0% found this document useful (0 votes)
27 views3 pages

QCM 4

The document contains a series of multiple-choice questions related to project management concepts, including the project charter, work breakdown structure (WBS), and project management process groups. It tests knowledge on project validation, cost estimation, leadership styles, and the roles of project managers and line management. The questions cover essential elements of project management practices and methodologies.

Uploaded by

hedimedghaith
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
27 views3 pages

QCM 4

The document contains a series of multiple-choice questions related to project management concepts, including the project charter, work breakdown structure (WBS), and project management process groups. It tests knowledge on project validation, cost estimation, leadership styles, and the roles of project managers and line management. The questions cover essential elements of project management practices and methodologies.

Uploaded by

hedimedghaith
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

1-The document that officially sanctions (valide) the project is the :

A. Project charter
B. Project plan
C. Feasibility study
D. Cost-benefit analysis

2. The work breakdown structure “control points” for the management of a project are the:
A. Milestones
B. Work packages (lot des travaux)
C. Activities
D. Constraints

3. Which of the following generally cannot be validated using a work breakdown structure?

A. Schedule control
B. Cost control
C. Quality control
D. Risk management

Answer questions 4–6 using the work breakdown structure (WBS) shown below (numbers in
parentheses show the dollar value for a particular element):

4. The cost of WBS element 1.2.2.0 is:


A. $20K
B. $30K
C. $50K
D. Cannot be determined

5. The cost of WBS element 1.1.1 is:


A. $12K
B. $13K
C. $25K
D. Cannot be determined
6. The cost of the entire program (1.00.00) is:
A. $25K
B. $66K
C. $91K
D. Cannot be determined

7. Which of the following is (are) the benefit(s) of developing a WBS to low levels?
A. Better estimation of costs
B. Better control
C. Less likely that something will “fall through the cracks”
(Moins de risques que quelque chose passe à travers les mailles du filet)
D. All of the above

8. One of your contractors has sent you an e-mail requesting that they be allowed to
conduct only eight tests rather than the ten tests required by the specification. What should
the project manager do first?
A. Change the scope baseline
B. Ask the contractor to put forth a change request
C. Look at the penalty clauses in the contract
D. Ask your sponsor for his or her opinion

9. An element of work normally found on the WBS that has an expected duration, a cost, and
resource requirements
A. Activity
B. Project Time Management
C. Project Schedules
D. Project Charter

10. You’ve constructed the WBS for your recent project. You’ve requested that the
subproject managers report to you in three weeks with each of their individual WBSs
constructed. Which statement is not true regarding the subproject managers’ WBS?
A. The work package level is decomposed to create the activity list.
B. The work package level is the lowest level in the WBS.
C. The work package level facilitates resource assignments.
D. The work package level facilitates cost and time estimates.

11.What are the five project management process groups, in order?


A. Initiating, Executing, Planning, Monitoring and Controlling, and Closing.
B. Initiating, Monitoring and Controlling, Planning, Executing, and Closing.
C. Initiating, Planning, Monitoring and Controlling, Executing, and Closing.
D. Initiating, Panning, Executing, Monitoring and Controlling, and Closing

12. A project manager that allows the team to make virtually all of the decisions without any
involvement by the project manager would be using which leadership style.
A. Passive
B. Participative/democratic
C. Autocratic
D. Laissez-faire

13. Project manager compares the completed work with requirements. What type of process
project manager executes?
A. Performing integrated change control.
B. Closing.
C. Executing.
D. Monitoring and controlling.

14. During project staffing, the primary role of line management is:
A. Approving the selection of the project manager
B. Approving the selection of assistant project managers
C. Assigning functional resources based upon who is available
D. Assigning functional resources based upon availability and the skill set needed

You might also like