Project Report
Project Report
December 2008
In response to a request from the Government of Mongolia, the Government of Japan decided to
conduct a basic design study on the Project for Construction of Railway Fly-Over in Ulaanbaatar
City in Mongolia and entrusted the study to the Japan International Cooperation Agency (JICA).
The team held discussions with the officials concerned of the Government of Mongolia, and
conducted a field study at the study area. After the team returned to Japan, further studies were made.
Then, a mission was sent to Mongolia in order to discuss a draft basic design, and as this result, the
I hope that this report will contribute to the promotion of the project and to the enhancement of
I wish to express my sincere appreciation to the officials concerned of the Government of Mongolia
December 2008
Eiji HASHIMOTO
Vice-President
Japan International Cooperation Agency
LETTER OF TRANSMITTAL
We are pleased to submit to you the basic design study report on the Project for Construction of
This study was conducted by CTI Engineering International Co., Ltd, under a contract to JICA,
during the period from March 2008 to December 2008. In conducting the study, we have examined
the feasibility and rationale of the project with due consideration to the present situation of Mongolia
and formulated the most appropriate basic design for the project under Japan's Grant Aid scheme.
Finally, we hope that this report will contribute to further promotion of the project.
Kenji MARUOKA
Chief Consultant
Basic Design Study Team on the Project for
Construction of Railway Fly-Over in
Ulaanbaatar City
CTI Engineering International Co., Ltd.
SUMMARY
“The Master Plan Study on Improvement and Rehabilitation of Road Network in Ulaanbaatar”
was conducted by Japan International Cooperation Agency (JICA) in 1999 to formulate the
master plan to improve the road network and traffic situation. The JICA study concluded that,
in addition to the two (2) existing flyovers, a new railway flyover is required, as a part of the
Middle Ring Road, to form an efficient road network and sustain the socio-economic activities
in the area. However, the Mongolian side recognized certain difficulties in constructing a new
railway flyover especially from the technical and financial viewpoints using their own funds.
Under such circumstances, the Government of Mongolia (hereinafter referred to as “the GOM”),
in June 2005, requested the Government of Japan (hereinafter referred to as “the GOJ”) to
implement the construction of the railway flyover project (hereinafter referred to as “the
Project”) under the Japanese Grant Aid Program.
In response to the application for Japanese Grant Aid, JICA dispatched the Preliminary Design
Study Team to Mongolia three times, between February 2007 and November 2007, to conduct
site surveys and hold discussions with the Mongolian side. Accordingly, the following points
have been confirmed:
1. The Project, which will connect the northern and southern areas of Ulaanbaatar City, is
urgently required to secure safe and reliable traffic.
2. The through-traveled lane of the new railway flyover will be 4-lane to accommodate the
traffic demand which is presently large enough to justify the construction of a 4-lane road.
3. The request of the Mongolian side to procure equipment for construction and maintenance
of the Project is set aside because necessity remains low.
4. The proposed location of the flyover is justified through the comparison of alternatives.
On the basis of the preliminary design study results, JICA decided to conduct the Basic Design
Study for the construction of a flyover above the railway and Narny Zam, i.e., a grade
separation structure connecting with Ikh Toyruu/Narny Zam and Engels Street. Accordingly,
JICA dispatched the Basic Design Study Team to conduct the Study in Mongolia from
March 20, 2008 to May 6, 2008.
-i-
2. STUDY RESULTS AND CONTENTS OF THE PROJECT
The Basic Design Study Team held discussions with the officials concerned of the GOM to
confirm the contents of the request for Japanese assistance, and it also conducted a field study
involving natural conditions, traffic situation, and procurement condition of construction
materials and equipment.
After deliberations in Japan on the basic design and the results of the field study in Mongolia,
JICA dispatched the Basic Design Study Team again to Mongolia, which discussed and
explained the contents of the Draft Report from October 30, 2008 to November 6, 2008,
including the engineering design, project implementation plan, project cost estimates and so on.
The Mongolian side had consented to the contents of the Draft Report, including the
undertakings that should be done without reservation by and under the responsibility of the
GOM. The concepts of conclusive planning of the Project are as described below.
The Project consists of the construction of a railway flyover having the total length of
895 meters, including the construction of approach roads from Narny Zam, as well as
from Ikh-Toyruu and Engels Street, to link the northern and southern areas of
Ulaanbaatar City.
Traffic demand on the project road has been forecasted to be 45,500 PCU/day in 2017
and thus, a 4-lane flyover is justified from the viewpoint of traffic capacity. On/off ramps,
which induce efficient dispersion of prospective traffic in the north–south direction, are
to be installed to ensure smooth access from/to Narny Zam Street. The maximum grade
of approach roads has been set at less than 5% to ensure climbing performance on
slippery frozen surface as well as to mitigate accidents on the steep slope in winter season,
as evidenced by the result of site survey on several road sections with steep gradient.
Since there are many underground utilities at the project site including main hot-water
pipes (φ500 x 2), the horizontal alignment as well as location of respective abutments and
piers has to be set to minimize effects to the existing underground facilities.
As for the superstructure, steel I-girder (4-beam) type has been adopted from the
viewpoint of economic and traffic safety, especially because of lower girder height and
gentler gradient of the approach road.
- ii -
Steel multi-pillar type piers have been adopted from the economical aspect and driver’s
visibility at intersections. Based on the geotechnical investigation result, cast-in-place
concrete pile is deemed appropriate for foundations, in principle, except for the limited
application of rotary penetration steel pile for P4 near the railway.
The appropriate period for concrete-placing and asphalt paving is deemed to be from
mid-May to mid-September based on the annual temperature records. Full utilization of
such weather-free construction materials as structural steel and pre-cast concrete products
has to be duly taken into consideration to pursue the shortest construction period, and the
construction schedule has to be formulated based on the condition that
manufacturing/pre-fabrication and construction/installation work can be done during
winter and summer seasons, respectively.
- iii -
3. SCHEDULE AND COST OF THE PROJECT
In case the Project is implemented with Japanese Grant Aid, the detailed design and tendering,
including the preparation of tender documents and assistance in tender evaluation will take
around nine (9) months, while the construction period will be around 37 months. Total cost to
be borne by the Government of Mongolia required for the complete implementation of the
Project has been estimated at 6,800 million Tg.
The direct recipients of benefit and/or utilization of the Project are the 1.031 million residents in
Ulaanbaatar City. The direct and indirect effects expected to be derived from the
implementation of the Project are as follows:
• Reduction of car exhausts due to shorter vehicular travel time and alleviation of
environmental burden.
The Project will contribute to: i) effective improvement of road network, as well as
ii) improvement of quality of social life in Ulaanbaatar City. Accordingly, it is deemed
justifiable to avail assistance through the Japanese Grant Aid Program for the implementation
of construction of the Project. The Mongolian side has sufficient institutional capacity in terms
of manpower and budget and thus, can sustain the maintenance work for the Project.
To assure the smooth implementation of the Project as well as realize the direct/indirect effects
mentioned above, the GOM shall carry out its obligations without delay and reservation, as
follows:
- iv -
Prior to Commencement of Construction Work
• To relocate existing utilities that will obstruct the construction of the Project.
• To improve the existing roads that will connect to the Project section implemented
under Japanese Grant Aid, namely Ikh-Toyruu and Engels Street, into 4-lane arterial
roads.
-v-
BASIC DESIGN STUDY
ON
THE PROJECT
FOR
CONSTRUCTION OF RAILWAY FLY-OVER
IN ULAANBAATAR CITY
IN MONGOLIA
TABLE OF CONTENTS
Preface
Letter of Transmittal
Summary
Table of Contents
Location Map/Perspective
List of Figures and Tables
Abbreviations
-i-
2-4 Project Operation Plan ...................................................................................................2-42
2-5 Project Cost Estimation..................................................................................................2-44
2-5-1 Initial Cost Estimation .......................................................................................2-44
2-5-2 Operation and Maintenance Cost .......................................................................2-44
2-6 Other Relevant Issues ....................................................................................................2-46
[APPENDICES]
- ii -
PERSPECTIVE
List of Figures
The study “the Master Plan Study on Improvement and Rehabilitation of Road Network in Ulaanbaatar”
was conducted by JICA in 1999 to formulate the master plan to improve the road network and traffic
situation. It was concluded by the JICA study that, in addition to the two (2) existing flyovers, a new
railway flyover is required, as a part of the Middle Ring Road in the aspect of forming efficient road
network and sustaining socio-economic activities. However the Mongolian side recognized certain
difficulties in constructing a new railway flyover, especially, from the technical and financial viewpoints
using their own funds. Under such circumstances, the Government of Mongolia (hereinafter referred to as
“the GOM”), in June 2005, requested the Government of Japan (hereinafter referred to as “the GOJ”) to
implement the construction of the railway flyover project (hereinafter referred to as “the Project”) under the
Japanese Grant Aid Program.
In response to the application for Japanese Grant Aid, JICA dispatched a preliminary study team to
Mongolia on three occasions between February 2007 through and November 2007, to conduct site surveys
and hold discussions with the Mongolian side. Accordingly, the following points have been confirmed:
1. The Project, which will connect the northern and southern areas of Ulaanbaatar City, is urgently
required to secure safe and reliable traffic.
2. The through traveled lane of the new railway flyover will be 4 lane to accommodate the traffic
demand which is presently large enough to justify the construction of a 4 lane road.
3. The request of the Mongolian side to procure equipment for construction and maintenance of the
Project is set aside because necessity remains low.
4. The proposed location of the flyover is justified through the comparison of alternatives.
5. No involuntary relocation of project affected persons is found, while it is necessary to acquire land for
the Project.
On the basis of the Preliminary Design Survey results, JICA decided to conduct a Basic Design Study for
the Project (hereinafter referred to as "the Study") and dispatched the study team to Mongolia from March
20, 2008 through May 6, 2008. The study team held discussions with the officials concerned of the GOM to
confirm the contents of request, and conducted a field study with reference to natural conditions, traffic
situation, procurement condition of construction material and equipment.
After deliberations in Japan on the basic design and the results of the field study in Mongolia, JICA
dispatched the Basic Design Study Team again to Mongolia, from October 30, 2008 to November 6, 2008
to explain the draft report after conducting studies extended to engineering design, project implementation
plan, project cost estimates and so forth. The Mongolian side had consented to the contents of the Draft
Report, including the undertakings that should be done without reservation by and under the responsibility
of the GOM through a series of discussion.
1-1
CHAPTER 2 CONTENTS OF THE PROJECT
As can be seen in Table 2-1-1, the original request of the GOM was for a 2-lane road. However,
during the series of discussions in the preliminary study stage, the Mongolian side strongly requested
the Japanese side to revise this into 4-lane in order to ensure traffic safety on the approach roads, as
well as at merging/diverging points of access to Narny Zam. The results of the Study summarized in
Table 2-1-1, therefore, comprise the scope of work for the portion of the Project that will be
undertaken with Japanese Grant Aid based on such major findings as traffic demand forecast, study on
practicability and construction economy, and comparison of bridge type alternatives.
2-1
2-2 BASIC DESIGN OF THE REQUESTED JAPANESE ASSISTANCE
2-2
requested in the preliminary study stage. Accordingly, the necessary widening of Engels
Street from 2-lane to 4-lane and the improvement of Ikh Toyruu Street shall be carried
out concurrently without reservation by and under the responsibility of the Mongolian
side. Therefore, the basic plan of the Project has been formulated based on the condition
that the above works will be implemented without delay.
2-3
(5) Road Operation and Maintenance
UBZZ which is the implementing agency for road maintenance under the Ulaanbaatar City
Government has much experience on road pavement work but less experience on systematic
bridge maintenance. Hence the type of bridge which requires simple maintenance has been
selected while it will be necessary for UBZZ to develop its capacity on bridge maintenance
work.
Table 2-2-1 Traffic Demand Forecast at the 2007 Level on Railway Flyover (PCU/day)
A: Traffic Before Flyover B: Traffic After Flyover B/A
Gurvaljin Bridge 21,500 20,400 95%
Peace Bridge 48,200 37,900 79%
Railway Flyover 0 25,600 -
Ikh Toyruu 31,100 33,900 109%
Engels Street 3,000 16,800 560%
Narny Zam, East 56,300 55,100 98%
Narny Zam, West 29,100 29,600 102%
2-4
( PCU / Day )
a) Maximum Grade
The site survey has revealed that the road sections having problems due to steep
slopes are Sansar Tunnel (6.4%) and Chingunjav Street (5.8%), while the roads
having lesser problems are Khusgol Street in front of Geser Temple (5.1%), East
Cross on Ikh Toyruu (5.0%), Ard Ayush Avenue (4.9%), Amarsanaa Street (4.0%),
Gurvaljin Bridge (4.0%), and Peace Bridge (3.7%).
Based on the above, the maximum grade of 5% shall be set for approach roads,
considering the risks against climbing performance on slippery road in winter season
due to frozen surface and the high accident rate on steep slopes.
2-5
b) High Visibility with Sufficient Sight Distance at Intersection
The abutment in the vicinity of Narny Zam shall be set 100 meters away from Narny
Zam to secure sufficient sight distance, and the multi pillar type shall be adopted for
the pier beside Narny Zam to improve visibility.
The former is warranted by the reason that it is necessary to keep sufficient sight
distance for traffic safety where roads for channelization run parallel to the railway
flyover and approach to the intersection with Narny Zam, while the latter is justified
by the fact that predominant directional traffic movement occurs between Ikh Toyruu
and Narny Zam (East Side) and the multi pillar pier type will secure high visibility at
the intersections.
2) Underground Utilities
Hot-water main pipes (φ500 x 2) exist 1.0 m deep beneath former bus terminal running
north-southward along Ikh Toyruu. The pipes are covered with heating insulator of
asbestos and splash prevention of asbestos is rather difficult in Mongolia provided that
relocation of pipe requires dismantle and/or removal of heating insulator.
Horizontal alignment is set to avert the hot water pipes, and location of pier and
abutment is selected taking into account that pipe relocation requires another budget
allocation and takes time to adversely affect the project implementation schedule.
It was confirmed that the affected utilities would be relocated under the responsibility of
the Mongolian side prior to the commencement of flyover construction work.
2-6
Table 2-2-2 Location of Pier and Erection Method
2-7
4) Bridge Design Approach
Bridge planning has been made by referring to the results of the survey on
structural soundness of existing bridges and the lessons learned from actual
practices.
i) Construction Economy
Since the railway flyover consists of six (6) spans and the joints are apt to
suffer damage, the continuous steel bridge type has been selected to minimize
not only the construction cost due to the shorter construction period but also
the maintenance cost by eliminating the weak points vulnerable to structural
damage
ii) Practicability
Frigid weather conditions with daily average temperature below 0°C last for
five months from November through March at the project site. It is, therefore,
important to increase work efficiency by applying the appropriate construction
method that would enable full performance of weather-free works, e.g.,
manufacturing of steel structures and pre-casting of concrete products.
However, bridge surfacing and asphalt paving works for which site works are
indispensable and sound quality control must be employed should be finished
by the middle of September.
2-8
causing frost damage, since the project site is located in the central business
district with heavy traffic.
v) Durability
The Steel-Concrete Composite Deck Slab Type is proposed to secure high
durability. High durability and performance could be secured by i) arranging
proper girder position against wheel track, ii) selecting an expansion joint that
would minimize sliding displacement, and iii) adopting quality paint to
optimize life-cycle cost.
a) Reliable Transportation
Construction planning shall be made considering i) importance of maintaining the
existing traffic at both railway and road and ii) practicability of a reliable
construction method. In case construction materials and equipment are transported
by railway through China, it will be necessary to transship them at the Zamin Uud
Station in Mongolia due to the difference in railway gauges (Mongolia: 1,520mm;
China: 1,435 mm). Through the study, it has been confirmed that all necessary
materials and equipment could be transported without delay. The Steel I Girder (4
Beam) could be selected on condition that neither problem nor risk has been
confirmed regarding transportation and transshipment.
Cement concrete placing shall be done at site within four (4) months, from the
middle of May to the middle of September. Therefore, construction planning has
to be made on condition that cement concrete placing is not in the critical path by
setting the optimum number of formworks together with their appropriate recycle
to meet volume requirements.
2-9
Furthermore, it is necessary that bridge surfacing and asphalt paving works shall
be completed by the middle of September in case the actual project
implementation plan is made.
2-10
• Secure the entrance to keep the way
Consideration on
Landownership/ for guest who is going to the Checking of
commercial building Supervision of
3 Water Concession/ building. Construction ―
near the intersection of Implementation
Commonage • Cleaning of site in front of the Plan
Narny Zam
commercial building.
• Accident on the • Pre-meeting with Railwa Authority
railway during and placing strict security control
construction shall be undertaken.
• damage at • Confirmation of relocation plan of Checking of
Casualty/ Supervision of
4 underground under ground utilities. Construction ―
Infection Implementation
utilities • To ensure the health and security Plan
• Increasing of control by the Contractor
infections in works • Instruction and education regarding
for the construction the infection to workers
• Multi pillar type pier has been
Trimming of existing selected to minimize occupied space Checking of
Beings/
5 tees due to by structure. Construction ― ―
Biogeocenosis
construction of pier. • To hold the meeting with Ulaanbaatar Plan
City to induce new tree plant.
6 Landscape Change of landscape • Securing high visibility in urban area Discussion
due to new bridge by adopting Steel Multi-pile Pier with
• Lessening oppression stemmed from Ulaanbaatar
high embankment by adopting lower city
― ―
abutment
• Selecting optimum color of
superstructure to harmonize with
urban landscape
7 Atmospheric Air contamination by • Proper operation of vehicles for Checking of Supervision of
Contamination exhausted gas from construction works Construction Implementation
construction machine • Maintenance and inspection of Plan
vehicles for construction works ―
• Alleviating adverse impacts brought
by fugitive dust by operation of water
sprinkler trucks
8 Water Waste water arising • Discharge waste water into existing Checking of Supervision of
Contamination from construction site. drainage after proper treatment Construction Implementation
9 Soil Infiltrate of waste • To construct a retention facility for Plan ―
Contamination water arising from oil and fuel for exclusive use.
construction site
10 Waste • Disposal of • Disposing construction wastes to Checking of Supervision of
construction waste designated places Construction Implementation
―
• Human waste arise • Setting of toilet and management of Plan
from workers. waste dumping.
11 Noise and Noise and Vibration • Restricting working hours at night Checking of Supervision of
Vibration arising from • Utilizing oil pressure equipment or Construction Implementation
―
construction non-vibration glove-hammer for Plan
equipment excavation of cast-in-place piles
12 Smell Exhausted gas from • Proper operation of vehicles for Checking of Supervision of
Construction construction works Construction Implementation
―
Equipment • Periodic maintenance and inspection Plan
of vehicles for construction works
13 Traffic Accident • Accident risk on • Prior consultation with railway Checking of Supervision of
heavy vehicle for authority and traffic police Construction Implementation
construction • Proper arrangement of guard position Plan ―
• Accident risk on • Prior notice to road and railway users
girder erection by public relations
2-11
2-2-2 Basic Plan
(1) General
b) Geometric Design
Road planning shall comply with the applicable Mongolian standard, with
supplementary application of Japanese standard on aspects that the Mongolian
standard does not refer or deemed to be insufficient.
2-12
c) Design Standard for Bridges
The following standards are deemed applicable for the Project:
i) Design Load
• Live Load: Type-B (Specification for Highway Bridges, Japan Road Association)
• Temperature Variation: +40~-40°C
• Seismic horizontal coefficient: Kh=0.1 for allowable stress analysis
• Earth Pressure: Coulomb Theory
ii) Materials
2-13