Sdvds
Sdvds
1.6. Long wall and short wall method: This method is also called as separate or
individual wall method. This is simple and it gives accurate values.
The following procedure is adopted.
1. The dimensions of long wall and short wall should be taken separately.
2. Irrespective of its lengths, the wall which is taken first is long wall and the wall which is taken
next is the short wall.
3. The centre line of the wall of the building is considered for determining the centre to centre
line length of long walls and short walls.
4. The centre to centre length of long walls or short walls is obtained by adding half the width of
the wall to the internal length to long wall on both sides and deduction for short walls.
5. Centre to centre length of long wall = internal length of long wall + ½ width of the wall.
6. Centre to centre length of short wall = internal length of short wall + ½ width of the wall.
7. To determine the lengths of different quantities such as earthwork, c.c. bed in foundation, R.R.
Masonry etc, length of long wall = centre to centre length of long wall + width, the width is
the respective width of the item in consideration.
8. Similarly length of the short wall = centre to centre length of the short wall – width,
where the width is the respective width of the item such as earthwork, c.c. bed etc.
1.7. Centre line method: In the centre line method, the sum of all the centre line lengths of long
walls and short walls are added to get the total centre line length. At the junctions of two walls,
the length is present in both of the walls. Hence half of the length of that width is to be subtracted
from the total centre line length.
Length = Total centre line length – ½ width x number of junctions.
UNIT – II
Estimation Costing & Valuation
Earthwork for Roads and Canals
Course objectives:
1. Learn calculating road works quantities and canal work quantities.
Syllabus:
Quantity and Cost estimation of road. Quantiy and cost estimation of canal
Learning Outcomes:
Students will be able to
Evaluate road work quantities
Quantity=
=
Fully Banking:
The quantity of excavation or banking can be computed by using various mensuration techniques
out of which three are given below:
1. Mid section Area Method,
3. Prismoidal Method.
Note: Use of tabular statement is advocated for calculation of earth work using any of the three
methods.
1. Mid section Area Method
In this method, the mean depth is to be calculated first by averaging the depth of two consecutive
sections, From the mean depth, the area of the midsection is to be worked out and the volume of
earthwork to be computed by multiplying the area of midsection by the distance between the two
original sections.
Volume of earthwork = Am x L
Where Am = area of midsection and
L = length of distance between two consecutive sections.
We get,
Am = Area of midsection + area of two sides = Bdm + Sdm2
Therefore, V = (Bdm + Sdm2) x L
Table: Mid section Area Method
Mean Quantity
Area of Area Total Length
Stations Depth depth (Bd+ Sd2)*L
Central of sectional B/w
or or or
Portion sides area stations
Chainage Height Height Embankment Cutting
B*d S*d2 Bd+Sd2 L
(d)
Trapezoidal Method
Considering a number of consecutive sections, having areas Al, A2, . . . , An-1, An.
Therefore, the total volume of earthwork = (L/2) (Al + 2A2 + 2A3 + . . . +2An-1 + An)
3. Prismoidal Method
From mensuration, volume of a prism having end faces that are in parallel planes
V = (L/6) (A1+A2+4Am)
Where A1 and 42 are the cross-sectional areas at the ends of a portion of the embankment or
cutting of length L and A, is the mid-sectional area.
UNIT-III
Estimation Costing & Valuation
Rate Analysis
Course Objectives:
• Understand the different specifications for civil works.
• Appreciate rate Analysis, contracts and valuation.
Syllabus:
Rate Analysis
Specifications, Purpose and method of writing specifications; General specifications. Detailed
Specifications for Brick work; R.C.C; Plastering; Mosaic Flooring; [Link] Masonary
Analysis of Rates:
Task or out – turn work; Labour and materials required for different works; Rates of materials
and labour; Preparing analysis of rates for the following items of work: I) Concrete ii) RCC
Works iii) Brick work in foundation and super structure iv) Plastering v) CC flooring vi) White
washing.
Learning Outcomes:
Students will be able to
• calculate rate analysis and prepare valuation reports for roads and buildings.
Rate Analysis
To estimate the cost of the building, the quantities of various items of work are calculated from
the drawings. The unit rates of various items of work are calculated from the specifications of the
various types of materials. The rates are calculated as per the rates in the standard schedule of
rates. The unit rates of various items of work increase considerably with the specifications. The
specifications indicate the quality of the work while the drawings are used for the quality of the
work.
3.0 Importance of Specifications
Specification specifies or describes thre nature and the class of work, materials to be used in the
the work, workmanship etc., and is very important for execution of work. The cost of a work
much depends on execution of the work. From the study of specifications one can understand the
nature of that work and what the work shall be. Drawings do not furnish the details of different
items of work, the quantity of materials, proportion of mortar and workmanship which are
described in specifications. Thus the combination of drawing and specifications form important
parts of contract documents.
[Link] of Specifcations:
Specifications are of two types.
1) General specifications
2) Detailed specification
3.1.1. Generl Specifications:
It gives the nature and class of the work and materials in general terms, to be used in the various
parts of work, from foundation to super structure. It is a short description of different parts of
work , specifying materials, proportions, quantities etc. It gives the general idea of whole work or
structure and useful for preparing the estimate.
3.1.2. Detailed specifications : Detailed specifications are written to express the requirements
clearly in a concise form avoiding repetition and ambiguity. The detailed specifications for
various items of work are as follows.
[Link]. Earthwork excavation of foundation
The following specifications shall be followed in the earthwork in excavations in foundations.
1. Foundation trench shall be dug to the exact width and depth of foundation.
2. Excavated earth shall not be placed within 1 m. of the edge of the foundation.
3. The bottom of the trenches shall be perfectly leveled both longitudinally and transversely.
4. If water accumulates in the trench, it should be pumped out. Care should be taken to prevent
water from entering the trench.
5. If rocks and boulders are found during excavation, they should be removed and the bed of the
trench should be leveled and consolidated.
6. Foundation concrete should be laid only after the inspection and approval by the Engineer in
charge.
[Link] Cement concrete in foundation ([Link])
The following specifications should be followed in cement concrete in foundation.
1. Course aggregate should be of hard broken stone, free from dust, dirt and foreign matter.
2. Fine aggregate shall be of coarse sand, consisting of hard, sharp and angular grains and shall
pass through screen of 5 mm. square mesh.
3. Sand should be free from dust, dirt and organic matters.
4. Water shall be clean and free from alkaline and acid matter.
5. Mixing should be done on a masonry platform or sheet iron tray in hand mixing.
6. Coarse aggregate and sand should be mixed by volume and cement by weight.
[Link] Random rubble masonry
The following specifications should be followed in random rubble masonry
1. The stones should be sound, hard and durable. Stones with rounded surface shall not be used.
2. No stone shall be less than 15 cm. in size.
3. Bond stones should be provided at every 1 m. length.
4. Cement mortar 1:3 to 1:6 shall be provided.
5. The joints in the stone masonry shall not be thicker than 2 cm.
6. The masonry shall be watered for at least 10 days.
[Link] Brick masonry
The following specifications should be followed in brick masonry first class
1. Bricks of standard size, copper red color, regular in shape, having sharp square edges should be
used.
2. The bricks should not absorb more than 20% of water when immersed in water for 24 hours.
3. The mortar used in brick masonry shall be 1:3 to 1:6.
4. The bricks shall be well bonded and laid in English bond unless otherwise specified.
5. Mortar joints shall not exceed 6 mm. in thickness and the joints shall be fully flushed with
mortar.
6. The bricks should be soaked in water before use in masonry.
7. The brick masonry shall be watered for at least 10 days.
[Link]. Plastering
The following specifications should be followed in plastering
1. The materials of mortar, cement and sand used in plastering should be as per specifications.
2. The joints of the brickwork shall be raked for a depth of 18 mm. on the surface.
3. Ceiling plastering should be completed before the start of wall plastering.
4. The thickness of the plastering should not be less than 12 mm. for internal plastering and 20
mm. for external plastering.
5. The plastering work shall be checked for horizontality with a straight edge and for verticality
with a plumb bob.
6. Any defective plastering shall be cut in rectangular shape and replaced.
7. The plastering should be watered for at least 10 days.
3.2. Task or Out-turn work:
The capacity of doing work by an artisan or skilled labor in the form of quantity of work per day
is known as the task-work or out-turn of the labor.
The following may be taken as the approximate quantity of work or out-turn or task for an
average artisan per day.
[Link] Particulars of item Quantity
1 Brickwork in lime or cement mortar in foundation 1.25 cu.m
2 Brickwork in lime or cement mortar in super structure 1.00 cu.m
3 Brickwork in mud mortar in foundation 1.50 cu.m
4 Brickwork in mud mortar in super structure 1.25 cu.m
5 Brick in cement or lime mortar in arches 0.55 cu.m
6 Brick in cement or lime mortar in jack arches 0.55 cu.m
7 Half brick wall in partition 5.00 sq.m
8 Coursed rubble stone masonry in lime or cement mortar 0.80 cu.m
including dressing
9 Random rubble stone masonry in lime or cement mortar 1.00 cu.m
10 Ashlar masonry in lime or cement mortar 0.40 cu.m
11 Stone arch work 0.40 cu.m
12 Lime concrete in the foundation or floor 8.50 cu.m
13 Lime concrete in roof terracing 6.00 cu.m
14 Cement Concrete [Link] 5.00 cu.m
15 R.B work 1.00 cu.m
16 R.C.C work 3.00 cu.m
17 12mm plastering with cement or lime mortar 8.00 sq.m
18 Pointing with cement or lime mortar 10.00 sq.m
19 White washing or colour washing three coats 70.00 sq.m
20 White washing or colour washing one coat 200.00 sq.m
21 Painting varnishing doors or windows one coat 25.00 sq.m
22 Coal tarring or solignum painting one coat 35.00 sq.m
23 Painting large surface one coat 35.00 sq.m
24 Distempering one coat 35.00 sq.m
25 2.5cm cc floor 7.50 sq.m
26 Flagstone floor laying with lime or cement mortar 10..00 sq.m
excluding L.C.
27 Terrazo floor 6mm thick mosaic work 2 cm thick cement 5.00 sq.m
concrete([Link])
28 Brick on edge in floor lime or cement mortar excluding 7.00 sq.m
L.C
29 Brick flat floor as in above 8.00 sq.m
30 Timber framing sal or teak wood 0.07 cu.m
31 Timber framing country wood 0.15 cu.m
32 Door and window shutters paneled or glazed 0.15 sq.m
33 Door and window shutters battned 0.80 sq.m
34 Sawing hard wood 4.00 sq.m
35 Sawing of soft wood 6.00 sq.m
36 Single Allahabad tiling 6.00 sq.m
37 Double Allahabad tiling 4.00 sq.m
38 Breaking of brick ballast 40mm gauge 0.75 cu.m
39 Breaking of brick ballast 25mm gauge 0.55 cu.m
40 Breaking of stone ballast 40mm gauge 0.40 cu.m
41 Breaking of stone ballast 25mm gauge 0.25 cu.m
42 Ashlar stone dressing 0.70 cu.m
43 Flagstone dressing 1.50 sq.m
44 Earthwork in excavation in ordinary soil 3.00 cu.m
45 Earthwork in excavation in hard soil 2.00 cu.m
46 Excavation in rock 1.00 cu.m
47 Sand filling in plinth 4.00 cu.m
48 Number of bricks laid by a mason in brick work upto a 600 bricks
height of 3m
3.3. Preparation of unit rates for different works
3.3.1 Cement Concrete:
The sum of total quantities of materials for cement concrete should 15.2 cu.m for every 10cu.m
of concrete.
Based on the proportion of the materials given each material quantity is determined.
I class brick work in Foundation and plinth with 20x10x10 cm brick 1:6 cement sand
mortar- unit 1cu.m- Take 10 cu.m
Particulars Quantity or No.s Rate per unit Cost
(Rs.) (Rs)
Materials
Brick I-class
Sand
Cement
Labour
Mistri 1/2 no.
Mason 7 nos
Mazdoor 7 nos
Boy or woman coolie 7 nos
Bhisthi (including 2 nos
curing)
Sundries T. and P. etc. Lump sum
Total cost of materials and labour
Add 1.5% of water charges
Add 10% contactor profit
Grand Total
3.3.4. Plastering:
To determine the volume of materials required for plastering, the area is multiplied with thickness
and it may be increased by 30% for 12mm plastering and 20% for 20 mm plastering for wet
mortar. Further to obtain the dry mortar they should be multiplied with 1.25 to get interms of dry
mortar.
12mm Plastering 1:6 unit 1 sq.m. Take- 100 sq.m
Particulars Quantity or No.s Rate per unit Cost
(Rs.) (Rs)
Materials
Sand
Cement
Labour
Mistri no.
Mason 10 nos
Mazdoor including 15 nos
raking of joints
Bhisthi (including 3/4 nos
curing)
Scaffolding, Sundries Lump sum
T. and P. etc.
Total cost of materials and labour
Add 1.5% of water charges
Add 10% contactor profit
Grand Total
3.3.5 White washing
White washing one coat- unit 1 sq.m. Take 100sq.m
Particulars Quantity or No.s Rate per unit Cost
(Rs.) (Rs)
Materials
White lime unslaked
Surkhi (or sand)
Glue Powder
Labour
White washer no.
Boy Coolie 2/3 nos
Sundries T. and P. etc. Lump sum
Total cost of materials and labour
Add 1.5% of water charges
Add 10% contactor profit
Grand Total
3.3.6 C.C. Flooring
2.5 cm cement concrete floor [Link] unit 1 sq.m. Take- 100 sq.m
Particulars Quantity or No.s Rate per unit Cost
(Rs.) (Rs)
Materials
Coarse Aggergate of
20mm
Sand
Cement
Cement for surface
finishing
Labour
Mistri 3/4 no.
Mason 10 nos
Mazdoor 5 nos
Boy or woman coolie 5 nos
Bhisthi (including 2 nos
curing)
Forms etc (according Lump sum
to requirement)
Sundries T. and P. etc. Lump sum
Total cost of materials and labour
Add 1.5% of water charges
Add 10% contactor profit
Grand Total
UNIT-IV
Bar bending schedule (or schedule of bars) is a list of reinforcement bars in a given RCC work
item, and is presented in a tabular form for easy visual reference. This table summarizes all the
needed particulars of bars – diameter, shape of bending, length of each bent and straight portions,
angles of bending, total length of each bar, and the number of each type of bar. This information
is a great help in preparing an estimate of quantities.
Figure 1 depicts the shape and proportions of hooks and bends in the reinforcement bars –
these are standard proportions that are adhered to:
(a) Length of one hook = (4d) + [(4d+ d)] – where, (4d+ d ) refers to the curved portion = 9d.
(b) The additional length (la) that is introduced in the simple, straight end-to-end length of a
reinforcement bar due to being bent up at say 30o to 60o, but it is generally 45 o) = l1 – l2 = la
2 45o 0.42D
3 60o 0.58D
General guidelines to be followed in preparing BBS:
The bars should be grouped together for each structural unit, e.g. beam, column, etc.
In a building structure, the bars should be listed floor by floor
For cutting and bending purposes schedules should be provided as separate A4 sheets and
not as part of the detailed reinforcement drawings.
The form of bar and fabric schedule and the shapes of bar used should be in accordance
with BS 8666.
It is preferable that bars should be listed in the schedule in numerical order.
It is essential that the bar mark reference on the label attached to a bundle of bars refers
uniquely to a particular group or set of bars of defined length, size, shape and type used on the
job.
This is imperative as a bar mark reference can then point to a class of bar characteristics.
Also, this helps steel fixers and laborers keep track of the type and number of bars needed to
complete a certain work.
Sl. No Dia. Of the bar Shape of the Bar Length of the Total length of
Hook bar
1
2
3
4
5
2
Unit-5
Types of contracts:
Lump Sum Contract.
In Lump-Sum Contract the contractor undertakes the execution or construction of a specific work
with all its contingencies, to complete it in all respects within specified time for a fixed amount.
The detailed specification of all items of works pertaining to the whole work, plans and detailed
drawings, and deposit of 10% security money, penalty, progress and other conditions of contract
are included in the contract agreement. The general specification and descriptions of different
part of the building with dimensions where required are included. The quantities or schedule of
different items of work are not provided, the contractor shall have to complete the work as per
plan and specification, within the contract fixed sum, within a fixed time irrespective of qualities
of different items. On completion of the work no detailed measurement of different items of
Work is required but the whole work is compared and checked with plans and drawings.
Lump Sum and Schedule Contract. — This is similar to lump sum contract but the schedule of
rates is also provided in the contract agreement. In this system the contractor undertakes the
execution or construction of a particular work at a fixed sum within a specified time as per plans
and the detailed specifications and conditions, and the schedule of rates for various items of work
are also provided which regulates the extra amount to be paid or deducted for any additions and
alteration. In this case also no measurement of various items of work involved in the original
work is required, but measurement of extra items only shall have to be taken. The original work
shall however be checked and compared, other conditions of contract are included in the contract
agreement.
Schedule Contract or Item Rate Contract — In schedule contract, the contractor undertakes
the execution or construction of a work on the item rate basis. The amount the contractor is to
receive depends upon the quantities of various items of work actually done. The contract
agreement includes quantities, rates and amounts for various items of work and the total amount
of contract (Bill of quantities with rate, amount and total amount), plans and detailed drawings,
detailed specifications and deposit Of 10% security money; penalty, progress, date of completion
and other conditions of contract. The payment to the contractor is made by detailed measurement
of different items of works actually don by the contractor. The system is used for all works,
Item rate contract may also be a percentage above or below the printed schedule of rates of the
department. Documents of contract or agreement are same as given in page 696 under, contract
document.
Labour Contract.
In labour contract the contractor undertakes contract for the labour portion. All materials for the
construction are arranged and supplied at the site of work by the department or owner, the labour
contractor engages labour and gets the work done according to specifications. The contract is on
item rate basis for labour portion only and contractor is paid for the quantities of work done on
measurement of the different items of work at the stipulated rate in the contract agreement.
Materials for scaffolding, centering and stuttering and other similar materials are supplied by the
department 'or owner; contractor may also use his own materials for scaffolding, centering and
shuttering, etc., if provided in the agreement. Contractor uses his own fools for working, but
plants and machineries are arranged by the department Or owner. An agreement with all
conditions of contract, rates, bill of quantities, etc., is prepared before the work is given out to the
contractor. This system of contract is not generally adopted in the Government department.
Private buildings are however constructed by labour contract system-Which is less troublesome.
Cost plus percentage contract
In this system contractor is given certain percentage over the actual cost of the construction as
his profit. Contractor arranges materials and labour at his cost and keeps proper account and he is
paid by the department or owner the whole cost together with certain percentage, say 10% as his
profit as agreed upon beforehand. An agreement is prepared with all conditions of contract in
advance. In this case proper Control in the purchase of the materials and in labour shall have to
be exercised by the department or owner.
Labour engaged through contractors. — Normally, laborer should not be engaged and paid
through contractor. In the case of emergency when labourers are not available directly and the
work is required very urgently, labourers may be employed through contractor. In such case if
possible, the quantifies of work done should be determined by measurement at the completion of
the work and the contractor paid at suitable rates on the measured quantities. But if this method is
not practicable, it is permissible to pay the contractor on the basis of number of labourers
employed day-to-day at current rates a profit or commission being included in the rate or paid
separately on lump sum or percentage basis. When payment on measured work is not possible a
record of the number of labourers employed day-to-day should be kept by the overseer incharge
and a report submitted to the Assistant Engineer or Executive Engineer to enable him to keep a
check on the work and expenditure and to deal with the contractor's claim.
CONTRACT DOCUMENT
Before the work is given out on contract an agreement or bond is prepared. The following
Documents shall be attached to the contract agreement or bond which should be duly endorsed
and sealed. Each page shall bear the signature of the contractor and the accepting authority and
all corrections shall be similarly initialled:—
Title page — Having the name of work, contract bond number, etc.
Index page — Having the contents of the agreement with page references.
Tender notice — giving brief descriptions of the work, estimated cost of work, date and time
of the tender, amount of earnest money and security money, time of completion, etc. Earnest
money, usually 2% of the estimated cost, is deposited along with tender.
Tender form- giving the bill of quantities, contractor's rates, and total cost of works, and time
for completion, progress of works, security money, penalty clause, etc.
Bill of quantities or schedule of quantities — giving quantities and rates of each item of work
and cost of each item of work and the total cost of the whole work.
Schedule of issue of materials — giving list of materials to be issued to the contractor with rates
and place of issue.
General specifications — specifying the class kind type of works in general.
Detailed specifications — of each item of work, and of-each material to be used in the work.
Drawings — complete set of drawings including plans, elevations, sections, detailed drawing,
etc. and site plan, all fully dimensioned.
Condition of contract — containing the terms and conditions of contract in detail. The
conditions specify the following
[Link] inclusive of materials, transport, labour, T. and P. all other agreements necessary for
completion of work, (2) Amount of the security money, (3) Time for completion of the work,
(4)Progress to be maintained. (5) Penalty for unsatisfactory and bad work, for failure in
maintaining progress for delay in completion .
CONDITIONS OF CONTRACT
(l) The pieceworker would carry on the work with due diligence and in workman like manner.
He would use. the best available materials subject to the approval of the Executive Engineer/
Sub-
Divisional Officer whose decision as to the rate of progress and quantity of work or material
would be final.
(2) Payments would be made after measurement of work on its completion or termination of the
agreement. In works of long duration, payments may be made at convenient intervals, usually
once a month.
(3) The Executive Engineer/ Sub-Divisional Officer may put an end to this agreement at his
option at any time.
(4) In the case of bad work or materials, the Executive Engineer/ Sub-Divisional Officer may
remove the same have them replaced, deducting the value of the work rejected and materials
removed, or the cost of replacing the same as he may think proper from any amount due or that
may become due.
(5) If the Government have to pay any/ compensation to any of the piecework under the
Workmen's Compensation Act, this amount would be recovered from the later.
(6) When the' agreement is terminated before the work is completed, the Executive Engineer/
Sub-Divisional Officer would take over the materials required for its completion if the piecework
accepts his valuation. If he does not accept the valuation, he must remove the materials from the
site
Of work within 14 days otherwise they would be removed at his expense.
Work charged Establishment. — The work charged establishment are the employees who arc.
employed direct on the work for the actual execution of a specific work or for the supervision of
the departmental labour, stores machineries, etc. Usually, work-supervisors, chaukidars, mates,
mistries. etc.; are employed as workcharged establishment. Their pay is charged direct to the
work for which provision is made in the estimate of the work by adding 2% to 3% over the
estimated amount of the work. The appointment of work charged employees is done by taking
previous sanction of the competent authority, usually of the Executive Engineer, in prescribed
form. The sanction specifies the name and designation of the employee, rate of pay, the period of
sanction and the name of the work and estimate to which chargeable. The application form for
sanction of Work charged establishment is given below
Wages of work charged establishment are prepared, drawn and paid on prescribed account form,
Form No. 29, which has seven columns containing—Item No. , Name of incumbent,
Designation, Period, Amount due, Amount paid, Dated acknowledgement of payee, and Dated
initial of officer making payment. The name of the work and No. and reference of the sanction
are written in red ink above the entries of the pay bill. The Sub-Divisional Officer or the
Assistant Engineer certifies at the bottom of the pay bill, that the persons were on duty during the
period shown against their names and each person was employed on the work and was on duty on
the work for which the appointment was sanctioned. The pay bill of the work charged
establishment is a combined pay bill and acquittance roll.
The service of the work charged establishment may be terminated at any time without giving any
notice, but usually; one month's notice is given. If the services are terminated earlier than the
period of sanction, they are not entitled for any leave, travelling and other allowance, but casual
leave and other leave may be allowed by the Executive Engineer. Actual expenses may be
allowed by the Executive Engineer for the journeys performed in the interest of work.
Tender.—Tender is an offer in writing to execute some specified work or to supply some
specified articles at certain rates, within a fixed time under certain conditions of contract and
agreement, between the contractor and the department or owner or party. The construction of
work is usually done by contract. Sealed tenders are invited and the work is usually entrusted to
the lowest tender. While inviting tenders the bill of quantities, detailed specifications, conditions
of contract and plans and drawings are supplied on payment of the requisite cost to the
contractors who tender or quote their rates.
TENDER SCHEDULE
Rs
NOTE: This schedule identifies the information that must be provided by Tenderers. If there is
insufficient space in this schedule, Tenderersmay present this information in their preferred
format or attach additional information to support this schedule.
Tender notice. — Tender for work or supply are invited by issuing tender notice in prescribed
Tender notice is posted in the notice board of the department and for major work the tender
notice in brief is also given in the newspaper . A typical tender notice inviting tenders 1 iven
below. The blank spaces are to be filled up as required
1. Sealed Tenders will be received up to A.M./P.M. on the . of by the Executive Engineer Name
of work
Division for the following work Estimated cost Rs. .
2. The work must be completely finished to the satisfaction of the Executive Engineer with in
months from the date of the order to commence the work.
3. The Tender Form with complete sets of blank forms of contract can be obtained from the office
of the Executive Engineer day (except Sunday and holiday) from per [Link] at .. A.M. to
........... every P.M. at a charge of as earnest
4. Each tender must be accompanied by a deposit of Rs. . money. Such earnest money may be of
the following forms
(1) Cash or Treasury Challan.
(2)Post office savings bank pass-book having the requisite amount in the account, pledged to the
Executive Engineer.
(iii) Deposit Receipt of State Bank or other approved Bank pledged to the Executive Engineer.
(iv) National plan loan or National Saving Certificate pleuged to the Executive Engineer.
5. The tenders will be opened at... A.M./P.M. on the ..... ...... day by the Executive Engineer or his
authorised agent at the office at
6. Power is reserved to reject any tender or all tenders without assigning any reason or given any
explanation.
7. Unless the person, whose tender has been accepted, signs the contract and deposits the security
specified within days, the earnest money deposited by him will be forfeited and the acceptance of
his tender will be withdrawn.
8. The tendered rates shall be for the complete work and shall include all quarrying charges,
royalty, testing, screening, tools and plants, carriage of materials to site, removal and changes of
rejected materials, all taxes, income-tax, sales-tax, octroi charges, materials, labour, etc.
9. The tender rates will remain valid for a period of three months from the date of opening
tenders.
10. The quantities in the bill of quantities are approximate and liable to variation or cancellation
for which contractor will not be entitled to any compensation. The quantities of any item or items
and the total cost may vary by 20% for which rates shall not be altered.
II. The rate should be quoted in the bill of quantities, legibly both in figures and words. Executive
-Division.
Earnest money.—While submitting a tender the contractor is to deposit a certain amount, about
% ofthe estimated cost, with the department, as earnest money as guarantee Of the tender. This
amount is for a check so that the contractor may not refuse to accept the work or run away when
his tender is accepted. In case the contractor refuses to take up the work his earnest money is
forfeited. Earnest money of the tenderer whose tender has not been accepted is refundable. The
amount of earnest money depends on the estimated cost of works and is as follows : Rs. 50.00 for
works up to Rs. 2,000.00,Rs. 100.00 for works above Rs. 2,000.00 Rs. 5,000.00, Rs. 200.00 for
works above Rs. 5,000.00to Rs. 10,000.00 and Rs. 100.00 for every Rs. 5,000.00 or part thereof
above Rs. 10,000.00.
Earnest money should be in cash or encashable at any time. Earnest money may be in the form
of deposit in Treasury or State Bank or other approved Bank or Government security, or Saving
Certificate or Post Office, Savings Pass-Book or cash Certificate, pledged to the Executive
Engineer
Security money. — On acceptance •of the tender, the contractor has to deposit of the tendered
amount as security money with the department which is inclusive of the earnest money already
deposited. This amount is kept as a check so that the contractor fulfils all the terms and conditions
of the contract and carries out the work satisfactorily according to the specifications and maintain
progress and completes the work in time. If the contractor fails to fulfil the terms of contract his
whole or part of the security money is forfeited by the department. The security money is
refunded to the contractor after the satisfactory completion of the whole work after a specified
time, usually after one rainy season or six months of the completion of the work. Instead of
collecting the whole of security money in one installment before starting the work, this can be
collected gradually by deducting from the running account bill of the contractor. Usually the
earnest money is taken as part of the security money and the balance amount of the security
money is collected by deduction from the running account bill of the contractor at 10% of every
running bill, up to the extent of 10 per cent of the total cost of whole work.
Measurement Book (M.B.). — The measurements of all works and supplies are recorded in The
measurement Book Form No. 23 and payment of all works and supplies are made on the basis of
measurement recorded. The measurement books are very important account records. All
measurement book are numbered serially register is maintained in the divisional office showing
the serial number of each book, the names of the sub-division or officer to whom issued, the date
of issue, the date of return and remark. A similar register is maintained in the sub-division office
showing the names of the officers, to whom issued, date of issue, date of return, etc.
No. L B D
Administrative Approval or Sanction—
For any work or project required by a department, an approval or sanction of the competent
authority of the department, with respect to the cost and work is necessary at the first instance.
The Approval authorises the engineering department to take up the work. Administrative
approval denotes the formal acceptance by the department concerned of the proposal, and after
the administrative approval is given the engineering department (P.W.D.) take up the work and
prepares detailed designs, plans an estimates and then executes the work. The engineering
department prepares approximate estimate and preliminary plans and submits to. the department
concerned for administrative approval.
Expenditure Sanction—
Expenditure sanction means the concurrence of the Government of the expenditure proposed and
represents allotment of the money to meet the expenditure. No expenditure can be incurred before
Expenditure Sanction is given. Expenditure sanction means allotment of fund or money for a
specific work and is usually, accorded by the Finance Department.
Technical Sanction—
Technical sanction means the sanction of the detailed estimate, design calculations, quantities of
works, rates and cost of the work by the competent authority of the engineering department. After
the technical sanction of the estimate is given, then only the work is taken up for construction. In
case of original work the counter signature of the local head of the department should be
Obtained in the plan and estimate before .technical sanction is accord*d by the engineering
department. The power for Technical Sanction differs from state to state. Power for Technical
Sanction in U.P.—TechnicalSanction can be given by—
(1) The Chief Engineer - Full Powers..
(2) The Superintending Engineer ... . Up to Rs. 15 lakhs
(iii) The Executive Engineer Up to Rs. 5 lakhs if the estimate is on a standard design.
Plinth Area.—Plinth area is the built up covered area of a building measured at floor level of An
orey. Plinth area is calculated by taking the external dimensions of the building at the floor level
excluding plinth offsets if any. Court-yard, open areas, balconies and cantilever projections are
not included in the Plinth area. Supported porches (other than cantilevered) are included in the
Plinth area.
The following shall be included in the Plinth All floors, area of walls at the floor level excluding
plinth offsets, if any, (h) Internal shafts for sanitary installations provided these do not exceed 2
sq m in area air condition ducts, lifts etc. (iii) The area of barsati and the area of mumty at terrace
level. (iv) Area of porches other than cantilevered.
The following shall not be included in the Plinth Area of loft, (h) Internal sanitary shafts
provided these are more than 2 sq m in area, (iil) Unenclosed balconies (iv) Towers, turrets,
domes etc. projecting above the terrace level, not forming a storey at the terrace level, (v)
Architectural bands, cornices etc. (VI) Sunshades, Vertical sun breakers or box louvers projecting
out.
Floor Area.—Floor area of a building is the total area of floor in between walls and consists of II
rooms verandahs passages corridors staircase room, entrance halls, kitchen, stores, bath floor and
latrine (W. Cs.) etc. Sills of doors and openings are not included in the Floor area. Area occupied
by walls, pillars, pilaster, and other intermediate supports are not included in the Floor area. In
short, Floor area is equal to Plinth area minus area occupied by walls.
For deduction of wall area from plinth area to obtain Floor area the area shall include—
(1) Door and other openings in the wall. (h) Intermediate pillars and supports, (iil) Pilasters along
walls exceeding 300 sq cm in area (iv) Flues which are within walls. But the following shall be
excluded from the walls area (1) Pilaster along walls not exceeding 300 sq m in area, (h) Fire
place projecting beyond the face of wall in living rooms, (3) Chulla platforms projecting beyond
the face of wall in kitchens.
The floor of each storey and different types of floor should be measured and taken separately.
The floor area of basement, mezzanines, barsaties, mumties, porches, etc. should be measured
separately.
Carpet Area — Carpet Area of building is the useful area or liveable area or lettable area. This is
the total floor area minus the Circulation area. verandahs, corridors, passages, staircase, lifts.
entrance hall. etc. and minus other non-useable areas as sanitary accommodations (Bath and
[Link].), air conditioning room etc. For office building Carpet area is the lettable area or useable
area and for residential building Carpet area is the liveable area and should exclude the kitchen.
pantry, stores and similar other room which are not used for living purposes.
The carpet area of a building for any storey shall be the floor area excluding the following :
(a) Sanitary accommodation, (b) Verandahs, (c) Corridors and passages, (d) Kitchen arid pantries,
(e) Stores in domestic buildings, (f) Entrance hall and porches, (g) Stair cases and mumties, (h)
Shafts for lifts, (i) Barsaties, (D Garages, (k) Canteens, (l) Air conditioning ducts and air
conditioning plant room.
The Carpet area of an office building may be 60% to 75% of plinth area of the building with a
target of 75%. The planners should aim to achieve a target to 75% of the plinth area. The carpet
area of residential building may be 50% to 65% of the plinth area of building with a target of
65%.
For a framed multi- storeyed building the area occupied by wall may be 5% to 10% of the plinth
area (a standard 3% for external walls and 200 for internal walls). For ordinary huilding without
frame. the area occupied by walls may be loco to 15% of the plinth area:
(d) Bridges and Culverts—Per running meter (running feet) of span depending on the roadway,
nature and depth of foundation, type of structure. etc. For small culverts approximate cost may
also be per number of culverts of different spans. Approximate cost of a bridge Of 3 spans Of 50
metre each span @ Rs. 30,090/- per running meter of span comes to 45 lakhs.
Approximate cost of bridges may also be worked out separately for sub-structure and
superstructure.
(e) Sewarage Project and water supply project—
On the basis of per head of population served. On the basis of area covered i.e., per hectare basis
(per acre basis). Approximate cost of sewerage project for a population of one lakh @ Rs. 100/-
head works
out as Rs. 100 lakhs. Approximate cost of water supply project for a population of 75000 people
@ Rs. 90/- per head comes to Rs. 67.5 lakhs.
(f) Over head water tank.—On the basis of capacity, per litre (per gallon) of tank depending on
the type of structure height of tank etc. Approximate cost Of an overhead R.C.C. water tank of
50,000 litre capacity Rs. 2.00 per litre works out as I lakh.
Plinth Area Estimate for Building-
This is prepared on the basis of plinth area o building, the rate being deducted from the cost of
similar building having similar specification, heights and construction, in the locality. Plinth area
estimate is calculated by finding the plinth area of the building and multiplying by the Plinth area
Rate. The plinth area should be calculated for the covered area by taking external dimension
ofthe building at the floor level. Courtyard and other open area should not be included in the
plinth area. Plinth area Estimate is only approximate, and is a preliminary estimate, to know the
approximate cost before hand. If the plan of the building is not ready or available, at the
beginning just prepare a proposal, floor area of rooms, etc. may be determined front the
requirement and 30 to 40 per cent ofme total area thus found may be added for walls, circulation
and waste to get the approximate total plinth area which multiplied by the plinth area rate gives
the approximate cost of the building. The approximate cost of a building having plinth area of
100 sqm@ Rs. 900/ - per sq m works out as Rs. 90,000/-
For storeyed building, the Plinth Area Estimate is prepared for each storey separately.
Revised Estimate—
Revised Estimate is a detailed estimate and is required to be prepared under any one of the
following circumstances :
(1) When the original sanctioned estimate is exceeded or likely to exceed by more than 5%
(2) When the expenditure on a work exceeds or likely to exceed the amount of administrative
sanction by more than 10%.
(3) When there are material deviation from the original proposal, even though the cost may be
met from the sanctioned amount.
The revised estimate should be accompanied by a comparative statement showing the variations
of each item of works, its quantity, rate and cost under original and revised, side by side, the
excess or saving and reason for variation.
Supplementary Estimate—
Supplementary Estimate is a detailed estimate and is prepared when additional works are
required to supplement the original works, or when further development is required during the
progress of work. This is a fresh detailed estimate of the additional works in addition to the
original estimate.
UNIT-VI
VALUATIONOF BUILDINGS
Valuation—Valuation is the technique of estimating or determining the fair price or value of a such
as a building, a factory, other engineering structures of various types, land, etc. By prop valuation the
present value of a property is determined. The present value of property may be decided by its selling
price, or income or rent it may fetch. The value of property depends on its structure, life, maintenance,
location, bank interest, legal control, etc. The value also depends on supply on demand and the
purpose for which valuation is required. Cost means original cost of construction of purchase, while
value means the present value (saleable value) which may be higher or lower than the cost. A building
whole cost of construction is Rs• 50,000.00, when put for sale may fetch Rs.60,000.00 this sale prices
the value of the building. Similarly, the value may be less than the original cost.
(1) Buying orSe11ingProperty. — When it is required to buy or to sell a property, its valuation is
required. —To assess the tax of a property its valuation is required.
(2) Taxation. To assess the tax of a property its valuation is required .Taxes may be Municipal Tax'
Wealth Tax' Property Tax, etc., and all the taxes are fixed on the valuation of the property.
(3) Rent fixation. In order to determine the rent of a property, valuation is required. Rent is usually
fixed on certain percentage of the amount of valuation (6% to 10% of the valuation).
(4) Security of Loans or Mortgage. ----- When 'loans are taken against the security of the property, its
valuation is required.
(5) Compulsory acquisition. Whenever a property is acquired by law compensation is paid to the
owner. To determine the amount Of compensation valuation of the property is required.
(6) Valuation of a property is also required for Insurance, Betterment Charges, Speculations, etc.
Gross income: Gross income is the total income and includes all receipts from various sources the
outgoings and the operational and collection charges are not deducted.
Net income or Net return— This is the saving or the amounts left after deducting all small
outgoings, operational and collection expenses from the gross income or total receipt.
Outgoings. — Outgoings or the expenses which are required to be incurred to maintain the ctrevenue
of the building. The various types of outgoings are as follows :—
Taxes, —These includes Municipal Tax, Property Tax, Wealth Tax, etc., which arc to be Paid by the
owner of the property annually. These taxes are fixed on the basis of 'Annual Rental value of the
property after deduction for annual repairs, etc.
2. Repairs: The repairs to required to be carried out every year to maintain a property in fit condition,
the amount go be spent on repairs depends on the age, construction nature of the building, etc., and
usually 10 to 15 percent of the gross income or gross rent or 1 to 1 h months is allowed for repairs. For
annual repairs to 1 of the total cost of construction may also be taken.
[Link] and Collection charges: These include the expenses on Rent Collector
Chaukidar, (watchman) Liftman, Pump attendant, Sweeper, etc. About 5 to 10 per cent of the Gross
rent may be taken on these account For small building none of these may be required and be no
outgoings on these account.
4. Sinking Fund. — A certain amount of the gross rent is set aside annually as sinking fund to
accumulate the total cost of construction when the life ofthe building is over. This Annualsinkin fund
is also taken as outgoings.
5. Loss of rent. — The property may not be kept fully occupied in such a case a suitable amount
should be deducted from the gross rent under outgoings.
6. Miscellaneous. —These include electric charges for running lift, pump, for lighting common places,
and similar other charges which are to be borne by the owner.
Municipal taxes. —Municipality needs money in order to undertake and maintain public utility
services and the same is collected by imposing taxes on the property. The main utility works are roads,
drainages, water supply, etc., and the construction and maintenance. The taxes are assessed on some
percentage basis on the net income from the property and varies from to of the net income. Usually for
small houses the taxes are less and for big houses the taxes are high
Scrap value. — Scrap value is the value of dismantled materials. Fora building when the life s over at
the end of its utility period the dismantled materials as steel, bricks, timber, etc., will fetch a certain
amount which is the scrap value of the building. In the case of machine the scrap value is the value of
the metal only or the value of the dismantled parts. The scrap value of a building may be about 10 per
cent of its total cost of construction. The cost of dismantling and removal of the rubbish material is
deducted from the total receipt from the sale of the useable materials to get the scrap value
Salvage value. —It is the value at the end of the utility period without being dismantled. A machine
after the completion of its usual span of life or when it become uneconomic, may be sold and one may
purchase the same for use for some other purpose, the sale value of the machine is the salvage value. It
does not include the cost of removal, sale, etc. Normally, the scrap value, or the salvage value ofa
property or an asset has got some positive figure, but it may also be zero or negative. As for example t
scrap value or R.C.C- structure will be negative, as dismantling and removal will be costly.
Market value. — The Market value of a property is the amount which can be obtained at any
particular time from the open market if the property is put for sale. The market value will differ from
time to time according to demand and supply. The market value also changes from time to time for
various miscellaneous reasons such as changes in industry, changes on fashions, means Of transport,
cost of materials and labour, etc.
Book value. — Book value is the amount shown in the account book after allowing necessary
depreciations. The book value of a property at a particular year is the original cost minus the amount
of depreciation up to the previous year. The book value depends on the amount Of depreciation
allowed per year and will be gradually reduced year to year and at the end of the utility period of the
property the book value will be only scrap value.
Rateable value. —Rateable value is the net annual letting value of a property, which is obtained after
deducting the amount of yearly repairs from the gross income. Municipal and other taxes are charged
at a certain percentage on the rateable value of the property.
Obsolescence. --The value of property or structures become less by its becoming out of date in style,
in structure in design. etc., and this is termed as Obsolescence. An old dated building with massive
walls, arrangements of rooms not suited in present days and for similar reasons, becomes obsolete
even if 'it is maintained in a very good condition, and its value becomes less due to obsolescence. The
obsolescence may be due to the reasons such as progress in arts, changes in fashions. changes in
planning ideas, new inventions, improvements in design technique, etc, A machine of old design may
become obsolete, though it may be in good running condition and its value will be less, Thus, though
the property is physically sound, it may become functionally inadequate and its economical return
becomes less.
Annuity- Annuity is the annual periodic payments for repayments of the capital amount invested by a
party. These annual payments arc either paid at the end of the year or at the beginning of the year,
usually for a specified number of years.
If the amount of annuity is paid for a definite number of periods or years, it is known as Annuity
certain. In such cases the amount of annuity will be higher, the lesser the number of the years the
higher will be the amount and vice versa to clear up to the whole amount of capital. If the amount Of
annuity is paid at the beginning of each period of year and payments continued for definite number of
periods. it is known as Annuity due,
If the payment of annuity begins at some future date after a number of years. this is known as Deferred
Annuity,
If the payments of annuity continue for indefinite period, it is known as Perpetual Annuity.
Though annuity means annual payment, the amount of annuity may be paid by twelve monthly
instalments or quarterly or half-yearly instalments.
Capital cost. — Capital cost is the total cost of construction including land, or the original total
amount required to possess a property. It is the original cost and does not change, while value of a
property is the present cost which may bc calculated by methods of valuation.
Capitalized value. — The Capitalized value of a property is the amount of a money whose annual
interest at the highest prevailing rate of interest will be equal to the net income from the property. To
determine the capitalized value of a property it is required to know the net income from the property
and the highest prevailing rate of interest
Example. —
Capitalised value of a property fetching a net annual rent of Rs. 1,000.00 and the highest rate of
interest prevalent being 5% is as follows :
In short capitalized value is— Net annual income x Year's purchase. =Rs. 20,000.00
For the same net income if the rate of interest is 8% the capitalized value,
=1000*100/8=Rs.12,500.00
l. Rental method of valuation — In this method, the net income by way of rent is found out by
deducting all outgoings from the gross rent (See pages 621-622). A suitable rate of interest as
Prevailing in the market is assumed and year's purchase IS calculated. This net income multiplied by
P, gives the capitalized value or valuation of the property. This method is applicable only when rent IS
known or probable rent is determined by enquiries.
2. Direct comparison with the capital value. — This method may be adopted when the rental IS not
available from the property concerned, but there are evidences of sale price of properties as a whole. In
such cases the capitalized value of the property is fixed by direct comparison with capitalized)value of
similar property in the locality.
[Link] based on profit — This method of valuation is suitable for buildings like hotels,
cinemas, theatres, etc. for which the capitalized value depends on the profit. In such cases the net
annual income is worked out after deducting from the gross income all possible working expenses
outgoings, interest on the capital Invested. etc, The net profit is multiplied by YAP to get capitalized
value. In such cases the valuation may work out to be too high in comparison With the cost of
construction
4. Valuation based on cost. In this method the actual cost incurred in constructing the building or in
possessing the property is taken as basis to determine the value of property, In such cases necessary
depreciation should be allowed and the points of obsolescence should also be considered.
5. Development method of valuation— This method of valuation is used for the properties which are
in the undeveloped stage or partly developed and partly undeveloped stage. If a large place of land is
required to be divided into plots after providing for roads, parks, etc., this method of evaluation is to
be adopted. In such cases, the probable selling price of the divided plots, the area required for roads,
parks, etc., and other expenditures for development should be known.
6. Depreciation method of valuation— According to this method of valuation the building should be
divided into four parts viz. — (1) Walls, (h) Roofs, (iii) Floor and (iv) Doors and windows and the
cost of each parts should first be worked out on the present-day rates by detailed measurements. The
life of each of the four parts should then be ascertained with the help of table in page (From l,
Annexure (B) to Chapter XIII of the Financial Hand Book Volume V, (Part l)
and the depreciated value of each part is ascertained by the formula D = P ( 100-rd/100)^n
Where D is the depreciated value, P is the cost at present market rate and rd the fixed percentage of
depreciation (rate of depreciation, r stands for rate and d for depreciation) and n the number of years
the building had been constructed. The value of rd may be taken as below
Structures With 100 years life, rd= 1.0, Structures with 75 years life, rd=1.3, Structures With50 years
life, rd = 2.0, Structures with 25 years life. rd = 4.0, Structure. with 20 years life, rd= 5.0. The values
arrived at will be exclusive of cost of land, water supply, electric and sanitary, fittings, etc., and will
apply to those buildings only which have been properly maintained. If the repairs had been neglected
in the past and the present condition IS bad or dilapidated suitable deduction should be made from the
values as deducted above, for neglected repairs. The present value of land and water supply, electric
and sanitary fittings, [Link] be added to the valuation of the building to arrive at total valuation of
the property.
Cost of land— For the valuation of the whole property the cost of land should also be added to the
depreciation value of the building. The cost of land should be taken as prevalent the locality from the
recent sale transactions or from the enquiries from the property Brokers or from the Sub-Registar’s.
For Mortgage purposes, the mortgage value of a property is taken as l/' 2 to 213 of valuation or
capitalized value.
Depreciation — Depreciation is the gradual exhaustion of the usefulness of a property. This may be
defined as the decrease or loss in the value of a property due to structural deterioration use, life wear
and tear, decay and obsolescence. The value of a building or structure will be gradually reduced due to
its use, life, wear and tear, etc., and a certain percentage of the total cost may be allowed as
depreciation to determine its present value. Usually a percentage on depreciation per annum is
allowed. The general annual decrease in the value of a property is known as Annual depreciation.
Usually, the percentage rate of depreciation is less at the beginning and gradually increase during later
years.
The amount of depreciation being known, the present value of a property can be calculated after
deducting the total amount of depreciation from the original cost.
follows :—
(l) Straight line method, (2) Constant percentage method, (3) Sinking fund method and (4) Quantity
survey method. In all these methods, it is necessary to decide the economic or effective life of the
property.
(1) Straight line method — In this method it is assumed that the property loses its value by the same
amount every year. A fixed amount of the original cost is deducted every year, so that at the end of the
utility period only the scrap value is left.
=(C-S)/n
where C— original Cost, S —scrap value, n—life of the property in years and D—annual
depreciation. The book value after the number of years, say N years = original cost —N x D.
(2) Constant percentage method or Declining balance method — In this method, it is assumed that
the property will lose its value by a constant percentage of its value at the beginning of every year.
The value of the property at the end of the second year=C1 — DC2 and so on.
The value of the property or the depreciated cost at the end of the m years = C ( S/C)^m/n
The formula will fail when S = 0. When the ratio(S/C) is very small, the depreciation for the first year
will be considerable.
(3) Sinking fund method— In this method the depreciation of property is assumed to be equal
to the annual sinking fund plus the interest on the fund Tor that year, which is supposed to invested on
interest bearing investment. If A is the annual sinking fund and b, c, d', etc., represent interest on the
Sinking fund for subsequent years, and C = total original cost, then —
At the end of year Depreciation for the year Total Depreciation Book value
So on
(4) Quantity survey method — In this method the-property is studied in detail and loss in due to life,
wear and tear, decay, obsolescence, etc., worked out. Each and every step is based some logical ground
without any fixed percentage of the cost of the property. Only experienced value can work out the
amount of depreciation and present value of a property by this method.
VALUATION OF BUILDINGS
Valuation of a building depends on the type of the building, its structure and durability, on the
situation, Size, shape, frontage, width of roadways, the quality of materials used in the construction
and present-day prices of materials. This also depends on the height of the building, height of plinth,
thickness of wall, nature of floor, roof, doors, windows, etc. A building located in market area will
have higher value than a similar building in the residential area. Building in the area having sewer,
water supply and electricity will have increased value. Building on freehold land. will have higher
value than building on leasehold land. The value also depends on the demands purchase which varies
from time to time. The valuation of building mainly depends on the will fetch if let out. Usually 6%
interest per annum of the capital cost is taken as annual rent, it be more or less according to the
prevalent market rate. The valuation of building is determined on working out its cost of construction
at present-day rate and allowing a suitable depreciation. Before valuation the age of the building
should be obtained from record if available or by enquiries or from visual inspection and its future life
should be ascertained. Present-day cost may be determined by the following method:
Cost from record -Cost of construction may be determined from the estimate, from the bill of
quantities, from record at present-day rate. If the actual cost of construction is known, this may
increase or decrease according to the percentage rise or fall in the rates which may be obtained from
the P.W.D schedule of rates.
Cost by detailed measurement -If record is not available, the cost of construction may be preparing
of quantities of works by detailed measurement at site and taking the rate for each item as prevalent in
the locality or as current P.W.D. schedule of rates .All the items of works should be thoroughly
scrutinised and their detailed specifications ascertained as actually exists
Cost by plinth area basis — Determination of cost by detailed measurements and bill of quantities
is laborious and lengthy, a simple method is to calculate the cost on plinth area basis, The plinth area
of the building G measured and the present-day plinth area rate of similar building in the locality is
obtained by enquiries and then cost calculated. To fix the plinth area rate it's necessary to examine
thoroughly the different parts Of the building, the foundation, structure, floor. roof, doors and
windows, finishing. etc. If judiciously worked out the cost determined by plinth area method will be
fairly correct and sufficient for practical purpose. Cost may be calculated by cubical content method.
Determination of depreciation— After deciding the cost of the building or structure by any one of
the above method it is necessary to allow a suitable depreciation on the cost. The depreciation depends
on the ultimate use of the building, the present age of the building, nature maintenance, etc. Generally,
for the first 5 to 10 years there is little depreciation of the building or structure. The depreciation
increases with the life.
For a building whose life is considered as 8() years, if well maintained the following may be
reasonable depreciation
The balance 10% represents the net scrap value on dismantling at the end of the utility period.
Mortgage Lease
Mortgage.—An owner can borrow money against the security of his property, and for that purpose he
is required to grant an interest to the Marty advancing the loan. The loan is required to be returned in
specified time. The person who takes the loans is known as Mortgagor, and the person who advances
the loan is known as Mortgagee, and the relevant document for the mortgage transaction is known as
Mortgage deed. When the loan is fully repaid together with interest the mortgagor has got the right to
free his property from the mortgagee, and this is known as Equity of redemption. The amount of loan
will depend on the valuation of the property, usually 50 to 70 per cent of the valuation is advanced as
loan. The interest should be paid by regular instalments, and the loan also may be repaid by regular
instalments spread over the specified period of the mortgage. If the mortgagor fails to pay the
instalment of loan as per condition of the mortgage deed, the mortgagee can take over possession of
the property and sell it to recover the amount of loan, the interest and other expenses. The surplus, if
any, is paid to the mortgagor.
Fixation Of Rent
The rent of building is fixed on the basis of certain percentage of annual interest on the capital cost and
all possible annual expenditures on outgoings. The capital cost includes the cost of construction of the
building, the cost of sanitary and water supply work and the cost of electric installations and the cost
of subsequent additions and alterations if any. The cost of construction also includes the expenditures
on the following:—
(l) Raising, levelling and dressing sites, (2) Construction of compound walls, fences and gates, (3)
Storm water drains, and (4) Approach roads and other roads within the compound. Allowing a certain
prevalent percentage of interest on the capital, the return may be worked put. The capital cost divided
by the Year's purchase will give the return. If the capital cost is not known, this may be worked out by
any method of valuation. The owner expects about 2 per cent higher interest than the prevalent interest
to cover up the risk of his investment. To this net return, all possible expenditures on outgoings are
added to get gross annual rent.
Dividing the gross rent by 12, rent per month can be calculated. The rent worked out by this Procedure
is known as Standard rent, while .the actual rent of the property, may be higher or lower than this rent
depending upon the situation of the property, type of construction, demand and supply, etc. In present
day an interest of 12 per cent may be a reasonable one for investment on building, but government
allows only 6 per cent interest.
Year's purchase (Y.P.).— Year's purchase is defined as the capital sum required to be invested in order
to receive an annuity of Re. 1.00 at certain rate of interest. For 4% interest per annum, to get Rs. 4.00
it requires Rs. 100.00 to be deposited in a bank.
To get Re. 1.00 per year it will' be required to deposit 1/4 of Rs. 100.00, i.e.,100/4=Rs.25.00.
Thus, year's purchase = 100/(Rate of Interest)=1/i Where i= rate of interest in decimal, For 5%interest,
In the case of a property whose period of utility is limited to a number of years a certain amount is
required to be set aside in the form of sinking fund, to accumulate the amount of original capital cost
at the end of the utility period of the property, otherwise the owner of the property will lose both
capital and income at the end of the utility period. Hence the Year's purchase will be reduced in such a
way that income of the property will provide both for interest on the capital and for accumulation of
the sinking fund to replace the capital. In such cases, Year's purchase
1/(i+s),
where s = sinking fund to replace Re. 1.00 at the end of the given period.
Government residential buildings are planned according to the salary of the official for whom the
building is meant. Normally, Government officials pay a rent of I / 10 of their salary, therefore, the
capital investment should be on the basis of this rent, considering the rental value as 6% on the capital
cost. But due to the tremendous increase in the cost of construction the capital cost may be fixed at
100% to 150% higher.
Example 4—-Find the plinth area required for the residential accommodation for an Assistant
Engineer in the pay scale of Rs. 400.00 to 1,000.00 per month.
Normally the quarters for the Assistant Engineer should be constructed at the cost of Rs. 14,000.00
having plinth area of 93.33 sq m.
But due to the increase in the cost of construction, this may be increased by 100% and the capital cost
of construction may be fixed as Rs. 28,0(k .00 and the approximate plinth area of 93.33.