is minimum clear overrun provided above top
floor served?
9. Is elevator sill support detail coordinated with
architect and elevator spec.?
10. Are clear hoistway dimensions coordinated?
R. Are references to Architectural drawings clearly
identified?
S. Are connections for architectural attachments
coordinated with structural requirements?
T. Are connections for equipment and systems
referenced to structural documents as applicable?
B-4
III. CIVIL/STRUCTURAL COORDINATION
√ √ √
ITEM Yes No N/A COMMENT
A. Do new or old underground utilities (power,
telephone, water, sewer, gas storm drainage, fuel
lines, fuel tanks) interfere with foundation
systems?
IV. MECHANICAL-ELECTRICAL-
PLUMBING/STRUCTURAL COORDINATION
A. Do footing elevations accommodate plumbing
inverts/elevations?
B. Are floor openings framed out to accommodate
ductwork and other penetrations?
C. Are lintel provisions included for all ductwork and
other penetrations?
D. Do toilet penetrations conflict with steel/concrete
beams and joists?
E. Does embedded conduit conform to ACI 318?
F. Has light fixture interference with structural
framing been checked?
B-5
√ √ √
ITEM Yes No N/A COMMENT
G. Are slab openings coordinated with risers (ducts,
hot and chilled water, conduit banks, bus ducts)?
B-6
√ √ √
ITEM Yes No N/A COMMENT
N. Are acoustic criteria for structure surrounding
heavy mechanical equipment known and included
in design (addl. mass)?
O. Are cooling tower/generator/chiller/boiler support
criteria coordinated?
Is separate steel above vibration isolators
included?
Is coordination with support criteria for vibration
isolators incl.?
P. Is cellular deck required?
Are trench headers considered in design?
Q. Have transformer vaults/network protection rooms
been designed to address special requirements of
the local authority, such as blast loading?
B-7
√ √ √
ITEM Yes No N/A COMMENT
1. North Sign?
2. Dimensions, grid lines, scale (need to be
consistent with others)?
3. Define elevations of floor?
4. Define all structural members & lateral load
resisting system
5. Locations of Openings, Mech. Units?
6. Cross Reference details?
C Are notes consistent with sections, details and
specifications.
D. Do drawings conform to design calculations and
sketches?
Do notes provide necessary design information for
prefabricated items?
E. Are special provisions for future expansion
shown?
F. Is the nomenclature consistent throughout all
drawings and specifications?
G. Are legend and abbreviation lists shown?
H. Are floor and roof elevations shown and in
agreement with architectural drawings?
I. Are typical details adequately referenced and
applicable?
J. Do scheduled items shown on plan correspond to
items in schedules?
K. Do all sections match the location and orientation
of section cuts on plans?
L. Are all scales indicated correctly?
M. Are drawings and specification coordinated?
N. Is there a clearly identifiable load path for gravity
and lateral forces?
O. Have design review comments been resolved?
P. Are all special details included and properly
referenced?
Q. Is there a clearly identifiable complete load path
for support of gravity loads and bracing of lateral
forces?
B-8
√ √ √
ITEM Yes No N/A COMMENT
R. Is lateral bracing dependent upon any sequence of
erection, or on a variety of building systems? Are
special construction procedures identified?
S. Are material tolerances considered and provided
for within materials, between different materials
and between structural and non-structural
elements?
B-9
√ √ √
ITEM Yes No N/A COMMENT
H. Are special requirements for sequencing of
earthwork operations identified in drawings or
specifications?
I. Are dewatering requirements indicated in the
specifications?
J. Are requirements for footing cuts shown on
drawings?
K. Is backfill and drainage fill properly indicated?
L. Are existing soil conditions shown in drawings or
specifications for bidding purposes?
M. Do the foundation plans clearly show the locations
of all foundation elements: footings, walls, piers,
caissions, cofferdams, mat foundations, pier caps,
grade beams, slabs-on-grade?
B-10
√ √ √
ITEM Yes No N/A COMMENT
Z. Are base courses and capillary water barriers
shown under slabs-on-grade and do they conform
to recommendations of the geotechnical report?
√ √ √
ITEM Yes No N/A COMMENT
A. Are pile driving limitations listed in the
specifications including hours of operation, energy
delivered, etc.?
B. Are bid lengths and quantities established?
C. Are unit prices called for variation from bid?
D. Is final layout for piles indicated on foundation
drawings?
E. Do driven pile schedules or notes specify driving
lengths, pile diameter and thickness, splices, cut-
off elevations, etc.?
F. Is test pile program shown on the drawings and is
detailed information provided in the
specifications?
G. Is the interface between the top of the pile and the
bottom of the pile cap/foundation clearly detailed
on the drawings?
H. Is pile cap reinforcing shown?
I. Are pile caps interconnected?
VIII. DRILLED PIER FOUNDATION SYSTEMS
A. Are drilled piers shown on the Foundation Plan,
showing relationship between piers and other
foundation elements?
B. Are requirements for drilled hole casings shown
on the drawings and described in the
specifications?
B-11
√ √ √
ITEM Yes No N/A COMMENT
B-12
√ √ √
ITEM Yes No N/A COMMENT
D. Are all structural elements, such as slabs, beams,
girders, columns, walls and foundations, clearly
identified, located, dimensioned and detailed?
B-13
√ √ √
ITEM Yes No N/A COMMENT
N. Are any special coating requirements for
reinforcing steel called out?
O. Is required concrete cover for reinforcing steel
called out?
P. Are sleeve locations and details called out?
Q. Is special trim reinforcement identified around
sleeves or openings?
R. Are construction joint details provided?
S. Are slab depressions identified and detailed?
T. Are finishing and flatness requirements specified?
B-14
√ √ √
ITEM Yes No N/A COMMENT
3. Specify bond type?
4. Specify cold/hot weather requirements?
5. Specify grouting procedures?
6. Is Special Inspection required?
B. Are control joints specified, and are they:
1. Spaced as required?
2. Placed to avoid concentrated loads?
3. Do they allow for arching at openings?
4. Are they placed to coincide with floor joints for
wall supported slabs?
C. Will all walls with reinforcing have cells at least
2"x2"? Are cells with reinforcing required to be
filled with grout, not mortar? Is extent of grouting
of cells clearly identified?
D. Is all reinforcing steel clearly shown? Are bond
beams shown for horizontal steel?
E. Are non-structural walls isolated to allow for
relative movement, yet braced for out of plane
forces?
F. Are locations of intermediate bond beams shown
on sections and wall elevations?
G. Are walls designed and connected for out of plane
forces?
H. Are lintel details provided for all openings?
I. Are shelf angles required for brick support
properly located and anchored?
J. Do shelf angle joints allow for deflection,
shrinkage, creep and brick expansion?
K. Are brick expansion joint locations coordinated
with brick lintels?
L. Are brick ledge details coordinated with
architectural elevations?
M. Are anchors for floor/roof joists, beams, etc.
properly located and detailed?
N. Are there joints to permit seismic drift or for walls
subjected to differential vertical movement or
settlement?
O. Are veneer tie details appropriate?
B-15
√ √ √
ITEM Yes No N/A COMMENT
P. Where masonry walls serve as shear walls to resist
lateral forces:
1. Have all stresses been checked and is reinforcing
adequate?
2. Are connections of diaphragms and collectors to
walls properly detailed?
3. Has overturning been properly considered?
4. Has reinforcing been provided at opening jambs,
heads, and sills to meet seismic or wind load
requirements?
Q. Have construction tolerances been considered?
XI. STRUCTURAL STEEL SYSTEMS
A. Is the AISC Code of Standard Practice referenced
and amended as necessary?
B. Are sizes and material grades clearly identified for
all framing members, bracing members, plates,
bolts, studs, etc., including special material
requirements?
B-16
√ √ √
ITEM Yes No N/A COMMENT
D. Are steel connections and details complete,
including:
1. Permanent bracing.
2. Column stiffneners and web doubler plates.
3. Bearing stiffeners in beams and girders.
4. Openings in steel and web reinforcement.
5. Sizes and dimensions of all connection materials
and welds and number of connectors.
6. Column splice details.
7. Truss details and end connections?
E. If connections are to be designed by the
Fabricator, are the following provided:
1. Shear, moment and axial forces necessary for
design.
2. Are forces given at service load or factored load?
B-17
√ √ √
ITEM Yes No N/A COMMENT
J. Are force diagrams given for trusses that are not
shown with detailed connections? Do they include
truss geometry and applied loads?
K. Are structural steel connections to concrete or
masonry shown?
L. Have the AISC Seismic Provisions for Structural
Steel Buildings, including Supplement No. 2 been
reviewed?
M. Is the Structural Welding Code of the American
Welding Society properly referenced, recognizing
that certain provisions of the code are mandatory
only when specified by the SER? Have the
following items been specifically addressed?
B-18
√ √ √
ITEM Yes No N/A COMMENT
S. Are any special restrictions on shop or field
assembly clearly identified?
T. Have construction tolerances been considered and
provided for?
U. Are secondary members sized for efficiency by
using fewer different sizes?
V. Is structure constructible/erectable? Are pieces
sized to permit connection?
XII. STEEL JOIST SYSTEMS
A. Where HVAC or major plumbing is run through
webs is the requirement to align panel points
specified?
B. Ceiling extensions (bottom chord) required?
C. Is depth of the bearing seat shown?
D. Are joist size and spacing shown?
E. Have type of bridging and spacing been specified?
B-19
√ √ √
ITEM Yes No N/A COMMENT
L. When defining loads on special joists are the
following considered?:
1. Define gravity and lateral loads separately.
2. Identify or estimate self weight.
3. Indicate net wind uplift.
4. Do not specify a standard joist designation with
special loading.
5. Consider constant shear joists where location of
loading is uncertain.
6. When joists are on a bias (not plumb), consider
effects of gravity forces on bracing.
XIII. METAL DECK SYSTEMS
A. Are gages, depths and types of metal decking
shown on the plans?
B. Do drawings specify that decking must be
continuous over two or three supports?
C. Have minimum required structural properties of
floor and roof decking been specified and
coordinated with the project specifications?
D. Is deck attachment pattern and fastener type
specified, including sidelap, support, and
perimeter conditions?
E. Does deck attachment pattern and fastener type
provide required shear diaphragm strength?
B-20
√ √ √
ITEM Yes No N/A COMMENT
XIV. WOOD SYSTEMS
A. Are species and grades of timber specified and
shown in the notes?
B. Is nailing schedule shown or reference made to
governing code requirements or applicable
criteria?
C. Are sizes and types of bolts, screws, nails,
engineered wood products and wood framing
connectors clearly identified and specified?
D. Are adequate details shown, identifying all
framing members and connections, including
details for diaphragms and shearwalls?
E. Are required lateral bracing, blocking and bridging
details called for on the drawings, including
blocking at bearings?
F. Are bolt spacing, end distances and edge distances
adequate?
G. Are beams, blocking lintels or headers detailed at
roof, floor and wall openings?
H. Are walls properly attached to foundations, floors
and roof?
I. Are typical details provided for wall construction?
B-21
√ √ √
ITEM Yes No N/A COMMENT
K. For wood structural elements engineered by others
(i.e., Glu-lam systems, pre-fabricated trusses, etc.):
B-22
√ √ √
ITEM Yes No N/A COMMENT
F. Is the end use of the building identified, along
with project specific conditions such as
importance factors, side sway criteria and
environmental conditions?
B-23