Classification: Confidential
Department Product Category Description DOCUMENT NO.
Heating Technical
Services CAT- B I&C Checklist for VTCY HTGPP23VTCY05
1 Name Plate Details
a Year
b Model
c Sl. No
d Fuel
2 Supply Voltage Details
a RY:YB:RB
b RN:YN:BN
c EN
3 Motor details
a ID Fan
b FD fan
c TF pump 1 & 2
d FD 2 Fan
4 Thermic Fluid Parameters
a Density @280 deg C
b Acidity
c Flash Point
d Fire Point
e Colour
f Volume (Heater+Pipeline)
5 Installation & Commissioning Checkpoints
1 Check foundation grouting of all componenets as per drawing.
2 Check tightness of all Instrumnet connection
3 Check DAE tank height as per NPSH requiremnet of pump & TF pipeline height
4 Check strainers in TF pipeline
5 Check platform must be free from coil, support should not be welded to coil
6 Flush TF pipeline
Perform pneumatic test for TF Pipeline & Heater at 6 bar pressure & note pr. drop at 1 hr interval, Bypass DAE
7 tank during Pneumatic test.
8 Check condition of refractory inside furnace & doors
9 Check if melboard is present in between refractory bricks.
10 Check bed nozzle height from casting, holes should be clear for BB units.
11 Check grate bar installation for SG units & below refractory as per drawing
12 Check TF pump pipeline should be installed with proper support & load is not on pump.
13 Cross check chimney top dia & height as per norms
14 Check ducting size as per P&I.
15 Check shed availibility
16 Check TF Pump alignment, perform clod & hot alignment
17 Check density of fuel available.
18 Check Insulation thickjness of ducting & pipeline as per P&I.
19 Check Soot Blower pneumatic line connection & guide operator for use.
Classification: Confidential
20 Check separate earthing availability at site for power & instrument earth.
21 Check Bearing greasing before ID fan & Gear oil in Gear Boxes as per recommendation prior to trial
22 Check alignment of ID fan pulley with motor pulley before starting ID Fan.
23 Check size of Incomer cable
24 Check Earthing of panel & motor insulation
25 Check Overload relay
26 Check current taken by Blower & Pump motors
27 Check the sequence of operation of Fans as per drawing.
28 Check mounting & position of all instruments as per P&I.
29 Programming of TIC as per drawing
31 Check pump flow from curve w.r.t power & NPSH
32 check pressure drop across coil & DP switch function
33 Check body temperature of Heater
6 Flue Gas Properties
a Oxygen
b CO2
c CO
d Temperature
e Draft
7 Operation Parameters
a TF Pump current
b ID Fan current
c Blower current
d TF Outlet Temp / High Set Point
e TF Inlet Temp / High Set Point
f Flue Gas Outlet Temp / High Set Point
g TF Flow (as per flow meter/ curve)
h Pressure Drop across APH
i Pressure drop across PCE
j Unit load (MKcal/Hr)
k Fuel Consumed
l Efficiency
Customer's Name
Address
Engineer's Name
Date of Visit
Release Date Rev Changes Prepared By Approved By
01-Mar-24 0 First Release (VTCY) Pranav Puneet Prabhakar Kumar