LAKE/ 041 Plastering Material Calculation Report
Project: Exterior + interior Second Coat Plastering
Area: 462 m²
Thickness: 2.5 cm
Mix Ratio: 1:3 (Cement:Sand)
1. Plaster Volume Calculation
Thickness: 2 cm = 0.02 m
Wet Volume = Area × Thickness
462 m² × 0.02 m = 9.24 m³
Dry Volume = Wet Volume × 1.33 (for bulking and wastage)
9.24 × 1.33 = 12.29 m³
2. Cement Requirement (1:3 Mix)
Cement Share = 1 part of 4 total parts
Cement Volume = 1/4 × 12.29 = 3.07 m³
Cement Weight = 3.07 m³ × 1440 kg/m³ = 4424.4 kg
Cement Bags = 4424.4 ÷ 50 = 110.6 bags ≈ 88.48bags
Per m² Cement Usage = 4424.4 ÷ 462 ≈ 9.58 kg ≈ 0.19bags/m²
Summary
Material Total Quantity Per m²
Cement for plastering 4424.4 kg (≈ 89 bags) 9.58 kg (≈ 0.19 bags)
Cement for parapet HCB 74 m2 *0.18bags≈ 14bags
wall LAKE/041
BASEMENT floor concrete work finalizing 1.32m3 * 2.8Q ≈ 8bags (4Q)
TOTAL CEMENT CONSUMPTIONS FOR LISTED ACTIVITIES -= 111 BAGS