Project Quality Plan
Project Quality Plan
NAME OF WORK
Reviewed by
Approved by
TABLE OF CONTENT
1|Page
Doc. No. : 1 PROJECT QUALITY PLAN
1.1 PURPOSE:
The Purpose of this project Quality plan is to provide a document to cover the Quality
assurance and Quality control system in accordance with ISO 9001:2005, which is
implemented, for project management function, procurement, construction and
commissioning function to comply with requirement of the client contract document.
2|Page
Doc. No. : 1 PROJECT QUALITY PLAN
All Personnel engaged directly and indirectly on the contracted works much comply with
this plan (For each Department) to fulfil the needs and expectations of client and to
ensure satisfaction by providing high quality of construction and services.
is committed to ensure that all materials and process meet client contract specification
requirement by vigilant and proactive management, supervision, system and system
regularly audited and monitored to ensure they are effective, relevant and correctly
implemented.
Engineer
Contractor
Contractor No
3|Page
Doc. No. : 1 PROJECT QUALITY PLAN
Various activities, for communicating the intent and consistency of the purpose of the system
and to document the result. Elements that address measurement of system performance, client
satisfaction and improvement process are described. Agenda of cross-reference of ISO:9001
system elements with of SECPL Management system elements are provided in this section.
4.2 Purpose:
To establish and maintain the documentation quality system in orderly and
understandable manner and consistent with the requirements of ISO 9001:2015, Each basic
element of the quality system program, as defined in this quality Management plan, shall be
applied to all activities performed by SECPL and its subcontractors vendors. To ensure that
4|Page
Doc. No. : 1 PROJECT QUALITY PLAN
5|Page
Doc. No. : 1 PROJECT QUALITY PLAN
6|Page
Doc. No. : 1 PROJECT QUALITY PLAN
Ensure that all functions at the project site are appropriately staffed, trained and
managed.
Defined and monitor performance targets for the project team.
Ensuring that periodical material re verification is carried out as per the extant
procedure.
Develop WBS along with Project Construction head, plan project milestones,
determine resource requirement, propose deviations in productivity norms as per site
conditions, and prepare supplier schedules and initial project plan along with the
planning manager.
Prepare project annual/monthly/daily work plan and budgets in consultation with
project construction and contracts heads for the approval of the project manager.
Ensuring timely and accurate planning, scheduling and expediting of resources and
adherence to productivity norms
Resolve all issues and queries which are escalated by the project execution team
Provide common technical services (to all project function as required)
Monitor & report actual project performance against budgets & raise an early warning
on non-achievement of targets.
Review actual cost vs. the budget
Carrying out periodic and final material Reconciliation in coordination with
store/BBS Engineer.
Verification and clearing of sub-contractor’s bills, in coordination with the approval
of project management.
7|Page
Doc. No. : 1 PROJECT QUALITY PLAN
Inspection of field activities as per approved inspection plans, obtaining clearances for
clients/consultant and making reports, issuing NCR and closing after
corrective/preventive actions.
Certifying all the measures, procedures and works and submit a written certification
per month.
Prepare weekly records, contribute quality matters in the Monthly Progress report and
submit to GC
Arranging Training to Engineers, Supervisors and sub-contractors representative.
Co-ordinate with stores team to plan inspection (Testing of raw materials.
Implement PQP & MQR at site.
To ensure that employees working at execution site are aware of quality requirements
and provide training in best practices.
Ensuring that all SHE measures and applicable legal issues for the project are
complied with throughout the duration of the contract including implementation of
revisions.
Ensuring that SHE legislation & legal issues, guidance notes and industry standards
are available for project reference.
Maintaining records on SHE and legal issue as per procedure.
Enduring that all personnel engaged at the project receive induction training, prior to
issue of their access control passes and or allowed for their respective job allocation.
Interact with client/consultants regarding all SHE and legal issues pertaining to
project.
Advise the project management and line management in planning and organizing
preventive measures necessary for SHE and legal issues.
Co-ordinate with store and procurement team to plan and procure for SHE gadgets
/PPE’s etc.
Advise the project management and line management in planning and organizing
measures necessary for establishing safe work environment towards avoiding
accidents.
Carryout hazard identification and risk assessment of all activities and recommend
required control measures.
Investigation of incidents including lost time accidents, fatal accidents, dangerous
occurrences, near misses and occupational diseases and taking remedial measures and
furnishing reports to QMS head on the above provide training on occupational health
and safety related subjects to all in association with concerned departments.
Maintaining occupation health and safety records.
Ensure constitution of site SHE committee and carrying out periodical (at least
monthly) walk down by SHE committee to identify critical areas of deficiency and
take necessary corrective preventive actions. Ensure discussions on safety in the SHE
committee meeting and define action plan.
8|Page
Doc. No. : 1 PROJECT QUALITY PLAN
The process of understanding and working with soil and rock, underground water, site
and structural conditions, in relation to a construction project is known as
geotechnical engineering.
In their professional capacity, geotechnical engineers plan and design the structures
for buildings, roads, embankments, canals and hundreds of other constructions
projects. Beyond their construction role, the geotechnical engineer will also deal with
geological hazards like landslides, soil erosion and in some extreme conditions
earthquakes.
Subsurface investigation: the job of the geotechnical engineer essentially starts with
a collection of soil samples from the project’s intended site, using bores and test pits.
Amongst other factors, the analysis will determine the ground’s stress bearing
capability and stability.
Field test: after research into soil quality and stress-bearing factors geotechnical
engineers must determine whether issues like erosion, settlement and slope will pose a
safety risk to the proposed project.
Computer analysis: as a geotechnical engineer, you will be required to analyse the
results of subsurface investigations and field tests with dedicated software. Your
ability to understand data and model future conditions will be crucial to the
development of the construction project. After analysis, geotechnical engineers may
be required to assist in the development of earthworks and foundations suitable to the
conditions of the site.
Ensure a collaborative approach is maintained across the team to facilitate the
planning and delivery of interface works, ensuring all issues are clearly understood by
teams and addressed and appropriate interventions developed and implement.
4.8 MANAGEMENT REVIEW
GENERAL
Review of integrated Management systems is carried out at quarterly to planned intervals to
ascertain the effectiveness of the system for the purpose of improvement under the leadership
of the Project Manager.
The input to the management review meeting covers
Follow-up actions from earlier Management Reviews if any
9|Page
Doc. No. : 1 PROJECT QUALITY PLAN
10 | P a g e
Doc. No. : 1 PROJECT QUALITY PLAN
11 | P a g e
Doc. No. : 1 PROJECT QUALITY PLAN
a. Field Quality Engineer shall ensure proper selection of IMTE which are having necessary
accuracy for the measurements to be made at site.
b. All inspection and measuring instruments shall be identified by calibration stickers/tags
indicating calibration status.
c. Field quality engineer/Inspector shall ensure that the IMTE are calibrated at prescribed
intervals or prior to use by using masters traceable to National/international standards.
The calibration shall be done at approved calibration agency or at site. After receipt of
calibration reports from approved calibration agency, field quality engineer/inspector
shall review the results of calibration and the maintain the records.
d. Wherever measuring instrument is found to be out of calibration, Field quality
engineer/Inspector assesses the validity of results of previous measurements shall
establish the action to be initiated regarding products measured as well as the instrument.
e. Field Quality Engineer/Inspector shall ensure that the instrument/gauges are stored,
preserved and handled in such a way that the accuracy and function are maintained and
are protected from damage/deterioration.
1 Batching Plant 3 Months Cement: +2% by weight
IS-4926 Aggregates: +3% by weight
Water: +3% by weight
Admixtures: +3% by weight
4.19 COMPETENCE
The necessary competency required for person(s) who is doing work under its control that
affects the performance and effectiveness of the quality assurance plan is addressed through
processes. The established procedure/system for Recruitment, Competence, Training and
Evaluation of all project involved personnel including workmen in a continuing process to
determine the necessary work competence of people to perform the work effectively and
efficiency, Identification of necessary Training needs and imparting training.
4.20 QUALITY AUDITS
SECPL Construction has established and maintaining a procedure for internal quality
audit. The procedure describes how internal audits are planned and conducted to check the
level of implementation and measure the effectiveness of QMS
Internal audits will be conducted once in three months & external audit will be conducted six
months to ensure the effective implementation of QMS system.
Audits are scheduled based on status, Importance and criticality. The auditors are selected
from independent of the department being audited.
The results of audit are recorded and brought to the attention of top management by MR
through Management review meeting for their timely corrective action.
12 | P a g e
Doc. No. : 1 PROJECT QUALITY PLAN
Maintaining hard copies, tracking and monitoring at all letters, correspondence, approval,
revisions etc. will be communicated through the PMIS portal for fast and easy retrieval
documents.
5.1.2 SCOPE
The major scope of this project is to describe handling and administration of documents
(Comprising incoming, Internal and outgoing correspondence and drawing) pertaining to this
project through the PMIS portal and to ensure that the latest issue of the required documents
including their previous revision.
5.1.3 Resonsibility & Authority
All the document and data control procedure will be controlled through the PMIS Portal by
the concerned department in charges.
Document controller (DC): To submit and track all the project documents and drawings in
accordance with document control procedures through the PMIS.
5.1.4 Management Flow of Receiving and Sending Internal/External Document
5.1.5 Procedure for Receiving Incoming Letters:
Letters received through PMIS/Mail/Hard copies will be received by DC
DC shall maintain an inward letter folder in the PC with the PMIS reference all the
letters received from the client/client rep
5.1.6 Procedure for Outgoing Letters:
Hard copy of the outgoing letters shall be signed by project manager and it shall be
scanned and shall be uploaded in the PMIS Portal
Every outgoing letter will contain a running serial number from DC on giving the
subject reference as per the CMRL Numbering sequence.
To promote Quality improvement
To form basis for Management Review
The internal quality audits shall be conducted as per the contract specification and as
per the relevant clauses of ISO 9001:2015 and shall cover all the operations and
activities of SECPL and sub contractors and vendors.
Once in 3months internally
The internal quality audit will be conducted by QA/QC Manager
5.2.3 Responsibilities
13 | P a g e
Doc. No. : 1 PROJECT QUALITY PLAN
The Chief QA/QC Manager shall prepare Quality audit plan, select the quality audit
personnel (here after called audit personnel) order the audit activity, review and
approve the audit report prepared by the chief QA/QC Manager.
The audited Department Manager shall be responsible for supporting the audit
activities and notifying the corrective action results of the deficiency to the chief
QA/QC Manager.
The chief QA/QC Manager shall be responsible for preparing quality audit checklist
and get approval by the MR. Quality audit results shall be notified to project manager.
5.2.4 Procedures
The QA/QC Manager shall be responsible for all the internal quality audit activities at
site. He shall appoint a leader of the audit team. The members of the team shall
consist of representatives drawn from the project Quality team site QA group or
having any other department having technical knowledge as well as knowledge of QA
system requirements.
5.3 PROCEDURE FOR ANALYSIS OF DATA
5.3.1 Purpose
The section shall describe the requirements of usage of necessary statistical techniques for
effective functioning of the quality system in contract.
5.3.2 Scope:
To ensure the monitoring and control of the quality system
To improve upon the existing quality system
5.3.3 Responsibility:
Chief Quality Assurance & Quality Control Manager shall be preparing the statistical
techniques control procedure to identify and control procedure to identify and control
procedure to identify and control process capabilities and perform quality trend analysis if
necessary.
5.3.4 Procedure:
1. Collect and analyse data’s from
Internal audits
Management review meeting
2. Collect information regarding to
14 | P a g e
Doc. No. : 1 PROJECT QUALITY PLAN
Customer satisfaction
Conformity of product
Trends of process & product
Opportunities for preventive action
Customer complaint
Trends of NCRs observed in system implementation
Sequence of operation starting from management function of engineering up to
construction, training & commissioning.
Approved Construction Schedule
Detail Engineering & construction
Methodology machineries & materials to be procured and used.
Division of work into work lots
Characteristics, Tolerance and workmanship standard to be met
Inspection and Test Plans
How the process will be monitored to ensure its continuing suitability
Finalized manufacturing quality shall be reviewing by QMS representative at site and
then approved by PM for adequacy.
The QA Manager shall bring to the notice of PM, the defects or deviation from MQP
if any during execution of work. Apart from the criteria mentioned in the MQP, the
QA Manager shall also ensure the routine quality check-up of other aspects such as:
Keep a track on resources engaged for at site.
Monitoring of Non-Conformities and taking appropriate action to close the same.
Time to time awareness training to site personnel.
Training on technical aspects related to any construction activity.
Co-ordination with PM for any inputs/suggestions for improvement.
15 | P a g e
Doc. No. : 1 PROJECT QUALITY PLAN
IN PROCESS INSPECTION
Concerned Field Quality Engineer/Inspector shall carry out stage inspection of
construction activities as per approved ITPs and method statements. Field quality
engineer/Inspector shall coordinate with CMRL C4-DPT01 for Inspection at the
stages of the FQP/FITP and obtain clearance.
Field Quality Engineer/Inspector shall hold the product until required inspections and
tests are satisfactorily completed and reports verified.
Relevant inspection authority of Engineering / Procurement / Construction function or
third party as per the following will inspect all incoming materials:
a) Mechanical / electrical components with engineering specification, drawings. Non-
conforming material equipment will be rejected.
b) Inspection at site store for all general store items.
c) The steps that will be adopted for procurement, Inspection and control of the materials.
d) All incoming material will be stored in storage area with proper identification Tag. If
material is inspected and found conforming to specification then it will bear Yellow
Tag.
16 | P a g e
Doc. No. : 1 PROJECT QUALITY PLAN
Frequency of check
Reference of check
Acceptance Tolerance
Format of records
Responsibility for completing the check
Inspection criteria
17 | P a g e