Test Estimation Techniques
explain test estimation tehniques
Test estimation is the process of predicting the effort, time, and cost required to complete testing activities in a
software project. It helps in planning, resource allocation, and setting realistic deadlines. Several techniques are
used for test estimation, and each has its own advantages depending on the project context.
🔑 Common Test Estimation Techniques
1. Experience-Based Estimation
Also known as expert judgment.
How it works: Estimators (test leads, managers) use their past experience on similar projects to estimate.
When to use: When historical data is available and estimators have domain knowledge.
Example: "In the last project of similar size, testing took 30 days with 2 testers. So, we'll estimate the same
here."
2. Work Breakdown Structure (WBS)
How it works: Break the testing tasks into smaller sub-tasks (test case design, execution, defect reporting, etc.),
estimate each, and sum them up.
When to use: When project requirements and scope are clear.
Advantages: More accurate as it considers each activity separately.
Example:
Test planning – 2 days
Test case writing – 5 days
Test execution – 10 days
Bug verification – 3 days
Total = 20 days
3. Delphi Technique
How it works: A group of experts anonymously estimate tasks. The estimates are averaged or discussed
iteratively until consensus is reached.
When to use: When unbiased group-based estimation is needed.
1/3
Advantages: Reduces individual bias.
4. Three-Point Estimation
Based on PERT (Program Evaluation Review Technique).
How it works:
O (Optimistic): Best case
M (Most likely): Realistic case
P (Pessimistic): Worst case
Formula:
O + 4M + P
Estimate =
6
When to use: When there is uncertainty and risk in tasks.
Example:
O = 2 days, M = 4 days, P = 8 days
Estimate = (2 + 4×4 + 8) / 6 = 4.33 days
5. Function Point / Test Point Analysis
How it works: Measures complexity using function points (FP) based on inputs, outputs, interfaces, etc. Test
points are derived from FPs.
When to use: In large projects with well-defined functional requirements.
Needs: Expertise in function point analysis.
6. Percentage of Development Effort
How it works: Testing effort is estimated as a percentage of the total development effort (commonly 25% to
40%).
When to use: In early project stages where only rough estimates are possible.
7. Use-Case Point Method
How it works: Estimates are based on the number and complexity of use cases in the system.
When to use: When requirements are use-case driven.
2/3
8. Top-Down vs Bottom-Up Estimation
Top-Down: Start with a high-level estimate and break down into tasks.
Bottom-Up: Estimate each task individually and sum them up.
✅ Tips for Accurate Estimation
Include buffer for risks and rework.
Consider non-testing activities (meetings, reporting, training).
Update estimates as more information becomes available.
Factor in team experience, tools used, and testing environment setup.
Would you like real-life examples or templates for any of these methods?
3/3